ESTIMATE
CONSTRUCTION OF SESSION DIVISIONS (EAST & WEST) IN MAUVE AREA, SECTOR G‐11/4, ISLAMABAD
PLUMBING WORK
SUMMARY OF COST
CONSTRUCTION OF SESSION DIVISIONS (EAST & WEST) IN MAUVE AREA, SECTOR G‐11/4, ISLAMABAD
PLUMBING WORKS
( BASEMENTS B-1, B-2)
RATE AMOUNT
S.NO. DESCRIPTIONS QTY UNIT
(Rs.) (Rs.)
A) WATER & Gas SUPPLY SYSTEM
6) Gas Piping
Supply, installation testing and
commissioning of GI Pipes Medium Quality
for natural gas piping from available main
source point to appartments including all
fitings, complete in all respects as per
drawings, specifications and as approved by
the engineer.
Total‐A 1,604,275
INTERNAL SOIL, WASTE WATER &VENT
B)
SYSTEM
1) uPVC Soil, Waste & Vent Pipe
Providing, fixing in position uPVC pipes
push fit type pipe embedded in floor and
wall or suspended from slab or clamped to
floor and wall including plugs, clamps,
hanger collars, supports, specials (bend,
tees, Y‐tee etc). Making requisite number
of holes in walls and floors where required
and making good the same as necessary to
the structure with non‐shirink grout,
labelling and testing to 8' ft water height
complete in all respect and as shown in
drawings
2) uPVC Vent Cowl
Providing and fixing uPVC cowl for vent
pipe of the following dia including all
accessories complete.
3) Cleanouts plug
Providing and fixing uPVC clean out plug
with cover for pipe roading and making
good the same as necessary to the
structure, complete including, rubber
gasket and clamp.
9) C.I. Covers & Frame
Providing and fixing C.I covers with frame
for underground and septic water tanks
complete in all respect as necessary to the
structure.
I water tank cover 24" X24" (50 kg Weight)
8 Nos. 18,572 148,576
10) C.I. Grating & Frame
Providing and fixing C.I grating with frame
for basement ramp chennel, complete in all
respect as necessary to the structure.
Total‐B 10,700,721
A INFRASTRUCTURE
EXTERNAL WATER SUPPLY
1) Centrifugal Pump (water Tank)
PLUMBING WORKS
( BASEMENTS B-1, B-2)
RATE AMOUNT
S.NO. DESCRIPTIONS QTY UNIT
(Rs.) (Rs.)
Providing, Installing, testing and
commissioning the centrifugal pump for
overhead tank filling having flow of 250 Gpm @
7 Bar (each pump), as per manufacturer
recommendation including all accessories such
as flanged pipes, gate valves, non‐return valves, 3 Nos. 1,355,000 4,065,000
foot valves, pressure gauges on suction and
delivery side of the pump motor control panel
with dry run protection complete in all respect.
Total (C) 4,065,000
PLUMBING WORKS
( BASEMENTS B-1, B-2)
RATE AMOUNT
S.NO. DESCRIPTIONS QTY UNIT
(Rs.) (Rs.)
EXTERNAL SEWER SYSTEM
1) Submersible Pump (Septic Tank)
Providing, installing testing &
commissioning submersible pump 250Gpm
and head of 7 M with Grinder for basement
toilets' sump pits, single phase motor
including control panel, gate valves, check
valves, float, gauges necessary for the 3 Nos. 1,520,000 4,560,000
complete operation to the pump and flow
switch, including control panel complete in
all respect.
2) Submersible Pump (sump Pit)
Providing, Installing, testing &
commissioning submersible pump with
flow of 80 GPM and 10 M head for waste
water sump pit, including control panel,
starter, gate valves, check valves, float,
gauges necessary for the complete 8 Nos. 623,900 4,991,200
operation of the pump and flow switch for
total discharge of 25Gpm & head of 30'ft,
complete in all respect.
3) uPVC Pressure Pipe
Providing, laying and jointing PVC class‐E
pressure pipe for submersible pump
discharge including excavation backfilling,
compaction bedding, lowering in trenches
to correct alignment and grade, jointing,
clamping, cutting pipes where necessary,
finishing and testing complete as per
drawing and to the satisfaction of engineer.
4) uPVC Sewer Pipe
PLUMBING WORKS
( BASEMENTS B-1, B-2)
RATE AMOUNT
S.NO. DESCRIPTIONS QTY UNIT
(Rs.) (Rs.)
Providing, laying and jointing uPVC flow
line sewer pipe including excavation
backfilling, compaction bedding, lowering
in Trenches to correct alignment and grade,
jointing, cutting pipes where necessary,
finishing and testing complete as per
drawing and to the satisfaction of
engineer.(sand bedding as require).
5) C.I. Covers & Frame
Providing and fixing CI covers for
underground and overhead water tank.
Construction of block masonry square
1,080,000
manhole 24 Nos. 45,000
Heavy duty C.I frame and cover 24" X24"
348,000
(30 kg Weight) 24 Nos. 14,500
6) Gully Trap ‐
I Providing and fixing 450 x 450mm C.I. Gully
trap with C.I. Frame and cover including
R.C.C. gully trap chambers as per drawing 4 Nos. 15,500 62,000
and specification complete in all respect.
Total D 14,138,772
E) MISCELLANEOUS
a) Supply, installation and commissioning of
brass tags of 40mm dia tags for equipment
and fixed with chains including all
accessories, complete in all respect, as per
drawing and specification.
e) As‐build Drawings
As‐build drawings for plumbing and fire
fighting works as per Contract document.
Total (A+B+C+D+E) 33,427,929
COST ESTIMATE
CONSTRUCTION OF SESSION DIVISIONS (EAST & WEST) IN MAUVE AREA, SECTOR G‐11/4, ISLAMABAD
PLUMBING WORKS
(Ground Floor)
S.NO. DESCRIPTIONS QTY UNIT RATE AMOUNT
(Rs.) (Rs.)
TOILET FITTINGS AND ACCESSORIES
A)
I Providing and fixing EWC with seat cover 20 Nos. 25,500 510,000
II Concealed Flush Tank 20 Nos. 36,136 722,720
III Bib Cock with Muslim Shower 20 Nos. 3,359 67,180
2) European Style Wall Hung Water Closet with
Seat Cover
Providing and fixing easteren type water closet
with coupled flushing cistern, including all
accessories and fittings, waste pipe and traps,
flexible pipe, including double seat and cover,
tee stop cock with check nut, with C.P
connector, all joints to services and drains
plugging and screwing as necessary to the
structure. complete in all respect, filling sleeve
opening with non‐shirink grout, and coated
with eppoxy. complete in all respect.
Providing and fixing EWC with seat cover and 40 Nos. 21,874 874,960
flush tank.
Tee Stop Cock with C.P. Connector, Pvc 40 Nos. 1,040 41,600
Thimble
Bib Cock with Muslim Shower 40 Nos. 3,359 134,360
IV Bottle Trap 40 Nos. 1,786 71,440
V Waste Coupling 40 Nos. 3,234 129,360
3) Wash Basin (Counter Top)
Providing and fixing wash basin counter top of
approved make with all accessories such as
basin mixer, tee stop cock, with check nuts,
flexible pipe, uPVC waste pipe, waste coupling
bracket set etc. complete including bottle trap,
and silicon sealant, all joint to service and
drain, plugging and screwing as necessary to
the structure. complete in all respect, filling
sleeve opening with non‐shirink grout, and
coated with eppoxy. complete in all respect.
3) Toilet Accessories
Providing and fixing bathroom accessories
including fixing with Rawal plug of approved
quality complete in all respect.
Total (A) 5,044,500
B) WATER & GAS SUPPLY SYSTEM
1) Polypropylene Pipe (PPRC)
Providing, fixing, jointing, poly propylene pipe
as per DIN 8077 / 8078 (PN 20) including
specials fittings as per DIN 16962 (PN 25) such
as socket, tees, elbows bends, reducer plug
and union etc), clamps, hanger collars,
supports, supported on wall or buried in walls
or suspended from roof slab as per
specifications including colour tagging,
providing sleeve in wall, testing @ 150 psi,
complete in all respect.
Total‐B 6,243,709
INTERNAL SOIL, WASTE WATER &VENT
C)
SYSTEM
1) uPVC Soil, Waste & Vent Pipe
Providing, fixing in position uPVC pipes push fit
type pipe embedded in floor and wall or
suspended from slab or clamped to floor and
wall including plugs, clamps, hanger collars,
supports, specials (bend, tees, Y‐tee etc).
Making requisite number of holes in walls and
floors where required and making good the
same as necessary to the structure with non‐
shirink grout, labelling and testing to 8' ft water
height complete in all respect and as shown in
drawings.
2) Floor Drain
Providing and fixing make floor drain / Floor
Gully of approved design with S/S grating
including requisite number of holes in wall
plinth or floor for pipe connection and making
good the same as necessary with non‐shrink
grout to the structure complete including
gasket, hangers and clamp.
I 110mmØ 110 Nos. 3,792 417,120
5) Cleanouts plug
Providing and fixing uPVC clean out plug with
cover for pipe roading and making good the
same as necessary to the structure, complete
including, rubber gasket and clamp.
Total‐C 9,522,560
D) INFRASTRUCTURE
A EXTERNAL WATER SUPPLY
1) Centrifugal Pump
Providing, Installing, testing and commissioning
the centrifugal pump for overhead tank filling
having flow of 250Gpm @ 6 bar pressure (each
pump), as per manufacturer recommendation
including all accessories such as flanged pipes, gate
valves, non‐return valves, foot valves, pressure 3 Nos. 818,344 2,455,032
gauges on suction and delivery side of the pump
motor control panel with dry run protection
complete in all respect.
2) Submersible Pump
Providing, Installing, testing & commissioning
submersible pump with flow of 80 GPM and 10
M head for waste water sump pit, including
control panel, starter, gate valves, check
valves, float, gauges necessary for the
complete operation of the pump and flow 3 Nos. 623,900 1,871,700
switch for total discharge of 25Gpm & head of
30'ft, complete in all respect.
E) EXTERNAL SEWER SYSTEM
3) uPVC Pressure Pipe
Providing, laying and jointing PVC class‐E
pressure pipe for submersible pump discharge
including excavation backfilling, compaction
bedding, lowering in trenches to correct
alignment and grade, jointing, clamping,
cutting pipes where necessary, finishing and
testing complete as per drawing and to the
satisfaction of engineer.
CONSTRUCTION OF SESSION DIVISIONS (EAST & WEST) IN MAUVE AREA, SECTOR G‐11/4, ISLAMABAD
PLUMBING WORKS
(First Floor)
S.NO. DESCRIPTIONS QTY UNIT RATE AMOUNT
(Rs.) (Rs.)
TOILET FITTINGS AND ACCESSORIES
A)
I Providing and fixing EWC with seat cover 20 Nos. 25,500 510,000
II Concealed Flush Tank 20 Nos. 36,136 722,720
III Bib Cock with Muslim Shower 20 Nos. 3,359 67,180
2) European Style Wall Hung Water Closet
with Seat Cover
Providing and fixing European type water
closet with coupled flushing cistern,
including all accessories and fittings,
waste pipe and traps, flexible pipe,
including double seat and cover, tee stop
cock with check nut, with C.P connector,
all joints to services and drains plugging
and screwing as necessary to the
structure. complete in all respect, filling
sleeve opening with non‐shirink grout,
and coated with eppoxy. complete in all
respect.
Providing and fixing EWC with seat cover 40 Nos. 21,874 874,960
and flush tank.
Tee Stop Cock with C.P. Connector, Pvc 40 Nos. 1,040 41,600
Thimble
Bib Cock with Muslim Shower 40 Nos. 2,359 94,360
3) Wash Basin (Counter Top)
Providing and fixing wash basin counter
top of approved make with all
accessories such as basin mixer, tee stop
cock, with check nuts, flexible pipe, uPVC
waste pipe, waste coupling bracket set
etc. complete including bottle trap, and
silicon sealant, all joint to service and
drain, plugging and screwing as necessary
to the structure. complete in all respect,
filling sleeve opening with non‐shirink
grout, and coated with eppoxy. complete
in all respect.
Total (A) 6,093,700
B) WATER SUPPLY SYSTEM
1) Polypropylene Pipe (PPRC)
Providing, fixing, jointing, poly propylene
pipe as per DIN 8077 / 8078 (PN 20)
including specials fittings as per DIN
16962 (PN 25) such as socket, tees,
elbows bends, reducer plug and union
etc), clamps, hanger collars, supports,
supported on wall or buried in walls or
suspended from roof slab as per
specifications including colour tagging,
providing sleeve in wall, testing @ 150 psi,
complete in all respect.
2) Gate Valves
Providing and fixing of full way gate
valves of bronze trim up to 3” (75 mm)
dia with threaded ends cast iron body
bronze trim flanged ends for 4" dia (100
mm) and above or equivalent or similar
for 125 psi together with all additional
material required for a complete
installation as describe in the
specification and as shown on drawings
and as approved by the Engineer.
3) ELECTRIC WATER HEATER
Fixing testing & commissioning of Electric
water Heater of following capacity
including inlet / outlet connections, gate
valve etc complete in all respects.
6) Gas Piping
Supply, installation testing and
commissioning of GI Pipes Medium
Quality for natural gas piping from
available main source point to
appartments including all fitings,
complete in all respects as per drawings,
specifications and as approved by the
engineer.
I 15mmØ 356 RFT 150 53,400
Total‐B 5,326,498
INTERNAL SOIL, WASTE WATER &VENT
C)
SYSTEM
1) uPVC Soil, Waste & Vent Pipe
Providing, fixing in position uPVC pipes
push fit type pipe embedded in floor and
wall or suspended from slab or clamped
to floor and wall including plugs, clamps,
hanger collars, supports, specials (bend,
tees, Y‐tee etc). Making requisite number
of holes in walls and floors where
required and making good the same as
necessary to the structure with non‐
shirink grout, labelling and testing to 8' ft
water height complete in all respect and
as shown in drawings.
III 110mmØ‐ (4") 250 RFT 1,236 309,000
2) Floor Drain
Providing and fixing make floor drain /
Floor Gully of approved design with S/S
grating including requisite number of
holes in wall plinth or floor for pipe
connection and making good the same as
necessary with non‐shrink grout to the
structure complete including gasket,
hangers and clamp.
5) Cleanouts plug
Providing and fixing uPVC clean out plug
with cover for pipe roading and making
good the same as necessary to the
structure, complete including, rubber
gasket and clamp.
Total‐C 1,216,042
Total (A+B+C) 12,636,240
COST ESTIMATE
CONSTRUCTION OF SESSION DIVISIONS (EAST & WEST) IN MAUVE AREA, SECTOR G‐11/4, ISLAMABAD
PLUMBING WORKS
(Second Floor)
S.NO. DESCRIPTIONS QTY UNIT RATE AMOUNT
(Rs.) (Rs.)
A) TOILET FITTINGS AND ACCESSORIES
1) European Style Wall Hung Water Closet with
Seat Cover with Concealed Flush Tank
I Providing and fixing EWC with seat cover 15 Nos. 25,500 382,500
II Concealed Flush Tank 15 Nos. 36,136 542,040
III Bib Cock with Muslim Shower 15 Nos. 3,359 50,385
2) European Style Wall Hung Water Closet with
Seat Cover
Providing and fixing European type water closet
with coupled flushing cistern, including all
accessories and fittings, waste pipe and traps,
flexible pipe, including double seat and cover, tee
stop cock with check nut, with C.P connector, all
joints to services and drains plugging and
screwing as necessary to the structure. complete
in all respect, filling sleeve opening with non‐
shirink grout, and coated with eppoxy. complete
in all respect.
Providing and fixing EWC with seat cover and 45 Nos. 21,874 984,330
flush tank.
Tee Stop Cock with C.P. Connector, Pvc Thimble 45 Nos. 1,040 46,800
Total (A) 5,595,090
B) WATER & Gas SUPPLY SYSTEM
1) Polypropylene Pipe (PPRC)
Providing, fixing, jointing, poly propylene pipe as
per DIN 8077 / 8078 (PN 20) including specials
fittings as per DIN 16962 (PN 25) such as socket,
tees, elbows bends, reducer plug and union etc),
clamps, hanger collars, supports, supported on
wall or buried in walls or suspended from roof
slab as per specifications including colour tagging,
providing sleeve in wall, testing @ 150 psi,
complete in all respect.
2) Gate Valves
Providing and fixing of full way gate valves of
bronze trim up to 3” (75 mm) dia with threaded
ends cast iron body bronze trim flanged ends for
4" dia (100 mm) and above or equivalent or
similar for 125 psi together with all additional
material required for a complete installation as
describe in the specification and as shown on
drawings and as approved by the Engineer.
6) Gas Piping
Supply, installation testing and commissioning of
GI Pipes Medium Quality for natural gas piping
from available main source point to appartments
including all fitings, complete in all respects as
per drawings, specifications and as approved by
the engineer.
2) Floor Drain
Providing and fixing make floor drain / Floor Gully
of approved design with S/S grating including
requisite number of holes in wall plinth or floor
for pipe connection and making good the same
as necessary with non‐shrink grout to the
structure complete including gasket, hangers and
clamp.
Total‐C 1,566,000
Total (A+B+C) 10,541,397
COST ESTIMATE
CONSTRUCTION OF SESSION DIVISIONS (EAST & WEST) IN MAUVE AREA, SECTOR G‐11/4, ISLAMABAD
PLUMBING WORKS
(Third Floor)
S.NO. DESCRIPTIONS QTY UNIT RATE AMOUNT
(Rs.) (Rs.)
TOILET FITTINGS AND ACCESSORIES
A)
I Providing and fixing EWC with seat cover 15 Nos. 25,500 382,500
II Concealed Flush Tank 15 Nos. 36,136 542,040
III Bib Cock with Muslim Shower 15 Nos. 3,359 50,385
2) European Style Wall Hung Water Closet with
Seat Cover
Providing and fixing European type water
closet with coupled flushing cistern, including
all accessories and fittings, waste pipe and
traps, flexible pipe, including double seat and
cover, tee stop cock with check nut, with C.P
connector, all joints to services and drains
plugging and screwing as necessary to the
structure. complete in all respect, filling
sleeve opening with non‐shirink grout, and
coated with eppoxy. complete in all respect.
Providing and fixing EWC with seat cover and 45 Nos. 21,874 984,330
flush tank.
Tee Stop Cock with C.P. Connector, Pvc 45 Nos. 1,040 46,800
Thimble
Bib Cock with Muslim Shower 45 Nos. 3,359 151,155
3) Wash Basin (Counter Top)
Providing and fixing wash basin counter top
of approved make with all accessories such as
basin mixer, tee stop cock, with check nuts,
flexible pipe, uPVC waste pipe, waste
coupling bracket set etc. complete including
bottle trap, and silicon sealant, all joint to
service and drain, plugging and screwing as
necessary to the structure. complete in all
respect, filling sleeve opening with non‐
shirink grout, and coated with eppoxy.
complete in all respect.
Total (A) 5,595,090
B) WATER & Gas SUPPLY SYSTEM
1) Polypropylene Pipe (PPRC)
Providing, fixing, jointing, poly propylene pipe
as per DIN 8077 / 8078 (PN 20) including
specials fittings as per DIN 16962 (PN 25)
such as socket, tees, elbows bends, reducer
plug and union etc), clamps, hanger collars,
supports, supported on wall or buried in walls
or suspended from roof slab as per
specifications including colour tagging,
providing sleeve in wall, testing @ 150 psi,
complete in all respect.
2) Gate Valves
Providing and fixing of full way gate valves of
bronze trim up to 3” (75 mm) dia with
threaded ends cast iron body bronze trim
flanged ends for 4" dia (100 mm) and above
or equivalent or similar for 125 psi together
with all additional material required for a
complete installation as describe in the
specification and as shown on drawings and
as approved by the Engineer.
3) ELECTRIC WATER HEATER
Fixing testing & commissioning of Electric
water Heater of following capacity including
inlet / outlet connections, gate valve etc
complete in all respects.
6) Gas Piping
Supply, installation testing and
commissioning of GI Pipes Medium Quality
for natural gas piping from available main
source point to appartments including all
fitings, complete in all respects as per
drawings, specifications and as approved by
the engineer.
5) Cleanouts plug
Providing and fixing uPVC clean out plug with
cover for pipe roading and making good the
same as necessary to the structure, complete
including, rubber gasket and clamp.
Total‐C 1,566,000
Total (A+B+C) 9,565,097
COST ESTIMATE
CONSTRUCTION OF SESSION DIVISIONS (EAST & WEST) IN MAUVE AREA, SECTOR G‐11/4, ISLAMABAD
PLUMBING WORKS
(Fourth Floor)
S.NO. DESCRIPTIONS QTY UNIT RATE AMOUNT
(Rs.) (Rs.)
TOILET FITTINGS AND ACCESSORIES
A)
Total (A) 5,595,090
B) WATER & Gas SUPPLY SYSTEM
1) Polypropylene Pipe (PPRC)
Providing, fixing, jointing, poly
propylene pipe as per DIN 8077 /
8078 (PN 20) including specials
fittings as per DIN 16962 (PN 25) such
as socket, tees, elbows bends,
reducer plug and union etc), clamps,
hanger collars, supports, supported
on wall or buried in walls or
suspended from roof slab as per
specifications including colour
tagging, providing sleeve in wall,
testing @ 150 psi, complete in all
respect.
3) ELECTRIC WATER HEATER
Fixing testing & commissioning of
Electric water Heater of following
capacity including inlet / outlet
connections, gate valve etc complete
in all respects.
2) Floor Drain
Providing and fixing make floor drain
/ Floor Gully of approved design with
S/S grating including requisite
number of holes in wall plinth or
floor for pipe connection and making
good the same as necessary with non‐
shrink grout to the structure
complete including gasket, hangers
and clamp.
5) Cleanouts plug
Providing and fixing uPVC clean out
plug with cover for pipe roading and
making good the same as necessary
to the structure, complete including,
rubber gasket and clamp.
Total‐C 1,496,177
Total (A+B+C) 10,182,874
COST ESTIMATE
CONSTRUCTION OF SESSION DIVISIONS (EAST & WEST) IN MAUVE AREA, SECTOR G‐11/4, ISLAMABAD
PLUMBING WORKS
(Fifth Floor)
S.NO. DESCRIPTIONS QTY UNIT RATE AMOUNT
(Rs.) (Rs.)
TOILET FITTINGS AND
A) ACCESSORIES
1) European Style Wall Hung Water
Closet with Seat Cover with
Concealed Flush Tank
2) Gate Valves
Providing and fixing of full way gate
valves of bronze trim up to 3” (75
mm) dia with threaded ends cast
iron body bronze trim flanged ends
for 4" dia (100 mm) and above or
equivalent or similar for 125 psi
together with all additional
material required for a complete
installation as describe in the
specification and as shown on
drawings and as approved by the
Engineer.
3) ELECTRIC WATER HEATER
Fixing testing & commissioning of
Electric water Heater of following
capacity including inlet / outlet
connections, gate valve etc
complete in all respects.
6) Gas Piping
Supply, installation testing and
commissioning of GI Pipes Medium
Quality for natural gas piping from
available main source point to
appartments including all fitings,
complete in all respects as per
drawings, specifications and as
approved by the engineer.
2) Floor Drain
Providing and fixing make floor
drain / Floor Gully of approved
design with S/S grating including
requisite number of holes in wall
plinth or floor for pipe connection
and making good the same as
necessary with non‐shrink grout to
the structure complete including
gasket, hangers and clamp.
5) Cleanouts plug
Providing and fixing uPVC clean out
plug with cover for pipe roading
and making good the same as
necessary to the structure,
complete including, rubber gasket
and clamp.
Total‐C 1,475,772
Total (A+B+C) 11,108,869
COST ESTIMATE
CONSTRUCTION OF SESSION DIVISIONS (EAST & WEST) IN MAUVE AREA, SECTOR G‐11/4, ISLAMABAD
PLUMBING WORKS
(Sixth Floor)
S.NO. DESCRIPTIONS QTY UNIT RATE AMOUNT
(Rs.) (Rs.)
TOILET FITTINGS AND ACCESSORIES
A)
1) European Style Wall Hung Water
Closet with Seat Cover with
Concealed Flush Tank
Fixing European type Wall Hung
Water Closet with concealed
flushing cistern, including all
accessories and fittings, waste and
traps, including seat and cover, all
joints to service and drains plugging
and screwing as necessary to the
structure with non‐shirink grout. (for
attach washrooms)
Total (A) 5,478,990
B) WATER & Gas SUPPLY SYSTEM
1) Polypropylene Pipe (PPRC)
Providing, fixing, jointing, poly
propylene pipe as per DIN 8077 /
8078 (PN 20) including specials
fittings as per DIN 16962 (PN 25)
such as socket, tees, elbows bends,
reducer plug and union etc), clamps,
hanger collars, supports, supported
on wall or buried in walls or
suspended from roof slab as per
specifications including colour
tagging, providing sleeve in wall,
testing @ 150 psi, complete in all
respect.
3) ELECTRIC WATER HEATER
Fixing testing & commissioning of
Electric water Heater of following
capacity including inlet / outlet
connections, gate valve etc
complete in all respects.
5) Cleanouts plug
Providing and fixing uPVC clean out
plug with cover for pipe roading and
making good the same as necessary
to the structure, complete including,
rubber gasket and clamp.
Total‐C 1,475,772
Total (A+B+C) 9,358,769
COST ESTIMATE
CONSTRUCTION OF SESSION DIVISIONS (EAST & WEST) IN MAUVE AREA, SECTOR G‐11/4, ISLAMABAD
PLUMBING WORKS
(Seventh Floor)
S.NO. DESCRIPTIONS QTY UNIT RATE AMOUNT
(Rs.) (Rs.)
TOILET FITTINGS AND ACCESSORIES
A)
I Providing and fixing EWC with seat cover 15 Nos. 25,500 382,500
II Concealed Flush Tank 15 Nos. 36,136 542,040
III Bib Cock with Muslim Shower 15 Nos. 3,359 50,385
2) European Style Wall Hung Water Closet
with Seat Cover
Providing and fixing European type water
closet with coupled flushing cistern,
including all accessories and fittings, waste
pipe and traps, flexible pipe, including
double seat and cover, tee stop cock with
check nut, with C.P connector, all joints to
services and drains plugging and screwing
as necessary to the structure. complete in
all respect, filling sleeve opening with non‐
shirink grout, and coated with eppoxy.
complete in all respect.
Providing and fixing EWC with seat cover 45 Nos. 21,874 984,330
and flush tank.
Tee Stop Cock with C.P. Connector, Pvc 45 Nos. 1,040 46,800
Thimble
Bib Cock with Muslim Shower 45 Nos. 3,359 151,155
3) Wash Basin (Counter Top)
Providing and fixing wash basin counter top
of approved make with all accessories such
as basin mixer, tee stop cock, with check
nuts, flexible pipe, uPVC waste pipe, waste
coupling bracket set etc. complete
including bottle trap, and silicon sealant, all
joint to service and drain, plugging and
screwing as necessary to the structure.
complete in all respect, filling sleeve
opening with non‐shirink grout, and coated
with eppoxy. complete in all respect.
Total (A) 5,478,990
B) WATER & Gas SUPPLY SYSTEM
1) Polypropylene Pipe (PPRC)
Providing, fixing, jointing, poly propylene
pipe as per DIN 8077 / 8078 (PN 20)
including specials fittings as per DIN 16962
(PN 25) such as socket, tees, elbows bends,
reducer plug and union etc), clamps,
hanger collars, supports, supported on wall
or buried in walls or suspended from roof
slab as per specifications including colour
tagging, providing sleeve in wall, testing @
150 psi, complete in all respect.
2) Gate Valves
Providing and fixing of full way gate valves
of bronze trim up to 3” (75 mm) dia with
threaded ends cast iron body bronze trim
flanged ends for 4" dia (100 mm) and above
or equivalent or similar for 125 psi together
with all additional material required for a
complete installation as describe in the
specification and as shown on drawings and
as approved by the Engineer.
6) Gas Piping
Supply, installation testing and
commissioning of GI Pipes Medium Quality
for natural gas piping from available main
source point to appartments including all
fitings, complete in all respects as per
drawings, specifications and as approved by
the engineer.
2) Floor Drain
Providing and fixing make floor drain /
Floor Gully of approved design with S/S
grating including requisite number of holes
in wall plinth or floor for pipe connection
and making good the same as necessary
with non‐shrink grout to the structure
complete including gasket, hangers and
clamp.
I 110mmØ 110 Nos. 3,792 417,120
5) Cleanouts plug
Providing and fixing uPVC clean out plug
with cover for pipe roading and making
good the same as necessary to the
structure, complete including, rubber
gasket and clamp.
Total‐C 1,475,772
Total (A+B+C) 9,955,015
COST ESTIMATE
CONSTRUCTION OF SESSION DIVISIONS (EAST & WEST) IN MAUVE AREA, SECTOR G‐11/4, ISLAMABAD
PLUMBING WORKS
(Eighth Floor)
S.NO. DESCRIPTIONS QTY UNIT RATE AMOUNT
(Rs.) (Rs.)
TOILET FITTINGS AND ACCESSORIES
A)
1) European Style Wall Hung Water Closet
with Seat Cover with Concealed Flush
Tank
Fixing European type Wall Hung Water
Closet with concealed flushing cistern,
including all accessories and fittings,
waste and traps, including seat and
cover, all joints to service and drains
plugging and screwing as necessary to
the structure with non‐shirink grout. (for
attach washrooms)
I Providing and fixing EWC with seat cover 15 Nos. 25,500 382,500
II Concealed Flush Tank 15 Nos. 36,136 542,040
III Bib Cock with Muslim Shower 15 Nos. 3,359 50,385
2) European Style Wall Hung Water Closet
with Seat Cover
Providing and fixing European type water
closet with coupled flushing cistern,
including all accessories and fittings,
waste pipe and traps, flexible pipe,
including double seat and cover, tee stop
cock with check nut, with C.P connector,
all joints to services and drains plugging
and screwing as necessary to the
structure. complete in all respect, filling
sleeve opening with non‐shirink grout,
and coated with eppoxy. complete in all
respect.
Providing and fixing EWC with seat cover 45 Nos. 21,874 984,330
and flush tank.
Tee Stop Cock with C.P. Connector, Pvc 45 Nos. 1,040 46,800
Thimble
Bib Cock with Muslim Shower 45 Nos. 3,359 151,155
3) Wash Basin (Counter Top)
Providing and fixing wash basin counter
top of approved make with all
accessories such as basin mixer, tee stop
cock, with check nuts, flexible pipe, uPVC
waste pipe, waste coupling bracket set
etc. complete including bottle trap, and
silicon sealant, all joint to service and
drain, plugging and screwing as
necessary to the structure. complete in
all respect, filling sleeve opening with
non‐shirink grout, and coated with
eppoxy. complete in all respect.
3) ELECTRIC WATER HEATER
Fixing testing & commissioning of Electric
water Heater of following capacity
including inlet / outlet connections, gate
valve etc complete in all respects.
6) Gas Piping
Supply, installation testing and
commissioning of GI Pipes Medium
Quality for natural gas piping from
available main source point to
appartments including all fitings,
complete in all respects as per drawings,
specifications and as approved by the
engineer.
2) Floor Drain
Providing and fixing make floor drain /
Floor Gully of approved design with S/S
grating including requisite number of
holes in wall plinth or floor for pipe
connection and making good the same as
necessary with non‐shrink grout to the
structure complete including gasket,
hangers and clamp.
5) Cleanouts plug
Providing and fixing uPVC clean out plug
with cover for pipe roading and making
good the same as necessary to the
structure, complete including, rubber
gasket and clamp.
2) Gate Valves
Total‐A 485,000
INTERNAL SOIL, WASTE WATER &VENT
C)
SYSTEM
1) uPVC Rain Water Pipe
Providing, fixing in position uPVC solvent
joint pipe for rain water pipe suspended
from slab or clamped to wall including
plugs, clamps, hangers collars, supports,
taging, painting, specials (bend, tees, y‐
tee etc.) making requisite number of
holes in walls and floors and filling holes
around the pipe with non‐shrink grout of
approved make where required and
making good the same as necessary to
the structure complete in all respect.
2) uPVC Roof Drain
Providing and fixing make uPVC scupper
roof drain approved design uPVC grating
including requisite number of holes in
floor for pipe connection and making
good the same as necessary with non‐
shrink grout to the structure complete
including gasket, hangers and clamp.
5) Float Valve
Providing and fixing Float valve for
overhead water tanks supply pipe,
including all accessories complete in all
respect.
6"Ø 6 Nos. 18,500 111,000
6) flange valve
Providing and install DI flanged
complete with buried gate valve,
Classified according to type, material,
diameter, and depth as indicated on
drawings and according to technical
specification
4"Ø 25 Nos. 35,000 875,000
6"Ø 16 Nos. 55,000 880,000
6) water filtration System
supply and fixing water filtration system
for potable water and uv ,inculding
Electrification , testing and comissioning
,complete in allrespect as per drawing
1 Job 1,499,999 1,499,999
and specification & instruction of
Engineer Incharge. Complete in all
respect.
Total‐B 6,070,201
Total (A+B+C) 6,555,201
COST ESTIMATE
ONSTRUCTION OF SESSION DIVISIONS (EAST & WEST) IN MAUVE AREA, SECTOR G‐11/4, ISLAMABA
SUMMARY OF COST ESTIMATE
TUBE WELL & FILTERATION PLANT
PKR 11,099,037
COST ESTIMATE
CONSTRUCTION OF SESSION DIVISIONS (EAST & WEST) IN MAUVE AREA, SECTOR G‐11/4, ISLAMABAD
TUBE WELL
SUB HEAD 1
DRILLING & BORING
SCHEDULE ITEM
Direct Rotary/Reverse Rotary drilling of bore for tube wells, in all
1 types of soil including shingle, gravel and rock
From Raft Bottom level to 250 ft. below ground level 20" to 26"
a) 250 Per Rft 850.00 212,500
i/d
b) Exceeding 250 ft. depth below ground level 15" to 18" i/d 250 Per Rft 545.50 136,375
Per set
2 Furnishing sample of water from bore hole. 2 of 2‐ 171 341
Bottles
Providing and installing M.S. blind pipe socketed/welded joint,
M.S. reducer (where necessary), in tube well bore hole, including
3 jointing/welding with strainer, etc. complete 500 Per Rft 2,309 1,154,475
12" i/d, 1/4" thick
TOTAL FOR SCHEDULE ITEM 1,503,691
Installation
Material Unit Total Cost
Item Description Qty Unit Unit
Rate (Rs.) (Rs.)
Rate (Rs.)
(2) (3) (4) (5) (6) 7=3x(5+6)
NON‐SCHEDULE ITEMS
Providing and installing fiber Glass Blank pipe in the tube well bore
1 hole including jointing with fiber glass blank pipe / strainer. 8" i/d 240 Per Rft 1,520 364,800
.20" thick
Providing and installing fibre glass strainer in tube well bore hole
2 including sockets,special sockets etc including jointing complete in 150 Per Rft 1,800 270,000
all respect 8" i/d thick with 10 % open area
Providing and instatalling Fiber Glass Bail Plug in tube well bore
3 hole 1 each 3,500 3,500
8" i/d 0.2" thick 10 ft long
Shrouding with gravel as per WASA specification
4 420 Per Rft 250 105,000
H‐8.2.3.1, H‐8.3.4 & H‐8.4.2.7
Taking sample one number at every 5 ft or from each stratum as
5 per direction of engineer including submission construction charts 120 each 70 8,400
e.t.c and result of strata analysis
Providing and sealing with puddle clay between shrouding and
6 1 Job 8,500 8,500
grouting etc
Sealing of annular apace around 12" mild steel housing pipe with
7 180 Per Rft 470 84,600
1:1 cement sand slury including all sorts of materials
COST ESTIMATE
CONSTRUCTION OF SESSION DIVISIONS (EAST & WEST) IN MAUVE AREA, SECTOR G‐11/4, ISLAMABAD
TUBE WELL
Development testing and disinfecting of complete well in
8 accordace with the tendered specification including disposal 1 job 55,000 55,000
arrangement of water as pumped
Providing and fixing MS cap to cover the pump house casing up to
9 1 each 2,000 2,000
12" dia 1/8 thick i/c welding
Providing/laying cement concrete block size as per drawing with
RCC ratio 1:2:4 to house casing complete i/c screening of
10 1 Job 35,000 35,000
aggregate shuttering M.S bars size 1/2" i/d & 2 Nos clamps at right
angle 1/2" thick 6" wide
TOTAL FOR NON SCHEDULE ITEMS 936,800
TOTAL FOR SCHEDULE ITEMS 1,503,691
TOTAL FOR SUB HEAD ‐ 1 2,440,491
SUB HEAD ‐ II
SUPPLY AND INSTALLATION OF 1 CFS CAPACITY VERTICAL
TURBINE PUMP
NON‐SCHEDULE ITEMS
Supply ,installing,testing & commissioning of Deep Well water
lubricated multistage turbine pump of KSB/GRUNDFOS or
Equivalent (ISO 9001/9002) for lifting 1 cusec clean cold water
1 1 No 1,837,693 1,837,693
against 210' dynamic head capable of being properly lowered in
12" pump housing pipe. It will have 120' pump setting all as
approved by Engineer‐in‐charge
Providing/fixing base plate size 3' x 3' x 1.5" with centre hole 12"
i/d including drilling of foundation bells discharge head bolts
2 1 Each 25,000 25,000
water level measurement holes etc duly finished as required by
engineer
TOTAL FOR SUB HEAD ‐ II 1,862,693
SUB HEAD ‐ III
MOTOR RATING
NON‐SCHEDULE ITEMS
Supply and installation of 40 H.P electric motor Siemens or
equivalent (ISO‐9001/9002 Certified) A.C Vertical hallow shaft for
1 1 Each 1,225,128 1,225,128
cooled 3 phase, 3 wire, 380/440 volts, 50 cycles, 1450 RPM.All
complete as approved by Engineer‐in‐charge
Providing and errection of an automatic star delta panel incoming
100 Amp TP MCCB with combination push button, Ammeter,
2 1 No. 329,000 329,000
Voltmeter, Hour meter, Selector switch, Indication Lights & auto‐
interlock, make MG or equivalent, complete in all respect .
TOTAL FOR SUB HEAD ‐ III 1,554,128
COST ESTIMATE
CONSTRUCTION OF SESSION DIVISIONS (EAST & WEST) IN MAUVE AREA, SECTOR G‐11/4, ISLAMABAD
TUBE WELL
SUB HEAD ‐ IV
POWER WIRING
NON‐SCHEDULE ITEMS
Supply and erection of four core PVC insulated PVC sheathed
a) copper cable, 600/1000 volt
grade cable in prelaid MS conduits/PVC pipe / trenches etc.
SUB HEAD ‐ V
NON‐SCHEDULE ITEMS
Supply and Fixing imported Air relief valve nominal dia 2 " in cast
1 iron construction suitable for a maximum pressure of 16 bar 1 No. 12,056 12,056
complete in all respects
Providing & fixing of pressure gauge 4" i/d 0‐150 PSI Capacity
2 including guage cock,copper pipe ,flair nut and driliing of holes in 1 No. 9,500 9,500
pipe etc complete job
Providing and fixing of Ball/Gate Valve of approved make & size
3 for isolation & drain all complete as approved by the engineer. Size 2 No. 45,000 90,000
dia 4"
Providing cement concrete /bricks blocks to support bends with
5 ratio 1:2:4 i/c of screening washing of stone aggregate shuttering 1 Each 4,500 4,500
and curing etc ,complete in all respect
6 Installtion of bulk flow water meter 8" China. 1 Each 40,000 40,000
Construction of brick support for tube well delivery pipe complete
7 1 Job 4,500 4,500
in all respects
Construction of R.C.C support for tube well delivery pipe complete
8 1 Job 2,000 2,000
in all respects
TOTAL FOR SUB HEAD ‐ V 235,336
COST ESTIMATE
CONSTRUCTION OF SESSION DIVISIONS (EAST & WEST) IN MAUVE AREA, SECTOR G‐11/4, ISLAMABAD
TUBE WELL
SUB HEAD ‐ V1
PROVIDING & INSTALLATION OF CHLORINATOR
NON‐SCHEDULE ITEMS
1 Providing and fixing of Gas Chlorinator 1 Each 312,000 312,000
TOTAL FOR SUB HEAD ‐ VI 312,000
GRAND TOTAL 6,459,833
NOTE:
Quantities of pipe given in BOQ are only average quantities for
1.0 Cfs tube well .
Placement of Blind pipe and the strainer to be decided at site
after careful examination of hydrogeological condition and grain
size analysis of strata after drilling hence quantities of usable
strainer and blind pipes and depth of drill hole may vary from site
to site.
Composite Labour Cost
Item Description Qty Unit Total Cost(Rs.)
Rate (Rs.) (Rs.)
SUB HEAD ‐ V1II
SCHEDULE ITEM
TUBE WELL PUMP ROOM ‐ CIVIL WORK
Pacca Brick work in foundation and Plinth in cement mortar ratio
1 313 cft 206 64,410
1:6
2 Cement plaster 1:4 upto 20 ft height ‐ 1/2" inch thick 827 sft 19 15,687
Cement concrete plain including placing ,compacting, finishing and
curing complete (including screening and washing of stone
3 20 cft 232 4,637
aggregate) 2" thick cement concrete screed and machine pad
(3'x3'x6" high)
Reinforced cement concrete in roof
slab,beams,columns,lintels,girders and other structural members
4 9 cft 374 3,366
laid in situ or precast laid in position , or prestressed members cast
in situ ,complete in all respect.
Fabrication of mild steel reinforcement bar cage for RCC boared
piles ,including cutting,bending,laying in position ,welding and
5 fastening ,including cost of binding wires and labour charges for 1 Per Cwt 8,076 7,832
binding of steel reinforcement (als oinclude removal of rust from
bars)
6 Distempering ‐ 3 coats 917 sft 7 6,624
COST ESTIMATE
CONSTRUCTION OF SESSION DIVISIONS (EAST & WEST) IN MAUVE AREA, SECTOR G‐11/4, ISLAMABAD
TUBE WELL
Providing and fixing of windows consisting of MS box section
frame 2"x1‐1/2" leaves frame 1‐1/2" x 1" box section frame for
glazing 3/8"x3/8" using 16 SWG sheet 'U' shaped rubber supported
with 1"x1/8" MS flat for fixing 3/16" thick glass panes MS box
7 section 1/2" x 1/2" of 16 SWG for fixing 24 SWG wire gauze on 16 sft 507 8,106
outer side by means of 3/4" x1/8" MS flat screws including grill of
MS flat 1/2"x 1/8" or 1/4"x1/4" square bars wiht independent
frame of 1/2"x1/2" box section of 16 SWG i/c all CP fitting and
paninting 3 coats complete in all respect.
Making and fixing steel grated door complete with laocking
8 arrangments, angle iron frame 2"x 2"x 3/8"(50x50x10 mm) and 28 sft 944 26,421
3/4" (20mm) square bars 4" (100 mm) center to center.
Painting new surfaces‐ Preparing surface and Painting Doors &
9 Windows all types (including edges) i) prime coat and ii) each sft
subsequent coat of paint. ‐3 coats
Prime cost 106 sft 7.66 812
Each subsequent coat ‐ 3 coats 106 sft 12.34 1,308
TOTAL FOR SUB HEAD ‐ VIII 139,203
COST ESTIMATE
CONSTRUCTION OF SESSIONS DIVISION (EAST & WEST) IN MAUVE AREA, SECTOR G-11/4, ISLAMABAD
1 Wiring
e) As items no 1(a) but 3x4sqmm copper PVC from DB to first socket outlet . No 1955 5,500.00 10,752,500
f) As above but from socket to socket with 3x 4mm² . No 1955 3,250.00 6,353,750
g) As above but from socket to adjacent socket with 3x4mm2. No 3765 1,850.00 6,965,250
h) As above but Industrial socket 3x6mm2. No 22 7,500.00 165,000
Circular light with glass /ploy carbonate cover, metal base 1x7W LED E-27
a) No 532 3,500.00 1,862,000
lamps suitable for bath rooms as directed by the Engineer Incharge.
b) Up lighter with R7S Q1, 300W or equal approved by Engineer Incharge. No 50 12,000.00 600,000
Recessed in wall stainless steel body light 5w TC-S lamp or equal as directed
c) No 33 8,500.00 280,500
by the Engineer Incharge.
Hanging light with ITC-Tel 70W lamp or equal as directed by the Engineer
d) No 20 66,000.00 1,320,000
Incharge.
i) As above but 1'x4' as directed by the Engineer Incharge. No 395 14,000.00 5,530,000
j) Track light with 2no's spot light fixtures each with 50w, Hispot,GZ10 lamps No 11 6,996.00 76,956
Recessed down light LED 3/5W with driver as directed by Engineer
k) No 300 1,083.00 324,900
Incharge.
l) Recessed down light with 7/11W LED E27 lamp as directed by Engineer No 4050 2,300.00 9,315,000
In ground stainless steel body light asymmetrical with 1x70w halogen lamp
m) No 53 29,000.00 1,537,000
as directed by Engineer Incharge.
n) 70W as directed by the Engineer Incharge. No 0
p) Wall bracket light double sided with 70w, as directed by the Engineer No 71 12,500.00 887,500
q) Circular down light for stairs with 2x11W as directed by Engineer Incharge. No 202 4,167.00 841,734
Step light with 1x5w CFL (energy saver) E27 lamp as directed by Engineer
r) No 135 5,833.00 787,455
Incharge.
s) As above but Exit light with 1 X 8W warm flourscent Brass/Bronze body, No 585 11,000.00 6,435,000
External light fixture with 2 x 9w plc (CFL) lamp as directed by the Engineer
t) No 28 8,750.00 245,000
Incharge.
Spot light with 1x70W HPIT lamp and starting gear or equal as directed by
u) No 7 12,500.00 87,500
the Engineer Incharge.
RATE
S.NO. DESCRIPTIONS UNIT QTY Amount
(Rs.)
v) flood light LED light 120W, as directed by Engineer Incharge. No 89 20,833.00 1,854,137
Flood light 1000W HPIT lamp & starting gear, or as approved by Engineer
w) No 16 41,667.00 666,672
Incharge.
Weather & water proof spot light with 1x12W or as approved by the
x) No 20 10,000.00 200,000
Engineer Incharge.
fountain Weather & water proof IP 66 spot light with 1x12W or as approved
xi) No 8 4,500.00 36,000
by the Engineer Incharge.
xi) coove light (rod type) for bulk head approved by the Engineer Incharge. No 3500 3,250.00 11,375,000
xi) Miror light 1 x 24" approved by the Engineer Incharge. No 250 4,500.00 1,125,000
5 Fans
Supply & installation of ceiling fan 56 inch sweep, as approved by the
a) No 1863 7,500.00 13,972,500
Engineer Incharge .
b) Exhaust fan of 12 inch sweep, as approved by the Engineer Incharge. No 412 2,450.00 1,009,400
6 LV PANEL, DISTRIBUTION BOARDS
Supply & Installation, testing & commissioning of LV panal with (ACB 2500
or recomended by engineer incharge),MCC, Pump & Lifts Panels , made of
12/14 SWG and angular frame, ICI red oxide painted for rust protection
a)i then powder coated in furnace of approved colour with voltmeter & No 2 12,500,000.00 25,000,000
ammeter, selector switches R.Y.B indicators, wires PVC duct, imported
locks etc. complete in all respect as per Schematic drawing P.f.i, 1800
KVAR for main and MCC(Lifts) to be included.
b) As above but SLV Panels 14SWG as described in schematic drawings. No 30 209,880.00 6,296,400
As above but D.B 1st BLP-1, D.B BLP-2,D.B LP,3 D.B BLP-4 No 4 75,000.00 300,000
c) As above but D.B 2nd BLP-5, D.B BLP-6,D.B,BLP,7 D.B BLP-8 No 4 75,000.00 300,000
q) As above but D.B FiftRLP-1 FRLP-2, FRLP-3 & FRLP-4 No 4 75,000.00 300,000
r) As above but D.B Sixth ,LP-8,LP-9, LP-12, LP-13 LP-14 & LP-15. No 4 75,000.00 300,000
s) As above but D.B Seventh LP-16,LP-17, LP-18, LP-19 LP-20 No 4 75,000.00 300,000
Sub-Total (1 to 6) 564,867,678
7 TELEPHONE & COMPUTER NETWORKING SYSTEM
Furnishing & Carrying out Wiring with 2 pair Telephone Cables 0.6mm
tinned copper screened of PTCL/Universal Cables in apropriate size of PVC
a) Rm 35000 95.00 3,325,000
conduit as shown in diagram directly from TJB/PABX to telephone point/
outlets complete in all respect.
Supply & installation, testing & commissioning of TJB (1x20 pair) telephone
junction made from 16 SWG steel powder coated suitable for incoming/
b) outgoing Telephone cables, approved terminating strips Galvanized Nos 45 20,000.00 900,000
inclusive but not limited to connection termination of cables complete all
respects.
c) As above but MDF of 500 pairs Nos 8 100,000.00 800,000
d) Supply & installation, Testing & Commissioning Telephone Outlets RJ-11 for No 850 600.00 510,000
e) As item no.7(b) but 50 Pair. No 20 25,000.00 500,000
f) Same as above but 4 pair Cat 6 UTP cable Avaya/Schneider in PVC conduit RM 27000 145.00 3,915,000
g) Data outlets/ RJ-45 CAT6 Twin Data Socket of Avaya/Systimax/Norden U.K. No 380 700.00 266,000
h) Supply, installation, testing & commissioning of fiber core switch 12 Ports of No 1 1,250,000.00 1,250,000
o Floor box for Data sockets 1no. Twin RJ45 & 2no. RJ 11 of Schnieder or No 114 16,000.00 1,824,000
p) 19 inch DATA Floor Standing Panel with atleast 8 no.13A Sockets No 10 50,000.00 500,000
q) Supply & installation test & connection of 1x200pair 0.6mm dia. tinned RM 100 2,000.00 200,000
r) As above but 20 pairs RM 1800 600.00 1,080,000
s) Digital EPABX with 100lines+500 extensions, operator console, DID, trunk Job 2 4,500,000.00 9,000,000
t) Executive Digital telephone set No 100 15,000.00 1,500,000
u) Standard Digital telephone set No 720 10,000.00 7,200,000
Sub-Total (7) 32,770,000
8 FIRE ALARM SYSTEM
Supply & installation, testing & commissioning of addressable smoke
a) No 1329 8,100.00 10,764,900
detectors as directed by Engineer Incharge.
b) As above but break glass type manual call stations No 339 8,500.00 2,881,500
Supply, installation, testing & commissioning of 11KV triple pole 630A, VCB
Siemens/Areva make consumer panel with 95KV BIL, 20 KA short circuit
level, with IDMT relay KWH, KVAR digital type meter(TOD type) of Frer
make, cable glands of 3 Core 120mm² 15KV, XLPE/PVC cable, termination
b) kit, anti condensation heater, CT's 100/5/5 Amps, dry type, epoxy cast resin No 5 2,352,000.00 11,760,000
P.T's 11000/110V, 100VA as per Wapda/Iesco latest spec's & tested at
works by Wapda.
Total 819,491,983
COST ESTIMATE
E-05 Providing & Installing, testing 24x 100/1000 ports Switch with
2x 1G RJ45 uplink-ports, 4x 10G SFP+, 370W PoE budget,
basic L3 (static routing and RIP) Advance Routing protocol
RIP VRRP Should support openflow protocol 1.3v, with 3
years NBD warranty Each Equipment/item must be compatible
with Entire System/Other Equipment’s. Complete allied
accessories as per instructions and to the entire satisfaction of
the Engineer. (Cisco/Ruckus/Juniper or approved equivalent)
45 No 375000 Each. 16875000
E-22 Supply & fixing 20mm (3/4") dia PVC conduit with all
especial such as bends, sockets, Junction etc recessed in the
wall or column as required. 20000 88 P.MTR 1,760,000
S.NO ITEMS QTY RATE UNIT AMOUNT
E-24 Supply & fixing 25mm (1") dia PVC conduit with all especial
such as bends, sockets, Junction etc recessed in the wall or
column as required. 15000 125 P.MTR 1,875,000
E-2 Providing & fixing of ANTI-TERRORIST HEAVY DUTY Tyer Killer, No 3 372,500 1,117,500
Fabrication of the Tyer Killer shall be done locally, Blocking width
from 3m to 5m, Manual operation in case emergency, Max
loading weight: 80T, Surface treatment: Paint with reflective strip,
Specified color: Black and yellow, Moisture & temperature resistant,
Working environment: -40°C ~+70°C, complete in all respect as
approved by the Engineer Incharge as required.
E-3 Providing, Supplying, Fitting, Fixing, Installation of Locally Fabricated No 5 950,000 4,750,000
Under Vehicle Surveilance System with Waterproof camera and lights,
ANPR (Automatic License Plate Recognition) compatible, Driver image
camera compatible, Open architectures for easy integration with
existing CCTV system, Video can be transmitted on IP, wireless, fiber
optics, or standard coax, NVR for multichannel recording, LCD flat-
panel monitor, high-resolution undercarriage imaging., Decision
Response Time: 4-5 seconds, Applicable to variety of vehicles, wide
vision, Load bearing Weight: 50T, All cabling and power accessories
are standard with all systems, Easy, hose-down cleaning of camera
and LEDs complete in all respect as approved by engineer incharge.
E-4 Providing, Supplying, Fitting, Fixing, Installation of Cell phone Jammer No 4 485,000 1,940,000
System for Court Rooms, TX frequency, 868 - 880, 927 -960, 1810 ~
1880, 2100 - 2150, 2400 – 2500MHz, Cover interface standards: GSM,
UMTS, WCDMA, 4G LTE, WiFi, Total output power: EIRP 45W, Patch
Antenna - integrated of high Gain each band Jamming range: distance
40-50 M (the signal intensity must <-80dbm in the location),
Automatic power switching power supply:50/60Hz/AC 100 ~ 240V
to DC 24V, IR Remote Control capability, Operating temperature : -
10℃ ~ +60℃, Storage Temperature : -30℃ ~ +70℃, Humidity: 95%
non-condensing Complete in all respect as approved by Engineer
Incharge.
E-5 Providing, Supplying, Fitting, Fixing, Installation, energizing, No 2 480,000 960,000
commissioning and testing of Tripod Turnstile with controller and
combination of fingerprint & RFID reader, SUS304 stainless steel
housing, Bi-directional tripod turnstile with arm drop function, LED
pictograms for intuitive user experience and high throughput in both
directions, Speed of throughput/Passing Speed: RFID Maximum 30
People/minute & Fingerprint Maximum 25 People/minute, Passage
width(mm) 500 to 600, Communication Interface: TCP/IP with history
management system & programming as per requirements, Complete
in all respect as approved by Engineer Incharge. (TENSA-Turkey/TISO-
Ukraine)
E-7 Providing, Supplying, Fitting, Fixing, Installation of 65" LED for Court No 6 275,000 1,650,000
Rooms, Resolution 3840 x 2160 4K UHD resolution, Complete in all
respect as approved by Engineer Incharge. (Samsung/Sony/LG)
Total 48,167,500
COST ESTIMATE
RATE AMOUNT
S.NO. DESCRIPTION UNIT QTY
(Rs.) (Rs.)
(SH: 8:- ELEVATORS)
1.0 Passenger Lift (Gear Less Lift)
Supply, installation, testing,
commissioning and maintenance
(during defect lianility period) of brand
new passenger elevator having capacity
of 1600KG speed 1.5m/s Twelve stops,
twelve openings including car, hoisting
machinery, counter-weight, support
brackets, embedded parts, access
ladder, separator screen and trap door, No. 6 14,500,000 87,000,000
emergency landing devices with
equipment tagging etc complete in all
respects as per specifications and
drawings and approval of engineers.
(European Make & Region)
CONSTRUCTION OF SESSIONS DIVISION (EAST & WEST) IN MAUVE AREA, SECTOR G-11/4, ISLAMABAD
CONSTRUCTION OF SESSIONS DIVISION (EAST & WEST) IN MAUVE AREA SECTOR G-11/4, ISLAMABAD
AIR CONDITIONING (VRF SYSTEM)
GROUND FLOOR
RATE AMOUNT
S.NO. DESCRIPTION UNIT QTY
(Rs.) (Rs.)
All heating, ventilation & air conditioning
works shall be completed, tested and
commissioned as per drawings,
specifications and as per instruction of
Consultant
Equipment
CONSTRUCTION OF SESSIONS DIVISION (EAST & WEST) IN MAUVE AREA SECTOR G-11/4, ISLAMABAD
AIR CONDITIONING (VRF SYSTEM)
GROUND FLOOR
RATE AMOUNT
S.NO. DESCRIPTION UNIT QTY
(Rs.) (Rs.)
CONSTRUCTION OF SESSIONS DIVISION (EAST & WEST) IN MAUVE AREA SECTOR G-11/4, ISLAMABAD
AIR CONDITIONING (VRF SYSTEM)
GROUND FLOOR
RATE AMOUNT
S.NO. DESCRIPTION UNIT QTY
(Rs.) (Rs.)
Supply and installation of UPVC B Class
pipe for condensate drain water with
Black PVC wrapping tape 3" wide for
insulation of drain pipe with 50% overlap
or as directed by the Engineer, including
all supports, hangers, fittings,clamps etc
complete in all respect as specified in
drawings and specifications. This
includes the drilling, chipping in wall to
conceal and to route the drain pipe to
nearest drain point.All condensate drain
2.2 piping shall be in the minimum slope of RFT 298 250 74,500
1% in the direction of flow and shall be
connecting with air conditioners with
cleanable air seal traps, and where
advised by the consultant, approved
quality flexible pipes connection with
indoor unit and drain line shall be
properly clamped and shall be
terminated to the nearest drain points
with proper approved quality connections
CONSTRUCTION OF SESSIONS DIVISION (EAST & WEST) IN MAUVE AREA SECTOR G-11/4, ISLAMABAD
AIR CONDITIONING (VRF SYSTEM)
GROUND FLOOR
RATE AMOUNT
S.NO. DESCRIPTION UNIT QTY
(Rs.) (Rs.)
Operation & Maintenance of the
entire VRF system installed by the
contractor, the contractor shall operate
and maintain the entire VRF system
with his own manpower inclusive of all
consumables, parts, material, etc.
except electric power for operation of
VRF system shall be operated &
3.3
maintained 12 hour/day, 07 days/week
with the deployment of 01 supervisor
and 01 A/C mechanic for a period of
one year after the issuance of
completion certificate complete in all
respects as per specifications and
drawings and as approved by the
Consultant
4.0 Civil works
CONSTRUCTION OF SESSIONS DIVISION (EAST & WEST) IN MAUVE AREA SECTOR G-11/4, ISLAMABAD
Equipment
CONSTRUCTION OF SESSIONS DIVISION (EAST & WEST) IN MAUVE AREA SECTOR G-11/4, ISLAMABAD
CONSTRUCTION OF SESSIONS DIVISION (EAST & WEST) IN MAUVE AREA SECTOR G-11/4, ISLAMABAD
Equipment
CONSTRUCTION OF SESSIONS DIVISION (EAST & WEST) IN MAUVE AREA SECTOR G-11/4, ISLAMABAD
Supply,Installation,testing,commissioning,adjusting and
balancing of MCC and control equipment.MCC shall be
made with heavy steel casing of approved gauge and size
and shall be further polyester powder coated having all
types of fittings and fixtures like circuit breakers, overload
3.1 relays, magnetic contactors, starters, CTs, volt and amp Nos. 1 600,000 600,000
meters, indicating lamps, bus bars, etc. electric
power/control and earth wiring, all fittings and fixtures shall
be approved by the consultant prior to purchase, complete
in all respects as per drawings specifications and as
approved by the Consultant.
All other electrical works including power and control
wiring, conduits, cable trays,terminal connections etc,
3.2 Job 1 1,600,000 1,600,000
complete in all respect as per specifications and as per
approved by consultant
4.0 Civil works
Including foundations,pads, opening in walls and others (if
4.1 Job 1 90,000 90,000
applicable).
CONSTRUCTION OF SESSIONS DIVISION (EAST & WEST) IN MAUVE AREA SECTOR G-11/4, ISLAMABAD
Equipment
CONSTRUCTION OF SESSIONS DIVISION (EAST & WEST) IN MAUVE AREA SECTOR G-11/4, ISLAMABAD
Supply,Installation,testing,commissioning,adjusting and
balancing of MCC and control equipment.MCC shall be
made with heavy steel casing of approved gauge and size
and shall be further polyester powder coated having all types
of fittings and fixtures like circuit breakers, overload relays,
3.1 Nos. 1 600,000 600,000
magnetic contactors, starters, CTs, volt and amp meters,
indicating lamps, bus bars, etc. electric power/control and
earth wiring, all fittings and fixtures shall be approved by the
consultant prior to purchase, complete in all respects as per
drawings specifications and as approved by the Consultant.
All other electrical works including power and control wiring,
conduits, cable trays,terminal connections etc, complete in
3.2 Job 1 1,800,000 1,800,000
all respect as per specifications and as per approved by
consultant
4.0 Civil works
Including foundations,pads, opening in walls and others (if
4.1 Job 1 950,000 950,000
applicable).
CONSTRUCTION OF SESSIONS DIVISION (EAST & WEST) IN MAUVE AREA SECTOR G-11/4, ISLAMABAD
Equipment
CONSTRUCTION OF SESSIONS DIVISION (EAST & WEST) IN MAUVE AREA SECTOR G-11/4, ISLAMABAD
Supply,Installation,testing,commissioning,adjusting and
balancing of MCC and control equipment.MCC shall be
made with heavy steel casing of approved gauge and size
and shall be further polyester powder coated having all
types of fittings and fixtures like circuit breakers, overload
3.1 relays, magnetic contactors, starters, CTs, volt and amp Nos. 1 600,000 600,000
meters, indicating lamps, bus bars, etc. electric
power/control and earth wiring, all fittings and fixtures
shall be approved by the consultant prior to purchase,
complete in all respects as per drawings specifications
and as approved by the Consultant.
All other electrical works including power and control
wiring, conduits, cable trays,terminal connections etc,
3.2 Job 1 1,600,000 1,600,000
complete in all respect as per specifications and as per
approved by consultant
4.0 Civil works
Including foundations,pads, opening in walls and others (if
4.1 Job 1 90,000 90,000
applicable).
CONSTRUCTION OF SESSIONS DIVISION (EAST & WEST) IN MAUVE AREA SECTOR G-11/4, ISLAMABAD
Equipment
CONSTRUCTION OF SESSIONS DIVISION (EAST & WEST) IN MAUVE AREA SECTOR G-11/4, ISLAMABAD
Supply,Installation,testing,commissioning,adjusting and
balancing of MCC and control equipment.MCC shall be
made with heavy steel casing of approved gauge and
size and shall be further polyester powder coated
having all types of fittings and fixtures like circuit
3.1 breakers, overload relays, magnetic contactors, starters, Nos. 1 600,000 600,000
CTs, volt and amp meters, indicating lamps, bus bars,
etc. electric power/control and earth wiring, all fittings
and fixtures shall be approved by the consultant prior to
purchase, complete in all respects as per drawings
specifications and as approved by the Consultant.
All other electrical works including power and control
wiring, conduits, cable trays,terminal connections etc,
3.2 Job 1 1,600,000 1,600,000
complete in all respect as per specifications and as per
approved by consultant
4.0 Civil works
Including foundations,pads, opening in walls and others
4.1 Job 1 90,000 90,000
(if applicable).
CONSTRUCTION OF SESSIONS DIVISION (EAST & WEST) IN MAUVE AREA SECTOR G-11/4, ISLAMABAD
Equipment
CONSTRUCTION OF SESSIONS DIVISION (EAST & WEST) IN MAUVE AREA SECTOR G-11/4, ISLAMABAD
Supply,Installation,testing,commissioning,adjusting and
balancing of MCC and control equipment.MCC shall be made
with heavy steel casing of approved gauge and size and shall
be further polyester powder coated having all types of fittings
and fixtures like circuit breakers, overload relays, magnetic
3.1 Nos. 1 600,000 600,000
contactors, starters, CTs, volt and amp meters, indicating
lamps, bus bars, etc. electric power/control and earth wiring, all
fittings and fixtures shall be approved by the consultant prior to
purchase, complete in all respects as per drawings
specifications and as approved by the Consultant.
CONSTRUCTION OF SESSIONS DIVISION (EAST & WEST) IN MAUVE AREA SECTOR G-11/4, ISLAMABAD
Equipment
CONSTRUCTION OF SESSIONS DIVISION (EAST & WEST) IN MAUVE AREA SECTOR G-11/4, ISLAMABAD
Supply,Installation,testing,commissioning,adjusting and
balancing of MCC and control equipment.MCC shall be
made with heavy steel casing of approved gauge and size
and shall be further polyester powder coated having all
types of fittings and fixtures like circuit breakers, overload
3.1 relays, magnetic contactors, starters, CTs, volt and amp Nos. 1 600,000 600,000
meters, indicating lamps, bus bars, etc. electric
power/control and earth wiring, all fittings and fixtures shall
be approved by the consultant prior to purchase, complete
in all respects as per drawings specifications and as
approved by the Consultant.
All other electrical works including power and control
wiring, conduits, cable trays,terminal connections etc,
3.2 Job 1 1,600,000 1,600,000
complete in all respect as per specifications and as per
approved by consultant
4.0 Civil works
Including foundations,pads, opening in walls and others (if
4.1 Job 1 90,000 90,000
applicable).
CONSTRUCTION OF SESSIONS DIVISION (EAST & WEST) IN MAUVE AREA SECTOR G-11/4, ISLAMABAD
Equipment
CONSTRUCTION OF SESSIONS DIVISION (EAST & WEST) IN MAUVE AREA SECTOR G-11/4, ISLAMABAD
CONSTRUCTION OF SESSION DIVISIONS (EAST & WEST) IN MAUVE AREA, SECTOR G-11/4, ISLAMABAD
SUMMARY OF COST
CONSTRUCTION OF SESSION DIVISIONS (EAST & WEST) IN MAUVE AREA, SECTOR G-11/4, ISLAMABAD
Basements (B-1,B-2)
RATE AMOUNT
S.NO. DESCRIPTIONS QTY UNIT
(Rs.) (Rs.)
FIRE FIGHTING SYSTEM
1) M.S. Fire Pipe
Providing, laying, jointing and testing black steel
seamless piping schedule 40 for fire fighting as per
BSS 1387 including welded fittings, hardware
clamps, welding, jointing material, protective
painting coating excavation, taging, backfilling,
compaction and bedding etc. complete in all
respect as per drawings and specification and to
the approval of the Engineer.
Total 43,327,362
COST ESTIMATE
CONSTRUCTION OF SESSION DIVISIONS (EAST & WEST) IN MAUVE AREA, SECTOR G-11/4, ISLAMABAD
Ground Floor
RATE AMOUNT
S.NO. DESCRIPTIONS QTY UNIT
(Rs.) (Rs.)
FIRE FIGHTING SYSTEM
1) M.S. Fire Pipe
3) Fire Sprinkler
Supply, installation and commission of fire
sprinkler including all accessories complete in all
respect as shown on drawings / specifications.
II Providing and fixing Side Wall Chrome Sprinkler 84 Nos. 1,459 122,556
4) zone control valves
Supply, installation and commission zone control
valves with all accessories and material as
specified complete in all respect as shown on
drawings / specifications.
CONSTRUCTION OF SESSION DIVISIONS (EAST & WEST) IN MAUVE AREA, SECTOR G-11/4, ISLAMABAD
1st Floor
RATE AMOUNT
S.NO. DESCRIPTIONS QTY UNIT
(Rs.) (Rs.)
FIRE FIGHTING SYSTEM
1) M.S. Fire Pipe
CONSTRUCTION OF SESSION DIVISIONS (EAST & WEST) IN MAUVE AREA, SECTOR G-11/4, ISLAMABAD
2nd Floor
RATE AMOUNT
S.NO. DESCRIPTIONS QTY UNIT
(Rs.) (Rs.)
C FIRE FIGHTING SYSTEM
1) M.S. Fire Pipe
CONSTRUCTION OF SESSION DIVISIONS (EAST & WEST) IN MAUVE AREA, SECTOR G-11/4, ISLAMABAD
3rd Floor
RATE AMOUNT
S.NO. DESCRIPTIONS QTY UNIT
(Rs.) (Rs.)
C FIRE FIGHTING SYSTEM
1) M.S. Fire Pipe
I
1" Ø 3123 RFT 350 1,093,050
II
1-1/4" Ø 367 RFT 524 192,488
III
1-1/2" Ø 509 RFT 596 303,384
IV
2" Ø 535 RFT 710 380,107
V
2-1/2" Ø 1269 RFT 1,109 1,407,549
2) Fire Hose Cabinet
3) Fire Sprinkler
CONSTRUCTION OF SESSION DIVISIONS (EAST & WEST) IN MAUVE AREA, SECTOR G-11/4, ISLAMABAD
4th Floor
RATE AMOUNT
S.NO. DESCRIPTIONS QTY UNIT
(Rs.) (Rs.)
I
1" Ø 3200 RFT 350 1,120,000
II
1-1/4" Ø 267 RFT 524 140,039
III
1-1/2" Ø 459 RFT 596 273,582
IV
2" Ø 576 RFT 710 409,236
V
2-1/2" Ø 1287 RFT 1,109 1,427,515
2) Fire Hose Cabinet
7) Fire Extinguisher
CONSTRUCTION OF SESSION DIVISIONS (EAST & WEST) IN MAUVE AREA, SECTOR G-11/4, ISLAMABAD
5th Floor
RATE AMOUNT
S.NO. DESCRIPTIONS QTY UNIT
(Rs.) (Rs.)
C
FIRE FIGHTING SYSTEM
I
1" Ø 2987 RFT 350 1,045,450
II
1-1/4" Ø 402 RFT 524 210,845
III
1-1/2" Ø 541 RFT 596 322,458
IV
2" Ø 535 RFT 710 380,107
V
2-1/2" Ø 1223 RFT 1,109 1,356,527
2) Fire Hose Cabinet
3) Fire Sprinkler
7) Fire Extinguisher
CONSTRUCTION OF SESSION DIVISIONS (EAST & WEST) IN MAUVE AREA, SECTOR G-11/4, ISLAMABAD
6th Floor
RATE AMOUNT
S.NO. DESCRIPTIONS QTY UNIT
(Rs.) (Rs.)
C FIRE FIGHTING SYSTEM
1) M.S. Fire Pipe
I
1" Ø 2987 RFT 350 1,045,450
II
1-1/4" Ø 402 RFT 524 210,845
III
1-1/2" Ø 541 RFT 596 322,458
IV
2" Ø 535 RFT 710 380,107
V
2-1/2" Ø 1223 RFT 1,109 1,356,527
2) Fire Hose Cabinet
3) Fire Sprinkler
CONSTRUCTION OF SESSION DIVISIONS (EAST & WEST) IN MAUVE AREA, SECTOR G-11/4, ISLAMABAD
7th Floor
RATE AMOUNT
S.NO. DESCRIPTIONS QTY UNIT
(Rs.) (Rs.)
C FIRE FIGHTING SYSTEM
1) M.S. Fire Pipe
I
1" Ø 3214 RFT 350 1,124,900
II
1-1/4" Ø 334 RFT 524 175,180
III
1-1/2" Ø 510 RFT 596 303,980
IV
2" Ø 557 RFT 710 395,737
V
2-1/2" Ø 1205 RFT 1,109 1,336,562
7) Fire Extinguisher
CONSTRUCTION OF SESSION DIVISIONS (EAST & WEST) IN MAUVE AREA, SECTOR G-11/4, ISLAMABAD
8th Floor
RATE AMOUNT
S.NO. DESCRIPTIONS QTY UNIT
(Rs.) (Rs.)
C FIRE FIGHTING SYSTEM
1) M.S. Fire Pipe
I
1" Ø 3195 RFT 350 1,118,250
II
1-1/4" Ø 389 RFT 524 204,027
III
1-1/2" Ø 576 RFT 596 343,319
IV
2" Ø 513 RFT 710 364,476
V
2-1/2" Ø 1289 RFT 1,109 1,429,733
2) Fire Hose Cabinet
7) Fire Extinguisher