PROJECT NAME: SINGLE STOREY RESIDENTIAL HOUSE

LOCATION: PUROK 3 BALSA, BRGY. TITUNOD, KOLAMBUGAN, LANAO DEL NORTE


OWNER: SPS. LOI DELANO & LESLIE OBLENDA

BILL OF MATERIALS

A. STRUCTURAL

1.) 2 x 2 x 8 wood 5 bundles 190 950


2x3x8 7 bundles 260 1820
2x4x8 6 Lengths 110 660
Marine Plywood 1/4" 16 sheets 270 4320
Amakan 22 sheets 290 6380
C.W.N #4 8 kilos 75 600
C.W.N #3 5 kilos 50 250
Hardinails 10 kilos 45 450
Corrugated G.I Sheets 14 sheets 450 6300
ridge roll 7 lengths 350 2450
Umbrella Nails 4 kilos 98 392
12mm dia def bar 18 lengths 235 4230
10mm dia def bar 30 lengths 210 6300
cement 40 bags 235 9400
gravel 5 cu.m 1000 5000
sand 10 cu.m 800 8000
CHB 4" 300 pcs 12 3600
SUB TOTAL 61,102.00
30% Labor 18,330.60
SUB TOTAL 79,432.60

B. PLUMBING PVC Sanitary Pipe 4" Series 1000 8 lengths 758.5 6068
PVC Sanitary Elbow 4 x 90 5 unit 96 480
PVC Sanitary Pipe 2" Series 1000 6 lengths 333.5 2001
PVC Sanitary Elbow 2 x 90 7 units 64 448
PVC Sanitary Tee 2 x 2 4 units 80 320
PVC Wye 3 unit 67 201
PVC Pipe 1" 6 units 160 960
PVC Pipe 1/2" 6 lengths 105 630
PVC Elbow 1/2" x 90 10 units 15 150
Female adpator 6 units 23 138
Ball Valve 1/2" 2 units 50 100
Clean Out 4" 2 unit 99.5 199
Floor Drain 4" 2 unit 120 240
Faucet 3 sets 60 180
Teflon 3/4" 3 roll 28.5 85.5
Water Closet and Lavatory with fittings 2 set 3890 7780
Kitchen Sink 1 unit 700 700
PVC Door 2 sets 950 1900

SUB TOTAL 22,580.50


30% Labor 6,774.15
SUB TOTAL 29,354.65
C. ELECTRICAL
Panel Board 1 unit 480 480
30 Amp Circuit Breaker 1 unit 235 235
20 amp circuit breaker 1 unit 485 485
10 amp circuit breaker 1 unit 330 330
16 mm THHN Wire 15 meters 24 360
14 mm THW Wire 10 meters 29 290
12 mm THHN Wire 28 meters 33 924
Junction Box with cover 10 pcs 23 230
Receptacle 7 units 15 105
1 Gang Switch 6 units 15 90
2 Gang Convenience Outlet 6 units 30 180
Electrical Tape 4 pcs 30 120
SUB TOTAL 3,829.00
30% Labor 1,148.70
SUB TOTAL 4,978
D. ARHITECTURAL & PAINT WORKS
Varnish Paint 6 Liters 370 2,220
Lacquer Thinner 2 Liters 312 624
Paint Tinner 2 Liters 280 560
Paint Brush 3" 2 pcs 38 76
Paint Brush 4" 2 pcs 44 88
Red lead Oxide paint 2 Liters 355 710
SUB TOTAL 4,278
30% Labor 1283.4
SUB TOTAL 5,561
GRAND TOTAL 118,326.25