Unbalanced Faults Analysis in Grid - Connected PV System - Listhianne
Unbalanced Faults Analysis in Grid - Connected PV System - Listhianne
occurs when the voltage level of the DC side is lower than array modeling, but also because of its good compromise
the required DC input value. When fault happens in the between simplicity and accuracy [3].
inverter connected energy system, the output current of the
inverter becomes irregular in shape.
Hence, this paper aims to analyze the effects of fault
penetration inside the grid–connected PV system. The grid–
connected PV system consists of three stages of voltage: first,
the 415V then the 11kV and lastly the 33kV. Various fault
condition is applied to the first stage of the grid– network and
the implication to this will be observed at the third stage that
is the 33kV part. To conduct this, a simulation was performed
using MATLAB®/Simulink software with PV system act as Fig. 3: Photovoltaic equivalent circuit
the main source that ends at the 33kV load. The grid-connected
PV system proposed in this paper is built using solar cells ⎡ ⎛ V + Rs I ⎞ ⎤
connected together to become a module, and a few of modules I = I ph − I o ⎢exp⎜⎜ ⎟⎟ − 1⎥ (1)
is then arranged together as array. Since solar cell block is ⎣ ⎝ ( N s kTa ) / q ⎠ ⎦
located inside a different section in the MATLAB®/Simulink
library, converters are used to change the unit-less voltage and Where, Iph is the photocurrent, Io is the diode saturation
current signals into something of use to the proposed grid- current,(NskT)/q is a thermal voltage of the array, Vt,
network system which consists of Ns that represents number of cells in
series, q=1.6 x10 -19 C stands for the electron charge, k
meanwhile is the Boltzmann’s constant, 1.38 x 10-23 J/K, a
represents the diode ideal factor, Rs and Rp are the
series and parallel resistance respectively. The
photocurrent, Iph influenced by solar irradiance and
temperature [3-4] can be calculated as in Equation (2):
3
⎛T ⎞ ⎡ qE ⎛ 1 1 ⎞⎤
I o = I rs ⎜⎜ ⎟⎟ exp ⎢ g ⎜⎜ − ⎟⎟⎥ (3)
⎝ Tr ⎠ ⎣ ak ⎝ Tr T ⎠⎦
Fig. 2. Solar cell symbol Where, Irs is the reverse saturation current at a reference
temperature and irradiance, T r and T are the 298K reference
Modelling of PV cell engages with the production of I– temperature, and the operating temperature in K
V and P–V characteristics curves with the output depends respectively, E g = 1.13 eV is the band energy gap of the
on (1-4). The parallel–series connection of the solar cells is
semiconductor used in the cell. Reverse saturation current Irs
based on manufacturer’s characteristics with other
can be expressed as in Equation (4)
parameters values have been displayed in the
manufacturer’s datasheet as in Table 1. With the
improvement of MATLAB® software, this solar cell need I scr
I rs = (4)
not to be designed from few functions as the 2009 version ⎡ ⎛ Voc q ⎞⎤
of MATLAB® now contains an already–masked solar cell ⎢exp⎜⎜ ⎟⎟⎥ − 1
block which implement all the parameters represented in ⎣ ⎝ N s kTa ⎠⎦
Equation (1) based on the single-diode PV cell equivalent
circuit in Fig. 3. The single-diode model is considered in With Voc represents the PV cell open–circuit voltage.
this study not only because it has been used widely in PV
361
2014 IEEE International Conference Power & Energy (PECON)
C. DC/AC Inverter
TABLE I : BBOXX 250W SOLAR MODULE DATASHEET
Inverter is a fixed power converter that converts DC output
Parameters Value voltage of PV system into AC output voltage. It is the essential
part in grid–connected PV system as inverter will convert DC
Open – circuit voltage (Voc) 42.3 V
voltage obtained from PV array to AC voltage required for
Short – circuit current (Isc) 7.95A
Maximum power voltage (Vmp) 34.5V distribution to network system and consumer. Inverter may be
Maximum power current(Imp) 7.10A
classified into few groups based on the phase, the methods of
Maximum power (Pmax) 250W commutation and also types of PV system. As this paper
Temperature coefficient of Isc (
implement a grid–connected PV system, a three–phase grid-
sc) 0.05%/°C
inverter is employed. This three– phase inverter is responsible
Temperature coefficient of Voc ( oc) -0.34%/°C
to output a 415V and synchronize the PV system with the grid.
It shows that the 415V is directed from a PV system connected
B. DC/DC Booster to a consumer’s network. Fig. 5 shows the connection of a
An increase of solar irradiance will increase PV array basic three–phase inverter with the use of Pulse Width
output current while an increase of module temperature will Modulation, PWM technique as the pulse controller.PWM
decrease PV array output voltage. Thus, PV array output technique is used at each transistor to control the AC output
power greatly depends on solar irradiance and module voltage by altering the ON and OFF periods of the
temperature parameters. As these two environmental semiconductors; in other words, it generates switching pulse at
parameters could change drastically at any time with the the gate terminals of each transistor [5]. Inverter benefits from
presence of cloud, rain, shadow etc., it is difficult to obtain a the implementation of PWM at each transistor as they remove
constant and high voltage output used for direct–current the lower order harmonics. Meanwhile, six Insulated Gate
(DC) inversion. Hence, a booster is employed for this system Bipolar Transistors, IGBTs are used to in order to obtain a
to regulate and convert the low DC voltage to high DC 415V and to produce a phase voltage. The application of IGBT
voltage fitting the needs to gain desired AC voltage from in the inverter provides a better voltage–controlled, high
switching speed as well as low ON–state losses [6].The six
inverter later. From Fig. 4, a booster consists of inductor and
transistors are controlled by six gate signals named D1, D2,
capacitor plus MOSFET that acts as the switch with resistor
D3, D4, D5 and D6 respectively. The inverter here has six
to represent constant load. switching modes in one line frequency [7] with 120°
When the switch is ON, the inductor begins to charge conduction mode for each pulse. The upper transistors have
taking energy from input voltage, Vin. The diode is OFF and phase–shift of 120° from each other [8] so does the lower
the output voltage, Vo is being provided entirely by the transistors with 180° difference for the lower transistor with the
capacitor having a delay caused by the capacitor as it upper transistor. For the ωt = 0 s, D1 and D6 conduct or turn
discharges through the resistor. When the switch turns OFF, ON leaving D4 and D3 turned OFF. At this time D5 and D2
the inductor’s magnetic field begins to breakdown. The perform PWM. For ωt = 3.33 ms, D1 still conduct due to the
field generates current and reverses the polarity of the 120° conduction, D2 turn ON and D3 and D6 perform the
inductor’s voltage (– to +). This voltage then combine with PWM. For ωt = 6.66 ms, D2 still ON, D3 conduct and D1
input voltage, Vin hence produce a higher voltage than the along with D4 perform the PWM. As for ωt = 0.01 s, D4
input source alone. Thanks to the fly–back voltage by conduct in the opposite direction, D3 conduct still as the third
inductor, the output has been boosted above the input phase perform PWM. This process continues until all the
voltage. This voltage forward–biased the diode, allows switch conduct according to its trigger time. All the conduction
current to flow onto the capacitor to recharge it. Through process is the same except that they are shifted by 120°.
the duty cycle implemented into the switch alters the time
that the inductor can charge. This then sets the output
voltage. Since the transistor is a low side switch, an n-
channel’s MOSFET is a good choice because it provides
speed needed to charge and discharge the gate quickly.
362
2014 IEEE International Conference Power & Energy (PECON)
D. Transformer
The operation of grid–connected PV system starts from
PV array until the transmission lines of 33 kV. It is crucial
to ensure that the output voltage that to be transferred to the
grid is high enough to enable the system to be synchronized
to the grid. This high voltage needed is depend on the
capability of the PV array to produce a suitable DC output
voltage with the help of boost converter or booster to
increase DC voltage to an appropriate level with the
involvement of inverter in converting to the AC voltage and Fig. 7: Faults location and voltage measurements
a transformer in the end to gain a desired high voltage and
also for isolation purpose. III. SIMULATION RESULTS OF PV
As the grid–connected PV system modelled in this
The PV array model was simulated with reference to the
paper imitates the real network system outside, a 415 V manufacturer’s datasheet where the detail of parameters are
cannot directly being step–up to 33 kV. Hence, two listed in Table I. The I–V and P–V characteristics curves of the
transformers are used for this mean. Three–phase respective PV array are obtained from the simulation test are
transformers are required to step–up voltages in the two shown in Fig. 8 and Fig. 9 with three different solar irradiance
stages of power transmission that is the 11 kV stage and the (400 W/m2, 600 W/m2 and 1000 W/m2 ) to validate the
33 kV. The primary and secondary windings of the developed PV array model to give the same characteristics
transformer may be connected in either way preferable to curves as what the manufacturer’s datasheet provided. By
obtain the desired output [8]. Fig. 6 shows ways to comparing I–V curve and P–V curve of the simulation to the
configure three–phase transformer in power system. Several manufacturer’s, it seems that both simulation curves give
studies in [10] [11] shows the effect of transformer similar curves as the manufacturer’s.
configuration windings with respect to the propagation of
faulted voltage.
(a)
(b)
Fig. 6: Three – phase transformer configurations
E. Faults
Faults can be categorized into two types: three–phase
balanced faults and unbalanced faults. Three–phase balanced
faults is defined as the instantaneous short circuit across the
three–phases [9]. Though it seldom occurs, it is the most
severe fault ever. Unbalanced fault on the other hand consist
of single line–to ground fault, double line–to–ground fault and
double line fault. The types itself already define what (c)
unbalanced faults mean. Hypothesis test have been done in Fig. 8: I-V curve characteristics (Y-axis = current [A], X-axis = voltage [V])
[12] to classify fault types from monitored data. To see the with solar irradiance of (a) 400 W/m2 (b) 600 W/m2 (c) 1000 W/m2
consequences of faults penetration in the system, three of
these unbalanced faults are implemented respectively at Bus
1and observations are made at Bus 3 as shown in Fig. 7.
363
2014 IEEE International Conference Power & Energy (PECON)
TABLE II
PHASE VOLTAGE DURING SINGLE LINE – TO–GROUND FAULT
CONDITION
TABLE III
PHASE VOLTAGE DURING DOUBLE LINE – TO – GROUND
FAULT CONDITION
364
2014 IEEE International Conference Power & Energy (PECON)
V. CONCLUSION ACKNOWLEDGMENT
This paper implements the utilization of photovoltaic The authors would like to thank Universiti Teknologi
(PV) array as the main source of the grid system. Along MARA cawangan Johor for providing the financial assistant.
with DC/DC booster and DC/AC inverter plus two stepped–
up transformer, the system act as the complete grid– REFERENCES
connected PV system before the real objective of this paper [1] Abbas Haijing, Zulkeflee Khalidin, “Fault Condiition Analysis in a Grid
made to happen. Fault analysis are being analyzed to show Connected PV Energy System”, International Conference on Circuits,
System and Simulation”, IPCSIT Press Singapore, vol. 7, 2011.J.
whether fault will create a severe disturbance to the system.
[2] N. Pandiarajan and Ranganath Muthu, “ Mathematical Modeling of
With the use of 2009 MATLAB®/Simulink, at the Photovoltaic Module with Simulink”, International Conference of
beginning, the design of PV array has been tested with Electrical Energy Systems (ICEES), Jan 2011.
reference to manufacturer’s datasheet and their I–V and P-V [3] Atiqah Hamizah Mohd Nordin, Ahmad Maliki Omar, “Modeling and
characteristics curves and it proved to be appropriate and Simulation of Photovoltaic (PV) Array and Maximum Power Point
correct in terms of getting the right characteristic curves. On Tracker (MPPT) for Grid – Connected PV System”, 3rd International
Symposium & Exhibition in Sustainable Energy & Envronment, 2011,
contrary, the use of DC/DC booster in the system helped so Melaka, Malaysia.
much as, through a MOSFET, a constant DC voltage needed [4] Vijay K. Sood, Prabhpreet Bhalla, “EMPT Model of Grid Connected PV
later can be produced plus inductor in the booster helped out System”, International Conference on Power Systems Transients (IPST),
in boosting the voltage value. Not to forget, the conversion July 2013, Vancouver, Canada, in press.
of voltage from DC–AC also has been designed and studied. [5] Ahmed S. Khalifa, Ehab F. El – Saadany, “ Control of Three Phse Grid
Connected Photovoltaic Power Systems”, IEEE, 2010.
Using PWM technique implement in a three–phase inverter,
[6] J. Michael Jacob, “Power electronics: Principles and applications”,
an AC voltage is produced before step–up the voltage to 11 Thomas Learning Inc., Delmar, 2002.
kV and 33 kV with two step–up transformers. Lastly, fault [7] H. C. Seo, C. H. Kim, Y. M. Yoon, C. S. Jung, “Dynamics of grid –
analysis has been done and the results have been studied. connected photovoltaic system at fault conditions”, Manpower
Unbalanced faults were being tested in this paper and it can Development Program for Energy & Resources, Ministry of Knowledge
be decided that double line to ground fault gives a more and Economy, IEEE, 2009.
severe effects on the grid–connected PV system than single [8] V. Jagannathan, “Power Electronics: Devices and Circuits”, 2nd
ed.,Asoke K. Ghosh, PHI Learning Private Limited, Connaught Circus,
line–to–ground fault. It can be deduced as well that faults New Delhi, Novemeber 2010.
existence in the system dipped the voltage results in a [9] H. Saadat, “Power System Analysis”, 2nd ed, McGrawHill, 2004.
low voltage during fault condition and in a real life [10] R. F. Mustapa, M. S. Serwan, N. Hamzah, and Z. Zakaria, "The
situation, this is may contribute to equipment shutdown, propagation of voltage sag through transformer connections in a power
damage small electronic devices due to high current and system network," presented at Power Engineering and Optimization
Conference (PEOCO), 2010 4th International, 2010.
may shorten life span of any system.
[11] R. F. Mustapa, M. S. Serwan, N. Hamzah, and Z. Zakaria, "Effect of
impedances line length to voltage sag propagation," presented at Power
and Energy (PECon), 2010 IEEE International Conference on.
[12] R. F. Mustapa, M. S. Serwan, N. Hamzah, and Z. Zakaria, "Hypothesis
testing for fault analysis and the propagation of faulted voltage through
transformer connections," presented at Research and Development
(SCOReD), 2011 IEEE Student Conference on, 2011.
365