RJS 00008
RJS 00008
Speaker Biographies
Note Paper
Madison, Wisconsin
PHILIP M. BENNETI'
Registered Architect
Professor and Program Director
Department of Engineering Professional Development
University of Wisconsin-Madison
Mr. Bennett began his college education with one and one-half years of study in the fields of
Forestry and Conservation. This was followed by a Bachelor of Architecture degree from the
Illinois Institute of Technology. He received his Master of Environmental Design degree from the
University of Wisconsin-Madison. Mr. Bennett has also studied Landscape Architecture at the
University of Wisconsin-Milwaukee and Madison, and has done some work in Form Perception
toward a possible Ph.D. degree in Environmental Design. Postgraduate studies and research
have also been undertaken in color, lighting, and vision. He is a recipient of the Wisconsin
Architects Foundation Scholarship, Alpha Rho Chi Medal from the Chicago Chapter AIA and
grants from the University of Wisconsin and the Optometric Extension Foundation Inc.
His earlier professional experience includes work for organizations specializing in hospital
laboratory and equipment design, electrical engineering, and landscaping. He has also worked
several years in the architectural design field at architectural offices in Chicago, Illinois; Stevens
Point, Milwaukee, and Madison, Wisconsin. Two years of the architectural design experience
were spent as a Project Coordinator. He also participated as an architectural consultant on a
design team in preparing performance specifications based on human function for the Reston Low
Income Housing Project, Reston, Virginia.
In 1967, Mr. Bennett was employed by the University of Wisconsin as a Subject Area Coordinator
at the Environmental Design Center for the Educational Resources Information
Center/Clearinghouse on Educational Facilities Project (ERIC/CEF). This project was structured
to develop a national clearinghouse on educational facility design information. As coordinator,
he was involved in setting up a manual and computerized search and retrieval system. The
resulting program provided the opportunity for instantaneous information searches and
bibliographic preparation for design professionals. During this project, he also served as editor for
the 1968 AlA Architect -- Researcher's Conference Proceedin~s and coordinator for the
Biblio~aphy of Environmental Desip References. He represented ERIC/CEF and the University
of Wisconsin at the Fourth Triennial Congress of the International Council for Buildings
Research Studies and Documentation (CIB) in Ottawa, Canada and Washington, D.C.
Thirty years of Land Use Planning and Zoning programs have served representatives of many
communities. These programs have enabled departments to structure land use programs that
manage and direct impacts and growth. Professor Bennett has prepared and conducted special
land use programs in Colorado, California, North Carolina and New Mexico. Each year, his
programs deal with land use impacts that can be accomplished through comprehensive planning
and zoning. In 1991, a new educational program focusing on Integrated Mining and Land
Reclamation was started in Reno, Nevada. This program is dedicated toward the planning of
resource extraction and land reclamation to support human and environmental requirements.
In 1977 and 1979, Mr. Bennett developed and conducted two ll-day housing inspection training
programs for Indian Housing Authorities. Each program was specially designed to provide
housing authority representatives an opportunity to understand the basic techniques and methods
that are critical for implementing effective housing inspection programs in their communities.
These two unique workshops presented in Madison, Wisconsin and Phoenix, Arizona served 120
representatives from 55 Indian communities across the nation. In 1979, Mr. Bennett received the
National University Extension Association's "Creativity Award" for development of the Existing
and New Residential Housing Inspection courses.
In 1980, he was made a member of the Editorial Advisory Board for a new publication titled
"Building Failures Forum" published in Ithaca, New York. Mr. Bennett was made a member of
the Colorado Association of Code Enforcement Officers and a "distinguished" member of the
Construction Specifications Institute. Since 1987, Mr. Bennett has served as a member of the
Architectural Technology Advisory Committee for the Southern Illinois University at Carbondale,
Illinois. Mr. Bennett also serves as a member of the Board of Directors for the new Association for
Project Managers. In 1994, he was invited to serve as an Advisory Board Member for the new
CADD Management Institute. He is co-author of "Construction Materials Evaluation & Selection
-- A Systematic Apmoach" and author of a 1984 manual titled "Construction Detail Bankini -
Systematic Storaie and Retrieval" both published by John Wiley & Sons, Publishers.
Special educational programming for the planning and designing of R&D facilities was
undertaken by Mr. Bennett in 1984. This innovative professional development program focuses
on planning and programming functional laboratory environments and the design development
of successful R&D laboratories. Mr. Bennett keeps the content of this program state-of-the-art and
relevant to research needs by conducting national surveys of R&D facilities, such as in 1992.
During the fourteen years of presenting this program, Mr. Bennett has taken it on location to
incorporate first-hand inspection of a wide variety of R&D facilities in Madison, Philadelphia,
Chicago, Boulder, Dallas, Research Triangle Park, Palo Alto, Detroit, Charlotte, Cincinnati,
Hartford, and Denver. This unique program serves representatives from industry, government,
and universities across the United States, Canada and several foreign countries. In 1998, Mr.
Bennett was invited to develop a special R&D Facility Design program to be presented in
conjunction with the XV IASP World Conference on Science and Technology Parks in Perth,
Australia in October 1998.
Madison, WI
HOWARD G. BIRNBERG
President
Birnberg & Associates
Chicago, Illinois
EDUCATION:
The Ohio State University, B.S. Architecture, 1972
Washington University (St. Louis), M.B.A., 1974
PROFESSIONAL EXPERIENCE:
Mr. Birnberg is president of Bimberg & Associates, a management consulting,
association management and publishing firm serving the design and construction
industry. He is a frequent speaker to many design and construction organizations. and
his articles have frequently appeared in industry publications. He has been a guest
lecturer at many universities including Harvard University, Northwestern University,
the University of Illinois. Arizona State University, Andrews University (Michigan) and
the University of Wisconsin. Mr. Birnberg served as an Adjunct Assistant Professor at
the University of Illinois. Chicago. as a lecturer on project management for the Harvard
University Graduate School of Design and as a lecturer on project management for the
past 16 years at the University of Wisconsin, Madison.
Mr. Birnberg served as the general editor for New Directions In Architectural and
Engineering Practice (McGraw-Hill, 1992) and is the author of Project Management For
Small Design Firms (McGraw-Hill. 1992) and Project Management for Building
Designers & Owners (CRC Press, 1998). He served as the advisor to the American
Institute of Architects and the Pennsylvania State University in the development of a self
assessment system on project administration.
He has been the executive director of several associations and is currently serving in that
role with the Association For Project Managers, an international organization of project
managers in the design and construction industry. Mr. Birnberg was a founder of the
association in 1991. He has also served as Director of Conferences for the Council on
Federal Procurement for Architectural & Engineering Services (COFPAES).
He is the author of more than a dozen manuals on various aspects of architectural and
engineers firm management and marketing. Mr. Birnberg is listed in Who's Who In
The Midwest.
CLUBS AND MEMBERSHIPS:
American Institute of Architects, former chair of the Chicago Chapter Office
Practice Committee, Insurance Committee, Membership Benefits Committee, 1993 AIA
Convention Planning Committee. former member of the Board of Directors. Chicago
Chapter and of the National AIA Practice Management Committee.
Madi8on, WI
Since 1952, Mr. Stephenson has been involved at middle and upper management
levels with the planning, programming, design, construction and operation of several
billion dollars worth of construction-related projects. These include work on
industrial, commercial and institutional programs throughout North America.
Mr. Stephenson has also chaired more than 60 partnering charter meetings for both
public and private sector projects, and has lectured extensively on the subjects of
alternative dispute resolution and partnering.
Mr. Stephenson has completed more than 60 Project Partnering Charters and has
recently completed a book on "Partnering" for John Wiley & Sons.
and
RESPONSIBILITIES
Philip M. Bennett
Program Director
Pla,nning-Design-Production-Construction
KEY ISSUE:
Successful Linkage
of Each Activity
in the
"Project Development Process"
1
CREATING THE LINKAGE ..I
Essential Information
T
T
I
A
M
F
E
F
Activity
. CHAIN OF ACTIVITIES ~
2
ATTRIBUTES:
ABILITY TO:
Events
Plan of Action
1. Planning
2. Scheduling
3. Coordination
4. Communication
5. Documentation
6. Management
7. Leadership
5
MINIMIZING STRESSFUL
CONDITIONS
~
6
A PROJECT MANAGER'S
SELF EVALUATION
7
wex project management 2001 seminar RalphJ. Stephenson, P. E.
Consulting Engineer
CONSTRUCTION
THINKING PATTERNS
ho 270 December, 93
Ralph J. Stephenson PE
Consulting Engineer
APPROACH PATTERNS
1. Improve capabilities
2. Gain control
4. Be creative
6. Continue to learn
7. Solve problems
ho 271 - December 93
I
/.02..
Ralph J. Stephenson PE PC
Consulting Engineer
GROUND RULES
3. Be selective in which
techniques you use.
ho 368 Dec 90
103
VISION
+
SKILLS
+ I
INCENTIVES I+ I RESOURCES
1+
ACTION
PLAN
- EFFECTIVE CHANGE
SKILLS
+ I
INCENTIVES I+ I RESOURCES
1+
ACTION
PLAN
- CONFUSION
+ +I 1+ PLAN
- FRUSTRATION
l l
l
Project management tools such as the above are usually very complex: They must be skillfully applied
by the project team to be effective. Thus the leader of the project, the project manager, should be well
versed in what these tools are, how they are best used, and what they are designed to help accomplish.
Excellent project managers realize that the list is merely a good starting point on which to build a
usable project management approach. Each individual should determine what goes into their tool box,
and then fill it with those implements that best suit that individual's talents, abilities and needs.
1. • Actions to be taken
A. Conceive
B. Program
C. Translate
D. Approve
E. Design
F. Construct
G. Turnover
H. Operate
II. • Concepts to effect change
A. Vision
B. Skills
C. Incentives
D. Resources
E. Action plan
III. • Functions
A. Planning
B. Organizing
C. Staffing
D. Directing
E. Controlling
F. Representing
IV. • Interrelations - organizational structure
A. Formal functional
B. Informal functional
C. Reporting
D. Staff
E. Temporary
V. • Participant resources
A. Conceiver
B. Translator
C. Constructor
D. User
E. Operator
F. Regulator
VI. • People behavior
A. Motivation
B. Hygiene
C. Learning
D. Value systems
E. Personal goals & objectives
F. Personal growth
G. Social relatedness
VII. • Performance measurement
A. Measurement units
B. Performance standards
VIII. • Planning and scheduling systems
A. Network modeling
1. Arrow diagraming
2. Classic precedence system
3. Modified precedence system
B. Bar or Gantt chart
1. Non scalar - not time scaled
2. Scalar - time scaled
C. Slant charts
D. Narrative schedules
E. Project data arrays
F. Money flow curves
IX. • Thinking processes
A. Plan
B. Translate
C. Control
D. Correct
E. Learn
Usually the project manager is most concerned with supportive actions which bring
resources to the point of effective use.
ho 494 Aug, 97
........
--,L.
RALPH J. STmPBlIINSON. P. Eo
~'"1..
. ...
.
OON.OL'l'DfG m.GIMJIIJIIK
--,L
,
~
<%..
\~
, ",,
wJ
~
.a. ~
"
~
~.,.~ "~
"C""'...,
~ . ~
~
~
~
"~,,~
~
~
..
"0
~
~ .. ~ ~
4IC""
...
""1..
~ ~
Q
"1..6
-
""-~
~
U
~
. .,....
~
.. ..
~
~~
~..,
~
~
"
'"
~
.."
~a.
-.&
c;...1...
.a.~ ~
c!). .
\)
.,jj C> i;:
,-Q
~~
? .....
.....-..>
~
~ e
~'
~~
/-04
H/o 81
4
Ralph]. Stephenson, P. E., P.C.
Consulting Engineer
Conceive
Program
Articulate
Approve
Design
Construct
Turnover
Operate
Maintain
Conceive
During the conceptual period the need, which may be for increased
facilities, larger dollar volume, more efficient handling systems or a
variety of other demands is visualized and put down in some rough
form. It may be a pencil sketch or may remain an idea in someone's
mind. Here the project sees its origin and it is this early idea that often
carries through the entire project. Agood conceptual grasp is essential if
the project is to be successfully completed.
Program
In the programming phase, the needs of the concept are put into easily
understood tabular form - so many square feet for storage, so many
square feet for office, so much floor to ceiling height for shipping
facilities, etc. The actual physical demands of the environment are set
forth in the project program or project bible.
Articulate
Approve
This is a critical point in the line of action. By now sufficient work has
taken place so the manager and the ultimate decision maker can
understand the project - can say: '1 like this or I don't like iti change this,
revise this; let's increase that a bit; let's cut down here": finally saying:
IIOK, I'm satisfied with this set of ideas showing the concept and the
program, and we have the financing and the land - let's move on!U
Approval unlocks the full design and construction of the project.
Design
In the design phase, products of the previous four steps are utilized to
prepare a set of working drawings and specifications that translate
concept into steel, concrete and space.
Construct
Turnover
When the facility has been built, it is turned over with appropriate
operating manuals to the owner or tenant. Turnover is an important
step and when done properly, it insures that a valuable commodity, the
completed environment, is properly given to those who must use it.
Operate
\..... The facility is now run-in and begins to achieve its full purpose.
Operation can be an important responsibility and often the design build
contractor will furnish his operational functions in connection with a
new environment on a paid contract arrangement.
Maintain
The end of the line of action is when the programmer, the designer and the
builder of environments has discharged his or her responsibilities. In a
continuing trustworthy relationship, the line of action will have no end
since before a project is finished, the competent professional will be re
involved in another program from its beginning.
mainta1n
II In
operate
.4 "
4 .4
4~
... 4
,~
t
fit
turnover ~Q
e!1
I
11
I
~
"'a
tit
t
I -f
g
"I
A
Q
J 'a.
J
,
il 1 J
r5 4
" 1
I ,
approve
Q n
- .4jt.
,
tt
-.:I
. -"
"
articulate I itt
if
proeram , -~
4
A "
.a:I
i,
Jl,
it 1
!
,t
~~
II i
~
~
\. \. ~
Ralph J. Stepheuon PE
Cem81l1:" Eaglneer DEVELOPMENT cyCLE ACTIONS It Oct, 1988 - boS21
ORGANIZATION
Ralph J. StephensOH1 P. E.
Consulting Engineer
• ho 336 - disk 162
• Development phases - Ralph J. Stephenson PE - ho 336
• Phase A - Launching a project
The launch phase of the work is concerned primarily with locating & nuturing
development opportunities or assets intended for long· term ownership and use. If
the company's desire is to create negotiable development assets, the launch group
works on the front edge of this effort. The launch group may call upon other
functional elements of the organization as needed but the launch group must be
independently creative, flexible, knowledgable & understand and enjoy the
development process.
The launch group is headed by the chief operating officer of the firm. Upper
management members in charge of the other functional elements are members of his
launch group. They are charged with locating high potential project opportunities,
and screening and profiling them so as to maintain a high percentage of success
probability.
The launch group should be relatively unstructured but must maintain a rigorous
discipline relative to communication with others in Element A as well as those in
their specific area of functional responsibility.
The project program staff works closely with the launch group to take over the
created and profiled opportunity and substantiate its validity, or justify its rejection.
The programming group's job is to bridge the gap between the free wheeling creative
actions necessary in the launch action and the project implementation action. They
often are the cool voice of business reason.
It is critical to understand that the program phase is where development funds are
actually committed. These funds are then spent during another phase. Thus projects
that emerge from the program analysis must be those with the highest probability of
success.
In a sense the program function forces the project to prove itself as a feasible course
of action to produce a negotiable development, or a long-term ownership asset.
Where deficiencies are located in a created opportunity, but there appears to be some
soundness to the project, the program function is responsible for effecting acceptable
changes to the elements that are their responsibility so as to make the project a go!
In this sense the program group must be every bit as creative as is the launch group.
Leasing during project implementation is basically rental work taking place that
allows tenant improvements to proceed concurrently, sequentially and in harmony
with owner work.
The project implementation staff also carries out major remodeling work to existing
properties as compared to minor improvements made by the properties staff.
Decisions on what is a major & minor project must be arrived at jointly by the
functional groups with the aid of the executive staff.
The property management group actually exerts management control over improved
properties to insure they are successful investments. The property management staff
is also responsible for continuous evaluation of each property to determine the best
future course of action relative to that property at any given time.
In a project oriented firm the individual programs or projects drive the company; as
such the support or ongoing group must be kept lean but be given all the tools
needed to properly buttress line activities.
Leasing of an asset usually signals the start of income flow which can be used to
/.10
Ralph J. Stephenson, P. E.
Consulting Engineer
retire outstanding indebtedness. Many of the actions of the leasing program are
accomplished in close cooperation with work accomplished in Elements B, C & D.
However, final responsibility for leasing results rests with the leasing department
and those charged with its managment.
The leasing program usually includes both lease negotiations, and design and
construction of the tenant space within the tenant's demised premises.
Tenant design and construction is usually carried out at a different pace than the
base or landlord design and construction. For this reason the design and construction
of the space may be assigned to a tenant coordinator who acts as the project manager
for the tenant space work. .
1.11
III eIII
~
0.
~
"0 III (")
a g
1
"0 \'t
i3
~
"0
- m Ei
(") (l'Q (")
c i3
rJ
~.....
()
:or
() e III ii ~ §:
fti '"I ::I
start of construction
project stage
end of
project
money available
~ cumulative project
.......
N doUars committed
cumulative project
$ doUars spent
TIme
Costa CommItted Compared to Money
S,pent on Construction Projects
Ralph J, Stephenson PE
Consulttng Engineer
ho350Jan90
( ( (
ho 420 - Oct, 93
Ralph}. Stephenson PE PC
Consulting Engineer
There are six basic participants in the process of designing and building
environments. These are the conceiver, the translator, the constructor, the user, the
operator and the regulator.
Conceivers - Those who conceive the idea and provide the wherewithal to bring the
environmental program to a successful conclusion. The conceiver may be the owner
but it also might be a governmental agency, a financial source, an architect, an
engineer, a contractor, a vendor or a potential tenant looking for space. We identify
the conceiver since he usually is the key person driving the project on to completion.
Users - Those who occupy and use the completed facility to conduct their work, their
recreation, their domestic living, or other activities for which the facility was
specifically designed and built.
Operators - Those who operate and maintain the completed physical environment
on a continuing basis. Usually the party responsible for this function is an owner or
tenant working through a plant or facilities manager.
Re&ulators - Those who fill a review & inspection position to help insure protection
of the health, safety & welfare of the people. This is usually done by enforcing
regulations written and adopted by qualified public or private bodies. Examples of
regulators include those who work for building departments, departments of natural
resources, public health agencies, fire prevention organizations, technical societies
and other such groups.
Ro,Pk
h"E0C31CK
_ _ ......- - - -""'- '---,
'""""iIo-- I
MOr1s'I
Spa.ce.
77/1?t!!! I Mon;.,Ior';"9
7cJe,.,./
£ r1 .,Ihe../sla..s""
t Co,.,-h-o //;"'7
Correc./,nr
Ef4//.r'h'len.,t
MarI~/~/.5
£../C.
-- -- ~
~AN'..5L.1T'OA/~ -
hCTUR,c
Or A
~ P,RO..lECr
""""
~
o I:'j
L5cr..r CAa..,...-I'
H
iii •
, rI.I
fJ
e -rc.. E-rc..
MACRO MATRIX BOUNDARIES
regulator
WHO TAKES operator
THE ACTION
constructor
translator
conceiver
property managment nl
leasing
construction 19
legal 18
ACTIONS TO financing Y1
BETAKEN
~ real estate 18
"
\tt estimattng Y&
architecture Y4
englneertng '13
planning n
~
~e ~
....
Q)d aM ~ s::
t,l
~E Ralph J. Stephenson PE PC
~s::
B
ec.
~I
i~
!9
00
t,lt,l
c.
as
II)
Q)
'tI 0
t,l
E~
i1~ ii Consultlng Engineer
323 Hiawatha Drive
Mt. Pleasant, Michigan 48858
ph 517712 2537
UNEOFACTION
Issue III • Februaty 4. }991 sheet
MM·} hoaspeOl
MM-l
l {, l
( ( (
regulator
WHO TAKES operator
THE ACTION
constructor
translator
conceiver
property managment nl
leasing
construction 1'9
architecture Y4
engineering 'Y3
planning n
...
\I construct
~~
....
~
... ~E
(work phase?)
~i
(J
e
11.11:1 \I
1:1 i: B
~~ Q~ .;!!l
Et
i~
Q.. III 1il
80
(J(J
[a Q..
tlS
\I
'tI 01:1
(J .ai5
Ralph J. Stephenson PE PC
LINE OF ACTION Consulting Engineer
Issue III • FebruaJY 4. 1991
MM·2 - bo aspe 02 323 Hiawatha Drtve
Mt. Pleasant. Mlcblgan 48858 sheet
pb517m2537 MM-2
A Ct..eA'(" VVIN"'oVl./ i5G7W..::t!'N
THt: ~;eo"/IC 7" ti 'THE CUve; o"vC;
IN4A!IFDIIiNf IN G,c,l:"i'crIVIi
MANA t; a '''''1 IN r - -
A ~~OO7"I-/
_ ... - --
I'N 7,; A!,...:"A C' / I"V C;
Su.cr-ACE ,:;r
r"/A£.
I!!JI ~,_ ,
7(.".::1
___~ I
I
QAlt; OINt:;
~ \'~ ~
A..
C,')/lt:iA~1' t!A Tlnl\!
MAA!;.t4 'TINt:;
eS",..IHA 7/Nq
P{.,I..I!:.'=#AS"Nq
I \( \\
1 ~ lJ
.;. C7oAL. S F
....
,
<:".7.15..1'£ c 7'1 VE S
'\,\ _. \ ;:'N'ANC/Nt;
t..eGA/'
~SIe,N
P.£A-S'oNN£l
L.A6C?..c.
:(NQ"
Y'AA.D ~ i~
~- /".., / ( c Jf I5
; Co4
iii •
I fIJ
~
o
l\ LJ I ii III ~
"--~ ~!
J
::
00 ~
•
6 T~£ REL4T,IC;)N 0;:- P£.C'.JJECr ~
~ /v1ANACj£M~NT ;rC:J .
'" C)J../t:jc:>/Nc; ~ANA4IfH€NT
l, l l
R..u..PH J. STl!::PHENSON. P. E.
CONSt."LTDfO ENGINEER
H/o 2;5
/.IP
1
~
~
~
..;:,..
>c-~
Or. -~
~'\; ~
c;::y
.......
o~
~
U ~
~~
&;::;. 0 ~.
~
~~~ \)
A-~ C()
><'~ \>'"
.~
<::>-
~
.~ .~
.~ ~
t )~ .~ .~
i ~
S))
\)
~ ~~
i
o\)
.~ ~
[\
~'= ~~ ~ ~~ ~
~ "
"> ~ '<) ~ ~
HO 206
/'17
RALPH J. STEPHENSON. P. E.
CONSULTING ENGI!<lEER .
-~
L~
~
~~
-q'
><:1 i
I
{ 0......... -<~-+- .
l'- ~~>
::-..;.>
\l ~.:;; I
~~
/
~
"
!J .$)
C>e>.
c::,.,<.J:'
!
~~ ""\.. ""'J,..~
I
~
<.I' Qtc:>
-~
.
,!)-10 :l
.0,..."..';.::.....
.po
I
~ ~
~
\, \J ...\I ~ ~ ~ \1
< ~ ~ ~
""
'\I
,C t ....
~
\j
....
~ "
~
l: ~ .... "(
~ -.J ~
( ~
....
\2 .\(
~
" Q
~ (
'"
q•
C tl
3 "~ '~..." ',"
U \J ~
\I ~
0 ~
~
l0 ~
~ t
~
~
~ ( " .... ~
~ ....
~ ~ 'l
.... ~ \ ~
"'...."
\j "') l1li .J
"0 Q
~
~
\J ~ ~ \J
"t
v ~
-t
\J
~ 'C"
~ Q ~ ~
"'I
"~
q
~
....
":io
...
~ ~'" ~ ~ ~ l:
~ '( ~ \J
"
"I{
'U 'll \J
""oJ "t "'\ 'Va
Ralph J. Stephenson PE
DESIGN/BUILD MATRIX
.... MaiDtaln
Operate
==
0 TurnOver
ros. CoDStract
~ DesIgn
Q Approve
0 Articulate
= Program
Conceive
<
All
.
r' i ! s i
If i
II
~ ~
I
i
I j ! J } i
a 8.
~
~
J .1
1"1
Q Q
eq
""
Q
..
Q
10
Q 8 ~
Q
«)
Q 8 Q
1"1
1"1
1"1
ho 358
/. 2/
Ralph J. Stephenson PE PC
Consulting Engineer
ORIENTED BUSINESSES
/. Zz.
Functional
Management
Functional
Project
Project
Management
Time Volume Size Diversity
I I I I
Competition, Organization
~
~
~
ho 364, Feb, 90
l. l l
Ralph J. Stephenson PE PC
Consulting Engineer
Concelyer· the ultimate decision making force behind the entire project
Developer
Owner
User
Translator· transfers the concept into construction documents
Programmer
Designer
Manufacturer
Vendor
Contractor
Constryctor - builds the components and the job
Manufacturer
Vendor
Specialty contractor
General contractor
Construction manager
Operator - operates the completed project
Facilities planning
Operation management
Plant engineering
Manufacturing engineering
Regulator· insures project adherence to the public good
Private
Public
Quasi public
1 ho 272 - Nov 89
Ralph J. Stephenson PE PC
Consulting Engineer
ho291 - Nov 89
Ralph J. Stephenson PE PC
Consulting Engineer
1 ho 292 - Feb 88
Ralph J. Stephenson PE PC
Consulting Engineer ~
team.
!jgII- Expense work includes those costs that do not
directly increase life or value of the faCility.
2 ho 292 - Feb 88
Ralph J. Stephenson PE PC
Consulting Engineer
A. KINDS OF PROFIT
1. Financial
2. Social
3. Self actualization
4. Value system
5. Technical
6. Enjoyment
7. Educational
1. Competence
2. Service
3. Integrity
4. Cost
5. Delivery
6. Understanding
1. Be smarter
2. Plan better
3. Control closer
4. Achieve more
1 ho 282 December, 93
Ralph J. Stephenson PE PC
Consulting Engineer
PR POTENTI LEVEL
1 ho 283 - Oct, 88
Ralph J. Stephenson, P. E., P.C.
Consulting Engineer
Action #8 - Employ the power of training Result #8 - You'll find that employee
attitudes improve.
DEFINITIONS
QUESTION
1. Goals and objectives for the project are clearly identified, and starting,
intermediate and ending measuring points established early in the project life.
2. A suitable project delivery system is selected as the goals & objectives are
defined.
3. An action plan showing desired and necessary courses of action from beginning
to end of the project is prepared.
4. The action plan is translated into schedules, and the resources needed are
determined and balanced for most profitable performance.
1 ho 223 Nov, 89
Ralph J. Stephenson PE PC
Consulting Engineer
5. A project organization is built under (not over) the resources required to provide
resource management quality, continuity, and monitorbility.
7. The needed resources are assembled and the project team gets to work.
8. Progress and performance of the project team is measured and evaluated using
management by exception.
9. The project is closed out promptly, cleanly, and totally as work draws to a close.
2 ho 223 Nov, 89
Ralph J. Stephenson PE
Consulting Engineer
ho 273, Nov 89
I...!,
Ralph J. Stephenson PE
Consulting Engineer
ho 285 Nov 89
Ralph J. Stephenson, P. E.
Consulting Engineer
In the design and construction industry there exist many factors which influence the degree
of success achieved on a project. They deal with project goals, profit types, project
sequencing, the nature of the participants and the kinds of problems most likely to be
encountered.
If the parties to a planning, design and construction program recognize the nature and
importance of these factors, a major step will have been made toward their proper and
effective combination and management.
Below are listed 38 basic influences on project delivery systems. Project management
concerns how to combine these into a successful job of which all participants are proud.
• Six major lOals to meet for desip &; construction project success
The client,. owner &; user must be assured upon completion of his job that:
1. The facility program and the facility design have met their needs, desires and wishes.
2.. The planning, design and construction work on the project has been accomplished within
3. All relationships on the project have been maintained at a high technical and professional
level, and have proven rewarding for those involved and affected.
4. The people involved at all levels of work on the job have realized a financial, professional
and technical profit for themselves and their associates by being on the project.
5. The project has been closed out with little or no residual potential for major problems of
maintenance or operation.
6. The entire process has been free of unresolved contested claims for additional money,
additional time, damage payments, and of the potential for future financial demands after
the job has been closed out.
• Nine major elements in the design &: construction sequence &: how they are done
1. Conceive the basic project
Visualize and state the fundamental nature of the proposed project, what purpose it is
to serve, and its base characteristics.
2. Prepare the program
Set down the physical characteristics of the total project in written and graphic form so
as to be able to translate these. characteristics into approval documents from which the
full design can proceed.
3. A rticulate the program for approval
Merge the concept, and the written and graphic program into written and graphic
construction language which can be reviewed and released by the ultimate decision
makers for full design.
4. Approve the basic project
Approve the concept, the program, and the merging of the two. This approval by those
in authority initiates the full design and construction process
5. Design the project
Build the project and make it ready for turnover to the owner or user.
Take over, run in, and make the new environment fully operational.
Contract documents which do not adequately portray the true contract scope.
4. Delay
A situation, beyond the control and not the fault of a contract party, that causes a delay
to the project
/. :: c".
Ralph}. Stephenson, P. E.
Consulting Engineer
....)
"t",
~~
';t~
....
\'"
'l" ~. 'lJ
\It
~
n
\I
~-~
't.I
~
......
...
~ "'
-t-,.
'( ~ \J
~
~
'"~
-..,')
Q ....
~
{ ()
h 'tt
.
u ~
~
'U
~
~
~ ~
')
0 a~
~~
~
~U
~
~~ Q "'l
"
~ ~
hit)
-End -direct
-Goals -Intermediate -dependent - predictable
-Objectives -Peripheral -dependent - unpredictable
DefInitions
ho 316 July. 88
J S TEPHENSON P
CONSULT~
RALPH
G ENGINEER • • E.
ho 197
!sum
h
1===V:'::.'t:l!!"c:t:
I.I:.Ima:It.
..
!\\
t) A. Adn-irislnllion
B. eonnu"'n
"'
C. C<ltporat. pl8IIning
D. DOV<IIopmenI. ",aI . _
E. F.. (& per'- i _ I ..m_
E MarIootng & .....
G. Training & ......tion
TM-1
l l l
Ralph J. Stephenson PE
Consulting Engineer
Some guidelines to identifying and writing out project goals and objectives are given
below:
Step 1.
Answer this question
Your statement now becomes a project mission from which detailed goals and
objectives can be generated.
Step 2.
Decide upon and write the major activity classifications within
which you wish to achieve the mission stated in Step 1. Some classifications for
detailed goal definition in project management
might include:
• Company
• Organizational
• Departmental
• Project
• Social
• Financial
• Community
• Technical
• Professional
• Educational
• Personal
• Project staff
• Career
Step 3.
1 ho 275 Nov 89
2.06
Ralph J. Stephenson PE
Consulting Engineer
Select the classifications you feel most comfortable with, and write
several brief statements of what you want to achieve within these
activity categories. Don't think about numbers and time frames yet. Concentrate on
getting good content in each statement. Typical statements might be:
- To implement a job data base tracking system for submittal turn around
procedure
Step 4.
When you have written out as many targets you wish or must achieve, and that you can ~
comfortably think of, reorganize them into a classification system best suited for the
project you are on. Classification can be by the original groups, or you may wish to
rearrange them by subject, time span, people involved, degree of achievability, people
influencing their achievement, or any other common qualities that allows you to work
comfortably in converting the desires to accomplishments.
Step 5.
Once you have a satisfactory list of desires, begin assigning quantities to the goals in
the list. Quantities may be in dollars, manpower, time, space, talent, opportunity, or any
other you may wish. This quantification step converts non numerical goals to numerical
objectives. It is a step you must take to get from wish to reality. Remember project
management is objective oriented. Converting goals to objectives is essential for
effective project management.
For example the unquantified target stated in Step 3 above, ''To significantly reduce job
meeting times and improve follow up results.", might now be amplified by such specific
objectives as:
- Within 3 weeks of field job start to have all project minutes being done on an
2 ho 275 Nov 89
.L.oc.
Ralph J. Stephenson PE
Consulting Engineer
- Within 6 weeks of field job start to be using technography methods to record and
- Within 7 weeks of field job start to publish job minutes by late afternoon of the
meeting day.
- Within 1 week of field job start to be discussing in job meetings only job matters
Step 6.
When you have enough objectives, to satisfy your initial needs, stop for a while and
concentrate on achieving what your objectives demand of you. The call now is for
actionl
Step 7.
As you put the goal and objective achievement process into operation, keep adding
goals and objectives to the list you have prepared.
Remember, your needs, and the project's needs change continually. In Step 1 you
defined the fundamental project mission. Around this stable base the detailed goal &
objective setting must continue as the project unfolds.
3 ho 275 Nov 89
'2.07
Ralph J. Stephenson, P;E., P.C.
Consulting Engineer
2.01"
RALPH J. STEPBENSON. P. E.
CONatTU.l'UC& JilN&TNl!lElI
As the space is leased, you, the landlord, will install tenant improvements
consisting of carpeting, partitions, doors and other items covered by the
lease. The tenant will have an opportunity to add additional cost items to
the basic tenant allowances at his expense, subject to your approval.
You have let contracts on the job to three prime contractors, architectural/
structural, mechanical and electrical. Your duties are as the prope rties
department full time project manager o The properties department is new
and you have only been with the firm a few monthso You recognize you have
the right education for the job, are interested in the work and are anxious
to learn. However, you also recognize you are somewhat inexperienced.
a little young for the responsibilities you have been given and have a tendency
to be more stubborn than is necessarily good for you and those who must
work with you.
This is your first major project with your new firm, although your experience
includes the project management of several successful jobs for a moderate
size general contractor in the community. The se were accomplished over
the previous four years of your employment.
You have met the three superintendents for the three prime contractors
and each appears competent in his own disciplineo
../.0'7
Page 1 of 2 H/O 132 10/76
I!ALPH J. STEPHENSON. P. Eo
Case Study Al OONl!ltnJrUl'G ENGINlI:BR
Definition of Objectives
has not said much in your meetings and you sense that he is highly concerned
with protecting his company's rights on the job. He is, however, you judge,
very competent, although you have also heard that he has a stubborn streak
engineer, but with good journeyman experience since he started in the trades
you have already noticed that he tends to look to you as his peer rather
All three primes will have their detailing and accounting work done in the
home office and will maintain a very small field administrative operation.
You, as the owner, want quality work and are willing to pay to get it. Your
help that he has come to expect from congenial and competent owners and
Your personal goals in this project are to do an excellent job and to gain
company to help you with your ongoing education. You have had two years
'Z/o
Page 2 of 2 H/O 132 10/76
Ralph J. Stephenson PE PC
Consulting Engineer
The Tarry lab is visited frequently by Bengst middle and top managers. Many of them
have shown a liking for the small community, and it has been tentatively decided by
Mr. Bengst to gradually shift Bengst headquarters to Tarry.
The Tarry facility is located on a beautiful 160 acre parcel of land bought several years
ago by Mr. Bengst. The existing building is a one story structure with a steel frame and
an attractive masonry and curtain wall exterior skin. It was designed by a Philadelphia
architectural/engineering firm. who also designed the Billings plant and office.
Bengst Corporation wants to add one story of similar construction to the building and to
concurrently develop a master plan for the entire site. Ultimately most major design
and production facilities of the company are intended to be moved to Tarry. In two
years the volume of business done by the software division is expected to increase
300%. The hardware division is expecting a 200% expansion within the next five
years.
The president of the company, Mr. Steel Bengst, is very active in the expansion
program and will watch the expansion work carefully. He has appointed a young
systems engineer at the Tarry plant, Karl Jong, to be the owner's project manager. Mr.
Jong is 28 years old. has advanced degrees in electrical engineering and business. He
is considered one of the bright stars of the emerging manager group at Bengst. (end)
1 ho 224 Jul, 88
Ralph J. Stephenson PE PC
Consulting Engineer .
Please note any questions you may have about the above information in the space
below.
2 ho 224 Jul, 88
Z. 12
Ralph J. Stephenson PE PC
Consulting Engineer
You have exhibited a strong interest in the company product and its facilities for several
years. Mr. Bengst has observed your work and has taken a personal interest in your
career. He decided, after several conversations with you to appoint you project manager
for the expansion program being contemplated in Tarry. You have been made aware of
the con'fidential decision made to shift the headquarters and operations of the company to
Tarry. You also have some concerns about the selection of Tarry, but these have not been
expressed by you to anyone. You however, know that one of the expanded Bengst main
market targets is to be the midsize & large medical computer users in Southwest USA.
The building in Tarry was designed to receive a future second floor on the present one
story structure. The structure occupies a position at the northwest comer of the site and has
access to local roads, and through them, to the freeway about 1/2 mile to the east. The
building, as well as the site would probably be readily salable in the current Tarry area
real estate market.
Mr. Bengst enjoys working to well defined guidelines and expects his staff to clearly
identify goals & objectives for their projects. On this assignment he has given you the
following assignment.
4. To set an authentic time table for the total expansion in conjunction with the
Bengst facilities engineering staff
1 ho 224.20w Jul, 88
Ralph J. Stephenson PE PC
Consulting Engineer
• Tom Bengst - VP of marketing & Steel Bengst's son - determined and competent
man of your age. Somewhat disappointed at not being appointed to be the
expansion program manger, but seemingly satisfied with your appointment.
• Frank Berenski - Facilities engineer for the company - competent individual, older
than you, bright and enthusiastic. Likes order & method.
• Trosta Miraldo· Your boss in the hardware &software systems design division
highly educated and a very competent doer. She had hoped to get the program
manager's job for the expansion. However she has a high regard for you and is
only marginally upset with your appointment. Still expects you will work for her in ..J
your systems design activities.
addition.
2 ho 224.20w Jul, 88
Ralph J. Stephenson PE PC
Consulting Engineer
Organizational Relations
Trosta Miraldo
Systems mgr
Tom Bengst
VPMktg
Karl Jong
Proj Mgr
John Donovan
AdminVP
Frank Berenski
Facilities Engr
ho 319 Jul, 88
Ralph J. Stephenson PE PC
Consulting Engineer
Vyvyan is organized around strong functional operations, but has a management that
understands and appreciates the value of project management. The firm has a good
reputation for competent architectural deSign and good technical backup.
The design department under Jon Teleman tends to design expensively, but will listen
if sound, rational reasons are given for disagreeing with their concepts.
The architectural production department head, Carl Trilar, is a hard headed man of 39,
who has a wealth of experience and is well thought of by his staff. He does not always
agree with the design group and frequently revises major details without consulting the
design team. This leads to hard feelings and recently has caused budget overruns on
several weakly managed projects.
The engineering departments have tended to follow patterns set by the design and
architectural department without too many problems or conflicts. However, Mr. Vyvyan
just brought in a new chief engineer, Bob Lott, who has already clashed with Carl Trilar
in a dispute in which Mr. Lott sided with Jon Teleman.
Your firm has been contacted by a moderate size developer, The Dreyfus Corporation,
and offered an architectural and engineering commission to design a new 8 story office
building of 240,000 square feet. The building is to be a tenant occupied structure with
a core utility space containing elevators, stairs, riser shafts, toilet rooms, telephones,
and electrical and janitor closets. Perimeter spaces will consist of standard rental
areas, and will be finished with a smooth concrete floor, acoustic ceiling, lights and
diffusers.
As the space is leased Dreyfus will install tenant improvements conSisting of carpeting,
partitions, doors and other items covered by the standard lease. Tenants will have the
option of adding additional items in the space subject to Dreyfus approval.
1 ho 226 - Dec 88
2.1'
Ralph J. Stephenson PE PC
Consulting Engineer
You have worked for several months cultivating the Dreyfus organization in the hope
Vyvyan would be awarded this project. When Mr. Dreyfus called yesterday and said
they had selected Vyvyan and Associates to do the work you were delighted. Mr.
Vyvyan has told you he wants you to be the project manager and to develop a solid
ongoing business and professional relation with Dreyfus.
Your pleasure has been somewhat dulled by the news that Dreyfus has also retained a
general contracting firm, Spencer Brothers, a traditional old line but reliable
organization, to advise the design team oncosts and construction materials and
systems during the design period. Mr. Dreyfus is known to want Spencer to build the
job on a negotiated basis. The chances of this happening are about 90%.
You have no bone to pick with Spencer but certain people in your firm, particularly Carl
Trilar, feel Spence(s appointment as a peer indicates a lack of confidence in you by
Mr. Dreyfus. You don't share this opinion and feel there is a good chance to profit from
the association with both Dreyfus and Spencer.
1. What goals would you set for the design work of Vyvyan and Associates?
2. What goals would you set for the relations between Dreyfus and Vyvyan?
4. What personal goals would you define for yourself in this situation?
5. Identify some of the department related peripheral goals that might emerge
from the project organization.
6. Could you shape the goal setting of Dreyfus and Spencer? How, and in what
direction?
2 ho 226 - Dec 88
2, 17
Ralph J. Stephenson PE PC .
Consulting Engineer
You are 35 years old and a project manager for Bishop Construction, a general
contractor. You have completed 3 years of engineering school at a good local college.
However you have not been able to complete your university work because of the time
demands of raising a family, and the pressures of day to day work at Bishop; but you
have always had a desire to go back to school and get your degree in engineering.
You have worked for the company about 8 years, and are considered a prime
candidate, along with 2 others, for a vice preSidential position to be available in about 1
year.
Yesterday your firm was successful in negotiating a general contract for a new 6 story
office building with a 150' x 150' footprint. The structural frame will be steel with a
conventional glass and masonry exterior. The building contains a core utility space
which houses elevators, stairs, riser shafts, toilet rooms and telephone, electrical and
janitor closets. Perimeter spaces are standard rental areas to be finished in base
building work with smooth finished, exposed concrete floors, acoustic ceiling grid, light
fixtures, and a modular diffuser drop pattern. Acoustic panels are to be stockpiled on
each floor for the use of tenants as they occupy the space.
Bishop has an opportunity to construct most of the tenant improvements, but this work is
to be awarded as space is leased. No final selection of the tenant improvement
architect or contractor has been made.
The owner is a reputable local development firm that will do about $50 million in new
projects next year. They have told your president that they are trying to develop a
project delivery system that places their deSign and construction needs under a single
responsibility.
The owner's project manager is a son of the development company's president, has
just turned 30 and is a business and law graduate of the same college you attended.
1 ho 265 - Dec 88
2./~
Ralph J. Stephenson PE PC'
Consulting Engineer
The architect on the project is about 40 years old and has a fairly
successful local practice. He is fair, competent and a good business man. He is very
concerned about his exposure to unjustified liability expenses. You have worked
together in the past and have come to know each other well, and to have a mutual
Market absorption projections indicate your company has about exhausted their
potential for obtaining hard money bid work in your area for the next 5 years and must
begin diversifying either geographically, functionally or both.
The owner wants quality work and is willing to pay to get it. You intend to use your best
subcontractors and suppliers on the job. You are also instituting more rigorous
planning, scheduling and cost control systems on this job than on any other in Bishop's
history.
Address the questions and considerations below and be prepared to answer them as a
team.
1.} What are the common characteristics shared by the prime members of this project
team?
3.} Define two important goals for your company on this project
5.) Explicitly state two objectives for your company on this project
2 ho 265 - Dec 88
Ralph J. Stephenson PE PC
Consulting Engineer
Note: Goals and objectives on a project like this may be classified into one or more of
several categories including:
a.) Financial
b.) Quality of finished product
c.) Organizational
d.) Planning and scheduling
e.) Career desires
f.) Personal desires
g.) Company growth and expansion
3 ho 265 - Dec 88
Ralph]. Stephenson, P. E.
Consulting Engineer
December 3, 1997
Partnering is not a business contract, but a recognition that every business contract
includes an implied covenant of good faith.
D. Project partnering.
A method of conducting business in the planning, design, and construction profession
without the need for unnecessary, excessive and/or debilitating external party
involvement.
E. Resolution
A course of action determined or decided upon that can result in clearing conflict or
dispute.
F. Strategic partnering.
A formal partnering relationship that is designed to enhance the success of
multi-project experiences on a long term basis.
II. Alternative dispute resolution (ADR) systems and their application in construction.
A. Some resolution methods available
1. Non binding
a) Prevention methods - produces maximum harmony - usually least cost.
(1) Intelligent and proper risk allocation
(a) Risk should be assigned to the parties that can best manage or control the
risk, i.e.
i) The owner, if the architect/engineer is expected to assemble and write
the program.
2...l!/
Ralph J. Stephenscm, P. E.
Consulting Engineer
December 3, 1997
2.22.
Ralph J. Stephenson, P. E.
Consulting Engineer
December 3, 1997
"Ou, experience is positive based on six contracts with fou, of them substantially
c) Increased responsiveness.
e) Improved communication.
I) Pillsbury/Fluor Daniel-1989.
~,24
Ralph J. StephenSQl1, P. E.
Consulting Engineer
December 3, 1997
5. ' Where several parties to the contract prefer to resolve disputes by contested claiming &
binding resolution.
6. Where poor contract documents are made the basis of the partnering effort.
7. Where excessive, one sided conditions are placed on sub contractors by prime contractors.
8. Where unfair or obscure payment processing systems are specified and enforced.
9. Where risk has been poorly defined and unfairly allocated.
V. What are some of the ingredients of a successful partnering effort plan?
A. Develop and maintain a strong desire to achieve project success for all.
B. Make intelligent commitments.
C. A void accepting or imposing unreasonable risk.
D. Work and act ethically, morally, and with integrity.
E. Work and act from a position of fairness rather than a position of power.
F. Suppress greed.
G. Try to establish an honest feeling of trust among participants.
H. Assign experience, competent people to responsible management positions.
I. Have empathy.
J. Prepare a good charter, a good partnership evaluation system, and a good issue resolution
process.
VI. Experiences and applications of the partnering concept.
A. W hat actions do others engage in that create problems for us, or do we engage in that create
problems for others? (sample responses from an actual charter meeting.)
1. Giving directions to proceed without a timely change order.
2. Failing to establish clear chain of command.
3. General contractor covering general conditions costs by charging subs.
4. Lack of timely acceptance of work.
5. Lack of timely responses to
a) RFI's.
b) Approval of shop drawings.
c) Site activity restrictions.
d) Change orders.
e) Value engineering.
o Acceptance of work.
6. Improper passing of general conditions responsibility to subs.
7. Lack of forum to evaluate and resolve open issues.
8. Slow submittal tum around.
9. Unreasonable punch lists.
10. Failure to recognize impact of changes on ongoing work.
11. Late submission of proposals.
12. Untimely submission of as--builts, operating & maintenance manuals, and training of user
personnel. '
13. Failure to maintain clean efficient, safe working conditions.
14. Do your own punchlists.
15. Pretest special systems - equipment start-up.
16. Untimely delivery of owner equipment.
17. Slow payment.
18. Design errors and omissions.
19. Resistance to solving problems perceived as contractor problems.
:2. 2.5"
RalphJ. Stephenson, P. E.
Consulting Engineer
December 3, 1997
2. Charter objectives
2.2.':;
RalphJ. StephenSQn, P. E.
Consulting Engineer
December 3, 1997
a) Submittals
2...27
Ralph J. Stephenson,. P. E.
Consulting Engineer
December 3, 1997
d) Legal matters
(1) No litigation.
(2) Settle disputes at originating level.
e) Abatement
(1) Establish, approve and publish a plan of abatement.
(2) Abate promptly.
f) Planning and scheduling
(1) Provide, obtain, and use accurate activity information.
(2) Oearly monitor the project against the plan and schedule.
(3) Commit to, and fulfill man hour projections.
g) Decision making
(1) AlE team to regularly inspect work and advise compliance.
(2) Define and clearly communicate quality expectations.
(3) Properly empower those at all decision making levels.
h) Policies and procedures
(1) Prepare, review, approve and publish polides and procedures that will serve as
guidelines to manage the project
j) Processing revisions
DESTRUCTIVE CONFLICT
Animosity or disagreement
which results in lowering
the potential for an
individual or organization
to succeed.
ho382 Dec 95
RalphJ. Stephenson,P. E., P. c..
Consulting Engineer
• Greed.
• Incorrect assumptions made from biased perceptions.
• Demands for higher quality than specified.
• Failure to meet commitments.
• Insufficient time to make required decisions.
• Lack of ability to do the job.
• Poor or inadequate training.
• Inadequate credentials to do the job.
• Indifferent leadership.
• Actual or perceived overwork.
• Bad blood among participants.
• Desire to take advantage of those in weaker positions .
• Misplaced attempts to demonstrate who is in charge.
2.31
Ralph J. Stephenson, P. E., P. C•.
Consulting Engineer
2. '32
RalphJ. Stephenson PE PC
Consulting Engineer
OBLIGATIONS
ho384 Dec 95
Ralph]. StephensonP.E. P.C.
Consulting Engineer
NEEDS
NEEDS
PEOPLE
ho 383 Nov, 93
£.3(.
Ralph J. Stephenson PE PC
Consulting Engineer
POSITIVE CONFLICT
ho385 Dec 95
Z. ~7
Ralph J. Stephenson, P.E., P.C.
Consulting Engineer
WHAT IS PARTNERING?
d) Adding value.
e) Improving communication.
• 3. Partnering is an agreement in
principle, and must not supersede or
supplant the planning, design, and
construction contracts in place or to be
written and executed.
• Strategic partnering
.,e,¥o
Ralph J. Stephenson, P. E., P. C.
Consulting Engineer
• Organizational partnering
PARTNERING SYSTEM
SYSTEM
THE USER.
COMPONENTS OF A PROJECT
PARTNERING SYSTEM
PROBLEM MENTIONS
Problem Type
1 - JMA - Job management - 1146 mentions
2 - CWO - Communicating with others - 984 mentions
3 - SMA - Staff morale & attitudes - 684 mentions
4 - pap - Personnel quality & problems - 593 mentions
Number 5 - ONN - Being a good on-site neighbor - 475 mentions
of 6 - T AC - Timely action - 467 mentions
Mentions 7 - PAS - Planning and scheduling - 396 mentions
8 - OAR - Organization, authority & responsibility - 371 mentions
1200 JMA
ON:]
~ 1000
1\
"'
800 SMA
600
PAS OAR
400
200
0
1 2 3 4 5 6 7 8
Problem Type 09/20/95
l
l l,
Ralph J. Stephenson, P. E., P.C.
Consulting Engineer
A. Approval Processes
B. Being AGood Off/On Site Neighbor
C. Closing Out the Project
D. Communicating With Others
E. Decision Making
F. Documents and Documentation
G. Financial Matters
H. Inspection and Testing
I. Issue, Conflict, and Problem Resolution
J. Job Management
K. Legal Matters
L. Maintaining Regular Project Evaluations
M. Organization, Authority, and Responsibility
N. Planning and Scheduling
O. Payment Processing
P. Personnel Quality and Problems
Q. Regulatory Agency Matters
R. Revision Processing
S. Staff Morale and Attitudes
T. Submittal Processing
U. Work-site Conditions
Don't hesitate to change wordings since it is entirely possible that your expression of
a desired objective may be different than that of the original.
A. Approval Processes
of the project.
12. Limit th~ release of public information through the owner's deSignated
representative only.
13. Anticipate, identify, and accurately communicate potential job problems
14. Ask questions and request information clearly and accurately
15. Be sensitive to the informational needs of the design and construction team
partners.
16. Communicate all issues in a timely fashion to all those affected by the issues.
17. Communicate clearly, accurately and in a timely manner through
2.,~' ~
Ralph J. Stephenson, P. E., P.C.
Consulting Engineer
26. Prepare well for progress meetings and make them brief and productive.
27. Promptly prepare and respond to requests for information, substitutions, and
clarifications of project documents.
28. Provide adequate data re: user-furnished equipment for construction to
proceed as desired.
29. Provide timely communications, responses, decisions ... and be available.
30. Recognize that project conditions and decisions affect other partners in
31. Regularly monitor and discuss, all anticipated outages with utility company
and subcontractor input and provide maximum possible notice to the user of
anticipated outages.
32. Respond promptly to requests for information and clarifications of contract
documents.
33. Stay in touch with the project, i.e. reading meeting minutes, attending
34. Prepare, publish and adhere to the lines of communication, authority, and
responsibility for the school building partnering team.
35. Prepare and respond promptly and completely to requests for information
and clarification of contract documents.
E. Decision Making
36. Make decisions in a timely manner and stand by the agreements you have
made.
37. Make timely decisions in all project related matters.
38. Provide adequate backup data, within expectations, to allow timely and
39. Recognize that project conditions and decisions affect other partners in
G. Financial Matters
41. Practice fairness in price proposals, backcharges, and all other financial
matters.
42. Provide for timely and professional technical inspection services with
43. Maintain the current issue resolution policy. (The current policy stresses the
resolution of conflict at the originating or lowest possible working level.)
44. Minimize disputes and resolve conflicts quickly and at the lowest possible
management level.
45. Prepare and publish an issue resolution policy which stresses the timely
resolution of conflict at the originating or lowest possible management level and
seeks to avoid litigation.
46. Prepare, publish, and implement a dispute resolution system designed to
resolve conflicts at the lowest possible management level.
47. Strive to resolve job conflicts quickly and at the originating or lowest possible
level.
I. Job Management
48. Anticipate events - be proactive.
49. Avoid surprises!
50. Be familiar With the contract documents.
51. Carefully evaluate and be sensitive to the impact that construction activities
may have on the environmental integrity and safety of all ongoing hospital
opera tions.
52. Continue to implement the partnering evaluation system (involving new
participants).
53. Continue to improve and implement agreed-upon project procedures that
provide all stakeholders guidelines for:
54. TIme commitments for procedures.
55. Prioritizing aSSignments.
2.4(, d'
Ralph]. Stephenson, P. E., P.C.
Consulting Engineer
56. Design and construct a facility that is built so as to recognize the need for the
builders and the designers to achieve a reasonable financial profit on their work.
57. Design and construct a facility that is built within the time and cost terms of
the lease-purchase documents.
58. Develop a organizational matrix showing lines of communication and
responsibility to be maintained on the project.
59. Encourage the participation of all parties at all project levels in the
partnering process and the partnering spirit.
60. Enforce the construction traffic and parking plans.
61. Foster understanding of construction documents
62. Identify and remedy incorrect performance in a timely manner.
63. Insure that each of their management team members is fully aware of the
requirements of the project.
64. Keep current with project status and requirements.
65. Keep paperwork to a minimum.
66. Maintain a close relationship between expectations and reality
67. Maintain a continuous and efficient work force and effective procurement to
ensure quality, sequence, and schedule
68. Maintain an adequate management and work force to fulfill contract
commitments.
69. Maintain client safety and user satisfaction during construction.
70. No surprises
71. Plan for and meet the human resource requirements of the project, and
maximize opportunities for women and minorities.
72. Plan for future service access to equipment during mechanical, electrical and
plumbing installation.
73. Plan for the future not for the past.
74. Prepare and publish a calendar of project events indicating when key
personnel are required to participate in project management activities. Partners
will attend and participate in all required meetings and provide backup
management where necessary.
75. Preplan work recognizing the impact plans have on achieving the design
intent.
76. Properly staff and maintain competent personnel, and equipment required
on the project.
77. Provide proper resources to support the agreed-upon plan and schedule of
work.
78. Provide resources to fulfill contract & charter obligations.
79. Recognize and be sensitive to the needs of other stakeholders on the project.
80. Strive for a zero punch list.
81. Use human and technological resources to their maximum effectiveness.
K. Legal Matters
Q. Payment Processing
107. Do it right the first time and strive to achieve a zero punch list.
108. Prepare, publish, promote, and adhere to standards of work place conduct.
109. Work closely with all regulatory agencies to assure compliance to their
current standards and regulations.
R. Revision Processing
110. Accurately price changes to the project in a timely, reasonable and fair
manner.
supplemental agreements.
113. Control revisions being considered for the project to maintain the planned
budget.
114. Prepare and implement guidelines for screening proposed changes to the
project prior to requesting formal pricing of the changes. (owner, user, designers)
115. Provide accurate data and adequate time to ensure pricing changes that are
fair and timely.
116. Provide reasonable change request budgets and identify insufficient budgets
promptly.
117. Provide reasonable field change orders and change issue budgets, and
accurately price changes to the project in a timely, reasonable, and fair manner.
118. Be available.
119. Be cooperative.
120. Be willing to suggest and consider cost and time effective options.
121. Establish a trustful work environment with other stakeholders.
122. Establish and maintain good informal working relations on the job.
123. Extend the spirit of partnering to all project participants.
124. Have fun!
125. Have fun and celebrate the successful completion of the project.
126. Maintain high job morale and cooperative attitudes among all project
participants.
127. Make the project a fun place to work and to meet new friends.
128. Promote and adhere to acceptable standards of conduct by the project team
achieved.
matters.
T. Submittal Processing
138. Prepare, package, and process submittals in a timely, fair, and considerate
manner consistent with the priorities of the contractors, designers, and owner.
139. Promptly review and determine the merit of properly submitted requests
U. Work-site Conditions
2..~'- "
Ralph J. Stephenson, P.E., P.C.
Consulting Engineer
• 2. A preconstruction management
system to set operating ground rules not
covered by the contract.
information for the business, government, and volunteer sectors in political geographic units
worldwide.
The information they collect, process, and sell is primarily concerned with methods by which wealth,
value, currency or other equivalents interact with the market places in which they are used as a
medium of exchange.
The company maintains information collection and market operations from offices located in 25
cities world wide. The home office is in the community of Telitreck, North Dakota. Telitreck has a
population of 120,500 people. Of these 1,500 work for NSEDS.
All data analysis is done at the home office and dispatched to the point of use electronically, and by
"To derive useful micro to macro global economic information from statistical data, and to
provide this information to our clients in accurate, easily used, and highest value-added form."
The company is family founded, owned, and operated. Family members have been actively involved ..J
in the direction of the firm for 51 years.
II. Facility types
A. New office and data processing center building.
1. 200,000 square feet on three floors and a lower level.
2. Reinforced concrete frame.
3. Patterned masonry exterior skin and panelized curtain wall.
4. Full amenities for employees and visitors.
B. Remodel existing building after move in to new building.
1. Existing building.
c) Plain face brick exterior skin. Good brick appearance. Punched windows.
2. Remodeled building.
a) Each floor completely gutted and remodeled.
b) Add full amenities for employees and visitors compatible with new addition.
c) Exterior skin fully renovated, pointed, and cleaned.
C. Site work for new office and for remodeled building.
1. Construct new parking - 1050 cars.
2. Rebuild existing parking lot· SOO cars.
3. Construct new retention pond.
4. Construct new employee recreation area.
1 ho412
Ralph}. Stephenson, P. E., P. C.
Consulting Engineer
2 ho412
Ralph}. Stephenson, P.E., P. C.
Consulting Engineer
3 ho412
Ralph J. Stephenson, P. E., P. C.
Consulting Engineer
The NSEDS Corporation, and their design and construction consultants intend to encourage, support
and implement a partnering system on their expansion program with the full participation of the
contractors and their subcontractors.
Partnering is a performance system designed to achieve an optimal relationship between all parties
to a construction contract. Further, it is a method of conducting business in the planning, design and
construction profession without unnecessary, excessive or disruptive external party involvement.
The partnering system is structured to draw on the strengths of each participating organization to
identify and achieve mutually profitable objectives.
The partnering system will consist of three main elements, preparation of a partnering charter,
establishing and implementing a partnering effectiveness evaluation technique, and establishing and
implementing an issue resolution procedure.
Contractors will be required to participate in establishing these three elements of the partnering
system in conjunction with the NSEDS Corporation and its consultants.
It is anticipated that within 14 calendar days of the issuance of a notice to proceed with construction,
the NSEDS Corporation, its consultants, and the prime contractors on the project will participate,
with their subcontractors, in a one day meeting to write a partnering charter.
The partnering charter is the basic manual for operating a partnering system. It includes at a
minimum the mission of the project, and the objectives of the project tearn. In addition it outlines in
broad terms, the project evaluation methods to be used, and the dispute resolution process to be
applied to conflict issues as they arise on the job.
It is anticipated that within 14 calendar days after the partnering charter meeting that a partnering
evaluation task force will be appointed by mutual agreement among the partnering charter
participants, and will meet to establish and publish a partnering effectiveness evaluation method.
This partnering evaluation method will set guidelines for measuring project performance as
periodically measured against the mission and objectives set out in the charter.
Also within 14 calendar days after the partnering charter meeting a mutually selected issue
resolution task force will be appointed from the partnering charter participants. This task force will
establish and publish an issue resolution procedure encouraging the use of alternative dispute
resolution (ADR) techniques.
Alternative resolution methods are voluntary, and designed to help resolve conflicts qUickly,
satisfactorily, and as near as possible to the originating level of the conflict.
As a part of their expected contract performance each party will be expected to participate in the
preparation and maintenance of the charter, the periodic evaluations, and the issue resolution
process. Outside costs for effectuating the partnership will be mutually agreed to by all parties.
Sample charter
I. Charter for new Detroit, Michigan Post Office, Area P
A. Mission
This partnering team commits to deliver a quality project on time, within budget, safely,
profitably for all, and of the intended quality, through mutual cooperation among the
participants.
B. Objectives
1. Maintain a clean and well maintained work site
b) Be a good neighbor.
d) Be available.
In all cases, individuals who are involved in a difference should be businesslike and not resort
to personal attack. The principles outlined in the Partnering Charter mission and charter should
be followed at all times in resolving differences.
Upon request, site meetings will be convened to discuss any unresolved issue and to attempt to
reach resolution. Any issue presented should be dearly defined and alternative solutions
suggested. The resolution process is to work through open communication and looking at the
other side's point of view. In addition, issues are to be kept in the forefront to ensure resolution
in a timely manner. A log of unresolved issues will be maintained from meeting to meeting.
if resolution cannot be reached at the job site, the principals of the involved firms or agencies
should attempt to reach resolution through informal discussion before the formal process
outlined in the contract documents is used.
If resolution is not achieved at the lowest level forum, the principals in the firms in conflict will
attempt to reach resolution thorough informal discussion.
Ill. Partnering evaluation
Each objective in the Charter is to be initially given a par weight. The par weight indicates how
important the item is perceived by the charter partners in relation to achieving the project mission.
Weights are assigned from 1 to 5. A weight of 5 indicates that the objective is of critical importance in
achieving the project mission. A weight of 1 indicates that the objective is of least importance when
evaluated against the highest weighted objectives.
The weights assigned to the objectives remains constant throughout the project. Therefore care must
be taken in assigning them properly at the start of the evaluation process.
The quality of the project performance in relation to the Partnering Charter objectives is to be
measured once per.month by representatives of all organizations participating in writing the
Charter. Partnering performance quality ratings are to be from 1 to 5.
A quality rating of 1 indicates very poor performance with little adherence to the standards set out
by the objectives. A quality rating of 5 indicates high and excellent adherence to standards set by the
objectives.
The total evaluation of the objective is the constant weight multiplied by the quality rating for each
objective for each evaluation. The total partnering performance is measured at each evaluation.
Total partnering performance = total of the objective weights x the total of the objective quality for
the period.
A comparison of current to past performance and to the expected par should be carefully analyzed
by the charter partners for trends both good and bad. Action on trends should be taken promptly
....J
after the analysis - maintaining good performance if the trend is up, and correcting poor
performance if the trend is down. The charter is the report card standard of performance.
02. Effectively administer the project 4.50 3.75 16.88 3.50 15.75
03. Close out project in a proper and timely fashion 4.00 3.50 14.00 2.00 8.00
04. Maintain effective lines of communication 4.25 3.75 15.94 3.00 12.75
07. Maintain technical excellence in all program, 3.50 3.00 10.50 3.25 11.38
design and construction work
!'\ 08. Maintain good job morale and attitudes 2.50 2.25 5.S3 2.00 5.00
""" 09. Maintain partnering effectiveness 4.00 3.75 15.00 3.25 13.00
2.;-7
RalphJ. Stephenson,P. E.,P. C•.
Consulting Engineer
-a.Partnering
-b.Proper risk allocation
-c.lncentives,
disincentives
Non Binding Binding
Resolution Resolution
02· INTERNAL
NEGOTIATIONS
AREAS
-a. Direct negotiations AREA OF PROJECT
-b.Step negotiations DISPUTE RESOLunON
CONTROLLED BY NON
PROJECT PAR7lCIPANTS
J
ab.Dlspute resolution
board -b.Private,udg
-c.lndependent advisory
opinion
EXTERIOR INSIDE OF
a mutually acceptable
contract is in etrect for
the project. -..Mediation
-a.Bench trial
ab.Minitrial
-c.Advisory opinion .b.Jury trial
ad.Advlsory
arbitration
FIGURE 1 ~ This line XX Is 1 e
critical transltle Ralph J. stephenson, P. E., P. C.
point where pre ,eet
ROUTE OF ISSUE & dispute resolut n
Consulting Engineer
October 16, 1993
DISPUTE RESOLUTION ho 404 dis res steps
Y
x control Is lost by
proJect participants.
d370
4()4
l l l
Z.G.-o
Ralph}. Stephenson,P. E., P. C•.
Consulting Engineer
RECOMMENDATIONS TO IMPRO\TE
BuSINESS PRACTICES
2. '-I
Ralph]. Stephenson, P. E., P. C,.
Consulting Engineer
• Listen well.
2.t,;.Z
Ralph J. Stephenson, P. E., P. C,.
• Be available.
accomplish anything"
component.
PLAN VISIBLY!
ho 284 December 93
I
.$,.0/
Ralph J. Stephenson PE PC
Consulting Engineer
ho 281 Nov 89
Ralph J. Stephenson PE PC
Consulting Engineer
1 ho 216 - December, 93
Ralph J. Stephenson PE PC
Consulting Engineer
interconnections
a. Formal
b. Informal
c. Reporting
d. Staff
e. Temporary
3. Make clear cut assignments
a. The manager should not assume a person will automatically
know his full pattern of responsibilities.
b. Don't leave definition of authority and responsibility to
chance. Be specific.
4. Build a feedback system
a. Organizational grapevines are often used for informal
feedback
b. Formal feedback systems should be built by specific
assignment (must have a standard of project performance
defined before a formal feedback system can be put in place)
5. Keep organization goal and objective oriented
a. Keep organization lean - avoid unnecessary staffing
b. Provide delegation and training opportunities
c. Tend to build around objectives and needs rather than people
(there are major exceptions to this - distinguish these early)
d. Provide for proper grading of decision to action time spans
2 ho 216 - December, 93
Ralph J. Stephenson PE PC
Consulting Engineer
3 ho 216 - December, 93
RALPH J. STltPHBlNSON. P. E.
OONl!n::rIl1'XNG ENGfNElIIK
SymbolS
1. Arrow or task )
A single definable action (or a single grouping of a number
of definable actions) requiring resources.
2. Circle or node ~
The starting or ending point of a task •••• a momentary
point in time.
4. Assign durations •
Hlo 3
RALPH J. STmPllENSON. P. E.
CONl!Iln.TING EIII'Gtl!l'~1!lR
-2
Hlo 3
Ralph J. stephenfOll PE PC
DefInition - A single definable action (or a single grouping of a nlrnber of definable actions) requiring resources.
DefInition - The starttng or ending point of a 1ask .... a momentary point In time.
3. a. Dotted or dummy arrow • for arrow diagramming
---~
b. Solid relation arrow· for precedence diagramming
•
Definition· A &ymboI representing the existence of a relaflonshlp between tasks. Dummies and retational arrows
Ryles for numbering nodes (for grrow diaaramrnlna) gnd tasks (tor precedence djggrgmmlng>
The I node Is the Initial node, and the J node Is the end node of a task
is numbered.
4. In arrow diagramming a node having a single arrow entering or leaving does not
have to be numbered unless the imriiedlately preceding node has not been nUmbered.
....J
ho 261 Dec,90
Ralph J. Stephenson,. P. E... p.e.
Consulting Engineer
CPM Exercise #1
,
(
I
I
I
I
- ~- ..,
.
I
·1
I
-
H/O 187
RALPH J. S'l"lIlPBENSON. P. E.
OOJll'B'C'J:.I1'DII'G E:BGtlII'JDJIIK
R..A.LPH J. STlIlPlDIlNSON. P. E.
00~G JilNGnnIIBB
~
,~
'-Q
Q,.
J
1
'Q..
t
I
~ ~
+
I
I
.,
"')
I~
......
::t
'" +
""
1(- ~
.... 'U
t. ~
'Cl \J V.
L,,--J
.. I •
"'( Q
t, •
~~
J/z
H!O 129
Ralph J. Stephenson PE PC
Consulting Engineer
~~-----:-----4•.'
If!
B D
c
(0 5 •
48 53
x
Late Finish Calculations
/
w
~
y
100
5 •
lOS
101 106
lOS
ho 293 - Dec 90 1(8
JAN 2000 3 45 5 90 11 135 13 180 15 225 JAN 2001 5 300 7 345 11 390 13 435 15 480
3 1 6 46 8 91 12 136 14 181 16 226 2 256 6 301 8 346 12 391 14 436 16 481
4 2 7 47 9 92 13 137 15 182 17 227 3 257 7 302 9 347 13 392 17 437 19 482
5 3 8 48 10 93 14 138 18 183 20 228 4 258 8 303 10 348 16 393 18 438 20 483
6 4 9 49 11 94 17 139 19 184 21 229 5 259 9 304 11 349 17 394 19 439 21 484
7 5 10 50 12 95 18 140 20 185 22 230 8 260 12 305 14 350 18 395 20 440 23 485
10 6 13 51 15 96 19 141 21 186 24 231 9 261 13 306 15 351 19 396 21 441 26 486
11 7 14 52 16 97 20 142 22 187 27 232 10 262 14 307 16 352 20 397 24 442 27 481
12 8 15 53 17 98 21 143 25 188 28 233 11 263 15 308 17 353 23 398 25 443 28 488
13 9 16 54 18 99 24 144 26 189 29 234 12 264 16 309 18 354 24 399 26 444 29 489
14 10 17 55 19 100 25 145 27 190 30 235 15 265 19 310 21 355 25 400 27 445 30 490
17 11 20 56 22 101 26 146 28 191 DEC 2000 16 266 20 311 22 356 26 401 28 446 DEC 2001
18 12 21 57 23 102 27 147 29 192 1 236 17 267 21 312 23 357 27 402 OCT 2001 3 . 491
19 13 22 58 24 103 28 148 OCT 2000 4 237 18 268 22 313 24 358 30 403 1 447 4 492
20 14 23 59 25 104 31 149 2 193 5 238 19 269 23 314 25 359 31 404 2 448 5 493
21 15 24 60 26 105 AUG 2000 3 194 6 239 22 270 26 315 29 360 AUG 2001 3 449 6 494
24 16 21 61 30 106 1 150 4 195 7 240 23 271 27 316 30 361 1 405 4 450 7 495
25 17 28 62 31 107 2 151 5 196 8 241 24 272 28 317 31 362 2 406 5 451 10 496
,'"
~ 26
27
28
31
18
19
20
21
29
30
31
63
64
65
APR 2000
JUN
1
2
5
2000
108
109
110
3 152
4 153
7 154
8 155
6 197
9 198
10 199
11 200
11
12
13
14
242
243
244
245
25 273
26 274
29 275
30 276
29 318
30 319
APR 2001
2 320
JUN
1
4
5
2001
363
364
365
3
6
7
8
407
408
409
410
10
11
8
9
452
453
454
455
11
12
13
14
491
498
499
500
'~
FEB 2000 3 66 6 111 9 156 12 201 15 246 31 277 3 321 6 366 9 411 12 456 11 501
~ 1 22 4 67 7 112 10 157 13 202 18 247 FEB 2001 4 322 7 367 10 412 15 457 18 502
~ 2
3
23
24
5
6
68
69
8
9
113
114
11 158
14 159
16 203
17 204
19
20
248
249
1 278
2 279
5 323
6 324
8
11
368
369
13
14
413
414
16
17
458
459
19
20
503
504
4 25 7 70 12 115 15 160 18 205 21 250 5 280 9 325 12 370 15 415 18 460 21 505
7 26 10 71 13 116 16 161 19 206 22 251 6 281 10 326 13 371 16 416 19 461 24 506
8 27 11 72 14 111 11 162 20 207 26 252 7 282 11 327 14 372 17 417 22 462 26 501
9 28 12 73 15 118 18 163 23 208 27 253 8 283 12 328 15 373 20 418 23 463 27 508
10 29 13 74 16 119 21 164 24 209 28 254 9 284 13 329 18 374 21 419 24 464 28 509
11 30 14 75 19 120 22 165 25 210 29 255 12 285 16 330 19 375 22 420 25 465 31 510
14 31 17 76 20 121 23 166 26 211 13 286 17 331 20 376 23 421 26 466
15 32 18 77 21 122 24 167 27 212 14 287 18 332 21 377 24 422 29 467
16 33 19 78 22 123 25 168 30 213 15 288 19 333 22 378 27 423 30 468
17 34 20 79 23 124 28 169 31 214 16 289 20 334 25 379 28 424 31 469
18 35 21 80 26 125 29 170 NO" 2000 19 290 23 335 26 380 29 425 NO" 2001
21 36 24 81 27 126 30 171 1 215 20 291 24 336 27 381 30 426 1 470
22 37 25 82 28 127 31 172 2 216 21 292 25 337 28 382 31 427 2 471
23 38 26 83 29 128 SEP 2000 3 217 22 293 26 338 29 383 SEP 2001 5 472
24 39 27 84 30 129 1 173 6 218 23 294 27 339 JUl 2001 4 428 6 473
25 40 28 85 JUl 2000 5 174 7 219 26 295 30 340 2 384 5 429 7 474
28 41 MAY 2000 3 130 6 175 8 220 27 296 MAY 2001 3 385 6 430 8 475
29 42 1 86 5 131 7 176 9 221 28 297 1 341 5 386 7 431 9 476
MAR 2000 2 87 6 132 8 177 10 222 MAR 2001 2 342 6 387 10 432 12 477
l l l
( ( (
JAN 2002 5 555 7 600 11 645 13 690 15 735 JAN 2003 5 810 7 855 11 900 15 945 17 990
2 511 6 556 8 601 12 646 16 691 18 736 2 766 6 811 8 856 14 901 16 946 18 991
3 512 7 557 9 602 15 647 17 692 19 737 3 767 7 812 9 857 15 902 17 947 19 992
4 513 8 558 10 603 16 648 18 693 20 738 6 768 10 813 12 858 16 903 18 948 20 993
7 514 11 559 13 604 17 649 19 694 21 739 7 769 11 814 13 859 17 904 19 949 21 994
8 515 12 560 14 605 18 650 20 695 22 740 8 770 12 815 14 860 18 905 22 950 24 995
9 516 13 561 15 606 19 651 23 696 25 741 9 771 13 816 15 861 21 906 23 951 25 996
10 517 14 562 16 607 22 652 24 697 26 742 10 772 14 817 16 862 22 907 24 952 26 997
11 518 15 563 17 608 23 653 25 698 27 743 13 773 17 818 19 863 23 908 25 953 28 998
14 519 18 564 20 609 24 654 26 699 29 744 14 774 18 819 20 864 24 909 26 954 DEC 2003
15 520 19 565 21 610 25 655 27 700 DEC 2002 15 175 19 820 21 865 25 910 29 955 1 999
16 521 20 566 22 611 26 656 30 701 2 745 16 776 20 821 22 866 28 911 30 956 2 1000
17 522 21 567 23 612 29 657 OCT 2002 3 746 17 777 21 822 23 867 29 912 OCT 2003 3 1001
18 523 22 568 24 613 30 658 1 702 4 747 20 778 24 823 27 868 30 913 1 957 4 1002
21 524 25 569 28 614 31 659 2 703 5 748 21 779 25 824 28 869 31 914 2 958 5 1003
22 525 26 570 29 615 AUG 2002 3 704 6 749 22 780 26 825 29 870 AUG 2003 3 959 8 1004
23 526 27 571 30 616 1 660 4 705 9 750 23 781 27 826 30 871 1 915 6 960 9 1005
24 527 28 572 31 617 2 661 7 706 10 751 24 782 28 827 JUN 2003 4 916 7 961 10 1006
~
25 528 29 573 JUN 2002 5 662 8 707 11 752 27 783 31 828 2 872 5 917 8 962 11 1007
"
\' 28 529 APR 2002 3 618 6 663 9 708 12 753 28 784 APR2003 3 873 6 918 9 963 12 1008
29 530 1 574 4 619 7 664 10 709 13 754 29 785 1 829 4 874 7 919 10 964 15 1009
30 531 2 575 5 620 8 665 11 710 16 755 30 786 2 830 5 875 8 920 13 965 16 1010
''l! 31 532 3 576 6 621 9 666 14 711 17 756 31 787 3 831 6 876 11 921 14 966 17 1011
~ FEB 2002 4 577 7 622 12 667 15 712 18 757 FEB 2003 4 832 9 877 12 922 15 967 18 1012
1 533 5 578 10 623 13 668 16 713 19 758 3 788 7 833 10 878 13 923 16 968 19 1013
'"
'-l 4 534 8 579 11 624 14 669 17 714 20 759 4 789 8 834 11 879 14 924 17 969 22 1014
5 535 9 580 12 625 15 670 18 715 23 760 5 790 9 835 12 880 15 925 20 970 23 1015
6 536 10 581 13 626 16 671 21 716 24 761 6 791 10 836 13 881 18 926 21 971 24 1016
7 537 11 582 14 627 19 672 22 717 26 762 7 792 11 837 16 882 19 927 22 972 26 1017
8 538 12 583 17 628 20 673 23 718 27 763 10 793 14 838 17 883 20 928 23 973 29 1018
11 539 15 584 18 629 21 674 24 719 30 764 11 794 15 839 18 884 21 929 24 974 30 1019
12 540 16 585 19 630 22 675 25 720 31 765 12 795 16 840 19 885 22 930 27 975 31 1020
13 541 17 586 20 631 23 676 28 721 13 796 17 841 20 886 25 931 28 976
14 542 18 587 21 632 26 677 29 722 14 797 18 842 23 887 26 932 29 917
15 543 19 588 24 633 27 678 30 723 17 798 21 843 24 888 27 933 30 978
18 544 22 589 25 634 28 679 31 724 18 799 22 844 25 889 28 934 31 979
19 545 23 590 26 635 29 680 NO" 2002 19 800 23 845 26 890 29 935 NOV 2003
20 546 24 591 27 636 30 681 1 725 20 801 24 846 27 891 SEP 2003 3 980
21 547 25 592 28 637 SEP 2002 4 726 21 802 25 847 30 892 2 936 4 981
22 548 26 593 JUl 2002 3 682 5 727 24 803 28 848 JUl 2003 3 937 5 982
25 549 29 594 1 638 4 683 6 728 25 804 29 849 1 893 4 938 6 983
26 550 30 595 2 639 5 684 7 729 26 80S 30 850 2 894 5 939 7 984
27 551 MAY 2002 3 -640 6 685 8 730 27 806 MAY2003 3 895 8 940 10 985
28 552 1 596 5 641 9 686 11 .131 28 807 1 851 7 896 9 941 11 986
MAR 2002 2 597 8 642 10 687 12 732 MAR 2003 2 852 8 897 10 942 12 987
1 553 3 598 9 643 11 688 13 733 3 808 5 853 9 898 11 943 13 988
4 554 6 599 10 644 12 689 14 734 4 809 6 854 10 899 12 944 14 989
CPM EXERCISE #2
Z2 C6 M4
T4 WI RS
LI S3 U2
X3 BI A2
N4 D2 F3
02 V3 G4
H3 KI
S./f'
a/o 1/'1
RALPH J. STBPHIDNSON. P. E.
(JO• •Ot4'DfG BtcG,• • •R
.EXERCISE fJ
3./9
H/O 39
02·Z O!l·A 07·8 09·S 11·V 15·G
~
~
'
-.a
)..
20·N
D
41 46
42 47 NETWORK MODEL
43 48 Issue #1 - January 13, 1998
44 49 FOR EXERCISE #2
45 50 exercise #2
WEX PM 99 Project Team
Ian 01
ban 22
ACTIVITY LEGEND
R.alph 1. Stephenson P.E.
Consulting Engineer
323 Hiawatha Drive
Note: Mt. Pleasant, Michigan 48223-9096
Float time shown in this network model is for the sole use of
the WEX PM 99 project team. Use of float time by others
is to be only by written permission of the WEX PM 99 team Sheet #1
bo #527 management
l, l l
.R.A..r..P:B J. STEPHBNSON. P. E.
OO.It'In4'J'R9 . . . . . . . . .
&DRCISB #4
CPM
9/1/74
H/O 89
LAUNDRY LIST EXAMPLE FOR PROJECT PLANNING - Ralph J. Stephenson PE PC
You have completed selection of the type of test pile to be used and must now write the test
speCification, select the number of piles and their location, and layout the piles in the field.
There is a possiblilityof saving &using the test pile cluster for the total building foundation
group. Therefore you plan to retain a test contractor that coukl also be awarded the full piling
installation contract
Load piling
~~~~~~;tiF
LATE FINISH OF
12
121 11 ,. 11 1~~1I 1111 1/1~ 1118 1/11 lo!1l 1/ ~ l!13 2114 ZII1 2119 zl II
~
l\:t
\),\
l (. l
( ( (
13 4 13 5 13 3 o 3
02-PREPARE TEST I 04-APPROVE TEST i 06-LAY OUT TEST 4ft KBttl2 a Pill
PROCEDURES 4 PROCEDURES-5 PILES IN FIELD· 3
TEST PILES· 3
1
74 Til 716 T19
o 0 ./
15 /11
l2l.1l 12111 /" o
~~
121iT
12126
12J11
o
12112
o
12113 1.:/
8 /01~6 f ...
TO! ro: r- I 69:OROEfi
PILE LOCATIONS - 1 DELIVER TESTING
~ EQUIPMENT - 15
1\\
~
2 116
1 0 o o o
1129 1/30 2114 2119 ~19
i~'''''l''!j'''X~l"RI!'YE-t!¥-''BlI'n"E"'_i rj~l"a:l"'RIIl'E""MO-"VI!IE"It"ES-T"" H·E TIR TO SET
LATE FINISH OF
"'"
ACTIVrrv
~
~
'i ToW no.t time ru..lon
E• .,awt E• ., finish
o
.1I2lI. 1129
~
• Activity number
• Activity cluc:rlptlon
• Activity utlmalad duration
In 01..,.... working daye
1/b----1L
t..teflnlsh
I. . . . ., • No.,.,.. 11, , . .
354 tat pi ntwk 318 • dllk 103
ho 354· Noy.
t..te ....
ReHryed activity numbere Relph J. Stepheneon PE
Coneulling Eng"
41 46
323 Hlewethe Drive
Mt. PI...ant, Michigan 48858
ACTIVITY DATA KEY 42
43
47
SHEET
#1
l l l
R...t..LP.B: J. S::t'JI1P:a:m:NSON. P. E.
OOll'BDUl'Dl'G lIlIrGnra:a:a
~~Total
*****
HI 7 10 2 3
719 7127 7/30 817 818 8/21 8/22 8/23 BI24 8128
Of·FAlI " DEL 09-ERECT 1O-f0RM, REINF 12·FORM, RElNF. I...cuRE
PENTHOUSE STRUCT STEEL" "POUR POUR"STRIP PENTHOUSE
STRUCT STEEL" METAl DECK· 7 f - PENTHOUSE FL EOOIP BASES· 2 EQUIP BASES· 3
DECK· IS DECK· 10
~ i 11.LAY
81i3X22
I 13·INSTL PIPE"
6
81211
,.., 911
PENTHOUSE EOOIP HANGERS
INSULa AT PENTHSE· II
RXlFING·4
7, 8129 ~9/
9I1f11)17
8131
'4
7/24
~
~
~
EStImaIIId d.mim
EarlySlart Early Iiniah
7f1
\9~
7, 111!1. 1015
• Activity number
21-1NSTAlL • Ae1iv1ty description
719 ELECT PANElS a • Aclivily estim8led
FEEDERS·S duralion in elapsed
7 , l - workirgdays
1 Q8.0EUVER I
PENTHOUSE
11"76 .1.1LU
FILTERS·ZO
lsIeSllil1 LaIe linish
13 o
_. 10/17 1213 1213
r 2O-MEASURE. i oJ 27.E TIR TO SET"
FAa, DEl & LATE ANISH OF
INSTAll 1----11 ACTIVlTV
DUCTWORK· 13
12/: 1213
m13
~
N
"'l\
041 046
042 047 Luther Mechanical Contractors
043 048 Washington D.C.
044 049
045 050
sheet
ph-1
l l l
(' r
1$ 7 14 3
~ ~aX2 ~9
/1
35 3
1/9 812. !114 9/& 1111
Q3.FI'.i&OEl. lHAV t3.!!>lStAI.I. PIPE i IS·HOISTt.-seT 111-.
PENTHOUSE
~
IlEOOlP MAJOAMECH& StOOiG&
IHSUl& HANGERS AT ELECT EOUIP AT 1-1- - - - - I lOUVERS·.
o PIJNI>.3$ FO:lFIMG.4 PEHTHOUllE • 6 PEHTHOOSE ·3
111.
,. /17
...,
lMS 'j&Jll1 1171
8r.!
~
~
~ !
t ' ..... __, ........ ~ r
IlI&
mNCAM
STOPS MffiOF
EXFAN·2
2
en
I/
~
51-ATT~S
from'
o
_ _-..,;;en
OR!G £iOl
FAN fl'.i HAS
• STOPPED
1111 917
101
5
811 en
i 52-A/E PREPARE
& S\JlIMlT 11l.1l.I.
15·S 'I
8i ale val
15
111211 12114
I 18-INSTAll All I
CONTROlS· 15
8
1110
22·TESI&
INSULATE PIPING!
A1H1-_ _-IAT PEN~HOUSE •
~ '~9
LATE START LATE FINISH
114 1110
~
~
"
CIt..,. Clt'deflOtion
bue plan of
Impact on
EstimaIed dI.Iaticrt
Early start Early firish
"_11 ,""Iy' NETWORK MODEL FOR
~a·A",u"1
5 333 olorloft "'" ord.. CLARION OFFICE BUILDING
lila. 1015
• 21.JNSTAlL
• Activity oomber
• ActIvity deGeliplion
dhlk 181
fENTHOUSE MECHANICAL
ELECT PANELS &
FEEOERS·S
• Activity eslimated eQUIPMENT BOOM 11
duration In elapsed
WOII<ingdays
1176 .I.lIli Buerytd ActIyUy NUmller' Luther Mechanical Contractors
041 046
Washington, D.C.
043 048
044 049
045 D50
ACDVIIY DATA KEY
sheet
ph-1
l.
l
l.
QUESTIONS TO BE ASKED
Who's in charge?
Who's liable?
RALPH J. STEPHENSON
CONSULTING ENGINEER
NETWORK PLANNING ABBREVIATIONS
~
And DA.FD Detail, approve,
At fabricate, deliver
DEMOL Demolish
DIFF Diffuser·
BAL Balance DK Deck
BALe Balcony DPFRF Damp proof
BD Board DR Door
BKFL Backfill DRINKG Drinking
BKFLG Backfilling DRN Drain
BLDG Building DUCTW1C Ductwork
BLKG Blocking DWG Drawing .~
BLT Bolt
BM Beam
BRG Bearing E East
BRK Brick EF Early finish
BSE Base EFRP Excavate, form,
BSl-fi' Basement reinforce, pour
EIB Excavate, install,
backfill
CASD Check and approve ELEC Electric
shop drawings ELEV Elevator
C/B Columns and beams ENERG Energize
CER Ceramic EQUIP Equipment
CL Column line ERCT Erect
CLG Ceiling ES Early start
CLKG Calking E T/R End t iIr,e re straint
CNTL Control EXC Excavation
CO Cutoff EXP Exposed
COATG Coating EXT Exterior
COL Column EXTG Existing
COMP Complete
CONC Concrete
H/O 2
Page 2
RALPH J. STEPHENSON
CONSULTING ENGINEER
\.r F
FAE
For
Fabricate
IAYG Laying
LF Late finish
FD Fabricate, deliver LN Line
FDN Foundation 18 Late start
FFG Fill, fine grade LT Light
FINL Final LTH Lath
FL Floor LVL Level
F11 Fill
FLSHG Flashing
Flvl Fom l>iACH Machinery
FJ:.iG Forming !<lECH 14echanical
FN Finish lV1El..reru.~ Men:..brane
FOG Floor on grade MEZ.Z .Mezzanine
FP Fire protection ME M.anhole
FRM Frame MLLWK Millwork
FliP Form, reinforce, pour MISC MiscelJ.aneous
FRPS Form, reinforce, pour, MK lviake
strip MSNRY Masonry
FTG Footing 1-11'L Metal
FX Fixture Ml'R Motor
ufo .,
Page 3
RALPH J. STEPHENSON
CONSULTING ENGINEER
S South W West
SBSTNTLY Substantially WASHG Washing
SDWK Sidewalk WK Work
SETTG Setting WLKWY Walkway
SEWR Sewer WLL Wall
sm Sheet ~ Window
SIDG Siding WP Waterproofing
SLB Slab WTR Water
SOG Slab on grade W TIE Weather time
SPDRL Spandrel restra.int
SPRNKLR Sprinkler
SS Structural steel
SS Substation
ST start
ST Street
STD Stud
STL Steel
STM Steam
STR Stair
STEP Strip
STRUCT Structural
SUl?T Support
SUHF Surface
SUS? Suspension
Sw"TCHGR Switchgear
SYS System
TT I..... _
RALPH J. STmPEENSON, P. E.
OO".'ln.lrDl'G lCIfGI_JIIIl
1-l
~
Dec. 1
2)4
2
239
1.!.
;:
244
4 1"
.J r~r: • 1
256
2-1/5 2-4/5
2
.,..J 261
2-1/5 2-4/5
266
"':)1
.,/" 11:
L1 271
3
2
..,
....
Feb. 1
277
3
2
282
3 2
3
287
4 1
4
292
Jt 1t
,...
r·!ar.
2
297
302
~z
4t
t
"2
3
307
4 1
!~ 312
Jt 1t
Apr. 1
320
3l1 1.1
4-:2- f
2
325
;>
"l,
330
4 J
h 335
0
H/O 136
Ralph J. Stephenson PE PC
Consulting Engineer
You are the project manager on a domino move realignment of space in a project
adding a 2nd floor to the Bengst Corporation office in Tarry, Montana. The addition
has been closed in and base building work is complete ready for tenant fit up.
The moves needed to complete Bengst tenant fit up involve shifting from 1st floor
occupancy to a combined 1st and 2nd floor use.
Note: The F space is to be remodeled in two phases while being occupied by staff.
To do
1. Prepare a network logic model for the move and remodeling sequence.
2. Quantify and calculate the logic model.
3. Analyze the move sequence and identify when you want to move E and remodel
F.
! ~ ) ...
~
...
~
'"
y~ ~
\
q t.lJ
I
I ---
\) ,
~
.
""
~
"
\J ~ "
"'C C() '-'J
~ ~
HO 209
5
'·MOVE
DEPARTMENT ATO
NEW 2ND FLOOR
SPACE -5
o 15 40 21 110 5
,.TIRTO START OF :1. RETAIN AlE FIRM· 4- PART FflEPARE & 5-COMPlEIE 7- CONSTRUCT NEW II· MOVE
ISSUE It! PfIOJECT 15 ISSue CONTRACT PREPARE'ISSUE OFFICE AOOfTION TO DEPARTMENT B TO
SlNMARY PLAN DOCUMENTS· <40 CONTRACT POINT WHERE MOVE NEW 2ND flOOR
DOCUMENTS-2I IN BEGINS· 110 SPACE -5
15, 110 5
3- RETAIN 6- AWARD 10- MOVE
CONSULTANT CONmACTS. DETAIL, DEPARTMENT E TO
CONl'RACTOR -15 APPV, FAB & DEL NEW 2ND FLOOR
EARLY LONG LEAD SPACE -5
rTCMS-1IO
~
~
~
R_ocdYily . _
MI M6
M2 M7
00 M8
h.allea 044 M9
00 050
o
15- INSTAll. MASTER
• Acllvl17 ......
LOCK SYSTEM (., 5, el • A.....I17 "_,Ipllo•
• 0 (ea""", acli"lyl -11...... ,"' ......
• M .._ d...tloe I • SUMMARY NETWORK MODEL
•..,.... werklat "ap
UENGST CORPORATION
EXPANSION PIdAN
""_ NI -Ja....,. 10
TARRY. MONTANA
247 bonplll1llJ1 pIaa • dlsIr.
Coosuhing Bngw_
l l
l
( , (
20 2 15
11·REMODEl FORMER 13-MOVE DEPT C INTO 15-REMODEl FORMER 17·MOVE DEPT D INTO
DEPT A .. B AREA TO NEW AREA FROM OlD DEPT C AREA INTO NEW AREA FROM OLD
NEW DEPT C AREA· AREAC ·2 NEW DEPT D AREA • AREAD·4
20 15
...
'J
12/9/92 Vyvyan partial laundry list 1
Foundation
Full building
Mechanical
Electrical
Roofing
Roof equipment
Some roof top equipment with screening
Roof screens to be prefinished metal panels
Curbs to be installed with roofing
Equipment can be set later
2.1.8.8. Rough interior work (ri)
Definition - All interior building components that can be exposed
totally or in part to weather.
Above floor rough interior work conventional as for base office
building
Interior partitions all metal stud and dry wall
All rolled shapes to receive spray on fireproofing
No spray on fireproofing on metal deck
2.1.8.9. Finish interior work (fi)
Definition - All building components that must be protected
totally or in part from weather.
Core area
Partitions - stud walls with dry wall taped, sanded & painted
Ceilings
Toilets - painted dry wall
Other areas - aoustic lay in
Floors
Toilet rooms - ceramic
Service areas - resilient tile
Other areas - carpeted
Tenant area
No ceilings - acoustic materials to be stockpiled on floor
Exterior dry wall sill walls to be installed, taped & sanded
2.1.8.10. Systems work (sy)
Definition - All work that can be installed as a system somewhat
isolated from other system components of the building
Three elevators
Two steel stairs
Mechanical and electrical room at basement
2.1.8.11. Site work (si)
Definition - All work outside the building line and inside the
property or hoarding (contract boundary) line. Site work outside
the property or hoarding line is called off site work (os)
All utilities brought into site underground
Electric
Gas
Water
Domestic
Fire protection
Sanitary sewer
Storm sewer
Landscaping sprinklers
Phone
All full depth asphalt paving
Parking lots striped and lit
Site fully landscaped
Sidewalks around building
Landscaped islands throughout parking areas
No wheel stops to be used
.2.2. Laundry lists
2.2.1. Procurement - early
Structural steel
Metal deck
Aluminum
Glass
Early superstructure resteel
Elevator (need dimensions & embeds for pits)
Mesh
Others?
2.2.2.4. Excavate, form, reinforce & pour exterior wall & column footings
'2.2.2.6. Excavate, form, reinforce & pour elevator pit slab on grade
2.2.2.17. Lay vapor barrier and set in floor work for basement slab on grade
indirectly. Also includes site preparation for start of field work on the
building area.
2.2.3.4. 05 - Excavate, form, reinforce & pour exterior wall & column footings
2.2.3.6. 06 - Excavate, form, reinforce & pour elevator pit slab on grade
2.2.3.17. 12 - Lay vapor barrier and set in floor work for basement slab on grade
2.2.5.5. Detail & trim structural steel- tier 1 - basement through 2nd floor
2.2.5.6. Detail & trim structural steel - tier 2 - 2nd through 4th floor
2.2.5.7. Detail & trim structural steel- tier 3 - 4th through 6th floor
2.2.5.8. Detail & trim structural steel - tier 4 - 6th through roof levels
part to weather.
TRANSLATE
ho 379 Dec 91
Ralph J. Stephenson PE PC
Consulting Engineer ~
SCHEDULE
ho 378 Dec 91
Ralph J. Stephenson PE PC·
Consulting Engineer
You and your partner own a small flat work firm, Regal Construction, Inc. located in
northern Missouri. You are Alan Dobson, president ,and your partner is Fred
Mikello, vice president. Both of you came from a large general contractor, the
Rasmussen Company, where you were a senior project manager, and Fred was a
senior field superintendent. The general superintendent for Rasmussen was George
Bushnell, a good friend to both of you.
You each left Rasmussen about eight months ago to start Regal, and have done
reasonably well constructing a small volume of sidewalks, drives and masonry work
along with some earthwork and carpentry. You've been able to purchase a front
loader and are now actively involved in finding ways to keep your equipment and
tradesmen, mostly laborers and cement finishers, busy.
This morning George Bushnell called and said Rasmussen had just been awarded
the general contract on a large educational park. The first of the projects is three
moderate size masonry wall bearing buildings. They must start in the field
immediately, but George says he cannot man the job for another 2 weeks. He asked if
Regal could start within two days on layout, clearing the site and constructing the
concrete and masonry foundations for the first three buildings, A, B & c. Footprint
sizes of the buildings are for A -150' x 200', B - 200' X 250' and C - 200' X 200'.
You reply that you could move on site immediately. George says to give him a rough
budget estimate along with a plan of work, a schedule and an idea of how Regal
would man the job all by tomorrow noon. If the cost and the schedule are in the ball
park you have a job.
The business and management objectives you are thinking about as you consider
how to plan the job include:
1. Maintain the plan of work finally agreed on. Plan the work and then work the
plan!
1 ho 263 - Jan 89
Ralph J. Stephenson PE PC
Consulting Engineer
4. Keep the total time of the job to no more than four and a half weeks.
6. Use equipment you own. Don't rent anything you don't absolutely have to.
You have just put down the phone. How do you proceed from here?
ho 263 - Jan 89
RALPH J. STEPHJDNSON. P.E.
Oo• •~.a JDJfaxwa.R
•• I,... ....,.
Wb-..
"A.5.K~ ~
, (\
~
-,d*A ~
v
12.t.¢ tl
,l.l.. /~ C
...H.•..L~,
U,2M/:)
~~~f:'.£
21..,2MF '
~~c$
.21., *H
21.."~I
,U./e
ZI.,lM ..;
u. /111. ,it.
f
JlC .. /C,
.U,Z.+t '
JJ.,16'M
.I J."
Zt. f/~ -it ¢
N
Z&.IC'
2J.,2,+f1l-p
.l1.//'lQ
:Itt; 1(;
.u .3fI~ It.
".
c
".
C)
;, ~ ~ H tI i J ' I to J ,. J , J , .I .. V..I !l~ ~
" " " i
4 .. $.i"
L I
,
£¢
L¢ I
i
J
I
J?. I
C
CF
-
M
-.
?;-,) rA~
2L,2Af .J
U .I,Q ,K.
le./e,
~i.,lA1 '
JI,,/~'M
;.t.¢ N
,I.e -It ¢
ZI.
2e.le,
2i.2.+1'J1op
~,",1'lQ
2e,IC
u2A~~
,-
~,
~ If • ., 'I ~~ ,
4 ~ . ", j
tt J• I. . "1 .. ,""
~ 11'1It J, ..I ~ .oi tJ.,j 12 ~ P•~. ~.,j ~
c
L \
I
I
£¢
L¢ I:
I
.e.. l
c
CF
-
M
-
k'>'T'At.
·""K~
-
~
.,
.~
_~iN'A
8
G -
,2J.¢ ~
,lJ•• he C
C - .0
Z&.-,&' iL ~ £"1' 1--
U.,2.11 D <t .l iI if - -
p - I'""- 1-- fo .- - -- I-
-l'" 1.1.£
2~./~jf: ~
",,- I-
-- - I-- ~- 1- - _. ~- ~- 1-
2J..I 2MF IT -- I-
- .... - ~-
-
f~~ ~t?
,II
If"
Nf
2.1.'1
2L./~I
~ v:: t/j Vj ~ ~ v: " -.,
2&0/(' A. z. ;,~ ~ ~ ~ '/j V S
.21.~ 2M,.J ttL ~
1/ V 1/ ;/ I/L IL/
I/~V .
U. riA
let/elf'
.K.
.- Vj ~
/ 1&/ ' /
/ / . _. 1--
4
i
I
.?.l,Z"" t L.,.e I~..... '-'
~ /j ~ c& ~ I/,: ~ ~ L/ ,Il AL - --I--' I,
."'" ..., - Lv
:~
/i.J.£flM .1 ,; v v-,; ~ ~ ~ ~ ~ 'l: ~ ~ !J ,
;"¢ N t:'6 ~ ~ L1I'. L
v IL: 'l: ~ ~ ~ l'l ~
2e.lc,-it' ¢
ZI../",
~ ~ ~ ~ ~ ~ VjI i!.t L /
r« ~ "l
.2i,2M*P :2: ~ 'l: 'l; -? 'i: ~ ~ ~ ~, // r.~
~ t& v~ ~
·l1·'/'la
2e,/c ~ ~ ~ ~ ~ ~ ~ ~ :'i ~v:: 1'> ~ ~ :%: ~
AT/
/
L .s
/ / / I. .3 ..j 4 ~ 4 4 ,2 &, II' til U, &, c, Z Z. Z. z .z fJ/
£¢ / / / / / / / 7'
L¢ z. 2.. .2 .2 4 Z. /4
/!!.. / I / / Z 1 / / Z 2. Z Z I /
I
/'9
C
.z z 2. Z 4 2. 2. Z 4 4 4 4 2 ,Z 38
CF
- I / I / Z / / 12.. Z 2 2 1 / Ie:;
-
M 2 Z. 2 Z2 Z i!.. 2- 2 4- 4 Z .2. .z .2. ,2 ...:J~
hrAJ..
2.. 2. 4 4 ~ It) 14 [/4 //!!I It! It! ~ lIP Ib lIP It", /4- 14 4- 4 .¢ 4 4 2/4
'-"-
'.
HO 245
...
........
\.
"~,
\1
~
\l ~
IcJ
\J
,"
~.
\J ~
'l \) \)
'l
~ "'l ~
') "
\1
N ~
'\
407
,
HO 244
~
1-1 / {\
I. I"
,
1 oJ ..,.SII '1
Wb-"
" J ., 10 " IZ ill IS" n M I() 21 t2 P .H l1li & ,; •
·.:SKl. r~
-isi*A
~J.¢ ~
,/J..IA t!
~&.I&'
U.,2~ b - -...- - - ~-
j~:/:'.£ -- I - !- -
2J.~2M ;:
f~4f ~4
-
III
.2J.~ ;til t% t% ~ l'l ~
V~ ~ l'i '~ ~
2L,/'lI
2~.1t:
5
Z',2.M ..;
,u.llt , (
V: /:
/ 'i~
.l£,./c, .~
If,
,U,ZAt i t:%: v: ~ '/ ~ ~ ~ ~: ~/ l'l V::' t'i. r,,; /
/ /:
,iA. I
't\. /~ ~ V/ ~ ~ 'l Vj :I ~/ -,. r,-j V ~~ ~ ~ /
:2It, /C"
I
~"A // r'/ t/ v/ l'l: '/ V/ V/ ~ V/ '/ ~</ ',/ v/ [%'/ [,j v/ v/
- v·'/ ~
C~tt:lNt4y'-iI'
l.t/ .:/v/ :// v:< // ~/ v~ /> ~ V/ v> /; t% V ~ :/j 0
t>
I
~
I I
/
/
/ I
/
1 .; ~ 4 ~
.Ii
. .c.
JIJ V ~ ~ ~
j
i" r
.z 4
J ~
~
J, J It
4 ,;z.
J~
.i!
..
" ..
V ~ .- • <II ~ ..
.z .z .l.
411
'..i~
0 CI
iIft/
~ .z t2. .l .l .l .z Q ..41 .z
~.,..,,,y
r"rAJ " /
ttl 0
I I
.0 Q
I I
/ J
I :..:1 ,l I~ 4 '"
~ I..... ~ ~ ~ 4 ~ IJ#
.~
~ "'"
~
-I
•
I ...
~ I~
2. ,ifI4
J61
£¢ I
L¢
IC
C.
CF
-
_. M
7-~ 7,A/..
-1,/ I
Ralph J. Stephenson, P. E., P.C.
Consulting Engineer
In construction the concept of profit is complex and often misunderstood. There are
many kinds of profit - financial, socioeconomic, value system, self actualization,
education, enjoyment, technical, and probably as many more equally important but
less obvious.
The basic profit potential is realized when the manager and his project team
have made certain to include all project elements in the estimating, planning
and control process; when they have made certain that everything is counted
and there are no missing pieces. Every element missed erodes the profit picture
just as a missing piece of a jigsaw puzzle spoils the pleasure in assembling it.
Once project elements are accounted for they must be properly arranged in a
logic pattern to produce the most effective plan of action. In any plan there are
identified desired and necessary relationships. The proper expression of desired
relations is a major factor in realizing level B profit potential. Here is where the
true skill of the project manager begins to impact upon the job. The
experienced, intelligent, knowledgeable manager will explore, stimulate and
select the most effective ways of assembling the job under his control. The level
B profit potential is highest when the best ways have been selected.
This profit is highest when the job is scheduled well and a selection made as to
where each task should be done in relationship to the discretionary time
available to it. Often discretionary time is identified as float time. Where the
good manager schedules the task when he has resource options ( time, money,
equipment, etc. ) will largely determine how profitable the level C management
work has been;
In a nutshell, level A profit potential deals with identifying all the elements
involved. Level B profit potential is concerned with arranging these elements in a
logical and effective action plan. The level C profit potential is achieved when the
project is managed well by proper scheduling within allowable resource limits.
Float is the amount of time between the earliest date an activity can start, according
to a given plan of work, and the latest date it can start according to the same plan of
work. Float time occurs in a task when the activities that restrain it are able to be
completed before the latest date by which the restrained task must start, as
determined by the latest allowable finish date of the project or project component.
Float time is not assigned by the planner, nor is it automatically allocated to activities
that are traditionally critical.
A few guidelines which have seen general acceptance and some legal concurrence in
practice are given below:
1. In a hard money fixed time contract the float time within the contract boundaries
belongs to the contractor.
2. Ownership of float time should be established very early in a project. Where some
question of ownership exists, the ownership rights should be noted on the plans and
schedules of work prepared by the contractor.
3. On negotiated projects, where there may be a cost and time span to be mutually
agreed on by the contracting parties as the project gets under way, ownership of float
time is usually a matter to be worked out in advance as job conditions demand.
4. Relative to subcontractors, the ownership of float time within a hard money, fixed
cost subcontract is usually set by implied consent, but normally rests with the prime
1 ho 280 - Dec 88
1413
Ralph J. Stephenson PE PC . J
Consulting Engineer ...,
In situations where there is very little interface between a prime contractor's tasks
and his subcontractor's tasks, it is possible that ownership of self contained float may
5. Ownership of float time does not release a contractor from the obligation to
provide a high quality service to the client. Where poor use of float time to the
detriment of the job is encountered, fault for the poor performance will usually
temper the ownership of the float.
In general most problems with float occur where approval delays are
encountered, where intermediate project dates are not specified but are
desired and imposed, when poor performance pushes tasks beyond scheduled end
dates, or where uncontrollable obstacles to meeting project contract obligations
appear.
2 ho 280 - Dec 88
~/.f.
12/9/92 ho 380 - Clarion base network data - issue #1, dated July 7 1
activity
10
11
12
13
14
\..
15
16
17
18
19
20
21
22
23
24
25
26
Acllvill••
Jul '90 I Aug '90 I Sept '90 Ocl '90 I Nov '90 I Dec '90 I
25 2 9 16 23 30 6 t3 20 27 3 10 1724 I 8 15 2229 5 12 1926 3 10 1724 31
OI·T/R TO JULY 7 I
~
09-ERECT STRUCT STEEL & METAL DECK· 7
-
AIR PIPG· 24
2~INSULATE DUCTWORK AT PENTHOUSE· C::::::::::l
12
-~
iii~
22·TEST & INSULATE PIPING AT PENTHOUSE
• 8
24-PAINT INT OF PENTHOUSE, INCLUDING
PIPING· 5 ii~
25-APPLY LIQUID WATERPRFG TO FLOOR· 3
Ii
26-CHECK, TEST & TURN OVER EQUIP ROOM
• 5 Iii
I
rEM ISS OWG AW CT SUB SHD
REV APP
U .....
MECHANICAL
Ir'r'" I
. ..
I BAR/LOUNGE
u '-D·
...
... C
"r-
~!RE
FIRE
I
~~
SEPARATION RESTAURANT
12TH FLOOR
11 "-0·
1: '·0·
~ 1'-0·
~ 11TH FLOOR ,
1'-0
10TH FLOOR
ITH FLOOR
,'-0-
I
I
AT INTERFACE
WITH EXIITINO BUILDING
I
aAD FLOOR "-0
I 2ND FLOOR "-0
, "-0
~
./
I ./ ...
..... 11T FLOOR
FIRE ORADINO 3 RESIDENTIAL
I I
III FIRE IEPARATlON
GRADE
1 8'-0
0
0 ..
::r: I 1.1&
MEZZANINE
t 8'-0
a ... L-- LOWER'LEVEL, __
-
~
l l l
CONTRACT DOCUMENT MATRIX SUMMARY PAGE 1
GRAND TRAVERSE RESORT VILLAGE TOWER & LOW RISE
0106 - RALPH J. STEPHENSON PE PC - DATE PRINTED: J'\~ 1 Z !'ia~
\..,
I S ACTIVI TY DESC AL LB LL LR TW S1 ES REC"
--------------------------------------
A
A
- SET HORIZ & VERT CONTROLS
MASS EXCAVATE TO 677'4
A
A
A
A
4
5
A HAUL EXCAVATION TO BORROW AREA A A 6
A CONSTRUCT HAUL ROAD A 7
A KEEP EXISTING ROADS CLEAN A S
A REMOVE ABANDONED UTIL IN EXCAV AREAS A 9
A STRIP BLDG SITE ~ STOCKPILE TOPSOIL A A 10
A DEMOLISH EXISTING ROAD IN EXCAV AREAS A 11
B OBTAIN FOUNDATION PERMIT B 2S
B EXCAVATE FOOTINGS-NOT FOR SLB ON GRD B B B 14
B ERECT NECESSARY CONSTRUCTION FENCING B 12
B PART BACKFILL AT EXT FOUND WALLS B B 8 B 8 72
B LAY OUT BUILDING 8 13
B BACKFILL INT FOUND TO EL ? S B S 19
B LAY DRAIN TILE AT PITS B 22
S X EFRP PIT SOG B 20
B X FRP EXT LOWER LEVEL WALLS B S B B 15
B X EFRP COL FTGS S B B S 17
B X EFRP WALL FOOTINGS B B B IS
B X DRIVE SHEETING AT EXISTING BLDG B B 23
B X PART APPLY EXT WALL ~TERPROOFING B B 8 B 25
B X PART INSTL EXT WALL DRAIN TILE B B B B B 34
B X FRPS COLS TO LOBBY LEVEL B 24
B X FRPS COLS TO LL MEZZ B B 26
\.., C
C
BACKFILL & COMPACT AT PITS
COMP INSTL DRAIN TILE AT EXT WALLS C
C 21
36
C X APPLY PIT WATERPROOFING C 16
C X FRPS ELEV !5 WALLS TO LB C 27
C X INSTALL TRENCH DRAIN COVERS C C 2.
C X INSTALL STEEL STAIRS & FILL C 31
C COMPLETE PHASE 2 ECAVATION C C C 33
C X FRP PIT WALLS C IS.
C BACKFILL EXT BUILDING WALLS C 3S
C - BACKFILL EXT RETAINING WALL
C X EFRP RETAINING WALL FOOTING
C
C
35
37
C X FRPS RETAINING WALL STEM C 39
C
C
- EXCAVATE FOR ALL SL~BS ON GRADE
POUR OUT SUPPORTED DECKS C
C C
C
C
C
49
53
C DEMOLISH EXISTING CANOPY C 77
C X CURE, PART & TOTAL STRIP SUPTD DECKS C C C 51
C X INSTL ELECT GROUNDING SYSTEM C S2
C X FRPS COLUMNS ABOVE LOBBY LEVEL C C 54
C X FRPS COLS ABOVE LL MEZZ C C C 43
C X CURE, STRIP & RESHORE SUPTD DECKS C C C SO
C X ERECT MISC MTLS RELATED TO SS CONC WOR C 190
C X CONSTRUCT LB SLABS ON GRADE C C 46
C X INSTL MISC IRON SKIN EMBEDS & SUPPORTS C C S6
C X COMP APPLY EXTERIOR WALL WATERPROOFING C 42
C X FORM & SET IN FLOOR WORK FOR SUPTD OKS C C C S5
C X INSTL EXPANSION JOINTS & RELATED EMBED C 44
C X CONSTRUCT LL SLABS ON GRADE C C C C S7
'C X INSTL MATERIAL & PERSONNEL HOIST C 47
~ C X PROVIDE CONTRACT C HOISTING C 4S
C X CONSTRUCT TOWER LL MEZZ DECK C C 41
HO 241 pg1
4.1'1
CONTRACT DOCUMENT MATRIX SUMMARY PAGE 2
GRAND TRAVERSE RESORT VI~~AGE TOWER ~ ~OW RISE
DWo - RA~PH J. STEPHENSON PE PC - DATE PRINTED: J'\:~ 1 ! ~;a)
A~ ~B ~~ ~R TW SI EB REC_
I S ACTIVITY DESC
------------------------------------- D 192
D X FURNISH E~EVATOR EMBEDMENTS
o X INSTA~~ E~EVATOR RAI~S, EQUIP, CAS D :S8
D X INSTA~~ E~EVATOR HYDRAU~IC CY~INDER D 59
E X ERECT ~R META~ F~OOR ~ ROOF DECK E E 108
E X ERECT, P~UMB ~ SO~T ~R STRUCT ST~ ~ JS E E 107
F X INST~ EXT SKIN MISC METALS F 00
F X INSTA~~ S~IDING DOORS F 79
F X INSTA~~ CURTAIN WA~~ G~ASS F 82
F 7~
F X ERECT A~UM SIDING
F X ERECT CURTAIN WA~~ FRAMING F 81
F X INSTA~~ BALCONY RAI~S F 78
G X INST~ P~UMBING FIXTURES G G 145
G X INST~ SPRINK~ER HEADS G G 109
G X INST~ GRI~~S ~ DIFFUSERS G G 139
G X INST~ FAN COI~ UNITS G 142
G X PROCURE FAN COI~ U~ITS G 99
G X PROCURE WATER SOFTENER G 94
G X PROCURE CHI~~ERS G 101
G X PROCURE DOMESTIC WATER TANKS G 93
G X PROCURE 80I~ER G 100
G X PROCURE COO~ING TOWER (OR COND) G 98
G X PROCURE FIRE PUMPS G 90
G X PROCURE HOT WATER TANK G 91
G· X PROCURE DOMESTIC WATER PUMPS G 92
G X PROCURE AIR HAND~ING UNITS G 9:5
G INST AF DOMESTIC MECH PIPING G G 134
G INST~ HARD CEI~ING SUSP ~ B~ACK IRON G G 107
G INST~ STUDS & IN WAL~ WORK G G 104
G X EIB UG UTI~ AT ~~ SLAB ON GRADE G G G G 32
G X INST~ WATER HEATING SYSTEM G G 1:59
G X INST~ OUTSIDE GREASE TRAP G 100
G X INST~ HOOD DUCTS G G G 134
G X EIB UG UTI~ AT ~B ~V~ S~AB ON GRADE G G 30
G X INST~ INSIDE GREASE TRAP G 101
G X INST~ AF SHT MT~ DUCTWK G G 133
G X INST~ ~ PIPE FUE~ TANK G G G 102
G X INSTA~~ ROOF EQUIP CURBS G 104
G X INST~ SIAMESE CONNECTIONS G G 131
G X INSTA~~ ROOF MOUNTED EQUIP G lOS
G X INST~ HOSE BIBBS G G 130
G INST~ MECH S~EEVES G G 12:S
G X INST~ A~~ MECH EMBEDS IN C CONCRETE G 45
G TEST· ~ BA~ANCE MECHANICAL SYSTEMS G G 188
G X INST~ SPRINK~ER SYSTEM G G 132
G X SET & PIPE CHI~~ER G 1:52
G X INSTA~~ WATER HEATING EQUIP G 100
G X SET & HOOK UP JACUZZIS G 143
G X INST~ TOI~ET ROOM ACCESSORIES G G 149
G X INST~ VV BOXES G G 140
H X PROCURE MECH CONTRO~ SYSTEMS H 88
H X INST~ E~ECT TRIM ITEMS H H 123
H X INST~ ~IGHT FIXT H H 120
H X PROCURE EMERGENCY GENERATOR H 87
H X PROCURE TRANSFORMERS H 102
4.20 . HO 241.P g 2
CONTRACT DOCUMENT MATRIX SUMMARY PAGE :3
GRAND TRAVERSE RESORT. VILLAGE TOWER & LOW RISE
0106 - RALF'H J. STEPHENSON PE PC - DATE PRINTED: J;.:I ~ : 'm
I S ACTIVITY DESC AL LB LL LR TW SI EB REC#
H X PROCURE MOTOR CONTROL CENTERS H 97
H X PROCURE UNIT SUBSTATIONS H 86
H X PROCURE SWITCH GEAR H 89
H INSTL ABOVE FLOOR ROUGH ELECT WORt< H H 170
H INSTL HARD CEILING SUSP ~ BLACK IRON H H 16S
H INSTL EXPOSED RUFF ELECT COND & FEEDER H H 119
H X INSTL POWER PANEL BOXES H 117
H X INSTL LIGHT PANEL BOXES H 118
fI X INSTL STUDS & IN WALL WORK H H 163
H I NSTL TV CONDU I T H H 127
H INSTL EMBEDDED ELECT CONDUIT H 115
H INSTL ELECT SLEEVES H H 124
H INSTL EMBEDDED ELECT BOXES H 116
H X INSTL TELEPHONE CONDUIT H H 126
H X INSTL ALL ELECT EMBEDS IN C CONCRETE H 40
H X INSTL FIRE SAFETY CONDUIT H H 128
H TEST & BALANCE ELECTRICAL SYSTEMS H H 141
H X F'ROCURE ELECT CONTROL SYSTEMS H H 114
H X INSTL & HOOK UP ELECT EQUIP H 129
H X INSTL GROUNDING MAT H 121
H X INSTL LIGHTENING ARRESTER SYSTEM H 122
J X FRP EQU I P BASES J J 1
J X PROCURE TRASH COMPACTOR J 90
J INSTL HARD CEILING SUSP & BLACK IRON J J 166
J X INSTL STUDS & IN WALL WORK J J 163
J X ERECT INTERIOR MASONRY J J J J J 62
J X INSTL LINEN CHUTE J 148
J X INSTL TRASH COMPACTOR J 171
J X INSTL TRASH CHUTE J 147
J X INSTALL INT HOLLOW METAL FRAMES J 103
J X INSTALL DOCK LEVELLERS J J 61
J X INSTL SHOWER PANS J J 146
J 0 INSTALL INSULATION AT EXPOSED SOFFITS J J J 63
J X INSTALL PLASTER SOFFITS J J J 80
J HANG BOARD J J 174
J TAPE & SAND BOARD J J 173
J
J
X
X
INSTL ACOUST CLG SUSP ~ GRID
INSTL SIGNAGE
J
J
- J
J
181
183
J X INSTL VANITIES J J 173
J X APPLY FP TO HOOD DUCT J J J 137
J X INSTL APPLIANCES J 130
J X INSTALL PLASTIC LAM DOORS & HARDWARE J 109
J X INSTL RESILIENT FLOORING J J 180
J X INSTALL DUMBWAITER J 2
J X INSTL MILLWORK & TRIM J J 172
J X INSTL INTERIOR LANDSCAPING J J 183
J X INSTL CERAMIC TILE J 144
J X INSTL ACOUST CLG PANELS J J 182
J X INSTL QUARRY TILE J J 179
J X INSTALL INT WOOD DOORS & HARDWARE J 111
J X INSTALL INT HARDWARE J 112
J X INSTALL INT HOLLOW METAL DOORS J 110
J X LAY CARPETING IN CORR & PUBL SPACES J J 177
J X INSTL VINYL WALL COVERING J J 187
4.zl HO 241 pg :3
CONTRACT DOCUMENT MATRIX SUMMARY
PAGE 4
GRAND TRAVERSE RESORT VILLAGE TOWER & LOW RISE
N
N
X
X
INSTALL STOREFRONT GLASS
INSTALL LR INSULATION,SHT MTL & RFG
N'"
N
N N
N
N N
N
68
73
...;
N X INSTALL ENTRY GLASS • N N N N N 74
HO 241 pg 4
Ralph J. Stephenson PE PC
Consulting Engineer
DEFINITIONS
Contract document matrix· A two dimensional grid of rows and columns. The rows
contain action items required to deSign, procure, and build the various project
components The columns usually designate the geographic location of the item.
At the intersection of a row and a column, the designation of the contract document
package in which the information appears is inserted.
Prolect laundry list matrix - A matrix listing of the actions that must be taken within
various project components to execute the plan of action for a project. In the matrix
form, the action is shown in the row. Supplementary information regarding the action is
shown in in the action row under the appropriate columns.
The first step in building a contract document matrix is to prepare a detailed random
laundry list of component actions required to deSign, procure and construct all project
work. Actions are usually classified by the major building component to which they
belong. For instance, constructing wall footings is a substructure work component
(sbw); forming a supported deck is a superstructure work (ssw) component; preparing
and submitting a design development package is a deSign work (des) component. A
suggested range of components is given below in the list of possible fields to be used
in the contract document and laundry list matrix.
As the laundry list is prepared, items of work are classified by the contract document
package to which they are assigned. Usually assignment to a specific package is made
to those items which are interdependent within the package. A typical package
assignment is illustrated below:
COP (contract docyment) package A - Foundation concrete (at random)
ho 329 - Nov, 88
Ralph J. Stephenson PE PC
Consulting Engineer
Note that the list may includes action items requiring work on several trades in addition
to concrete work. This definition of related activities is one of the main reasons a
contract document matrix is valuable - it encourages the owner, designer and
constructor team to properly assign actions, and consequently, drawings and
specifications that depict the action, to the correct issue package.
The list is constantly refined and items added and relocated when necessary so as to
ultimately produce a document packaging plan that allows that allows the most
effective procurement and installation processing.
• A contract document package may contain the drawing and specs needed for several
trade contracts.
2 ho 329 - Nov, 88
Ralph J. Stephenson PE PC
Consulting Engineer
1.) The design team is guided toward preparing a set of documents that best fits the
project delivery method selected and the proposal strategy desired by the owner and
the construction team.
2.) The matrix provides a detailed reference check list to help insure that all items in
the project are placed in the most effective portion of the documents.
3.) The laundry list prepared can be arrayed in approximate construction sequence
within components to provide an excellent planning check list (laundry list) from which
detailed and summary network models can be prepared.
4.) The matrix helps identify the timing of the package issues and allows most effective
use of the deSign and owner team's attention in making project related decisions.
5.) The matrix will often point the way to the most effective project delivery method for
the circumstances surrounding the job.
6.) Submittal requirements can be anticipated in advance and planned for by the
design team when identified properly in the matrix. This has the effect of alerting all
concerned with procurement that is truly needed to properly bring critical materials and
equipment to the site.
* * *
The laundry list matrix is a natural extension of the contract document matrix and is
often prepared concurrently. It contains supplementary column data about each task as
defined in the list of suggested data fields given below.
4. CSI specification section number for major trade items used in action - csi
3 ho 329 - Nov, 88
Ralph J. Stephenson PE PC
Consulting Engineer
Samples - smp
Warranties - war
• Front end work· fen - All non construction project related work
concerning such items as real estate & financing
• Exterior building skin work - esk - All elements needed to close the
building to weather.
• Interior rough work - irw - All interior building components that can be
exposed totally or in part to the weather without damage to their prime
4 ho 329 - Nov, 88
Ralph J. Stephenson PE PC
Consulting Engineer
function.
• Interior finish work - ifw - All interior building components that must be
totally or partially protected from damage by weather
• Unit systems work - usy - All work that can be installed as a unit
somewhat isolated from other component work inside or outside the
building.
• On site work - ons (sometimes called site work - siw) - All exterior
work outside the building line and inside the property or contract
boundary lines.
• Off site work - ofs - All exterior work outside the property or contract
boundary lines.
7. Responsibility codes - The identification code of those who are to take the
action (rsp).
5 ho 329 - Nov, 88
~Z7
1:(ALPB J. STEPHENSON CONSULTING ENGINEER 111084 WARWICK ROAD DETROIT 23. MICHIGAN PHONE Z73,!:,:I~
Subject
s-/."" ( CAtII.,. t - Roo",. ,P..,,,,.., Do te _!l._~_~=/,...."?3
__
Poge _...1II'll""",,,__
.1'1
, .. I :'#~
I
.;..I -~
. ... '~"'-,
"
~-
' •
;., -~.'
... - ; ,
.'" ,.."",J. '_ ,_". ,
HI ./ " :
-.., --
,~ .,
' .• '. ~""" .. ' " -~
I
--,,
f
Project _______________________ Date _ _ _ _ _ RALPH J. STEPH~-:NSON
,- - - - - - - - .-- --1------·
..If.t:: /n
LJa y1e sh"l'" d~-:;;S -I-.b~-;t~ .... ~,..r .s;{~r-
, d'~? tI:l/;'=';-OVA./
L)a~e Liafe.
---
,t",.61!:
_____ s«.6h't,;//I!:'''/
__ _ _ ~i"'k4l'~o.... /1&:."" an.
5tdmZ 5/(1),,.,.3 .cc""1"4"c.::: vc,£
I-
-
. -
-
I
:
,
~ :
I
I
I
I
,I
i I
!
...
i !
!
! ,
,
I - \
I
i I,
,\ - I
I I !
-i
I - --+
:
I
. i. i
I. , 1
---,--'
i
I .-f-- i
..
I
I
- ~
,
o.
•
- ,, -
-- - - I
!, ,
!
!
-_.
_._ ------ !
1
-----i
I
I
. -,--- I
'-'--'
0
I: I
I
!
iI --'- !
--r
!
, !
,
I
~, - I,
...
-
'------. I I -.
,. I.. _'
ANALY: 0' GC REV TO 1. CHAllC,
RECElVEcn. PROPOSo\LS a: RECOMMcn. ACCEPT
CONIRACI'OR
SUBMm.a:
CHAJ...K. TACK a:
TACK a
PROPOSo\LS (5. SUB11m' CONIRACI'OR RECOMMAND
PREPARE a:
RE1N10
UQUlO MARKER
LIQUID
6) RECOMM1O 10 BE AWARDCIL
SUBMrrcn.
SUDCONIR(5.1.
BOARDS (6}
"ARKER
OWNER (5) SElECIEO 11. 2) CONIRACf (5)
SHOP OWGS (6}
21 BOARDS (en)
TO 3. FVLL
RECElVEFDP RECOMMF'DP CONIRACI'OR HEIGHT
I'ROPOSo\LS 15. CON1RACI'OR PREPARE&. DE"OUNTSL
6) roBE SUBMrrF'DP PARTITIONS
SEIJ!X:TED 11. 2) SHOP DWGS (6} (FOP)
'A G
a: APf!'II FPA FABaDEL
PROPOSo\LS &. RECOMMFPA ACCEPT
CON1RACI'OR
SUfIMm.a: FOlDING
... FOLDING
slJBMrr CONIRACI'OR RECOMMFPA PREPARE a:
RElN10 PARITI10NS (6}
PARTITIONS
RECOMM1O 10 BE AND AWARD SUBMrrFPA
SUDCONIR 15. I. (FPA)
OWNER (5) SEIJ!X:TED 11. 2) CONIRACf (5)
~
SHOP DWGS (6}
2)
~
C 0'
RECEIVEWWP RECOMMWWP CONIRACI'OR
5. WOVEN
PROPOSo\LS (5. CONIRACI'OR PREPARE a:
WIRE
6) roBE SUBMrrwwp PARTITIONS
SEIJ!X:TED II. 2) SHOP OWGS 16}
(WWP)
P1Q-01
l l l
R.u,PH J. STEPHE~aO~. P. E.
t'I):oI'af.'l.1'~O £:01'01."11:1:.
~
~~ ~1.~,
" ~~ ~ ~
f~
1-lc)
~
'1.,
~~ ~~
"
~
"
.~ " ~~ ~
~
~ ~~ ~
~~
~ ~
~
s
~~
~~
~~ "'1.I'\l ~
'\..~
"
1.~
tl
i~
~~
~ ,,)
~
;
" " "
"
" "
~.
...... ~ .")
-..
"f. ~ ~
* *'
- He 239
RALPH J. STEPHENSON. P. E.
CONSULTING ENGINEER
ill
~~
~
~t 8
~
~ ~
~ ~
l
"
~
~
~!~ \j
~t
-..;: ~
~
~~ ~
.~
~i
"tl ~
~'.J
,~t
~
~
~f
,)&
~
~~
~~
~ .~
~~~ ~
~~\l~l
'~ ~~
~1~
~ ~
~~ ttl ~ <:£\l ~
~\
~ ~ .\l' ~ '<) ~~2.~
~
::::: U)
" '} 'l) "l ........
ho 198
RALPH J. STmPHlllNSON. P. E.
OONSULTUC'G ENG'Il'I'JIIBR
I
Q(
q ~ ~
~\}~
~ ~ ~ ~~
~~ ~ ~ \)~
~ ~ ~ I I I
~ ~.~ ~nh \)~~~~
~~~'t5\{\{
~
~i ~~~ ~ ~ ~
~ ~
~ ~ ~ ~~
~
~~ ~ ~§~ ~ ~ ~ ~ ~
~'" ~~ ~ ~ ~
1
~
"\-. '\..
~""
~~ 1 ~
~
~
\~ ~ 1~~ ~ ~
~
~ ~ ~~
~~
~ ~~
~\Q
~ ~ "1
~ .~ ~ ~ t ~~\)
~~ ~
~ ~ ~'\.
~.~.~} ~~1'i- ~~"'''' ~ ~.~ ~~ ~
I: ~~ ~.~
~~ ~~~Q ~~~l ~~l~
~~ ~
~~
11\j"~\l
.~ ~~~ ~~ ~~~
~ ~ ~ .~ ~ ~!h ~,,\
~ ~~ ~ ~.~~
~j ~~ll)~
~ ~
~.t~
~\l<l\)
~ ~ ~~ ~~
~ ~~~~ ~\'..'1
~ .~q
'~ ~" l~ .\.-:'\
~~
~'J
1
~
"'I ~
~~ ~~~
~~~
~ ~
f~ ~ ~~
~ .~
.~ M' 1~~ t~1 ~'v
~.~,-
\\~~
~~1 ~~ 'n~
~ \),~
:-.~~
')
~~~ ~~~
~~~ \\J ~'\\ ~~ ~},- ~~~ ~~~
\\l 'I' ~
~ 4.33
~~ " t\J ~ ~ '<'\
RALPH J. STmPBBlNSON. P.E.
OOJfBDV1'IJfe BlJfe........
1- 1
I~ ..I
H/o 147
x =i + d + t(n-l)
i =x - d t(n-l)
t =x - i - d
(n-l)
Examples:
For x unknown
i = 160
d =7 wd
t =4 wd
n = 11 units
For i unknown
x = 325
d = 10 wd
t =6 wd
n = 21 floors
For t unknown
x = 352
i = 280
d = 9
n = 15 sectors
HO /'fJ? 1/16/82
ELe/'4EA/TS Or Bl../s/~ess
cf' MAA./A($L!.I'1eNr
"
-
AoMIAI.I,s.,.....A "1"" t.:IA./ O~I(A 7,lC)IIJS
OV~;...IIiA'O Dh'f.I!CT
SrAI"F L",./e,
O..vc$O,,"/6 PA'V4C ;
8A~t.;P ON LliVl/!.
~r liND C:LO:S/~G,
fiAIV'N....N~ p
Olf'c:qAJV'/ iii! /Nt;;"
¢
MA""A.~.eM£NT
.5rA'1="I'N<.i;J
S
ACTJON-S
D I "'(lie.,.Nv ~
D
C C:uvT~c/"'LI""<i;
C
;f~,PR.e' S4!~TIN~
~
5.01
RALPH J. STEPHENSON
~
~
CONSUL.TING ENGINEER
~
.
"
~
j ~
I ,
~
~
- ~I u
~
~
I! !"
"
'-I
I-
~
1
I i~ ~
~
~ \i ~
~
'"~....
~ r- ~
~ ~
,'" ~
....~
~ q~
~ "
to:
~ '" "
~
~ ~ :!
i ~
~
~ Ii
~
\I
~ "'"
~
~
~
~~
~~
~
~ '" ~
~ ~
'"
~
~
••
~
f s'oz
- "',
..
~~
~
,c.lS- A fclt
IltNI'-lr ~
Ralph J. Stephenson PE PC
Consulting Engineer
board of
directors
TRAPIDONAL
ORGANIZADONAL president &
CHART chief vp of
STRUCTURE operating
officer
- admin
vp of vp of vp of
finance engineering manufacturing
RALPH J. 8'l'mPBl11NIION. P. Eo
OO_'C'VrD<l'& llIX&'IlQD'B.
'-l ......
Q ~ \Il
'.u ~
-.J C C
<
~ t::
'e
~
....
,,~
~
~
'1:
~
~
~
~'l
V
\aI~
){.
'-tl ~ ~
~'"
HO 119 10/76
RALPH J. STBIPBlIlN8()N. P. E.
OO_l7.UHl!I'& JIbir&ut:B'IIIB
HO 120
R.ALPH J. STBPHBNSON. P. E.
CONSL"LTll'lG ENGINEER.
H/O 236
Phase Needs
1. Programming
B. Validation 2. Real estate control
3. Financing acquisition
The project financial 4. Cost analysis
feasibility is conftnned. 5. Approval
land is controlled. and a 6. Architectural design
fonnal pro forma made. 7. Land planning
Some conflnnation site 8. Traffic analysis
and building design studies 9. Go or no go approval, and
are made. This phase Others
produces a go or no go
decision.
c. DesIgn 1.
2.
Design development
Schematics
The design & construction 3. Preliminaries
delivery system is selected 4. Construction document
and documents adequate to production. and
construct the pr~ect are Others
prepared & isSued for
construction.
1. Procurement
D. Construction 2. Construction
3. Turnover
The project is built & given 4. Warranty. and
to the owner & occupant using Others
the delivery system selected
earlier.
ho 363 Dec, 92
2. Professional Service Ralph J. Stephenson PE
Contract Characteristics Consulting EDgtneer
.
iI
A. Agreement Totally negotiated - broad multlvalue competition
premises 2. Partially qualified - moderate multivalue competition
3. Totally qualified - narrow multivalue value competition
B. Authority
Umlts
-1]. Asagent
2. As limited agent
3. As contractor
2.) Expenses
1. Single responsibility
a ADmhouse
D. Scope of b. In house & outside consultants
2. Split responsibility
services a In house, client & other prime consultants
b. In house & other prime consultants
c. In house & client
ho 362 Jan, 90
3. Construction Contract Ralph J. Stephenson PE
Characteristics .Consulting Engineer
.
iI.
Totally negotiated - broad multlvalue competition
A. Agreement 2. Partially qualifled - moderate multivalue competition
premises 3. Totally qualifled - narrow multi valuevalue competition
B. Authority
limits {! As full agent
2. As lim1ted agent
3. As contractor
a. All
trades
{
1.) Provide management
b. um1ted1 2.) Provide design
trades 3.) Provide construction labor
4.) Provide construction materials
D. Scope of
services 2. Split responsibility - in house. subcontractors &
other primes
1.) Provide management
a. All in { 2.) Provide deSign
trades 3.) Provide construction labor
contract 4.) Provide construction matertals
ho 361 Jan, 90
pro forma gmp
estimate guaranteed
maximum
control control control price est
est 13 comfod level
est 11 es',2 IorgfJI price
pro foImaa
gmp 'arge' pdce
$
ti' Esnmated
po$SIbIe actual
conslnJcllon cOlI
cos,
TIME
Ralph J. Stephenson PE PC
Consulting Engineer
THE ITERATIVE COSTING SEQUENCE
323 Hiawatha Drive
Mt. Pleasant, Michigan 48858
ph 511712 2531
Issue #1 • February 5, 1991
In . ho aspe 1.10
Sheet
IITI
l l l
Ralph J. Stephenson PE PC
Consulting Engineer
1.) The degree of need for those you manage to communicate with each
other
2.) The amount of time required to be spent by you with each of those you manage,
and
3.) The effort required of you by your subordinates to assist them to work well with
each other, and with you, an effective span of management is usually limited to
your direct management, you may be able to manage 20 to 30 people. This was
proven in an analysis of Sears middle management many years ago. There it was
found that where department managers had little if any contact with each other that
store managers could properly handle the responsibility for as many as 30 of these
you and there are no links between the subordinates, the number of two way
communication channels in the system is 4, one for each of your subordinates to and
If 2 way links must be maintained among both you and your subordinates within a
managerial span of control of four, you are now managing 20 paths. Still not too
many, provided anyone link or set of links does not require excessive time.
rises rapidly. For total linkage and 6 subordinates the number of 2 way links is 21 and
1 he 279 - Oct, 88
Ralph J. Stephenson PE PC
Consulting Engineer
If you are managing 20 people with links limited to one from them to you and none
from them to others, you are only managing 20 x 2 =40 communication channels. If
you must manage total links between 20 subordinates under these conditions you
may find yourself trying to keep in touch with so many communication channels
that you never do gain control of the management process.
The span of management has many historical precedents that have repeatedly
proved the difficulties in trying to directly manage too many people. One of the
earliest examples of formal span of control analysis is found in the Bible. The book of
Exodus 18:12 - 27 tells of Jethro warning his son in law, Moses, that he has stretched
his span of management too far and is in danger of losing control of the Exodus
mission, leadership and quality.
Military management for thousands of years has proven that careful attention must
be paid direct control numbers for the safety and effectiveness of troops under each . ~
level of the military hierarchy. .."",
This is possible for the experienced and excellent manager, but is hardly ever
achieved by the emerging manager without help from his or her's superior
management staff and the company executive staff.
2 ho 279 - Oct, 88
::>:/2
RALPH J. STJup
OOKII'O:t.T
DrG BlrG
:J:UlINSON
•
P .Eo
Df&:.I•
,
.. 8
8
8
HO 122
Ralph J. Stephenson PE PC
Consulting Engineer
proper time span as well as among the appropriate people and groups of people. A
decision to action time span chart shows the time dimension between the point
Who makes the decisions and who acts on them is another phase of management
that is an integral part of the full decision making process. The handout shown here
displays the decision maker role for a medium large company with several
departments or divisions. Time spans for larger or smaller firms will vary from
these. For example in a small construction company doing $15 million volume per
year, the president's decision to action time span may only be 4 to 6 months. The
individual or group.
Good grading of the decision to action time will help assure that the organization has
assigned the responsibility for decision making at the proper management level.
This assurance leads to proper assignment of tasks and operations at lower levels of J
The benefits of preparing a decision to action analysis for your firm include:
1. Helps identify responsibility for short, medium and long range planning.
2. Encourages proper assignment of activities to those who are responsible for
implementation of decisions
3. Helps identify the people and groups best equipped to make decisions and to
4. Forces careful evaluation of all time scale decisions by showing the time waste
1 ho 278 Nov 89
RALPB.' J. STmPlImNSON. P. E.
OOl!lilliitn./X'Il!IiIG B::.I'i'GlNlIIJIIB
Dec/sloN 70 Ac-rIO;1J
~C4 ~.e..s/.oi!!Nr
4a,...,,,'V',,..s 7/f'1II47n::J,v
LhC4! r:k~T
O~"",r/oA./S
P""..,('C"""AS; ....v..
D/~6::'TOif
Ralph J. Stephenson PE PC ,.I
Consulting Engineer .."
aitain University, a small private engineering, science, liberal arts school in the
northwest United States city of aitain, is about to embark on a major (for them)
expansion plan. It involves the planning, design, and construction of a new university
activities building, a modest athletic facility having a gym and indoor pool, along with
support facilities, and a small combined library and book store.
The expansion program has been written, the desired planners, architect, and
engineers have been selected, and the Board of Regents of the school has given the
project a go ahead.
The site of the new building group extends across two city public rights of way (ROW),
Francis Avenue and Fourth Avenue. Preliminary negotiations have been conducted
with the City of aitain by Mr. Carlton, of the University, and with the city manager,
George Dell. It appears that vacation of the ROWs can be accomplished on a
reasonable basis. Several live utilities are known to be in the two streets but exact
sizes and locations have not yet been determined.
1 h0232 Nov 88
Ralph J. Stephenson PE PC
Consulting Engineer
The discussion has generated several Questions now being addressed. Some of these
include:
1. The only available survey map of the area is an in-house student survey prepared
ten years ago as a semester project. A new survey has not been budgeted and might
be challenged as an excessive cost by the Board of Regents.
Why?
If not, why?
If yes, why?
3. How should the project be organized and what should be the role of the various
parties involved?
If so, what should be his title, authority, responsibilities and his activities?
6. The contract for architectural, mechanical, and electrical design services are not yet
awarded, but all agree that the three firms at the meeting are the ones to do the job.
With whom should the architectural, mechanical and electrical engineering contracts
be executed?
7. How do answers to the above question affect the claim potential forthe project?
8. If you were an alumnus, and a local general contractor serving on the Board of
Regents of the University, and acting as an ex officio advisor to the program group, how
would you have answered questions 1 through 7 so as to maximize the potential for
2 h0232 Nov 88
Ralph J. Stephenson PE PC
Consulting Engineer
9. What role would you recommend Mr. Goldmark be requested to play in the project?
3 h0232 Nov 88
RALPH J• STIIIPHBlN8O N • P. E. '
.
QO_trIJrIHG m:.GINJII'IIP .
$.I'}' ho 199
J. ·STlIlPHBNSON• P. E. '
----
RALPH
OO.S'C7LTI.trG ,
BNGTl'I''III'IIIR .,;'
::::z. ~ ho 1 00
Ralph J. Stephenson PE PC
Consulting Engineer
You are to be the Jonquil project manager for the Bengst program if your firm is
awarded the contract. You met Mr. Bengst during one of the regular marketing tours
required of Jonquil project managers each year. However he is not well known to you,
nor you to him.
Jonquil has been asked by Mr. Bengst to meet with him and Karl Jong to discuss
designing the lab expansion, along with doing the master planning for the Tarry site.
You have been asked by the president of Jonquil to outline your approach to planning,
organizing, designing, and launching the expansion plan, completing the move in on
time, and meeting the quality standards of Bengst and your firm.
1. How will you organize to do the building design and the master site
planning?
2. Will Bengst be able to occupy the building while the second floor addition is
being built?
3. What is the time frame within which design and construction will occur?
5. What organizational and decision making structure do you desire the owner
to establish?
6. What ownership arrangement is best for Bengst of the new facility as well as
their existing facilities in Billings? Ready operating capital is essential to Bengst.
7. What pattern do you wish Jonquil's future relations with Bengst to take?
8. As an internal question, what steps will you take to insure that Jonquil's
future relations with this client will remain as you wish them to be?
1 ho 224.1 ae Jul, 88
~Zl
Ralph J. Stephenson PE PC
Consulting Engineer
10. The home office of Jonquil is in Philadelphia. What local Tarry affiliations, if
any, would you try to establish for the project work?
11. What are your comments on the Tarry and Billings locations relative to
Bengst's long range planning?
2 ho 224.1 ae Jul, 88
Ralph J. Stephenson PE PC
Consulting Engineer
You are a project manager with a NOCMA, a moderate size design/build &
development firm with offices in Minneapolis and Milwaukee. The current
work load of the firm is high but the backlog has dropped and project
managers are being encouraged to look for work of a suitable nature to
improve the firm's base of operations & volume over the next one and a half
years.
Your company has been working hard to encourage the concept of the
expanded profit center organization. Presently company management is
considering how best to be an umbrella manager that can truly leverage the
abilities and efforts of others to accomplish a mission of worth to all
involved.
It's 1 :45, Tuesday afternoon and you are sitting in your office thinking over
the relation of design, construction, financing. land ownership, equity and
debt, legal factors, and real estate, all relative to how to best improve
your chances of producing construction assets of yalue. Your phone rings
and it is Karl Jong calling from Bengst Corporation. You went to school
with Karl, and were good friends throughout college. Now you exchange
holiday greetings and an occasional letter. He knows you are in
construction and you know he is in software/hardware design.
Mr Jong describes a project to which he has been assigned and asks for
your help and advice. He adds that he has reviewed the purpose of his call
with Mr. Steel Bengst and has Mr. Bengst's permission for you to spend a
day or so with them on a fee basis to help establish the best project
delivery system for the project. Mr. Jong adds that he expects you, Larry
Mark, to be directly involved in the short term consulting and if any
construction results, it also.
You have just put the phone down from Mr. Jong's call and are outlining a
course of action and an agenda for a two day meeting with Mr. Jong. At the
end of the meetings it is your intent that Mr. Jong be able to use your
1 h0224.3 Dec 90
5: %'3
Ralph J. Stephenson PE PC
Consulting Engineer
2 h0224.3 Dec 90
Ralph J. Stephenson PE PC
Consulting Engineer
Trosta Miraldo
Systems mgr
Tom Bengst
VPMktg
Karl Jong
Proj Mgr
John Donovan
AdminVP
Frank Berenski
Facilities Engr
ho 319 Jut 88
Ralph J. Stephenson PE PC
GRApHICALLY Consulting Engineer
UNSTRUCTURED
ORGANIZATIONAL
CHART
HO 312 - Dec 90
Ralph J. Stephenson P.E ., p.e.
Consulting Engineer
(A management case study in working well with owners and other prime
contractors)
Your firm, the Oldenberg Construction Company, has just negotiated a time and
material upset price contract for the architectural and structural construction work
on a large local hotel. The other contracts for plumbing, heating, ventilation and air
conditioning, fire protection, electrical, security systems, food service equipment and
fixtures, furnishings & equipment (FFE) are to be awarded as prime contracts to local,
well qualified contractors. None of these except yours have been awarded as yet.
The owner's representative, Stanley Wozniak has asked your opinion of how the
entire project could best be delivered and how you would organize the job if you
were in his position. Mr. Wozniak has had about 5 years of experience constructing
shopping centers for your client He is somewhat uneasy about this job since at $27
million it is the largest job he has worked on to date, and it is a new type of project
for him.
Although you know that most of the primes being considered perform well, the
work whenever they sense a project is going poorly in trades other than their own.
2.) What kind of planning and scheduling would you expect to do on job like
this.?
4.) What type of contract would you have used if you were the owner on the project?
• WORKING DRAWING - Graphically define the contract scope of work & show
the appearance of the completed project.
• SPECIFICATIONS - Verbally describe the contract scope of work and define the
qualitative standards to be maintained in the completed project.
• PLANS &; SCHEDULES - Graphically define the sequences, procedures & amount
of resources to be used to construct the project.
1 ho 301 Feb 88
Design work phases RalphJ. Stephenson PE PC
Consulting Engineer
ho 444 Sept, 94
~.O/4
Design work phases Ralph J. Stephenson PE PC
Consulting Engineer
• SCHEMATIC DESIGN PHASE - The conceptual development of the project in accordance with
the program requirements. Usually review and approval of schematics in part or completely allows
design development work to begin. During schematic design the rough program phase estimates are
refined to a level of detail consistent with the information available. These kinds of estimates may be
known as order of magnitude estimates.
• DESIGN DEVELOPMENT PHASE - The program and schematics are used to fully develop
preliminary architectural and engineering details of the facility. Approval in part or fully of design
development documents allows preparation of construction documents, or working drawing to begin.
Estimates may now be refined to a point where early stages of construction, such as site preparation,
mass excavation, grading, foundations may be moved into final construction document design.
Occasionally the design development phase documents can be used for providing a guaranteed maximum
proposal for selected portions of the project .
• CONSmUCfION DOCUMENT PHASE - The full set of construction contract documents are
prepared in such detail to allow the project construction contracts to be awarded and field work to begin.
At the point where part or all of the construction documents are completed, hard money proposals, or
fixed cost proposals may be solicited. The type of project delivery system selected determines how the
work is to be awarded.
(..016
The project program Ralph}. Stephenson, P. E.
Consulting Engineer
c.. 0/ c
The project program Ralph J. Stephenson, P. E.
Consulting Engineer
vendor or a potential tenant looking for space. We identify the conceiver since he
usually is the key person driving the project on to completion.
2. Translators
Those who translate the environmental program into construction language.
Traditionally we think of the architect/engineer as the translator. However careful
consideration of this matter shows there are many others who translate the conceiver's
fundamental ideas into understandable, workable construction language.
Subcontractors, suppliers, vendors, manufacturers, contractors, and the conceiver may
all playa role in translating.
3. Constructors
Those who interpret the construction language and convert it to an actual physical
environment. Occupying this role are general contractors, specialty contractors,
vendors, suppliers, manufacturers, artists and others who actually put the materials into
place in the field.
4. Operators
Those who operate and maintain the completed physical environment on a continuing
basis. Usually the party responsible for this function is an owner or tenant working
through a plant or facilities manager.
5. Regulators
Those who fill a review & inspection position to help insure protection of the health,
safety, & welfare of the people. This is usually done by enforcing regulations written
and adopted by qualified public or private bodies. Examples of regulators include those
who work for building departments, departments of natural resources, public health
agencies, fire prevention organizations, technical societies and other such groups.
6. Users
Those who use the facility either directly or remotely. Direct use is permanent or
temporary occupancy of the facility. Indirect use is any interface with the building's
occupants that is conducted from a location other than at the facility.
23, Personnel special needs.
24. Plumbing needs.
25. Power needs.
26. Project delivery systems to be considered.
A method of assembling, grouping, organizing & managing project resources so as to best
achieve project goals & objectives.
27. Public transportation needs.
28. Receiving needs.
29. Recreational needs.
30. Security needs
31. Shipping needs.
32. Special hazards and environmental problems.
33. Stand by needs.
34. Storage needs.
35. Structural needs.
36. Surveillance needs
37. Trash disposal and recycling needs.
38. Vertical transportation needs.
I (.hVIT' 0;=
,e,.:r-I!!!~ r IV..!:
Ot-Ir,P<.l r
IOUrPf:../T UNIT
/ P~.sOIV
______~~~~0=/~
'" P.6f..so~
-U ... 8.3 r6~
31 P~~OI\/:j
2S;31 =- • 8/ J2I'fo
c:.oz
H/o 148
RALPH. J. STBIPHlDNSON. P.E.. P.O.
OOKB'OL'rDfG BwGIJOI• •
HO 210
)
SUPPORTING STAFF '£Xc:'-CUTIV£ STAFF
R£ ~Q/J/Sj.1l11,.. I T 1£ S RE. SPON SIB/LIT I£.~. ___
~.~r!.t?!!..~_J..fi{)TItORITY ACTIONS f A..UTHJHijTY
...
----I
®
....,
-...."
Q)
----------------------~~---~
~--->r---------------------~
h/o 183
Ralph J. Stephenson PE PC
Consulting Engineer
• The forerunner managed company tries to optimize the probability of being right.
• It is critical to understand that both types of companies can be, and often are
successful or unsuccessful. The style of forerunner or conservative is merely an
indication of the way the organization achieves success or goes through the twinges
of failure.
Forerunner
- Aggressive in their field of work
- Young
- High risk takers
- High leveraging of all resources
- Good morale
- General absence of recognizable management structure
- Healthy cooperation among lower management
- Strong competitive drive at all levels of management
- Strong sensing (not necessarily knowledge) of total purpose about
Financial return on investment
Social obligation
Professional integrity
Techrricalexcellence
Ethical behavior
1 ho 315 - May, 88
~.6S
Ralph J. Stephenson PE PC
Consulting Engineer
Conservative
- Usually well managed from top down
- Moderately well managed from bottom up
- Tends toward paternalistic management
- Major decision making centered in top management
- Good financial strength, if mature
- Dependable
- Predictable
- Closely controlled employee training
- Modest salary structure
- Good standard employee financial benefits
- Usually stress hygiene as opposed to motivational drive .J
- High levels of employee loyalty in those who like the system .....,
- Provision of employee security
- Generally pretest decisions at executive management levels
C:.O~
Ralph J. Stephenson PE PC
Consulting Engineer
There is also a special requirement for creative thinking that demands getting rid of
what Roger von Oech in his book, A WHACK ON THE SIDE OF THE HEAD, calls
mental locks. These mental locks are recognized by such familiar phrases as:
The above statements indicate a set pattern of thinking, that when used blindly, get in
the way of the creative process.
Other major obstacles to thinking creatively include making premature judgments, and
excessive use of the self fulfilling prophecy. The self fulfilling prophecy usually indicates
you have your mind made up before even starting any heavy thinking about the idea.
You then never give your brain a chance to do any creative thinking.
Remember, it is nearly impossible to be creative and judgmental at the same time. So,
in project management it is a good idea when creatively considering a complex matter
to prepare a random, or non judgmental, laundry list of things that have to be done or
thought about. The list should include all items within reason, whether or not you and
the others involved think it should be included. Often the combination of a single idea
1 ho 225 Nov 88
c",o7
Ralph J. Stephenson PE PC
Consulting Engineer
1. Gather all facts that time will allow, about the subject under consideration. Try
not to be judgmental while you are collecting information.
2. Think hard about the data and the other information you have gathered in
3. Forget about the problem! Let the material looked at so far, and the ideas you
might have, get mulled over by your subconscious. This period is called gestation.
4. Ideas (illumination!) will usually start springing to mind soon after the gestation
period starts. However, in some cases it might take several days, weeks, or even
months. Be alert for the sudden revelation of the solution. When the solution or
idea or lost thought appears grab it and write it down!
6. Follow up and check to see if the solution was a good one and if it has worked.
Creativity is a simple, elegant way of life. All you must do to enjoy it is to unlock
2 ho 225 Nov 88
c.. of'
Ralph J. Stephenson PE PC
Consulting Engineer
Zoom thinking of this type is known as situational thinking. The process allows and
encourages you to examine as many aspects of a subject system or decision as time
allows.
• A. The reason for failure of Impulsive, narrow minded men and women as
managers is often because they don't, can't, or won't look carefully and see what's
going on around them.
• E. To think situationally
1 ho 229 Jul88
Ralph J. Stephenson PE PC
Consulting Engineer
2 ho 229 Jul88
c;./o
Ralph J. Stephenson PE PC
Consulting Engineer
QUESTIONS TO CONSIDER
1. Is my decision legal?
2. Is my decision balanced?
ho 365 Nov, 93
C.II
Ralph J. Stephenson PE PC
Consulting Engineer ..,J
Mr. DeBono calls his technique PMI. It involves a short pause period before answering a
prime question, during which the decision maker examines three aspects of the
question, its pluses (P), its minuses (M), and its interesting features. Use of PM! on a
specific question should take only a
relatively short time. For practice exercises, Mr. DeBono suggests 3 to 5 minutes for the
whole PM! process. However the time period will vary depending on the time available
and the nature of the question.
PM! is not a decision making process; it is a thinking process to be combined with other
decision tools to help improve your thought processes, and consequently make better
decisions than you do now.
A point to be stressed before using PM!, according to Mr. DeBono is to think slower but
think better! Most of us jump too rapidly to a position that must then be defended
irrespective of our second thoughts on the conclusions reached. Thus are born the often
destructive self fulfilling
prophecies. PM! can help reduce the probability of taking indefensible stands on critical
issues.
To use PM! first frame the question or situation you are addressing in clear, easily
understood terms. For instance in considering a project delivery system, let us assume
there is a choice available between using traditional, hard money methods compared to
non traditional dovetailed guaranteed maximum price methods.
Taking each method individually let us see how our thinking about the systems can be
improved with PM!. Again to be stressed is that PMI is not a decision making technique;
it is a thinking technique from which more effective decisions can result.
1.) Select one of the methods to consider first, say, the non traditional, hard money
delivery method (method 1).
1 ho 325 Sept 88
c.. /'2.
Ralph J, Stephenson PE PC
Consulting Engineer
2.) Visualize or write all of the good points (the pluses) you can think of about method
1. Keep your mind only on the positives. This is called directional thinking.
3.) Visualize or write all the negatives or detracting points of method 1. Keep your
mind directed toward the negatives.
4.) Visualize or write all the interesting features about method 1 you can conjure up in
a few minutes of thought. Mr. DeBono suggests you say to yourself. "It would be
interesting in considering method 1, if.........
6.) Make the decisions you are charged with using any of the decision making tools
available to you.
Notice the stress in the above step by step procedure on thinking about the matter. It is
thinking that encourages better use of the powerful scientific management tools
available.
2 ho 325 Sept 88
Ralph J. Stephenson PE PC
Consulting Engineer
Optimism, skepticism, and conservatism are ingredients a good manager knows how
to mix and use, just as a good cook knows how to prepare and serve food. Although
a formal study of probability and statistics is certainly of help to a project manger in
the construction industry, it is not essential to understanding many of the basic
elements of preparing for the probable.
• A. Over optimism is often the manager's enemy. It can blind him to the
true needs for success.
• G. The normal distribution says that in every situation there are two
extremes of happenings and a range of probable happenings in between. A
game example is throwing dice; it is probable that 2's, 3's, 11's, 12's will come
up less frequently than 4's
1 ho 227 Jul88
Ralph J. Stephenson PE PC
Consulting Engineer
2. Over optimism casts a false glow on the situation. It may blind the
manager to his true chance for success.
3. Subjective temptations such as ego, greed, and false pride over feed
ambition.
4. The manager loses his cool. (When things are going wrong and you
have overextended yourself, pull back temporarily, calm down the
active mode, and objectively evaluate the situation. Stop. and think!)
2 ho 227 Jul88
Ralph J. Stephenson PE PC
Consulting Engineer
1. Set your priorities in terms of the probable rather than the merely
possible. Always try to work from a position of strength.
2. Set attainable goals and objectives. Don't put them out of range for
either yourself or others.
3 ho 227 Jul88
R.ALPS: J. STlCPmIlNSON. P. E.
OO.8DL'1'IHG lIlNGDI'lII• •
r'£/C.f!
ca.:s7'
/h/~ ..:5t1-/QI:./~ de kp·?~
..Dc./...,A,yS J;4tf'Ciers ....=o,f' TNt!!
/t11.S;r~.s ~NAGoEI{""S 1-//t::VH
~~oat..eMS P/f/o/(/r'f' ATT.e/\/7"'/o"v
kOAr
RE..J1fC:r.s
~s
.54v'/AI~S
..;51-1/'p,Nf.eAIToS
WAST!!:
CAw.s~ M4T~o.o.:f
..f"e.sov~c.es SJ!e/f'VICISS
?If'OCJVC7S 5TAFP
\..., .o.t!!c.ISloiV.s
~C/L/rIE.s
Manage by Exception
To manage by exception (MX) means to build and use an alarm system that goes off when something is
wrong but otherwise remains silent.
4. If used incorrectly can give a false sense of security and well being.
5. Is silent only on items predetermined not to be critical. Conditions may change.
E. The big advantage of MX is that much of the decision making is done in advance (much like a trouble
shooter's manual, a decision tree or a decision table).
F. The manager must understand that once freed by a good MX system from the demands of routine work,
he must fill his time with creative effort directed toward improving his plans, organization, staff, and
decisions.
G. MX is invaluable in detecting trends - movements toward or away from objectives.
H. Beware of overreaction to an MX alert. Remember MX is a tool of the manager, not the manager.
1. Three MX alert levels
1. No unusual difficulties - everything OK.
2. Moderate deviations - the situation needs the manager's attention and analysis.
3. Above average deviations - the performance is unacceptable and needs corrective action, or is
1 h042S
RalphJ. Stephenson, P. E.
Consulting Engineer
4. Electronically reported
a. Easily used on selective basis.
b. Data available quickly.
c. High processing error potential.
2 h0425
Ralph J. Stephenson PE PC
Consulting Engineer
lime waster
Possible causes
Solutions
A. Lack of planning
1. Failure to see the benefit
a. Recognize that planning takes time but saves time in the end
2. Action orientation
a. Emphasize results, not activity
3. Success without it
a. Recognize that success is often in spite of, not because of
planning
B. Lack of priorities
1. Lack of goals and objectives
a. Write out goals and objectives
b. Discuss priorities with subordinates
C. Overcommitment
1. Wide span of interests
a. Say no
2. Confusion in priorities
a. Put first things first
3. Failure to set priorities
a. Develop a personal philosophy of time
b. Relate priorities to a schedule of events
D. Management by crisis
1. Lack of planning
a. Apply the same solution as for lack of planning (see A above)
2. Unrealistic time estimates
a. Allow more time
b. Allow for interruptions
3. Problem orientation
1 ho 252 Jut 88
Ralph J. Stephenson PE PC
Consulting Engineer
a. Be opportunity oriented
4. Reluctance of subordinates to break bad news
a. Encourage fast flow of important information as essential for
E. Haste
1. Impatience with detail
a. Take time to get it right. Save the time required to do it again
2. Responding to the urgent
a. Distinguish between the urgent and the important
3. Lack of planning ahead
a. Take time to plan. It repays itself many times over
4. Attempting too much in too little time
a. Attempt less
b. Delegate more
H. Visitors
2 ho 252 Jul 88
'.2/
Ralph J. Stephenson PE PC
Consulting Engineer
1. Enjoyment of socializing
a. Do it elsewhere
b. Meet visitors outside
c. Suggest lunch if necessary
d. Hold stand up conferences
2. Inability to say no
a. Screen
b. Say no
c. Be unavailable
d. Modify your open door policy
I. Telephone
1. Lack of self discipline
a. Screen and group calls
b. Be brief
2. Desire to be informed and involved
a. Stay uninvolved with all but essentials
b. Manage by exception
J. Meetings
1. Fear of responsibility for decisions
a. Make decisions without meetings
2. Indecision
a. Make decisions even when some facts are missing
3. Overcommunication
a. Discourage unnecessary meetings
b. Convene only those people needed for matters at hand
4. Poor leadership
a. Use agendas
b. Stick to the subject
c. Prepare and distribute minutes immediately after the meeting
K. Indecision
1. Lack of confidence in the facts
a. Improve fact finding
b. Improve validating procedures
2. Insistence on all the facts - paralysis by analysis
a. Accept risks as inevitable
3 ho 252 Jul 88
{,. 2 z
Ralph J. Stephenson PE PC
Consulting Engineer
L. Lack of delegation
1. Fear of subordinate inadequacy
a. Train
b. Allow for mistakes
c. Replace if necessary
2. Fear of subordinates' competence
a. Delegate fully, but within the subordinate's competence
b. Give credit
c. Plan corporate growth to maintain challenge
3. Work overload on subordinates
a. Balance workloads
b. Staffup
c. Reorder priorities
4 ho 252 Jul 88
Ralph J. Stephenson PE PC . J
Consulting Engineer """'"
B. The manager should start with the assumption that most people
1 ho 231 Jul 88
Ralph J. Stephenson PE PC
Consulting Engineer
b.) Security
(1.) Status
(1.) Confidence
(2.) Spirit
(4.) Assurance
3.) Education
2 ho 231 Jul 88
Ralph J. Stephenson PE PC
ConsuHing Engineer
confidence in him
they do
• 4. Communicate freely
A. Within allowable boundaries keep people informed about
to be liked to be effective
3 ho 231 Jul 88
Ralph J. Stephenson PE PC
Consulting Engineer
C. Make it known that the more important jobs that you delegate are
training assignments. You then retain control of the activity and can
1.) Use guided actions. Be available to help the subordinate do the new
work
2.) Show the learners how to do the job, and encourage them to further
delegate, where appropriate, by having them train or coach their
subordinates in the activity
3.) Delegate the whole job and involve subordinates in the early planning
as well as the activity itself
1. Hawthorne experiment (1927) - encouraging workers to get things off their chest
was proven to increase production
4 ho 231 Jul 88
c... Z. 7
Ralph J. Stephenson PE PC
Consulting Engineer
5 ho 231 Jul 88
t..2..P
Ralph J. Stephenson PE PC
Consulting Engineer
• 2. Training is teaching and learning the specific, explicit process of doing things. It
is vocational and procedural.
• 3. Coaching is a limited one on one, or one on few teaching effort to educate, train,
or to do both. It is personally guided dialogue between teacher and learner.
• 6. Good staff performance allows the manager to devote more of his time to
concentrating upon, initiating action of, and directing and controlling the resources
at his disposal.
• 7. The need for good training, educating & coaching is ongoing irrespective of how
good or bad business & organizational times are.
• 8. The excellent manager will usually try to teach what he knows to those who
wish to learn
1 ho 230 ~ Dec, 90
Ralph J. Stephenson PE PC
Consulting Engineer
from learning.
(2.) Show that added skills give more, not less, security
(5.) Show the employee that training will be truly relevant; ..J
that what he learns can be used now, for his and the
company's benefit.
C. Insights - the key elements of a subject that deal with the intellectual, the
physical and the procedural requirements of learning. Insights are of different kinds:
1.) Intellectual insights - those that concern the whole concept of what is
to be learned
2.) Physical insights - those that concern getting the physical feel of the
process - the touch, tone, heft and smell of the job
3.) Procedural insights - those related to sequential demands of the
operation
2 ho 230 - Dec, 90
6..90
Ralph J. Stephenson PE PC
Consulting Engineer
• 10. The basic phases of a training program are planning, instruction, evaluation
A. Planning
B. Instruction
C. Evaluation
3 ho 230 - Dec, 90
t-.3 1
Ralph J. Stephenson PE
ConsultlDg Engtneer
ho 377 Dec 90
f'
~
tJ
Positive
t
Perfomance
Improvement Cycle
'l1me
(from The 9 Master Keys
to Management - Lester
R Bltt1el)
l l l.
Ralph J. Stephenson PE PC
Consulting Engineer
The purpose of decision making for the responsible project manager is to insure that
an objective recommendation is provided to his or her upper management. Upper
management is then responsible for adjusting the objective decisions of the project
manager to a decision in line with what upper management staff personally,
politically, professionally, subjectively, and technically feel is the appropriate
selection.
\.. 1. Select, write down, and verify the various decisions possible. What courses of
action are available?
3. Assign a weight to each factor that describes numerically, to those to whom the
recommendation will be made, how important the project manager and his team
think this factor is in selection of a course of action. Factors should be given a weight
of one to ten. One means the factor is of minimum importance in the evaluation.
Ten indicates the factor is crucial to the evaluation.
It is essential to realize that the factors selected and screened for use must all be of
relative importance and that the assignment of weights should spread from one to
ten. A help in doing this properly is to determine the most important and critical of
the factors and assign it a value of eight to ten. Next select the least important factor
and give it a weight of from three to one. The remainder should fall somewhere in
between. Remember more than one of the factors being weighed can receive the
same number. You are not rankina the factors, you are weiahina them.
4. Assign a value to each potential course of action or each decision possible for each
of the factors selected and weighed. If there are three courses of action possible, and
you have selected five factors by which these are to be judged, you will have to assign
3 x 5 = 15 values to the entire array. This can be seen in the following matrix example
where alternative project delivery systems for constructing a warehouse are being
considered.
The three delivery systems under consideration are an award of a hard money
contract from a full set of contract documents, retention of a non liable construction
manager to run the project, or use of a liable general contractor involved early as a
construction consultant and providing iterative estimating help leading to
submission and acceptance of a guaranteed maximum price.
fmj~i:t d~liveI)! SJSlems h~ing i:mlsidereg &: their xa1u~ in SiltiSUing th~ deminds
af eilm filam: af imJZartanc~ - warehcmle I!m,j~a
The selection analysis above indicates the best delivery method of the three being
considered is a progressive pricing system leading to submission of a guaranteed
maximum price for which the contractor will construct the project.
It should be emphasized that the validity of factor selection, the factor weighing, the
selection of alternatives and their valuing depend totally on the exercise of sound
judgments by those making the analysis. Usually for each decision to be made such
an analysis as above is made by several qualified staff. Some may not even be
associated with the project directly but only acquainted with the key demands of the
project program and mission. This wider range of views and ideas often lends
strength to the recommendations.
Reasons that good design and construction record keeping is essential include:
manager is responsible.
construction claims.
environment.
4. An increased demand for higher levels of cost control than ever before.
5. The documentation demands being made by more complex financing and
$90 per hour for your managers when they are not engaged in a profitable
7. Be certain the form, when complete, will provide the data you need: the
8. Provide a specific place on the form for a date and the users signature.
9. Review all forms at least once per year to see if they should be discarded,
1 ho 360 Dec 90
record types and their uses
doeumenl record record record record record record record record record record record
action auplv opin chn". dec .. appvl. progr. r..ree dala doc re.ulla
aelion a"rml. flow proc.g
Lrtffi_'Of_~_
x x x x
x x x x
I: x x x x
4 s of occupancy x x x x
5 Change orders x x x x x
6 Checklists x x x x
7 Claim notification letters x x x Ix x x Ix
8 Clarifications x x x x x
9 Color «:X)ded network models x x x x x x x
10 Construction record drawings x Ix x x x x x
11 Construction site plan x x
12 Consultant tists x x
~ I~·t_m~t~n~'
x x x x x
1 IngS X X X X x
specifications x x x x x
1 IContractor lists x x
17 Contracts x x x x x x x
18 Cost estimates x x x Ix x x x Ix
19 Cost reports x x x x x x x
20 Diaries x x x x x x x x x
21 Document control files x Ix
22 Equipment data tabulations x x
23 Expense reports x x x
24 Field orders x Ix x x x
25 Field reports x x x x x x
26 x
27 Impact reports x x x x x x x x
28 Interoffice memos (IOC) x x x x
29 lsoquant line comparisons x x x x
30 Letters x x x
31 Logs x x x x x x x x x x
32 Maintenance manuals x
33 Meeting minutes x x x x x x x x x x
34 Money flow curves x x x x x
35 Monitoring reports x x x x x x x
36 Operation manuals x
3 x x x x x
~
x x x x x x
3 9 Phone records and logs x x x x x x x
40 Photos x x x x x x
document record record record record record record record record record record record
action suptv opln chngs dec • appvls progrs r..ree data doc results
action agrmts flow procsg
~hase orders x x x x
50 Quantity takeoffs x x x
55 Resource histograms x x
management x
ample logs x x x x x x x
58 Schedules of values x x x x
~::
x x x x x
x x x
smittals x x, x x x x x x
66 Waivers x x x
67 Warranties x
68 Work orders x x x x x
For a document control system the basic classification system is much simpler. A
document irrespective of type or classification is filed by a single number assigned to
it as it is received. This number is referenced to the date of its production and filed
wherever possible in order according to that date. Thus a document dated July 3D,
1987 is set earlier in the stack than one dated July 31,1987 and receives a lower
number in the sequence.
1 ho 299 December,93
Ralph J. Stephenson PE PC . J
Consulting Engineer ....."
The basic physical arrangement within the file system recommended here is in
ascending order of date of document. Once consecutively numbered however, there
are many other criteria by which the documents might be arranged, the content
identified and the document retrieved.
To start the process a single document control copy is made of all written material
received, sent or circulated internally that pertain to the project. These are physically
arranged chronologically by their official date (the date of the document).
The documents are next divided into time span packets, punched with an oversized
punch and put in loose leaf binders. A packet period of one month has been found to
work well in most cases.
Each document is given a number that will identify it uniquely (the only document
in the file that has that number). A workable system is to number by the month in
which the document was prepared. Using this method a base month is selected and
designated as month #1. Month #1 is preferably January of a year in advance of
starting major work on the project. Succeeding months are numbered in ascending
order. For example if the base date selected is January I, 1987, then January, 1987 is
considered period #1. February, 1987 is period #2, March, 1987 is period #3 and so on.
Thus a document written in June, 1987 and being filed in a document control system
using a base date of 01 as January, 1987 will be assigned a document number starting
with 06. When there are a large number of documents to be filed it is advisable to use
a self advancing numbering stamp.
Once the first two digits of the document identification number is assigned, the last
three are then assigned. The remaining three digits reflect the approximate
chronological position of the document within the month. If a letter is received
dated March 20, 1987, with a control system base month #01 date of January, 1987,
ho 299 December 93
I
Ralph J. Stephenson PE PC
Consulting Engineer
Now, every document in the entire file has a unique number and will be identified
by that number as to the month and the approximate position in the month it was
dated. The name of the system, single number filing, is used since every document
filed is identified with a single number irrespective of what type of document it is.
A retrieval data base file should contain the following minimum fields:
1. Document control number (den)
2. Document type (dty) -letter (Itr), transmittal (trm), etc.
3. Date document prepared (the basic criteria of the order of the documents in
the file) (ddp)
4. Date document received (ddr) - all incoming documents should be date
stamped
5. Organization from (ofr)
6. Organization to (oto)
7. Individual from (ifr)
8. Individual to (ito)
9. Subject codes (sco) - Subject codes identify the content nature of the
document. For instance a letter concerning mud sills (msi), forming (fmg),
supported decks (sde) and building 148 (148) along with a request for
information (rfi) would be assigned all the subject codes indicated.
The document records (unit entries in a data base program) are next put into the data
base file. Methods of entering data vary but the guidelines below should assist in
setting the procedure.
a. Item 1 through 8 in step #4 above are entered directly as a routine data entry
task, directly from the master document file material.
3 ho 299 December, 93
C.·fl
Ralph J. Stephenson PE PC
Consulting Engineer
Let us assume the document file has been prepared for several months of document
control records and you wish, or are required, to move to the next level of
documentation by conditions encountered on the project.
This level of documentation usually involves preparing a project history from the
master document file. The project history is an abstracted chronological narrative of
important events on the job.
To prepare a project history, the master document file is read and annotated so each
document (depending on relative importance) can be abstracted and put in some type
of narrative. Often the annotation is completed in step #5 as subject codes are
assigned.
The program selected to process the narrative should be a word processor of some
type. For example Think Tank or More can be used by entering the document
number number as a heading followed by the document date. Next, the main
heading is exploded and a brief summary (under 30 words) of the document is
entered in the exploded area. Thus when prepared properly, the information can be
sorted by document number or date (whichever is typed first). In addition the
abstracts can be searched for key words to build subject files for specialized uses.
The important pivot is the unique document control number which allows the
document to be filed in ascending order of document number and to always be found
in the file as a numbered file document, no matter how many subject codes it is
4 ho 299 December, 93
Ralph J. Stephenson PE PC
Consulting Engineer
assigned. For instance document number 09124 can always be found after 09123 and
before 09125 in the master chronological file, no matter how many subjects are
assigned or what the subject being sought.
An extended use of the project history is to build special reference files for specific
uses. For instance one such use is to search the data base subject codes for a set of
documents, and then to call each of the project history abstracts of these documents
from the file, and to print and assemble them into a subject file to be used for a
deposition.
When the project history is partially or wholly available, the document control file
can be used at a higher level by selecting major classifications of project problem
areas. This selection is made on the basis of the strong positions the preparer of the
claim feels he has.
Experience indicates it may be best to concentrate early on the strong positions and
win them by good logic and sound documentation. However, additional strong
points sometimes emerge by a combination of proper actions taken in a variety of
smaller and apparently unimportant points and issues. The analyst must be able to
discern and select what information is to be used in any given situation.
Problem areas on a job may cover a variety of situations. It is often of help to use a
basic list of normal complaints (causes of contested claims) and to derive from these
the specific complaints that are related. Let us take an example.
ho 299 December, 93
Ralph J. Stephenson PE PC
Consulting Engineer
have either individually or in concert given the non liable construction manager an
intended plan of action, that in their opinion as liable parties to a contract
arrangement with the owner (the ultimate decision maker), will satisfy the project
contract they have with the owner, their client. This plan conflicts with that of the
non liable construction manager.
When the owner's agent, the non liable construction manager, pits his desires
against those of the prime contractor's, relative to achieving project objectives, the
conditions of the contract must be closely analyzed.
In a hard money, fixed time contract, use of time and money are generally the
prerogative of the contractor so long as the ends are achieved. Any interference with
how the contractor achieves these ends must be viewed as an interference with the
contractor's right to enjoy an optimum profit derived from the job plan which he
has signified as his intended plan of work.
The proof in such situations is however often difficult to provide. But if the
document control system is properly prepared, the subject coding accurately done
and the project histories well written, it is a relatively simple matter to retrieve all
documents relating to the problem and to build a special history for any specific delay
or interference.
Not all the above steps are taken in the preparation of project documentation. If the
level of documentation called for is at 2 to 3, it is generally adequate to prepare a
subject file of the documents and only take Step #1 above if specific minor problems
are encountered in a well defined, limited time period.
ho 299 December, 93
Ralph J. Stephenson PE PC
Consulting Engineer
When the level of project difficulty is raised to 9 or 10 which indicates a job upon
which very serious problems are being encountered, Steps #6 and 7 should be
initiated. Hopefully a full Step #6 and 7 program will not be needed, but on especially
troublesome jobs, may be necessary.
7 ho 299 December, 93
Ralph J. Stephenson PE PC
Consulting Engineer
Documentation Degree
The degree of needed documentation on any project is determined by the current or
potential level of difficulty perceived.
One method of setting documentation degree (dd) is by use of a scale of one to ten,
one being a minimum amount consistent with good practice and ten indicating a
maximum amount needed to protect those involved from current or potential
problems.
The approximate ranges shown below are reference guidelines for selecting and
preparing documentation systems:
At these levels the project usually is informally organized, with full trust by all
parties of all other parties. Most instructions and requests are oraL Revisions and cost
commitments are made on a full confidence basis relative to scope, expected
payment and resolution. The project team understands and communicates well
internally and externally, and all on the team exhibit a high degree of honesty,
competence and integrity. Usually meetings are held on an as needed basis only.
1 ho 305 December, 93
Ralph J. Stephenson PE PC
Consulting Engineer
It should be cautioned that a low dd does not mean the project will not encounter
difficulties. The number merely indicates a recommended level of documentation
being maintained as of a given point in time.
In add 3-4 project the usual procedures for processing work during programming,
planning, design and construction are well defined and followed carefully by all
parties to the contracts. Usually the project contract documents have been carefully
prepared and checked thoroughly. This helps assure that the scope of work is clear
and the project is constructible.
Documentation de&ree #5 & 6 (dd 5-6) - claim prone jobs on which trouble potential
is conjectural
2 ho 305 December, 93
Ralph J. Stephenson PE PC J
Consulting Engineer ..",
In a dd 5-6 the level is set high to permit those involved to more quickly react to
sudden project difficulties than on a normal project. To reemphasize, the dd level is
set by the nature of the project and is only raised or lowered when sufficient
justification for a change is noticed.
Documentation dearee #7 (dd 7) - claim prone jobs on which trouble potential is very
likely
On a dd 7 project, comments for dd 5-6 apply, with the qualification that a yet higher
dd level requirement than 7 is highly probable. In other words if the job is claim
prone and some of the claim prone characteristics are causing actual problems, the
documentation level of 7 indicates a movement into higher levels is near at hand.
If dd 8-10 needs are met on a day to day basis as the documentation is sent or
received, the cost will be much less than if it is done later. In addition the analysis
will be fresher and more accurate. In addition, the knowledge that such a high level
file is being built often acts to dampen the conflict and difficulty and may even lead
to quick resolution of the difficulties.
3 ho 305 December, 93
Ralph J. Stephenson PE PC
Consulting Engineer
Step 1 - Prepare and arrange the document file material- Document copies are
arranged, usually chronologically, for future entrance into a single number filing
system.
step 2 - Month number the the documents..; Each document is uniquely identified
with a number that relates to the month in which the document was prepared.
Step 3 - Day number the documents - When the document has been assigned its
month number it is further numbered sequentially by the date within the month.
This system is called a single number filing system, since all documents are now
uniquely numbered. For instance there would only be one document 04245, a
document prepared in the 4th month from the base date, and being the 245th
document chronologically entered in that 4th month.
step 4 - Build the document control file format - With the document uniquely
identified, the document copy of the original is coded and a data base retrieval system
established. Code fields to be used might include:
Document type
Organization from
Organization to
Individual from
Individual to
Subject codes
Others as needed
4 ho 305 December, 93
Ralph J. Stephenson PE PC
Consulting Engineer
Step 5 - Enter the document data in the document control file - If justified and
required, document data is now entered into the data base file for storage and
retrieval in whatever manner required.
Step 6 - Prepare the project history - A project history is prepared in the form of a
chronological narrative summarizing the entire project from the document control
file. Each major document is reviewed, if appropriate, and entered as a brief unit
description of an event, or of events, occurring within a given time period.
• dd levels 5 & 6 - claim prone jobs on which trouble potential is conjectured - Take
steps 1,2,3 and possibly 4
• dd level 7 - Claim prone jobs on which trouble potential is very likely - Take steps
1,2,3,4 and 5
5 ho 305 December, 93
RALPH J. S~JI1IINIIO•• P.E.
Oo.w'DUlL'I. . . . . . ._
P 1
P 2
ho 202 'Oil 2
R.A.LPK J. 8'1"BPB1DMIIOB. P.E.
001rlRnll.'Jlr. ".DnI••
SE TUCSON ABB
REC ABB MEANING ORGANIZATION CAT
49 BUL BULLETIN DT
74 COR CHANGE ORDER DT
75 HWM HANDWRITTEN MEMO DT
46 LTR LETTER DT
32 MLG MAILGRAM DT
48 PRQ PAYMENT REQUEST DT
50 PUO PURCHASE ORDER DT
47 SBM SUBMITTAL DT
30 TLX TELEX DT
69 TMS TRANSMITTAL DT
70 BIM BIOTIC MECHANICS MECHANICAL CONTRACTORS NM
52 CAS STRAND, CHAS. A. CO. NM
5 CRR CONTROL AND REGULATOR CO NM
53 CTS SIERRA, CHARLES T. CO. CONSTRUCTORS NM
6 FRS FRENCH STEEL NM
26 FXS SKONE, FRED X. TRE ENGINEER NM
18 HWL HIRTWELL LTD. NM
55 JAH JONES 8c HIGGINS ARCH/ENGRS NM
71 JTD DARTH, JAMES T. BIM CHIEF ENGR NM
7 KLP PAGE, KARL L. FRS ESTIMATOR NM
12 LFJ JAMES, LEE F. CTS PROJECT MANAGER NM
17 PAR ROLLA, PAUL A. HWL VICE PRES NM
8 RGH HIAL, ROBERT G. CTS VICE PRESIDENT NM
9 RTK KREITZ, ROBERT T. CRR PROJECT ENGINEER NM
25 TRE TRIELECTRIC CO. ELECTRICAL CONTRACTORS NM
56 TSS STIRTON, TOM T. JAH PROJECT MGR NM
13 TTB BEaN, TOM T. HWL PROJECT MANAGER NM
66 ANS ANCHOR BOLTS SU
34 APV APPROVAL SU
60 CFR COMPANY FROM SU
2 COl COILS SU
22 CON CONTRACT SU
36 COS COLOR SELECTION SU
10 CST COIL STEEL SU
3 CTL CONTROLS SU
61 CTO COMPANY TO SU
65 CWK CONCRETE WORK SU
54 DAM DAMAGED SU
59 DCT DOCUMENT TYPE SU
31 DEF DEFECTIVE SU
11 DEL DELIVERY SU
67 EMS EMBEDMENTS SU
44 ENG ENGINEERING· SU
1 FAN FANS SU
14 FRA FOR REVIEW AND APPROVAL SU
68 HLD HOLD SU
62 IFR INDIVIDUAL FROM SU
23 1ST I NS"rRUMENTAT I ON SU
63 ITO INDIVIDUAL TO SU
28 MCC MOTOR CONTROL CENTER SU
72 MEC MECHANICAL SU
27 MTR MOTORS SU
38 OLP OFF LINE PRODUCTION SU
45 PCH PURCHASING SU
73 PIT PITS SU
37 PNT PAINT SU
42 PRT PROTOTYPE ~ •.5".3 SU
41 PSS PAINT SPRAY SYSTEMS bo 203 pg 1 SU
R...u:..P.B J. STmPBlIINBON. P. E.
OCQll1Rl'.ll.l'D. 1IIIr. . . ._
39 QUA
------------------------------ --------------------------
QUALITY ASSURANCE SU
,.J
33 REL RELEASE SU
21 REV REVISIONS SU
40 SAF SAFETY SU
43 SAL SALES SU
35 SBM SUBMITTAL SU
24 SFW SOFTWEAR SU
20 SHL SHELL SU
sa TUO TURNAROUND-SUBMITTALS SU
16 URG URGENT SU
64 YR YEAR SU
FMSO: PFILE=SORTHABB
FFILE=HABB
TITLE=SE TUCSON ABB
TYPE=R
ROUTE=P
FM51: ABB
MNG
ORG
CAT
ho 20) pg 2
1
General Summary:
Lee James reported that all pit and foundation work was
meeting dates between early and late starts and finishes.
Still having difficulty getting dimensional information
about mechanical and electrical sleeve and thimble sizes and
locations.
can be improved.
Old Business:
~o 204 pg 1
2
New Business:
good job.
Closing:
ho 204 pg 2
Friday .JUlyS,1SB2
H/o 2.50
Apdl 5, 199
Attention.
W.W.T.P.
COntract 77· ~
Gentlemen.
----
When material ba. been received and !n.lf.l:a';Ued we vill,.",notify you of t.'e
iiiPact of tliI. delay to the project.
-x. I" i
r-.t '/J
Z:u_?,
:e I'-t e<:
/,(.~
\1DWLll
HIRTWELL SE TUSCON
~ ...........
R.A..t.PB J. 8~.
PAGE
P. Eo
SUBJ CLASS
SUMMARY A
SUMMARY B
------------------------------------------------------------------------
1 07115 0726 82 LTR CRR CTS RTK RGH
CTL/COI/SPD
STS/DEL/DAM/RFI
SHD/FRA/UON/URG/FAN
PRQ
RFP/SHL/REV/FAN/UFV
CON/CTL/IST/RFI/SFW
MTR/MCC/RFI
STS/DAM
REL/APV/SBM/COS/PNT
SAF/PSS/RFI
ho 205 pg 1
REC. DOC.
SUBJ CLASS
SUMMARY A
SUMMARY B
------------------------------------------------------------------------
11 08008 0809 82 LTR CTS HWL LFJ TBB
SHD/TUO
RFP/CWK/ANB/EMS/PIT
HLD/CWK/ANB/EMB
BUL/RFP/EMB/ELE
eUL/RFP/ENB/MEC
CWK/REV/ELV
ho 205 PI 2
P1 Ralph J. Stephenson PE
Project History for Period #8
-----------------------------
Schedules or Networks in Effect During Period:
Network model issue #4 dated 3/8/82, sheets 1, 2, 3, 4, 5
H/o 218
Ralph J. Stephenson PE PC
Consulting Engineer
You work for Joe Gather, the Director of Physical Plant at West Fork University, a
state college in Maine. Currently you are acting as the owner's project manager on a
$4 million library addition for the school. It is late March, and the project is to be
completed by early July, next year. Construction is proceeding under a traditional
project delivery system.
The first three months of the job have gone well. Mobilization and site layout
proceeded as scheduled, mass excavation is substantially complete, and all spread
footings are installed. Basement wall construction is now moving into full
production.
Over the past 3 weeks there have been some concerns on the part of the architect, the
engineer and the general contractor about possible. changes to the project. A new
director of library services, Larry Insotel, recently joined the staff and is mildly
criticizing the design, privately to you, and by inference in the weekly construction
meetings. It is your intent to have these meetings weekly until the substructure is
complete and then to conduct them every 2 weeks up to the pOint when the building
is closed to weather. ~
Mr. Insotel has a moderate knowledge of building design and construction but has
never participated in a major facility expansion. He is conscientious about his
responsibilities, and seems to respond well to predictable demands made on his time.
He reports directly to the Vice President of Administrative Services, the same vice
president to whom Joe Gather reports.
You realize that you will soon have to do something about the matter of change
implications and rumors, since field work is showing signs of slowing. Nobody on
the project apparently wants to go through the trouble and potential expense of
unneeded revisions, cost fishing expeditions, bulletins, change orders and long
arguments about how to collect for the extra money and time that might be
involved.
As the owner's project manager and design and construction representative on the
job answer the following questions
2. What steps would you take now to help resolve any current or potential problems
you have identified in question 1 above?
3. What indications are there that any of the problems might be cleared by the use of
appropriate documentation.
4. What documentation would you design to permanently (for the full length of the
project), or temporarily (tailored specifically to a temporary problem) help restore full
and confident job implementation in the field?
5. Write a mission statement for the documentation system you are considering.
6. Prepare a layout and description of one of the documents you would tailor to the
current project situation.
c.. c.'
4
PHOTO FILE BY RECORD # - DATE PRINTED: PAGE 1
REMAR"::S 1
F'-"1ARKS 2
EL DEseR
LuCATION
REC# ROL# P# DTE YR CAM FLM SF'D JOB # F TY
BOB 3( BETTY INSF'ECT BASEMENT OF FARM HOUSE BEING TOURED BY BOB to( BETH
DEMOLISHED AND REMOVED ROOF SLABS FROM WATER PLANT FLOCULATION TANK
ROOFS
WATER PLANT PRECAST DECKS
FLINT, MICH
59 0024 06 0911 84 XA ASA 100 84026 PCO
H/o 242
-------------------------------------------------------------------
6.90
-------------------------------------------------------------------
6.2(1 **+9
-------------------------------------------------------------------
3.40 *+*7
4.30
3.20
H/o 24;
12/10/93 To do list - Mary Glenn 12/10/93
2 98 2114/90 Get info on CSI/UCI oodes from AGC or AlA and their history for efa class tac b
3 98 12n190 Write or call Joe K & thank for procurement booklet phn m
10 85 2114/90 Write Stanton thank you for close out info wrt m
11 83 2118/90 Bring courthouse construction notes up to date· see a:nls0211 epsen file tac m
12 80 2128190 Prepare ho re management principles for const proj mgrs & superintendents top m
(,. C. 7
Page 1 of 2 H/O 125
10/76
RALPH J. STmPHl!lNSON. P. E.
Claim Prone Job Characteristics OOJfIl'OUrUlG JIlJfGOIlIIlIIB
(continued)
Contested construction claims have increased over the past few years and now must be recognized as a
serious road block to proper and profitable construction procedures.
The reasons for the increase in contested claims are many and must be understood in the sense that our
society has become somewhat legalistic. That is to say, the recourse to legal resolution, as opposed to
interpersonal, technical, or administrative resolution of problems has become a common fortunately
shows some signs of diminishing as costs and time involvement in legal matters have increased
astronomically.
However, there are claims, there always have been claims, and there will probably always will be
contested claims. Those in construction should however, thoroughly understand the structure of the
contested claim.
Several years ago a firm specializing in construction claims and their settlements studied some of the
most common causes of disputes. Of two hundred occurrence of contested claims the following percentages
were found.
A legitimate change within the contract scope for which the owner must pay.
Examples
Advice
- The client or owner is obligated to pay for the change, if there is a charge.
- Payment for the work should be explicitly agreed upon before starting.
2.Consauctivechange-42%
An owner's action or inaction that has the same effect as a written order.
Examples
- Shop drawing corrections, showing additional work not covered in contract documents.
Advice
- Make certain the scope and costs of additional work is clearly understood.
Contract documents which do not adequately portray the true contract scope.
Examples
- A retaining wall shown dotted on the contract documents and expected by the architect/engineer and
- Contract documents that expect performance by default. For instance, specifying a miscellaneous iron
Adyice
• Expect to pay your architect and engineer for good quality assurance in the production of contract
documents.
- Don't expect your contractor to design the job unless it is a design/build project.
4. Delays - 41%
A delay situation beyond the control and not the fault of the contractor.
Examples
• Rock encountered that delays the job but was not shown on the contract documents.
Adyice
· Be as thorough as possible in defining physical conditions of the site upon which the facility is to be
constructed.
- Specify weather standards when it is necessary to clarify time extensions that might be caused by
inclement weather.
- Don't stop field work without proper authority and a very good reason.
More work with no time extensions, or the same work and a shorter time period in which to do it.
Examples
· Owner refuses to grant time extension for work that will take longer to perform.
· Owner makes use of float time with the expectation that the contractor will not request or require a
time extension.
Adyice
- Never assume the contractor will do extra work within the contract time.
- Work out an early agreement on the use of float time in the network model.
6. Maladministration - 35%
Owner interference with the contractor's right to enjoy least cost performance.
Examples
- Owner directs contractor to provide a certain space in a facility early without such early turn over
Adyice
- Make certain the site is fully available to the contractor before the job begins.
- Oearly define the time frame and the sequence by which submittals are to be processed, and do it
Examples
- Artesian water encountered in sand seam outside of where soil borings were taken.
- Restrictive easements or assessments on the property not made known to the contractor before contract
execution.
Adyice
- Make certain soil borings are adequate to show any unusual conditions.
Examples
- Specifying installation of above ceiling work that won't fit in the space provided.
Advice
- Expect the design team to check their work thoroughly for interferences.
- Accept your legitimate design and administrative duties and responsibilities and take care of them.
Withholding data or information during the pre contract period, that affects construction on matters of
importance.
Examples
- On a steel erection contract not telling the bidders that the steel had been refabricated from a previous
pb.
- Failing to tell bidders that there is a cost cap on the first two months costs
- Not telling bidders that there is a high pressure gas line through the site that must be accommodated
during construction.
AdVice
- Be certain all bidders know as much as they must know to propose properly.
- Locate, to the best of your ability, all site obstructions before bidding.
- Don't expect the contractor or the architect and engineer to read your mind.
10. Termination· 7%
Examples
- The section of the project is no longer needed and is removed from the contract
- The owner doesn't like the way the superintendent talks back to him.
Advice
B. Destructive conflict
Animosity or disagreement which results in lowering the potential for an individual or
organization to succeed.
e. Positive conflict
Hostility that is managed so its resolution raises the potential for well intentioned individuals
or organizations to succeed at being excellent.
D. Responsibility
The assignment, spoken or understood, that a person in an organization has as their part in
maintaining the organization's health and vitality.
E. Risk
Any exposure to the possibility of harm, danger, loss or damage to people, property, or other
interest. To expose to a chance of loss or damage.
II. Why are disputes often not resolved promptly and fairly.
A. Differences in goals and objectives of parties to the project.
B. Greed.
e. Improper assignment of risk.
III. Some actions entailing risk in the planning, design, and construction profession.
A. Approval processes.
B. Being a good neighbor.
e. Closing out a project.
D. Communicating with others.
E. Maintaining constructibility of a project.
F. Maintaining construction document quality.
G. Managing cost growth.
H. Maintaining a good work site.
I. Keeping job morale & attitudes healthy.
J. Managing and resolving legal matters.
K. Paper and administrative work.
L. Payments.
M. Planning and scheduling the work.
N. Setting and maintaining polides and procedures.
O. Processing revisions.
P. Material and equipment procurement.
Q. Maintaining integrity of the design and engineering program.
R. Establishing a profitable cost structure.
S. Managing quality.
T. Processing submittals.
U. Controlling time growth.
IV. How to recognize risk on a project (adapted from Mr. Papageorge, R. A.'s comments on risk)
A. Identify as many potential threats to project success as early as possible.
B. Identify where problems will be caused by taking risks to help assure project success.
e. Evaluate and analyze the project team's ability to take the risks identified.
D. Evaluate and analyze the project team member's abilities to take the needed risks.
E. Identify the impact of legal contractual obligations on the risks being considered.
F. Evaluate and analyze existing project conditions and the restraints they exert on the project.
G. Establish and implement a systematic procedure for identifying and adjusting risk to acceptable
levels to assure a high probability of project success.
V. Helpful hints to effectively manage risk in construction
A. Start the job at the right time.
B. Profile the job before committing resources.
C. Always remember - good management is risk control.
D. Don't lose your personal intellectual grasp of risk on your job.
E. To manage risk correctly, read the documents.
F. Evaluate the quality of the total contract documents.
G. Be certain to obtain and read all pertinent contract documents.
H. Match your price to the project delivery system being used.
I. Avoid being made a limited agent on a hard money job.
J. Avoid over-the-wall management.
K. Keep abreast and aware of current industry trends, particularly organizational patterns.
L. Be aware of your client's must, want, and wish list, and respect them.
M. Understand and account for other project participant's profit needs and desires.
N. Don't hesitate to scrub your proposal if the risk is excessive relative to the rewards.
~ ,,~
1~ ~~~~
t ~
~ ~~K~
~ 3~~u
~T
q ~~sr
~ 'l~ ~~}
, ~-.:
~ ~~~~
~~~~
~~li~
~
~
~
I
I
, \i
~ ~()
lI ~~
~~
Q ~ ~
I ~~~
~
~~~~
~ ~h~
~~
~~Q
~~
~ !l~~~
~ "l
I''t ~ ~
~
~
~
~
*
~ ~~~
'.J
rt>~ ~ ~
1~~ht
11/
~ ~~~~
~~f~ ~ ~~~t ~ ~
I
I ~
~ ~
~ ~
~:r
l ~
~
'"
~ ~ ~ ~
'l
~R
~
~~
7.0/
H/o 150 '3/77
Ralph J. Stephenson PE PC
Consulting Engineer
A. Rarely is more than one problem out of four worth other than a manager's
fleeting glance.
B. The good manager must quickly identify where his efforts are going to do the
most good.
C. The effective manager must understand Pareto's law· the principle of the vital
few and the trivial many.
D. In general, fewer than one third of the people a manager supervises require more ....i
than two thirds of his time. ...",
E. Managerial missteps resulting from not understanding the vital target concept
include:
1. Following prejudices
2. Sticking with pat systems
3. Doing what is easiest
4. Playing hunches
ho 233 December, 93
( ( (
1$ 100 7 10
.,
7/27 7130 8t7 8121
7, o 1111"'3.------".,
"=
/l
00 3$ 100 3 100 ,
7f8 8124 W. M 8t7 WI.
~fAB&DE· r-,.....".'I""'A:-:-:::AY,....-~ i1ll!Ei'!f IEtil I
~'rI4ClU PENlHOUSI! ' dl!~jk··
~ .. .'MsUL& 1_ _-II.~~!'IS,iI 1 - - -
100
111 0
/10 ·fItiMP '·21... ·
. . ... .. RJOFI.NG." .
I OHIRTO.lJlY 1 8121 &.24
1
100
Mil
llit 7
a
100 0
8/31 8/3
~----------~~ ~
'4
~
~
~
%CIOIl1l Eslimaled dunlIion
Eartylllart EaJ1y lirish
o 5
l/IIl 10/5
- Adlvily number
21-INSTAlL - Activ_,. cMscription
ELECT PANELS .. - Adlvily esIimaIed
FEEDERS-S duration in elapsed
wortOng days
11/6 .l1l1J.
laIalllart laIa finish
o 3 o o
11121
1------11
i_ 16& GiOOiM!
WATEFI'A'G TO
A.OOR· 3
11126
I
1-._ _ _ _
2&-CHECK, TEST
IITURN OVER
-1_ EOlIP ROOM· 5 _
I 1213
r27-ETIRTOSET
_
LAlE FINISH OF
ACllViTY
1213
, ,
11121 if126 11~H 11", 1~§ 1~
LAlE START LATE FINISH
11113
~
()
'i\.
......, • July 7
..... ., - _ _ '111 NETWORK MODEL FOR
332 111' mlr phi 1111h1ph1
dltllt lat
CLARION OFFICE BUILDING
PENTHOUSE MECHANICAL
EQUIPMENT ROOM 11
flew""' Act!ylty Nymbm
041 046 luther Mechanical Contractors
042 047 Washington, D.C.
043 048
044 049
045 050
sheet
ph-1
l l l
RALPH J. STIIlPHJ!:NSON. P. E.
OO:wetn.TIJlG Jil:JrGIJIB..:a
Oolor Coding
Green
Orange
-Blue
Yellow
Note that the evaluation is made on the basis of the current date.
Ohanges in color are significant, indicating a deteriorating or
improving sequence of work depending upon the progression. Color
coding is primarily used to locate undesirable trends in work
progress and to show job history.
Node Sequence
Page 1 H/o 61
RALPH J. STEPHlIlNSON. P. E.
Oo_uvrIWG JilNGIJOIImR
Page 2 H/O 63
llALPB J. STlDPHIUNSON. 'P. Eo
Oo~.G "or...1IIft
. I 2. 3 -'I S (,
1:s7AS,i( c.UIe~£N1LY y
PAST eF 'OATE !
N IV Y Y
~LO;( e.oD£
....
/!U.U£
--~ ~
x X,
'81"1
- currently past early finlsh (U) date.
Hote tb.a t the evalue t10n ls _de on the basl, ot the current da te.
Chan. .s ln color are slplflcant. lndlcatlng a d.terloratlng or·
19proTlng s.quence ot work 4ependlna ~on the prosres.lon. Color
coding 1. prl. .rl1y us.d to looate unde.lrabl. trends ln work
progre.s and to .how job hls tory.
7.07
H/O 91
RALPH J. STEPBlIlNSON. P.E.
OOJll'I!I'C'V1'Dl'G l!ll!II'GIH'JCER
Monitaring #1
Was completed
Task Color Code Status evening of Will be completed
2 - 3 Camp. Sept. 1
2 - 4 Camp. Sept. 7
2 - 5 Camp. Sept. 9
.. -.-VICTORIA
_ ~ECHANICAL
. . .- _.. , ... _•..
- .. __. _.. COMPANY ---_._. _. ----- ---'-'-"--'-- ---_ .. _._-_._
. .• _. __ _---_._ _-_ .. _
•. ...
Page 1 of 11
..... _ .. _ ! . ........ _ ..._.. _.~ ...._ .... __.. _...
_._._. " . 4 ' __ · _ _ .~. _ ~ __ .... _0_ _ _ •
._-_.. _.. --..-- ----·eD'··-·... ..- --.....-- .-.......-.--...-. --cosr"-' "NOOE'-SEQUENCt:'-~--' -._-_.
._.__! __ ~_.. _J?~.X s _~~~_ ..c; Q... Ar~.Q_I?f:.S~~} ~T..I.O~ .... ___....._ _.......___•..~Ls_ ...._.b.(~_ .. ~(_F__ .Ld F._ .. _IL_ ......_..
-'-i131 170
31 170 0
..... 0..- 0
"'0'" ...- "00 .--.-----. -._-.---.--- --··-·------·-····i111~6 11246 11116 112:'6
1126' -il'Z46-'Tll:i6"Ti2j,,'" a
'--8-"-'
132 138 6 6 2 P INS SPRINKLER PIPl~G 2&80 9166 10146 9~36 102l~ 20
... --1 H ]39-8'-'-T'- f- '-"p- iN~ SHY- r-riiouclf"T lNG-S --';800 n06 10 11'6 --'-9i96-'Iij2'1C:~ '-'-1 s····-·
134 140 3 1 2. PINS OMS1C WTR PPG-(~G 720 91Zb 101V6 9156 1021' 26
- ... i ~S-'-is 1---3-------1--2 --·-·p--T~~s·i"lTG·&i.:l.NG--P·PG·· J ~,·cLlj-··-720·- 'II 146 l"(fl'ib--9I66-rOd'6-'-~T-"
136 15~ e 1 2 IN~ 101M PLMG RISERS 1920 9216 10126 9306 10~1~ l'
i~''i i ~i 2 4·------i- -Z-'---p' It:S ";\UFF ·Ei~EC· CNuT&FORS -.. .. - 91~6 fQiu~-' 9176' To 4: 16-:----·i4"·-·-··
138 153 0 0 0 ~246 10U6 92:1:16 lOZl6 _ .~9__.. _..
1:?8 -i~14'--' ~ .." --,-' -2- "'c' INs···~PF:x"N-Kt.:·ER"-pj"PG-· .-.._.- 2~6o- S246···lOi66·--·'I306 i-HHc:-, 22
139 15~ DOD 9306 1022' Wlib l021~ 16
..- i39'-i5~ --- ·a---2-"2----'-iii""sStd,,1·fCDucTc;VfTNGS -4110',)' --9306--10~1~-T,;ffb'--.iTo~-(,----g---·
1~O 1~3 0 0 . D. . ..... .... 9166 10Zl' 91~6 lUl16 26
140··1563-···· i i - - 'c-li~s - DMs-fc--\iTR' P-PG-CLG-'-720'" clloo-'l(:iia6 -~io'C; 'ilOl t) 3\:1'--'
-. ---'---"--' --_._---_._._----------_.
--------_._. - - ._._----- -_.._. --_. -----_. ---------.- "---" '-..-.-- - - --.--.--.----.- -.----
.DAJ.t.£. N1E 5IW~N _A~ 1·~QIHH.[lI\Y. YR. __ t.OIJN .Tf:T...~O.L 1NiHCA 1 ~S C.RITl CAl.lTEM
L.eC COST - ~ARLY- "Tt(T SC:-Q .._-- -- ---
....._...1... J._ DAY.S.. _.p.~.f'__.. C.ILANLLt1ES'RIe.T_IOI'L__.__ _.. _____.______;!..S. ____ .~!§ ___;_LE_ -,.. ~f __ JJ:...___
13~ 151 3 1 2 P INS Hl~~CLNG PPG IN CLG 720 9146 10196 9166 1921~ 25
- ".. 132-'1'3 (I ·---6·----- - 6 ... -}----1l-Tf~5 "~PlnN~L:EiCPlr'J NG· ..·-· -2lHHr-"'916'6--10'14o---9236-10216 -~u-
140 156 ~ 1 2 C INS DMSTC WTR PPG-tLG 720 9166 10~S6 9206 11016 30
Tsr HOI' ---~-- 1---2----r.--rNS-iii't'(LNu- ""P/:'lk ·Ct:G---4eo---9rt6J:O-Z96----l}'2()6--rl016-·-----;'1,1 '
108 11' B 2 1 C iNS SHT MTL DUCT&fl1NGS 4S00 9206 lQ076 9296 10186 13
-----1"21·-174 ..,--. 3·-------,- T- ---C--EF( STOOS 'F-UR DRY -w'l.C[------·-----r0046---nrZ7.b---roo6'i,-rO ~66 . -1'4-'
In 123 4 1 1 r INS 1N \~LL foIECH/t:I.f· r. INK 1920 luC46 lOBo 111 ..)"f6 l022~ U
122-1(3 --4------3- i --'ii INS"--J;{~!I.L;"ECH/EU.;:,~WI'.r'if20 10Ci46-fcfl~ib--foo161n,6" 11
161 g;. 3 :. 2 P E.R STUD's FOR DRY \>IAt.L 10076 10266 1Cl16 HOLl> 15
1,6 ) 2 i .--';:-. -- f'---C - C' n,i61 N ~jLL M~cH-n:U: C -wiZ-- "I 4-?i\J' lOot!"--l.O~ ,,,-):(lli6-'l'o:C ~-t;--·r.::j'-
12£, H"f 3 :3 1 C INS IN WI.L. ME(;tlltLf.:.C WK 1440 10006 10276 10126 lOi% 13
162 ).()!:i·--4·· .. -.~.- 2 C-ER STUDS rOlf bRy \~ALC -.-.-- ---10126 i1C46--16r~b"llu<j6 i"'--
163 )64 4 1 2 P INS IN WLL MECH/EL[C WK 1920 101i~ 110~b 101~6 110~6 14
16:~1Mt '4' -3 2 ---'P -IN!; IN l'ilL. M'ECti/tuc~iK--Hi20" rO).361io2vl01B6--11C;:;1i "1L;
H,I 11'.1L: I.; 1 2 C INS Jr.; IJL.L. ~ECI1/EL[C W~ 1920 10196 llHl6 10226 111'6 16
107 '-1611"'lj --,.. 3--'2---C-Jf~S IN' WLL. ~1EC}i1EL?C- \iK"'f9~W"ioT~e;;iTiub-1022b'--Tl He, ---it;-
125 1.2£' :; 5 ". ! ___ P_ ti~_NG I)H~_. !i~L.!::-_ __ _____ .1.02:'6 Jg.?~6._1Q2~.~ __~..9.i ____.0. ..
. . ..."J
--_ .. _--- -----.- -'-'--' --- --- ---.-----.---- ----- --------- -- ----------_..-------------. --_.
"". ... .
. \
__ f.R.Q.J~5= T...~~ ...J.6:- ~.(l._.1. S?~[;.. n.o •. t ...gJ!!.f:!>...A.PH l.l._. 2.~!..)_9J.Q. __..__._ .... __ .___._ _.__ .. _.._._____.__..
.. .~~LPt!...:J_ SJfP'IiHlS.O.N.-''... E . _ . c..ot:i.SU~. T!\i:tl
" ..DATE!; ML,sl-lmm A..S. MQ1:iTlhD~Yt.VR ... ·Q~. jI~ :r.FT~9~._.H'i;::::ATES ('R1TICAL ITEM
toe cos').' LATE -STr{T"s"LQ"-- _..- . - -•. _ ...
__ •. __ L ._.J.__ DA.Y.S. RSP.3:.0_ .A~D .. DE SC;R ~ PJ H)~~.. __ ... ___ .. _....__....._ ~{~._. ~j ;';._._.J:! f __ .. _L!.f.__.__It..
.1 2.. 106... __ 0 .•._•..._.. T/H 10 START OF Pii.OJI:CT ... 192-"_ 102b !)3lt: !):U£> (;
2 3 6!> TIl{' pouR ·ClJt·l·[,l fL SOG" - -_·······6016 .. ··bait. "ii:nb --'92i"6 -"b'"
0 1
2 6 70 0 R TIR TO CLAY INSUL & RFG 6016 71~b 9066 10226 3~
'--'2-' -S-·· . 5'6'''-'·'0'' 're ·TlR·-'tO-·CE·t'f-Rf· MTC ott-I<. ....__• "'-"-cjCfio'-7 2o~·--trifui.:.·- nrCJb'L~'--' ';'-4' ..
105 111 9 1 1 INS TO/R PLUMSG RISERS 2160 veS6 92~6 9206 10056 11
'--;(o2-fos' ". _oil - . 2 .... f" .. P '1 NS sHt· MTC-OC H rY1i~Gs"" i,"coo-- '9006 924(;-' "iji7e.-- iC'I~(., '--')'2
101 107 6 6 1 PINS SPRJNKLER PIPG 2880 90e6 920b 9156 lOO~6 14
106 112' "4·"-" 3"-1'-'- p'INS 'RUFF fLEC CNDT(-f:DR'S-' ......···90S69~06··-- 91-36' '10016"- .. it; ..
103 109 3 1 1 PINS DMSTC wTR PPG-C~G 720 90~b lU016 9106 1U056 11
. "-ni4-ffo"'-"'i;' .. _-. C-'l" P-fNS- 'H,'G&cfI\GPPG-TN-','Ct---96C> '-'-96'~'~''i6066-' -9"13-6-io iii; _···20-····
11~ I1S 6 4 1 ER INT MSNRV PARTNS 9216 100bb 9~6b 1U)36 11
ios' '11 ~-. 's .... '-"2- "1-"- f'-f N5' s'~IT" M-TI. 6ucn~F1 tNG~ ·iteoo· . -9zci"l0076'-"92~'''loUlt;--'--ij .
13i 139 8 2 2 PINS SHT MTL DUCT FiT~6S ~800 9~06 10116 9290 1~20& 1~
107 li4 ·· .. -5-····6 .. TO< CINS sp'fflNKLER PIPG ... , 2ltOO '91(;" loil6'--9226"Iolb6 io'
-"'H~-i~}--'~-" '-i'-+--"~N"~N;6~'~§~~~EC\/i'k~Rt-f\-~!:~=-i-~~g--'~'~1t--i~i~: :}g~-·}g·H~--- ~.~-.. ..J
109 116 3 l I e INS DMSTC WIR PPG-CLG 720 9136 10146 9156 1016b 2~
137 1~2 4 3 2 P INS RUFF EL~C CNDT&FDRS 9146 10186 9176 10216 24
--12;? . '12:f '-i;--' - ·f-C---·p· ir~b-·lN-WCL MECHif.L·[ c"wi '-1 9icr-io(;}4t6' Ii.ff96 -'100" 6'--102 g"---l Y"
127 123 ~ 3 PINS IN WLL MECH/ELlC WK 1920 10046 loi96 10076 10226
1 11
lit. 140-'3-"--'"l"i-'-p' iN'S' DI-ISTC Wlf< Pl'G-<.Ct-·······,2ci "9f36 - n\r~t;·-- '9i-%--'102iiJ '2f)"
13~ 151 3 1 2 PINS HTG6CLNG PPG l~ 'LG720 914~ 10196 9166 102]~ 25
.. 139 lS!) "'fi" 2'-"2:- "c' INS sHl"MIL [)GCT&FllN('S Id:lOCi' 93'06 '10216 fo-n611bH, );:,
121 124 3 S 1 C ~R STUDS FOR URY WALL 10046 102~b 1006b lU,(.,G 1~
. --1&3 1"5~" "-4""--'- it --t· -E'R n.ft--f.,S~\jRY··PARf";~S· ._- .....- -'1cY616--io-Z2Q -'Hiof;"(;- 'fJ~f-j6' --Hi··..
___ i:~B f~'4 '5-'-' 6--i-"{ INS SPR 1 NklEf<"rlJ PC; 24(;0· iii·4t. i02b~""9j(j'b"'li()fb-'2i-
lU· 12', :-; 1 1 C lf~~ IN \~I I. MEUI/e:.LlC ,/K 1414(.\ lCJi..It'b 10276 10116 l02~6 1.3_
12 C· 11. f" --3'" . '3 -.. 1 ' . C 1~IS '1 II; ~iL.L··t-iE6·iI t::L. f C WK.' flt4 0" i 008 ::-102 7t. -):6 i.2 C;. 10;; 96" 13
14(11::,(, :1 1 2 (iN;:' Of'l;STC viTR PPG"CLG 720 SllM.10Ztib 9.20() llvlli .__ ;?CL
--I~i"i~9"3"-'- ·3····-2·---t- II~S RUff"ECC-C" (NiJYc.F"6k-s---··· --····--9206ioi8·6--··-92i-b··-J.Ti,;ii~ 2(;
161 162 3 5 2 P lk STUDS fOR DRY W~LL l007~ 10266 10116 110l~ l~
l~l 15i·----2- 1 2' "'-llis HT('&CL~ic,- PPc:' IN"Cl.G ··4eo··.. ·917t:. 102~~' --9iob 1iolt.~··-·3()·-
128 1.29 5 S 1 cor·lp rlANG DRY rli\l.. t 11016 11016 llC~() l1CJ:.:d, (;
- .. 1"6:J 16 t.: ... 4--'" i ' ;f" PINoS IN ~;LL t·1E CI~I f~L i.: t"
'1 i; (: o-'lOlZE> 110io-10'1 ~ (, 'l1ti ;':)-" i;:;-"
~il<
163 lUi! 4 3 2 P J:~S 11.. \<iLL ~iECII/EL.lC I"K 1920 101~" 11026 10186 lllJ!;>b 1-:+
. -·16l"-16-~ . "-4- . -. ·5.... · 2- .._-( ·r.r~· STUDS'-FOH L1KY ·wn.t.:. _.-..__...... 10'j;26' -11'04'0 - 11) 1:;6 ''11."(. ~c. ···n··
_..... _---_._--_..... _. --_.. __. __ .- ..._._.- .... _._--- .. _ .. _-_ .. -.... --"'---'-'--'''''- -,-_... _-_.
._J?R()JE c;J _No1-<1~ lO__ .J.ssvt:. ...NO.••. L_ .Q"'.H.DN'~ Ik ;?o_L~~.7C!. ________ .•_____.___.____......
... 1_ ... L.l.06 ._.__T If< . TO START _qFP~OJECL ____ , ...__..~.926_._ J_O.?~, __ .?.31~_,~~.l~. .._JL
~ __o......,
2 3 65 0T/R POUR OUT l~T FL SOG
1 6016 6226 8316 92~6 15
2 4 69. 0 2 T/R10 POUR OUT 2ND O E ' K 6 0 1 6 6166 9076 Y226 11
101-j'076' -~-6 ....f --. p- I1~S SPRINKL'ER'''~ 1PG --"'2a'e'o---90~6'" 9'286 '--915-6-1(;0~6 ----14-
__ .19]~Ob ____Jl_ _ ..._.. ?_~. ___~.J.N§.....§,I·iI __ Mn.-P_~I&U:r.NGS_~.~QQ __ .JQj.6_,~~_4k. __ .~.U.2._~QO~9 __.J.?~_
103 109 3 1 1 PINS OMSTC wTR PPG~CLG 720 90U6 10016 910~ 100~6 17
105 111 9 1 1 INS TO/R PLUMBG RISERS 2160 9086 9236 9206 10056 11
'106' J 1 i 4-....·- 3-'i"" --'P INS RUFF-Ei.ECCN[)T{.FDR-S· - "--'90-8-6--9306 "'9l36-100;,6----'16
-..·-i-;j3·-139--·-B-------2---~C---p-H·is"··SHf-Mn.:··DUtT·FiTt"rcr$·-1anfo---9'2'06"-'l-0"1'lo-9-2-96-1Cj~~fo--,":;-
132 138 6 6 2 P INS SPRINKLER PIPING 2680 9166 10146 9Z36 1021e 20
··--li4·l'.O ----3 '---I-----i---P"-INS -o",s'Tc"wnf PPG-CLG 720- 9l'a6 101"0" --91~6-104!l6 .. --Zo'
135 151 , 1 2 PINS HTG&CLNG PPG IN CLG :20 9146 1019& 9166 lU216 25
--iil6 l!i3 -r" -- "1: ·--2-----1NS toiR' PLMG 'RI SERS- . -. - 192cf- 9216"lOI'6··93061o'1~-··· 'l!)
137 1,2 4 3 2 P INS RUFF ELEC CNDT&FORS 9146 10186 9176 10216 24
------2- -"6 -To--'--"o---R'---'I7R- -ro-'CCAY-I ffsUL -;;- R'fG----·-·- ·6'crn--,1'6·6·--VOSc'"1.-(J[2i:> ._- 3Z
2 7 102 0 T/R TO e EXT MSNRY&GLZNG 6016 6016 10226 10226 0
12 i! -1t~ I. r
1 1 .. i INS 1 N WLL -MEeHl fLEC wiCIs'zo-l ()04o"lo196' f()076" '10-21.(,---n
]22 12~ 4 3 1 P JNb IN WLL MECH/ELEC WK 1920 10046 10196 10076 lD22~ 11
- 121 -l'U.· 3 " - 5 -l--C'- E'I~' -blUDS FOR'- OHI( wACl-··---- ._. 1001+6 'lo~~6 ·H)066--rOU·6-- 14
153 158 4 4 2 ER INT MSNRY PARTNS 10016 1072b 10066 lU276 1~
.- 1:;!S·1.;f9-- '!:i---~" T-----"P'" HANG- DRY' WALl:" .... "-"" --'--'-' 'lCJ2!HiToG~'6 -lO·2!it·b-U)dC----O·
126 127 3 1 1 C INS IN WLL MECH/ELEC WK 1440 10086 10216 1012~ 102~6 13
_
....... .. _--_
- ._--------•...... _--------_ ..
.... _-_._--_
... _._--_._--_._-_._-------_ .. __ ...
- - .- - .--. -. _._---_._._- _... -.--- -.. ---------- -----------.--- .. .... "--' ----- -.. -.----- .... _..
_
----------
. \.
C;ONSlJLl~NT
DATES
-- ---
ARC SHOWN AS MONTH.DAY.VR '0' IN TFT COL INDICATES CRITICAL ITEM
--.- - ---- -- . -- -- LOC - --- --- - - - ----- ------ -- - - -------COST - -,. OTAC FI. T- SEQ - ----- --
___I_____~ __DA~ __.B§P__C;_Q.__ ~tiD__ Q!:_$_rJH~lJ9ti _________________ ~_~____ ~I;;_ ElF L/i- if
----
1 2 106 0 T/R TO START OF PRO~ECT 1026 1026 ~316 ~316 0
-----------27 10i----- -O--------t)R -TO C-fXT-MSNrdc,GLi'~G--------- ------60-i6- - 6016-T6T26--10226----0--
12S 128 5 5 1 P HANG DRV WALL 1025~ 10256 10296 10296 0
128 129----- - S---S--l----CO-MP HANG DRY -wAL.I----- -------- ---Tl01~ - i1016-- ii6-~6--n056---0-
130 131 4 1 1 INS FIN TUBE PIPING 960 11086 11086 11116 1111b 0
118 1?1 3 ~ 1 P ER STUDS FOR DRV WALL 9296 10146 10016 101~6 11
122 123----4- -- ... f--f----p -1t~S-IN--~'-L.L-MECt1/ELECW"-19-20---fo046--10196- fO-01l-iOZi(,'--n
122 123 4 3 1 P INS IN WLL MECH/ELCC WK 1920 10046 1019b 10076 1022(, H """'"
102 108- ----6 ----- '2" ---r---p- -"iNS -SHT---MT[- i,)-CTC,F- t T NG5---'4coci- --90S-g---- 92 t+6-- 9176 -T00!16 --- li
108 115 S 2 1 C INS SHT MTL DUCT&FTTNGS 4eOO 9206 10076 9296 10186 13
126 127 3 3 1 C INS IN WLL MECH/[LEC W~ 1440 10086 10216 10126 10296 13
121 124 3 5 1 C ER STUDS FOR DRY WALL 10046 10226 10066 10266 14
163 164 4 3 2 P INS IN WLL MECH/ELEC WK 1920 10136 11026 10166 110~6 14
133 139 8 2 2 PINS SHT MTL DUcT FT1NGS 4COO 9206 10116 9296 102~6 15
f36 t~3--- --e----f---i---TNS--TOiR- pL-MG- RfsERS-- ----lci20--92iE; -10-126 9306- 102H,-- --1~-
139 1~5 a 2 2 C INS SHT MTL UUCT&FTTNGS 4~00 9306 10216 10116 l~Ol~ 1~
--n,3 l~A---- -4----- 4---Z----ER· 1NT MSNRV- PARTNS - ..----------I0016 --10226 -1006-6---1'0276---""1.5
161 162 3 ~ 2 P ER STUDS FOR DRV wALL 1007~ 102a~ 10116.11016 l~
----167 He ---4----- ----~- - '2" -- c--n~s J N" \-IL-L -,..,e;CH/ELL-,c;;--WK- --1920--10 19-(j 11106 - Hf.2z6- -111 :-.C-- -r~-
103 109 3 1 1 PINS DMSTC WTR PPG-C~G 720 90Bb 10016 9106 10U~6 17
'16£ 16& ---4---" ~ --2-C:- ER- STU[)~ FOR-ORY WALL - - -..- -1'o1"21; 11046 -101s-b---no96'-----17
107 114 S 6 1 C INS SPRINKLER P!P~ 2400 91~6 10126 9226 lOl~~ 18
!::IS lS)____ 3 ______ ~__ 2 P IN~_t-:tTG_&~LtH.i ppc; iN _~L._G____ 12Q___~_~t!6 101y/',) 91b6 lC2~t.> 25
- - - -- - ---_.. _...
. _-----_._._-----_._----
-----_........... _---_.
----... _- ._.....
...... - .... __ .. __ -.--.- ..-.". . ._----
Project: 76:10
Target Completion Date: November 30, evening (working day 234) for fin tube piping
Actions taken:
Inspected project
General Summary
As of September 24, (working day 188) The project basically in healthy condition.
An evaluation of the job against late starts and late finishes shows that all major
tasks are currently meeting or bettering late starts and late finishes.
Accurate information on exterior masonry and glazing status was not available
from the general contractor. This work should be watched carefully since it affects
hanging board upon which installation of our fin tube piping depends.
Projecting directly from late start/late finish sequences, it appears activities over the
It is anticipated that on September 29, according to the current early start schedule,
studs for drywall are due to start at the first floor. However, looking at installation
printed 11/20/98 ho 141- November 98
7. '2.. '"
Ralph J. Stephenson, P. E., P.C.
Consulting Engineer
September 25
progress of toilet room plumbing risers it appears these are lagging early start/early
finish targets. Therefore, interior masonry which restrains installation of studs will
probably be late and may delay installation of in-wall work past the current desired
early target of October 4, (working day 194).
In summary, the project is moving fairly well. The superintendent is on top of the
job and our projections for work over the next week indicate the job should stay
healthy.
Ralph J. Stephenson, P. E.
Monitoring #2
W as ~Qmi21eteg
Task Color Code Status - evening of Will be completed
The question of hazard or not, reqUired correction or not, the appropriateness or not of
the abatement action required is often in dispute.
• Acceleration
Contract work performed in a time period shorter than that originally conternplated by
the contract; or contract work performed on time when the contractor is entitled to an
extension of time for his performance.
• Administration
• Administrative operations
Actions performed by those persons who provide the support services which make
possible the production of products or performance of services by the line operations staff
of an organization or business.
• Administrative settlement
• Adversarial
Taking the position of an opponent or enemy. Opposing one's interests or desires.
• Advisory arbitration
An abbreviated hearing before a neutral expert or a group of neutral experts acting as
arbitrators. The neutral arbitrator or arbitrators issues an advisory award and renders
prediction of the ultimate outcorne if the matter is adjudicated.
• Advisory opinion
An abbreviated hearing before a neutral expert or a group of neutral experts acting as
advisors. The neutrals render an advisory opinion and often predict the ultimate outcorne
if the matter is moved to binding resolution.
• Advisory relations
The interaction of parties related to each other by an obligation, either contractual or
informal, where the service performed is of an advisory nature only.
• Agency authority
A relation in which one person or organization acts on behalf of another with the other
person's or organization's formal authority.
• Agent
A person or firm whose acts are asserted by the third party to bind the principal.
• Apparent authority
A situation in which one person or organization acts on behalf of another person or
organization without the other person's or organization's formal authority.
• Approval
An official or formal consent, confirmation, or sanction.
• Arbitration
A method for settling disputes whereby an officially designated third party (usually one ~
to three people) hears and considers arguments and determines an equitable settlement.
Usually considered binding upon the parties.
• Architect, engineer ruling
The ruling of the architect or engineer in an issue or dispute on a construction project on
which he or she is the design professional of record. Where specified the ruling may be
binding if accepted as Specified in the contract.
• Articulate
To express oneself easily in dear and effective language
• As-builts
See construction record documents
• Assigned contractual relations
The interconnection of those parties bound by subsequent assignment of a contract to
other than the initial parties.
• At-risk
A position or action that puts an individual or organization in the position of possibly
suffering harm , loss,or danger. Often the hazard poses an uncertain but potential danger.
• At-risk construction manager
A manager of a construction program who takes the responsibility for paying for the
construction of the project and then collecting his costs from his client under a contract
with the client.
• Audit - as applied to projects
Inspect, analyze &: evaluate project status, management and health against criteria
established as a standard of performance for any give point in time. The audit
encompasses such measurements as:
'1.0'2.
Ralph]. Stephenson,. P. E.
Consulting Engineer
Each auditing situation is unique and the scope of the audit should be determined as
specially fits each individual project and project team. All, or a part of the above
measurements might be used to make the audit.
Auditing usually is done through the following steps, listed in general sequence.
• Authority
The prerogatives, either vested or acquired over a long period of time, that allows an
individual to carry out their responsibilities and duties. This includes the right to
determine, adjudicate, or otherwise settle issues or disputes; the right to control,
command, or determine.
• Basic contractual relations
The interconnection of those parties bound by the initial contract to perform in a certain
manner for certain considerations to be paid.
• Bench trial
A trial before a judge without the benefit of a jury.
• Binding arbitration
A process in which opposing parties submit disputes to binding determinations by a
neutral third person or panel.
• Binding resolution
A third-party imposed solution to a contested claim in which the conditions are legally
binding on the parties.
• Breach of contract
Failure to perform all or part of a contract where there is no legal excuse for such failure.
• Building components
The basic units into which most building construction projects can be divided. Usually
the components represent distinct construction & construction related actions that have
common characteristics.
• Design work (des)
Project related work that concerns production and issuing of contract documents
• Exterior skin (esk)
• Change
Any revisions to the contract documents that alter the scope of work agreed to.
• Change order
An official notice that the changes Specified in the change order are to be done. A
properly executed change order is a revision to the scope of work and the contract
documents.
• Charter
A document prepared and agreed to, by the project partnering stakeholders and
containing a set of informal guidelines to successful performance in the execution of
noncontract project matters. The charter is normally signed by the stakeholders and is
used in conjunction with a mission statement from which the guidelines are derived, a
partnering evaluation system by which noncontract practices are periodically evaluated,
and an issue resolution system containing guidelines to the settlement of contested
disputes about project matters.
• Claim
A demand for something as due; an assertion of a right or an alleged right. In
construction generally a demand for something as due, or in which the demand is
disputed.
• Claim avoidance
A technique and procedure for generation of situations in which the demand for what is
due as a result of a contract agreement is honored without formal dispute, or in which the
dispute is settled by an administrative settlement.
• Claim potential
The measure of potential that any project has to encounter disputes during its
implementation.
• Claim prone job
A design and construction project that has a relatively high potential for the generation of
contested claims by or against any of the at risk parties to the project.
• Close out
The process of completing a construction project. Usually extends from the start of
preparing the contractors punch list through receipt of final payment to the designers
and constructors. May occaSionally extend through the warranty period.
• Closed shop
A work area in which only union workers can be employed on the job.
• Closed system
A system in which there is no import or export of information or physical materials, and
in which, therefore, there is no change of components.
• Color coding
• Green - Activity on time - currently not past earliest possible finish date.
• Orange - Activity on time - currently past earliest possible finish date, but will make or
better scheduled or latest possible finish date.
• Blue - Task behind - will not make scheduled or latest allowable finish date
• Commissioning
An inspection and testing system'designed to independently evaluate a facility
mechanical or electrical system to insure that its installation and perfonnance is in
confonnance with the requirements of the contract documents.
• Commitment
The state of giving a tangible or intangible benefit in a trusting and honorable manner.
The act of pledging oneself.
• Committed costs
Committed costs are promised funds for purposes, that if such purposes are aborted a
penalty must be paid, and a loss is often incurred.
• Option costs
• Right of first refusal costs
• Legal fees
• Early engineering fees
• Legal fees
• Early planning fees
• Displeasure of political entities
• Staff time expenditure lost
• Loss of credibility
• Loss of opportunity
• Communicate
To convey information about, to make known or to impart knowledge, ideas, or thoughts.
• Competition
The rivalry between two or more organizations to secure the patronage of prospective
clients
• Competitive
The act of being able to engage in competition with a reasonable probability of winning
the prize awarded for being successful.
• Conceive and communicate
To mentally form and develop an idea for construction of a faciHty, to initiate the effort to
provide resources needed for design and construction of the facility, and to translate the
concept of the facility into a common language from which the project can proceed
through to completion and occupancy.
• Conceivers
Those who conceive the idea and provide the wherewithal to bring the environmental
program to a successful conclusion. The conceiver may be the owner but it might also be
a governmental agency, a financial source, an architect, an engineer, a contractor, a
vendor or a potential tenant looking for space. We identify the conceiver since he usually
is the key person driving the project on to completion.
• Conflict
A state of disagreement and disharmony.
• Construct
To convert a concept and its related plans and Specifications into an actual physical
environment.
• Construction advisor
one who provides, as required & on request, the teaching, coaching, and guidance needed
by those who manage the actual construction process from conception through
programming, approval, design, construction, turnover, operation and maintenance.
• Construction consultant
one who provides on an ongoing contract basis for the life of the project, the teaching,
coaching, and guidance needed by those who manage the actual construction process
from conception through programming, approval, design, construction, turnover,
operation and maintenance.
• Construction management
A system of attempting to better manage the construction process by providing expert
construction knowledge and resources throughout all phases of the project. The goal of
the process is to make available to the participants, information best provided by an
expert skilled in construction practices, so that when the project moves into the field the
managers can provide the owner with the highest potential for project success.
• Construction manager
one who provides a system of managing the construction process by providing expert
construction knowledge and resources throughout all phases of the project. The goal of
the process is to make available to the participants, information best provided by an
expert skilled in construction practices, so that when the project moves into the field the
managers can provide the owner with the highest potential for project success. Services
can be for construction at risk or on a services management basis only. The construction
manager is responsible for delivering the project to his client.
• Construction record documents
A set of annotated contract documents showing the as-constructed sizes and locations of
all elements of the project which differ from the original, and subsequently issued
contract documents. As-built drawings are generally called construction record drawings
or documents.
• Construction services contract
A legally enforceable oral or written agreement between two or more parties specifying
construction-related services to be provided by one or more of the parties to other
contract parties. The services generally relate to services that directly concern the relation,
nature, cost, performance, or installation of Specified work into specific facilities
construction.
• Constructive change
An owner's action or inaction that has the same effect as a written directive.
• Constructors
Those who interpret the construction language and convert it to an actual physical
environment. Occupying this role are general contractors, specialty contractors, vendors,
suppliers, manufacturers, artists and others who actually put the materials into place in
the field.
• Consulting services contract
A legally enforceable oral or written agreement between two or more parties specifying
design and construction related services to be provided by one or more of the parties to
other contract parties.
• Contested claim
A demand or claim in which the demand is disputed.
/.0'1
Ralph]. Stephenson, P. E.
Consulting Engineer
• Contingency
A program of action set out against the possibility that an unlikely or unintended event
may occur.
• Continuous
Uninterrupted in time; without cessation.
• Continuum
A continuous or ongoing series of actions, normally uninterrupted.
• Contract
A legally enforceable oral or written agreement between two or more parties specifying
goods or services to be provided by one or more of the parties to others of the contract
parties.
• Contract document matrix
A two dimensional grid in which the rows contain action items for the various project
components and the columns usually designate the geographic location of the item. At
the intersection of a row and a column is inserted the designation of the contract
document package in which the information is contained.
• Contract documents
Usually considered to be the construction documents which provide the full definition of
the scope of work for which the parties are legally responsible. Could include the
agreement, the drawings, the specifications, instructions to bidders, addendum, and any
other material included by mutual agreement and clearly identified as part of the
contract.
• Contract services
specialized services provided on demand or by request to clients by individ uals or
groups within the company to individuals and groups outside the company. These are
provided by contract with the client.
• Contractor
The party, where there is a principal and a contractor, who agrees to the doing or not
doing of some definite thing for a stipulated sum.
• Control
Maintaining firm, competent managerial direction of any given situation. Controlling
leads to achievement. It is usually accomplished by the invisible use of leverage.
• Coordinate
To harmonize in a common action or effort. Many design and construction consultants
recommend the word not be used in contracts since it has indistinct meanings as related
to management in design and construction.
• Core ethic
the fundamental value statement upon which the company is built, managed and does
business.
• Cost growth
An increase in project costs from the expected costs, and occurring during the planning,
design, construction, and occupancy phases of the line of action.
• Cost/benefit
A comparative measure of benefits to be gained at a cost. A cost/benefit analysis usually
establishes standards by which the benefits are given a value, and standards by which
value-added is measured against what is desired, and what can be afforded. This allows
the highest benefit/cost ratios to be identified within the standards adopted.
• Credentials
A formal certification for a qualified person to do something for which special talents,
training and education is required.
• Critical path method
A mathematical modeling technique which allows the user to establish ranges within
which resources can or must be used.
• Critical transition point
The point in a project delivery system at which the responsibility and authority for the
work passes from the supportive group to the ex'e'cutive group.
• Culture - business
A way of doing business that has been generated by a group of human beings and is
passed along from one business generation to another, generally by unstructured
communication.
• Cuts
Excerpts from catalogs, drawings, or flyers that depict a configuration to be used in the
construction process.
• Daily reports
Daily technical reports about the project containing data on manpower, weather, major
activities, equipment on job, and other job related statistical information. Usually the
daily report form is preprinted and in loose leaf form.
• Decentralize
To undo the centralization of management and decision making.
• Decision table
A tabular display of information depicting a defined situation which permits alternative
courses of action to be evaluated by yes or no answers to explicit questions.
• Decision tree
A graphic device showing alternate courses of action from beginning a given situation
point. The decision tree is used to graphically show the impact of various possible
decisions at any given point in the decision process. It can be quantified or unquantified.
• Decision-to-action time span
The amount of time required from the point at which a decision is made to the point
where the decision is implemented. In a management structure it is important to insure
that the full span of time from decision to action is covered, from shortest to longest.
• Defective or deficient contract documents
Contract documents which do not adequately portray the true scope of work to be done
under the contract.
• Delay
A problem or situation beyond the control of the contractor, and not resulting from the
fault or negligence of the contractor, which prevents him from proceeding with part or all
of the work.
• Delegate
To commit powers or functions to another as one's agent or substitute.
• DepOSition
A written record of sworn testimony, made before a public officer for purposes of a court
action. Usually the deposition is in the form of answers to questions posed by a lawyer.
Depositions are used for the discovery of information, or as evidence at a trial.
t'.~'f
RalphJ. Stephenson, P. E.
Consulting Engineer
• Design
Generically, to conceive in the mind, to form a plan for, and to create in an artistic and
highly skilled manner.
• Design/build
A method of providing total design and construction services under one cost and liability
umbrella. Usually a design/build contract is based on a scope of work performance
specification prepared by the owner or user. The ultimate aim of the design and build
system is to provide a single source management and liability for the total facility
program.
• Destructive conflict
Animosity or disagreement which results in lowering the potential for an individual or
organization to succeed.
• Development
A business operation in which the primary goal is to locate and produce profitable and
marketable real estate assets.
• Diary
Similar to a log but dealing more with personal observations of the individual writing it
relative to his feelings about the job and the people.
• Differing site conditions
Where actual site conditions differ materially from those indicated in the contract
documents; or where unknown physical conditions at the site differ materially from those
ordinarily expected to be encountered in work of the nature contemplated by the contract.
• Direct negotiations
Conflict in which the matter in dispute is taken immediately to those that have the J
authority to make a final binding decision in any project related matter. These are called ...,."
the ultimate decision makers.
• Directed change
A written or verbal change that falls within the scope of the contract. The owner has the
responsibility of paying for the change.
• Discovery
The act of disclosing or being compelled to disclose data or documents that a party to a
legal action is compelled to disclose to another party, often an unfriendly one, either prior
to or during a legal proceeding.
• Discrete
Consisting of, or characterized by distinct or individual parts; discontinuous.
• Disincentive
A penalty imposed on a contract party for less-than-satisfactory performance on a project.
The disincentive is usually coupled to a bonus or incentive.
• Dispute
To engage in argument or discussion. To quarrel or fight about.
• Dispute resolution board - drb
A method of dispute resolution where project participants establish procedures, by
contract, to proactively settle disputes as they arise during the course of the project.
drb's seek to anticipate problems and get the parties to resolve them before the problems
harden into formal claims.
t:/o
RalphJ. Stephenson, P. E.
Consulting Engineer
• Due diligence
A process by which the legal affairs of a business are investigated and reported as part of
the preparation for commercial transactions such as acquisitions, mergers, joint ventures,
privatizations or general commercial contracting.
• Dysfunction - organizational
An organizational problem that hinders or prevents achieving objectives. May be
temporary or permanent.
• Early finish (EF)
The earliest possible date by which a task can finish in a network model if it has been
started at its early start date.
• Elapsed duration
The estimated or actual amount of calendar or clock time an activity requires to
accomplish, considering all direct and indirect influences upon the task's activities.
Includes temporary work delays and stoppage due to influencing actions on the task.
• Empathy
Identification with and understanding of another's situation, feelings, and motives.
• Engineer or architect of record
The legally licensed architect or engineer who oversees the production of drawings and
specifications from which something is to be built. The architect or engineer of record is
usually required to sign and seal the documents and is liable for their correctness.
• Enrichment
Adding to the scope of work originally contracted for with the intent to avoid being
charged or paying for the extra work. Often seen in as-noted remarks on submittals, or on
inadequate identification of scope of work in a bulletin or change order.
if· II
Ralph J. Stephenson, P. E.
Consulting Engineer
• Ethical
In accordance with the accepted principles of right and wrong that govern the conduct of
individuals in a profession and in their relationships with others.
• Everyone-must-know communications
An organizational communications system based on the managerial belief that if
everyone in the organization knows what all or most other people in the organization are
doing and working on, the organization's overall output quality will be superior.
• Ext-e cutive
The executing arm of the organization closest to the flow of expense and income
experienced in achieving the organization's prime objectives. Qosely related to line
operations.
• Executive
Of, relating to, capable of, or suited for carrying out or executing. The executing arm of
the organization is that closest to the flow of expense and income experienced in
achieving the organization's prime objectives. Closely related to line operations.
• Feedback loop
The loop of communication around a project through which information is conveyed to
and through the various components of the project.
• Field order
An official notice that the actions or changes described in the field order are to be done.
The field order is usually issued only in emergency situations where the time between
decision and action does not permit issuance of a bulletin followed by a change order. A
method of payment is usually specified in the field order.
• Financing
Providing the funding either or both interim and permanent for planning, designing, and
constructing a facility.
• Force majeure
An unexpected or uncontrollable event.
• Free enterprise system
An economic system under which the means of production, distribution and exchange
are in large measure privately owned and directed.
• Functional - as related to continuous management
Designed or adapted to perform some Specialized activity or duties, usually concerned
with the continuous operation of the company.
• Functional component
A group designed or adapted to perform some specialized activity or duties, usually
concerned with the continuous operation of the company.
• Functional operations
Management and staff direction of the application of resources to accomplish each
specialized activity. Usually defined as a department or division of the company. Usually
concerned with continuous operations of the organization. Contrasts with project
operations.
• Functionally diversified operations
Services that provide many specialized activities offered under one or more management
organizational structures.
• General conditions
The portion of the contract agreement that contains contractural-Iegal requirements for
the work.
• General requirements
The portion of the contract agreement that contains overall technical support
specifications governing work on the job.
• Generic construction
The field of business practice that encompasses all phases of the construction industry,
including programming, plannin~ designing, buildin~ operating, and maintaining
facilities. Described best as the full set of activities shown in the line of action. (See line of
action.)
• Geographically diversified operations
Services that provide specialized activities offered under one or more management
organizational structures located in different physical locations.
• Goals
The unquantified desires of an organization or individual expressed without time or
other resources assigned. (See objectives for related definitions.)
• Grapevine
The communication line for informal transmission of information, gossip, or rumor from
person to person. The grapevine is often more accurate and rapid than formal
transmission lines.
• Graphics oriented data processing
Data processing in which the majority of the information is entered or gained by the use
of a joy stick, mouse or other control which gives direct hand related movement and
entry onto a console screen.
• Growth measures
The measurable factors which account for increased business activity of an organization.
In the architectual - engineering - planning business these growth factors may include
• Competitive forces
• Dollar volume
• Fee levels
• Number of offices
• Organizational structure
• Productivity
• Profit levels
• Resource availability
• Services offered diversity
• Staff diversity
• Staff size
• Guaranteed maximum price (GMP)
The price for a Specified scope of work to be provided by a contractor that contractually
binds his performance to a specified guaranteed maximum price. Often the guaranteed
maximum price is tied to a time and material performance with the price not to exceed
the agreed upon maximum.
• Hard-money
A total price agreed to for the entire work, and to be paid in a mutually satisfactory
schedule of payments.
• Histogram
A graph showing a quantity on the vertical axis measured against equal intervals of time
shown on the horizontal axis. In construction, often a depiction of the resources required
per day over a period of time.
• Horizontal growth (Integration)
A management system that emphasizes diversifying by expanding existing functions by
classes. For instance a design office could accomplish horizontal integration through
dividing their operations into various kinds of projects such as commercial, institutional
and industrial. These all use the same or similar functional disciplines but the
organization is divided into separate groups that concentrate mainly on one of the three
main building types.
• Hygiene
The elements in an organizational situation that are acceptable to an individual but do not
necessarily motivate him. These same elements, if unacceptable to the individual, may act
as negative influences.
• In-house work
Relating to activities that are managed and directed by a permanent staff of an
organization.
• Incentive
A bonus paid to a contract party for performing its work in a superior manner to that
specified. The incentive is usually coupled to a penalty or disincentive.
• Incentive-disincentive system
A payment system used in construction to pay a bonus or incentive to a contract party for
performing their work in a superior manner to that specified. The bonus may relate to
cost, time, quality, safety, or other such measurable component of the total job
performance. 1£ the standards set are not reached by a measurable point on the project, a
disincentive is triggered where the contract party is penalized for inferior performance on
the project.
• Independent advisory opinion
An opinion rendered by a qualified neutral of what outcomes can be expected if certain
courses of action are followed.
• Industrial revolution
A complex of socioeconomic changes, such as the ones that took place in America in the
19th century and which were brought about by extensive mechanization of production
systems and the use of large-scale factory production.
• Interfaces
Points at which different but related activities exert direct influences upon each other.
Interfaces are often the points where direct objective activities contact dependent
objective activities. Poor management of interface situations usually causes problems and
dysfunctions.
• Isoquant line
A line drawn on a network model and connecting some or aU equal date or resource
points on the activities shown. The date isoquant line is the equivalent of a straight line in
a time scaled bar chart.
• Issue
A point or matter of discussion, debate, or dispute.
? It(.
RalphJ. Stephenson, P. E.
Consulting Engineer
• Issue resolution
A method of reaching agreement and closing out disputes and problems at the lowest
possible management level, in the shortest possible time, and with the lowest potential
for residual hard feelings.
• Judicial system
Of, relating to, or proper to courts of law or to the administration of justice. Decreed by or
proceeding from a court of justice which is vested with the authority for such action by a
set of legally dictated processes established by laws enacted by a legislature.
• Jury trial
A trial before a jury.
• Late finish (LF)
The latest allowable date by which a task can be completed in a network model without
forcing those tasks that follow past their latest allowable start dates.
• Late start (LS)
The latest allowable date by which a task can be started in a network model without
forcing those tasks that follow past their latest allowable starting dates.
• Laundry list
A list of items, usually at random, that are to be classified, rearranged and used to build
specifically sequenced tabulations, network models, narrative schedules or other systems
of which the items in the laundry list are a component.
• Law
The actions or processes by which the rules of a society are enforced and through which
redress for grievances is obtained
• Leadership
The process of persuasion or example by which an individual induces a group to pursue
objectives held by the leader or shared by the leader and his or her followers. - John W.
Gardner
"The art of getting someone else to do something you want done because he wants to do
it" - Dwight D. Eisenhower
• Leverage
The effective use of vested and earned authority to solve problems and achieve goals and
objectives.
• Liable
Legally obligated or responsible.
• Life cycle cost
The total cost of a system over its entire defined life.
• Limited agent
The individual or organization acting as an agent and authorized to do only what is
specified or what is reasonable to believe the principal wants done. A contract can be
used to define the amount of authority to be granted an agent.
• Line activities
Those activities that are most closely identified with the flow of basic expense and income
related to the prime objectives of an organization.
• Line of action
A sequential statement of activities necessary to conceive, design, build and operate an
environment. Related to the generic (G) construction process.
• Liquidated damages
The amount established by the parties to a contract which must be paid, by one or either
of the parties, in the event of a default or a breach. Is related to the damages suffered by
late performance.
• Litigation
The process of contending in court, either as a plaintiff or a defendant.
• Log
A permanently bound, dated, hand written record of job related events that have
occurred on a project. The log is usually in ink, and is maintained by an individual in
responsible charge of the work with which the record deals.
• Long list
The initial list of those participants offering professional planning, design, and
construction services for a particular project. This list is usually prepared by the conceiver
of a proposed project from those having qualifications to do the job. The long list is
narrowed to a short list from which the final selection is made. (See short list.)
• Luck
Preparation meeting opportunity
• Macro matrix elements
The individual elements or components of a three dimensional matrix that defines the
actions needed, the skil1s that must be applied to do the action, and those who must take
the action.
• Maladministration
The interference of the owner in the right of the contractor to develop and enjoy the
benefits of least cost performance. . j
• Manage ".",
To define, assemble and direct the application of resources to achieve specific goals and
objectives.
• Management
The act and manner of defining, assembling and directing the application of resources to
achieve specific goals and objectives.
• Management by exception
A measuring and monitoring system that sounds an alarm to the manager when
problems have appeared or are about to appear, and remains silent when there are no
problems. The system identifies the problem area, thus permitting the effective manager
to manage the exception while leaving the smoothly running operations to continue
running smoothly.
• Manager
One who defines, assembles and directs the application of resources to achieve specific
goals and objectives
• Managerial grid
A numerical grid which positions a manager in a matrix by defining his concern for
people as compared to his concern for production. This grid has been highly developed
by Blake and Mouton and is useful in establishing managerial systems that are desirable
and needed.
• Marketing
The process of conceiving, formulating and implementing a process by which the
ultimate service or product of an organization can be successfully sold.
'?"
RalphJ. Stephenson, P. E.
Consulting Engineer
• Matrix
A two or more dimensional display of related data.
• Matrixnnanagennent
A management technique that employs a multiple command system. Usually results in
one employee having two or more bosses on a time to time basis.
• Mediation
An attempt to effect a settlement between disputing parties through the unbiased efforts
of an objective third party, usually well known to those in dispute and acceptable to
them. Mediation differs from arbitration in that it generally involves a single individual
as the ruling party, is less formal, and is generally not binding. (This definition of
mediation varies with the degree of legal significance attached the resolution of disputes,
and the dispute location.)
• Mentor
A wise and trusted counselor, coach, or teacher.
[Mentor - a tutor in Homer'S Odyssey]
• Meritshop
A work area in which the workers may be either union or not, and in which there are no
major jurisdictional boundaries governing assignment of work.
• Minitrial
A private process where opposing parties present condensed versions of their cases, both
to designated executive representatives, and to an impartial advisor, and then negotiate.
The executives hear both sides, thus gaining a first hand perspective of the parties
positions. The impartial advisor then points out possible outcomes an helps the parties to
settle, if possible. Minitrials provide a structure to negotiate and ground rules to facilitate
settlement.
• Mission
A statement of the most important result to be achieved by the project being successfully
completed.
• Mockup
A full-sized scale model of a structure, used for viewing, demonstration, study, or testing.
Usually used in construction to obtain approval of a system, materials or a product.
• Moneyflow
The flow of income and expense measured against time.
• Monitoring
Measurement of current project conditions and position against the standards of
performance set for the job.
• Motivation
The elements of a given situation that encourage and make effective, successful and
meaningful, the activities of those engaged in the situation.
• Multiplier
A number usually applied to a direct cost by someone providing a service. The product of
the multiplier and the direct cost determines the actual charge to be billed for the service.
The multiplier adds the overhead and profit to the direct cost.
• Must list
Those items that must be included in the scope of work to make the project a go. If any of
the items in the must list are not able to be included the project is a no-go.
• Need-to-know communications
An organizational communications system based on the managerial belief that
information should only be offered and provided to those who truly need it and can use it
to add value to the product they are responsible for producing.
• Negotiated contract
A contract obtained through offering multi-value benefits in addition to cost benefits to
the prospective client. Usually conditions of the final contract are negotiated after an offer
has been conditionally accepted.
• Network
A system of interconnected, interacting components. Usually a part of an open system.
• Network plan
A graphic statement of the action standard of performance to be used in achieving project
objectives.
• Network planning
A graphic technique of showing necessary and desired actions needed to achieve end,
intermediate and peripheral objectives.
• Neutral
An unbiased outside expert capable of objectively listening, analyzing, and evaluating
construction-related demands or claims which are in dispute and rendering an opinion or
decision as to its disposition.
• Nonbinding arbitration
Involves an evidentiary hearing before one or more third parties who draw cOhclusions
regarding issues in dispute. The presentations may be condensed, as in a mini trial. The
third renders a decision, but the decision is not binding on the parties. The intent is to
predict the probable adjudicated outcome of the case as an stimulus to a settlement.
• Nonbinding resolution
A suggested solution to a contested claim or problem in which the conditions are not
legally binding on the parties but are an expert's recommendations for resolution.
• Objectives
Quantified targets derived from established goals (see goals). The most commonly used
resources in converting goals to objectives are money, time, human abilities, human
actions, equipment, and space.
• Objectives - dependent
Objectives to be achieved that are affected by major influences beyond the manager's
direct control. The dependent goal may be predictable or unpredictable.
Dependent goals, while usually beyond the manager's control, may well be within the
company's ability to reach. Lack of correlation between company and individual effort to
achieve a manager's goals that are affected by others, may cause severe dysfunctions.
• Objectives - direct
Objectives that can be achieved by managing conditions within the manager's direct
influence.
• Objectives - end
Objectives realized from and upon total completion of the defined project work.
• Objectives - intermediate
Objectives achieved at specific and identifiable stages of the project, i.e. partial occupancy
of a building, turnover of a mechanical system for temporary heat, or completion and
issuance of foundation plans for early start of construction.
• Objectives - peripheral
Objectives realized on an ongoing basis through the life of the project and achieved as an
indirect result of project activities. Peripheral objectives may be personal, professional,
technical, financial or social. Peripheral objectives might include staff promotion,
profitable subcontractor operations, specialized experience, or achievement of design
excellence in a special field.
• Off-site
Located outside the contract site boundaries.
• On-site
Located within the contract site boundaries.
• Ongoing organization
The arrangement and interrelationships of people charged with providing supportive
action on an ongoing basis within the company. Examples of functions contained within
the ongoing design or construction organization are estimating, administration, legal,
marketing, sales, purchasing, and accounting.
• Open shop
A work area in which both union and non union work(!rs can be employed on similar
tasks.
• Open system
A system which exchanges energy, information and physical components with its
environments.
• Operators
Those who operate and maintain the completed physical environment on a continuing
basis. Usually the party responsible for this function is an owner or tenant working
through a plant or facilities manager.
• Organization
The arrangement of resources (talent, skill, money, time, space, people, et a1) that has
evolved, or been selected, to accomplish the functions, activities, and management, and
goals and achieve the objectives of a business or institultion.
• Organizational structure
The categories of parties to the planning/design/construction/operation process and
how they are organized for the work. The organizational structure is shown by a set of
relations between the parties that identifies the responsibility and authority lines along
which the project is to be implemented.
• Over-the-wall management
A management style which subscribes to the actions of participants completing their
work responsibilities and duties, and then passing the work product along to others (or
throwing it over the wall) without adequate briefing for the successors to do their work
effectively. Often identified by statements such as "We did our job and now they can do
theirs", or, "That's not my job."
• Overhead
That portion of an organization's cost that cannot properly and accurately be allocated to
any specific operation on any specific project.
• Owner furnished items
Those items furnished by the owner according to the contract documents.
• Par
An amount or a level considered to be average; a standard.
• Par performance
A rating, usually numerical, that expresses the level of performance that will be accepted
as the normal degree of competence expected of an individual or organization in the
performance of an action.
• Partnering - a base statement
A method of conducting business in the planning, design, and construction profession
without the need for unnecessary, excessive and!or debilitating external party
involvement.
• Partnering· Associated General Contractors
A way of achieving an optimum relationship between a customer and a supp1ier. A
method of doing business in which a person's word is their bond, and where people
accept responSibility for their actions.
Partnering is not a business contract, but a recognition that every business contract
includes an implied covenant of good faith.
• Partnering - Construction Industry Institute
A long term commitment between two or more organizations for the purpose of
achieving Specific business objectives by maximizing the effectiveness of each
participant's resources.
The charter is an agreement in principle and must not supersede or supplant the design
and construction contracts in place or to be written.
• Peer review
A partial or full audit evaluation of the project done by objectively based individuals or
organizations outside those owning, designing, building or operating the facility.
• Percentage fee
A fee determined ultimately by a percentage of project cost, all as specified by the
contract.
• Perception
The process of becoming aware of something through any of the senses. To become aware
of in one's rnindj to achieve an understanding of.
• Performance document
A document which provides information as to the performance desired and the amount
that is to be spent.
%.ZI
Ralph]. Stephensons P. E.
Consulting Engineer
• Principal
A person who authorizes another to act as his agent, or a person primarily liable for an
obligation.
• Problem
A deviation from an accepted and / or approved standard of performance.
• Production management
The action of defining, assembling and directing the application of resources to achieve
design production goals and objectives. These goals and objectives are set for produdng
the end product of a design effort· usually a set of documents that define the
construction of an environmental improvement.
• Professional
Having great skill or experience in a special contributive field of work.
• Profiling
The preparation and use of a selective, flexible and tailored systems of screening projects
for potential partidpation.
• Profit - educational & training
Fulfillment of learning and teaching goals held by individuals and their companies.
• Profit - financial
Fundamentally, the difference between organizational cash income and organizational
cash expense. Further definitions of finandal profit are complex and often unique to an
organization or project.
• Profit - self actualization
Personal fulfillment realized after basic needs of shelter, safety, protection, love and
freedom from hunger are achieved. ..J
• Profit - socio economic ""'"
Company, group or individual achievement of social objectives within a financially
profitable set of activities.
• Profit - value system
Company and project fulfillment of personal, profeSSional, technical, sodal and financial
values held important by individuals and groups related to the company.
• Profit plan
Arnanagement tool for formalizing the firm's financial objectives in order to establish
yearly financial goals, and to provide intermediate financial targets throughout the year.
(adapted from Howard C. Bimberg - Project Management for Building Designers and
Owners)
• Profitability plateau
The leveling off of profit over a period of time due to a need for increased overhead
caused by an increase in operations costs. These operations cost increases are often
generated by an increased work load and the resulting added management staff required
without a corresponding increase in production or direct cost income.
• Proforma - in real estate development
A financial model unusually built early in a construction program to show by projecting
income and expenses, how the money flow to and from the project will occur. It is often
used to establish the capital amount to be allocated to a project based on simulated
operating conditions. The term pro forma means accordin~ to form.
• Program - as defining a step in the design process
A narrative oriented statement of the needs and character of the proposed user
operation, the requirements of the user and owner, the nature of the environment to be
planned, designed and built, and the corresponding characteristics of the space that will
satisfy these needs and requirements. Sometimes called the brief.
• Program· as defining a generic construction effort
A major planning, design, construction, and operational construction effort made up of
several projects
• Programmed construction
a project management system which provides:
• A proactive team atmosphere
• A strong and trustful relation between project parties
• A high profit potential
• Strong and continuous emphasis on good project planning & scheduling
• Encouragement to develop full project team participation
The purpose of the project history is to give a quick, accurate look at past job events in a
glance. The degree of detail is dictated by the potential for trouble that exists.
• Project management
The art, science and profession of defining, assembling and directing the application of
resources so as to profitably execute a work effort that has identifiable objectives, and a
well defined beginning and end.
• Project manager
One who helps establish objectives generated by a need, plans how these objectives are to
be reached through a set of work actions, and then assembles and directs the application
of available resources to achieve the objectives on one or more projects.
Usually the project manager is most concerned with supportive actions which bring
resources to the point of effective use.
• Project operations
Management and staff direction of resources to accomplish overall project activities.
Contrasts with functional operations.
• Project organization
The arrangement and interrelations of people charged with actually achieving project
objectives. (See organizational structure.)
• Project schedule report
A narrative listing of network activities and the corresponding data re each action. The
project schedule report is normally developed in a data base format from which selective
reports and arrays can be prepared.
• Project stages
The groupings of actions that make up the entire project work sequence.
• Project superintendent
The manager involved in the actual construction process and most directly responsible
for the expenditure of funds to carry out the project. Usually the superintendent is
responsible for field execution of the work.
• Project team
A specific management group assigned to achieve a set of objectives by accomplishing a
group of related, discrete operations which have a defined beginning & end. Examples
include the design team, the program team, the construction team, the tenant work team,
and others of a similar nature.
• Question· closed
Questions that can be answered with a yes or no, or with a simple statement of fact.
• Question· direct
Asked with strong indication as to who or whom should answer.
• Question· open
Questions that cannot be answered with a yes or no, or a simple statement of fact.
• Question· overhead
Asked of a group without indication as to who or whom is to answer.
• Question· relay
Passed along to someone else by the party originally asked.
• Question· reverse
Returned to the questioner by rephrasing or rewording the original question.
• Record
Any retained information that can be effectively used in the future.
• Regulators
Those who fill a review & inspection position to help insure protection of the health,
safety, & welfare of the people. This is usually done by enforcing regulations writtenand
adopted by qualified public or private bodies. Examples of regulators include those who
work for building departments, departments of natural resources, public health agencies,
fire prevention organizations, technical societies and other such groups.
Formal relations are precisely defined and most day to day business is accomplished
within the formal relation framework. The line expressing a formal functional relation
usually has an arrowhead at each end to show a mutual exchange of responsibility and
authority. If there is a higher authority to be implied a single arrowhead can be used
pointing to the superior party.
• Relations - informal
The natural channels along which organizationally related material is most easily and
comfortably transmitted. The informal relation exists by mutual consent of the parties to
the relation, and is stimulated to maximum effectiveness by a mutual profit gained from
the relation.
Extensive use of temporary relations creates business dysfunctions, breaks down morale
and causes internal tensions.
• Resolution
A course of action determined or decided upon that can result in clearing conflict or
dispute.
• Resolve
To find and implement a solution to a problem, a dysfunction or an issue of conflict.
• Resource allocation
The assignment of project resources such as money, time, space, people and equipment to
activities that must be done to achieve project objectives. Usually resource allocation is
• Risk management
The management and conservation of a firm's assets and earning power against the
occurrence of accidental loss.
• Safety and drug testing
the provision of testing, coaching, training and monitoring required to maintain a safe
and legal work site.
• Schedule
A graphic or written tabulation of project activities showing where the activities are to
start and finish. The schedule is derived from the plan of action and the network model
by locking the tasks and the resources they require into a Specific time position.
• Selling
Establishing and implementing the strategy of achieving the objectives of the marketing
plan. The physical process of closing the negotiation for services and products for a
consideration.
• Shared savings
An arrangement by which a construction contractor and its client share in any savings
realized by building a facility for a lower cost than the guaranteed maximum cost.
• Shop drawing
A submittal in the form of a drawing, usually made specially for the application shown.
Shop drawings usually show details of fabrication and installation.
• Short list
The final selection list of those participants offering professional planning, deSign, and
construction services, usually to the conceiver of a proposed project. Usually the final
selection is made from the short list. (See long list.)
1'.2'
Ralph J. Stephenson, P. E.
Consulting Engineer
• Situational thinking
1he ability to accurately evaluate a set of project influences by mentally moving from a
long overview (macro) of them to a detailed picture (micro) and back, and being able to
stop anywhere in between to consider other scale pictures of these influences and their
relationships.
• Span of control
The number of organizationally related individuals a manager directly controls on a one
to one basis.
• Specialized construction
The field of business practice that encompasses single phases of the construction
profession. Examples of "5" construction organizations are architecturall engineering
offices, mechanical contractors, plastering contractors, and planning consultants, among
others. Includes nearly any single organizational unit active in design, planning,
construction or related fields.
• Specification
A narrative description of the various materials and systems to be incorporated in the
work. The specification concentrates on identifying quality of materials, source of
materials, allowable practices, and general requirements and conditions of the contract
performance.
• Sponsor - parmering
In the partnering context, a person or organization that strongly supports or champions
an activity and assumes responsibility for its implementation.
• Staff
A supportive unit of any organization in which the basic function is usually advisory in
nature. Staff functions are occasionally defined as overhead or non production. They are
considered to be the organizational partner of line operations. (See staff relations and line
activities.)
• Stakeholders
The parties at risk financially and legally or in an extended sense, those affected and
potentially put at risk during the execution of a planning, design, or construction
contract. Stakeholders are also those who participate in writing a partnering charter and
are a signatory to the charter.
• Standard of performance
A well defined, explicitly stated, approved and accepted statement of the measurements
to be used as a gage of performance, and goal and objective achievement.
• Standing neutral
A technically trained, educated, and credentialed professional who is active in the
planning, design, and construction disciplines. The standing neutral must be capable of
objectively listening, analyzing, and evaluating construction related demands or claims
which are in dispute.
• Standing neutral system
A process where neutral third parties are available to assist with resolution of all disputes
arising during the course of a contractual relationship. The intent which includes dispute
review boards and standing neutrals is to have one or more individuals on call to address
disputes as they arise. It usually requires the neutral to render a nonbinding
determination of the issues in dispute, although in some cases, and upon request, the
neutral can act as a binding arbitrator.
f, 2-7
RalphJ. Stephenson, P. E.
Consulting Engineer
• Strategy
Applies to the management skills required to attain an macro result. Strategy is
sometimes considered the action take to plan, direct, and implement larger and longer
range programs, particularly in the military.
• Sub contractor
A contractor whose business agreement is directly with a prime contractor
• Submittal
Any document submitted by contracting parties to the owner's agents for review for
accuracy, responSibility of design, general arrangement, and approval. Submittals are
used by the fabricator and the installer to show adequate details so the intent of the
contract documents can be achieved. There is a mild ongoing professional controversy as
to whether approved submittals are contract documents. Generally they are not
considered contract documents, but aids to better fabrication and installation procedures.
• Sum zero game
A situation in which there is a winner and a loser. The loser often will lose what the
winner wins.
• Superior knowledge
The owner's withholding specifiC data on matters of substance not known to contracting
parties during the pre contract period.
• Supportive
The administrative group of the project organization which is responSible for bringing
resources to the point of use by the ex'e'cutive project group.
• Surety
One who has contracted to be responsible for another, especially one who assumes
responsibilities or debts in the event of default.
• Suspension
An owner's or owner's agent action of stopping all or a part of the work.
• Synergism
The action of two or more substances, organs, or organisms to achieve an effect of which
each is individually incapable.
• System
An assemblage or combination of things or parts forming a complex or unitary whole.
• Tactics
Applies to the management skills required to attain a micro or current result. Tactics may
be considered the actions taken to plan, direct, and implement the day-to-day action
itself.
• Talent
A capacity for achieving identifiable success. Usually talent is considered an abstract
resource.
• Taskforce
A temporary grouping of individuals and resources who are responsible for
accomplishing a Specific objective.
• Technography
The action of preparing meeting notes and related material on electronic equipment as the
notes and materials are generated. Often the recorded material is projected on a screen for
viewing by those in the meeting.
• Tenant coordinator
The title usually given to developer's owner representative. The tenant coordinator is
responsible for integrating and directing the lease execution, construction process, tenant
move in, and operational start up of tenant spaces in the base building.
• Tenant work
Work done by the landlord inside a tenant space, and paid for by an allowance negotiated
by the landlord with the tenant when preparing and executing the lease for the space.
• Termination
The dismissal of a contractor, from a project, for convenience, resulting from factors
beyond the contractor's control, or for default when the contractor's performance is not
acceptable.
• Text oriented data processing
Data processing in which the majority of information is entered or gained by the use of a
key operated control panel such as a keyboard. The signals are usually entered in discrete
elements.
• Third party
A party to a contract or agency agreement other than the principal or agent.
suppliers, vendors, manufacturers, contractors, and the conceiver may all playa role in
translating.
• Trust
Reliance on an organizational or individual or integrity, justice, fairness, good judgment,
and other relational qualities that give confidence in the perfonnance of the duties
demanded of the organization or the individual.
• Turnkey
A project delivery system in which a single contractor is given the total responsibility to
pian, design, construct, and turn the key over to the owner upon its completion. Often, a
turnkey contractor will provide land and financing, and in some cases, operate the facility
for a specified time after construction.
• Turnaround time
The amount of time required to process submittals.
• Turnover cycle
In the construction or fabrication of several similar units, the amount of time required
from the completion of one unit to the completion of the succeeding unit.
• Ultimate decision maker (UDM)
The individual or group at the lowest management level that has the authority to make a
final binding decision in any job related matter.
• Unilateral meetings
A decision meeting at which only a portion of the parties affected are invited to
participate.
• Unionshop
A geographic work area in which all labor classified participants are required to belong to
a specified union.
• Updating
The process of revising and reissuing a project network model to bring it into
conformance with a current desired and necessary plan of action. Updating often, but not
always, results from monitoring and evaluating the project. Usually the updating is done
when it is found that the current plan of work does not adequately depict the actual
conditions under which the project is being executed.
• Upset price
A guaranteed maximum price agreed to in a time and material contract. (See time and
material contract.)
• User
Those who occupy and use the completed facility to conduct their work, their recreation,
their domestic living, or other activities for which the facility was specifically designed
and built.
• Value
The increase in worth of an open system to which an item of value has been added. Often
multiplied by the weight of a factor to give the weight & value rating of a factor to help
determine a choice of alternatives.
• Value added
The improvement in the worth of anything that results from the efforts, contribution and
involvement of specific people, processes, materials and ideas.
• Value engineering
An engineering and architectural cost analysis process designed to achieve minimum
total cost while maintaining maximum product quality within the price constraints.
• Vertical growth (integration)
A management system that encourages diversifying by adding new functions to existing
functions. New functions added usually bear an organizational relation to the existing.
An example of vertical integration is incorporating real estate control, building design,
financing, construction, leasing and asset management into a single development
operation.
• Vested authority
The endowing of privileges, strength and leverage from a superior, usually to a
subordinate. Generally gained qUickly, rather than being earned by long and proven
service in a related field within the organization.
• Want list
Those items that are wanted and can be included in the scope of work, over and above
the must list items, since they provide a definable and acceptable rate of return on their
cost.
• Warranty
A legally enforceable assurance of the duration of satisfactory performance or quality of a
product, a piece of equipment, or of work performed. Often the warranty period begins
when the installation is turned over to the owner.
• Weight
The relative importance of a factor being used to help evaluate a choice. The importance
is frequently measured by a numeric scale from 1 to 10, in which a very high positive
influence is indicated by a rating of 10. A very low influence is indicated by a rating of
01.
Degrees of importance between the highest and the lowest are indicated by number
ratings from 02 through 09. The weight of a factor multiplied by the value added by the
decision choice being considered gives a weight & value rating of a factor to help
determine a choice of alternatives.
• Win-win
A situation in which there are no losers. Usually some parties win more than other parties
win.
• Wish list
Those items that the owner and the user wish they could include but might not be able to
due to budgetary or other reasons. Wish list items are best added, not deleted, as the
project moves into construction.
• Working drawings
The set of contract drawings that pictorially show the intended appearance of a job when
complete.
• World of nonwords
The world in which we live by our physical actions.
• World of words
The world in which we live by simulating actions through words and other symbols what
might happen in the world of nonwords.
CONTROLS
07.00 PREFORMED ROOFING AND CLADDlNQlSlDlNG
01800 MATERIAL AND EQUIPMENT 07500 MEMBRANE ROOFING
. 01850 STARTING OF SYSTEMSICOMMII8IONING 07570 TRAFFIC TOPPING
01700 CONTRACT CLOSEOUT 01flOO FLASHING AND SHEET METAL
01800 MAINTENANCE 07700 ROOF SPECIALTIES AND ACCESSORIES
07800 SKYUGHTS
DIVISION 2-SIfEWORK
07100 JOINT SEALERS
02010 SUBSURFACE INVESTIGATION
020!50 DEMOLITION DIVISION a-DOORS AND WINDOw.
02100 SITE PREPARATION
02140 DEWATERING 08100 METAL DOORS AND FRAMES
02150 SHORING AND UNOERPINNING 08200 WOOD AND PLASTIC DOORS
02180 EXCAVATION SUPPORT SYSTEMS 08250 DOOR OPENING ABSEMBUES
02170 COFFERDAMS 08300 SPECIAL DOORS
02200 EARTHWORK 0&400 ENTRANCES AND STOREFRONTS
02300 TUNNEUNG 01500 METAL WINDOWS
02350 PILES AND CAISSONS oaeoo WOOD AND PLASTIC WINDOWS
02450 RAILROAD WORK oeeo SPECIAL WINDOWS
02480 MARINE WORK 08700 HARDWARE
02500 PAVING AND SURFACING 08800 GLAZING
02100 PIPED UTILITY MATERIALS 08IlOO GLAZED CURTAIN WALLS
02610 WATER DISTRIBUTION
02880 FUEL DISTRIBUTION DIVISION I-FINIIHES
02700 SEWERAGE AND DRAINAGE
02780 RESTORATION OF UNDERGROUND PlPEUNES 09100 METAL SUPPORT SYSTEMS
02770 PONDS AND RESERVOIRS 01200 LATH AND PLASTER
02780 POWER AND COMMUNICATIONS 09230 AGGREGATE COATINGS
02800 SITE tt,m~OVEMENTS OY2!50 GYPSUM BOARD
02Il00 LANDSCAPING 09300 TILE
~ TERRAZZO ,
DIVISION a-CONCRETE 09!100 ACOUSTICAL TREATMENT
09540 SPECIAL SURFACES
03100 CONCRETE FORMWORK 09550 WOOD FLOORING
03200 CONCRETE REINFORCEMENT 09800 STONE FLOORING
03250 CONCRETE ACCESSORIES ote3O UNIT MASONRY FLOORING
03300 CAST·IN·PLACE CONCRETE 018!0 RESIUENT FLOORING
03370 CONCRETE CURING 09180 CARPET
!l3.00 PRECAST CONCRETE 09700 SPECiAL FLOORING
03500 CEMENTITIOUS DECKS 09780 FLOOR TREATMENT
0360(1 GROUT 09800 SPECIAL COATINGS
03700 CONCRETE RESTORATION AND CLEANING 09900 PAINTING
03800 MASS CONCRETE 0IKI50 WALL COVERINGS
DIVISION 10-SPECIALTIES DIVISION 1'-SPECIAL CONSTRUCTION
10100 CHALKBOARDS AND TACKBOARDS 13010 AIR SUPPORTED STRUCTURES
10150 COMPARTMENTS AND CUBICLES 13020 INTEGRATED ASSEMBLIES.
10200 LOUVEAS AND VENTS 13030 SPECIAL PURPOSE AOOMS
~ 10240 GRILLES AND SCREENS
10250 SERVICE WALL SYSTEMS
13080
13090
SOUND, VIBAATION, AND SEISMIC CONTROL
RADIATION PAOTECTION
10260 WALL AND CORNER GUARDS 13100 NUCLEAR AEACTORS
10270 ACCESS FLOOAING 13120 PAE·ENGINEERED STRUCTURES
10280 SPECIALTY MODULES ~3150 POOLS
10290 PEST CONTROL 13160 ICE AINKS
10300 . FIREPLACES AND STOVES 13170 KENNELS AND ANIMAL SHELTERS
10340 PREFABRICATED EXTERIOR SPECIALTIES 13180 SITE CONSTRUCTED INCINERATORS
10350 FLAGPOLES 13200 LIQUID AND GAS STORAGE TANKS
10400 IDENTIFYING DEVICES 13220 FILTEA UNOERDRAINS AND MEDIA
10450 PEDESTRIAN CONTROL DEVICES 13230 DIGESTION TANK COVERS AND APPURTENANCES
10500 LOCKERS 13240 OXYGENATION SYSTEMS
10520 FIRE PROTECTION SPECIALTIES 13260 SLUDGE CONDITIONING SYSTEMS
10530 PAOTECTIVE COVERS 13300 UTILITY CONTROL SYSTEMS
10550 POSTAL SPECIALTIES 13400 INDUSTRIAL AND PROCESS CONTROL SYSTEMS
10600 PARTITIONS 13!500 RECORDING INSTRUMENTATION
10650 OPERABLE PARTITIONS 13550 TRANSPORTATION CONTROL INSTRUMENTATION
10670 STORAGE SHELVING 13800 SOLAR ENERGY SYSTEMS
10700 EXTERIOA SUN CONTROL DEVICES 13700 WIND ENERGY SYSTEMS
10750 TELEPHONE SPECIALTIES 13800 BUILDING AUTOMATION SYSTEMS
10800 TOILET AND BATH ACCESSORIES 13800 FIRE SUPPRESSION AND SUPERVISOAY SYSTEMS
10880 SCALES
10900 WARDAOBE AND CLOSET SPEQALTIES
DIVISION 14-CONVEYING SYSTEMS
DIVIIIDN I1-EQUIPMENT
14100 DUMBWAITERS
11500 INOUSTRIAL AND PROCESS EQUIPMENT 18050 BASIC ELECTRICAL MATERIALS AND METHODS
11800 LABORATORY EQUIPMENT 18200 POWER GENERATION
11850 PLANETARIUM EOUIPMENT 18300 HIGH VOLTAGE DISTRIBUTION (AbOveIlOC).Volt)
11860 OBSERVATORY EQUIPMENT 18400 SERVICE AND DISTRIBUTION (IIOC).VOIt and Belowl
11700 MEDICAL EOUIPMENT 18500 LIGHTING
11780 MOATUAAY EQUIPMENT lMOO SPECIAL SYSTEMS
11850 NAVIGATION EQUIPMENT 18700 COMMUNICATIONS
le850 ELECTRIC RESISTANCE HEATING
18900 CONTROLS
DIVISION II-FURNISHINGS 18950 TESTING
12050 FABRICS
12100 ARTWORK
\..r
Ralph J. Stephenson FE PC
Consulting Engineer
The process of closing out a construction project has emerged as one of the most important sequences of events a
project team may encounter during the course of the project. Reasons for this are:
• The close out process usually results in a formal and legal acceptance of the facility by the owner or
occupant. Thus responsibility for the correctness of the work passes from the design and construction team to
the owner. The transition must be clear and indisputable to avoid contested claims and residual Obligations.
• The conditions imposed by the warranties on workmanship, systems and equipment must be clearly defined
and accepted by all concerned if adequate guarantees of performance are to be placed in force.
• The design and construction team must have a definitive point in time where their contractual obligations
have been fulfilled and they can consider their legal relations closed out so far as project design and
construction administration and operations are concerned.
• The owner must have a specific point in time where he can consider the project legally his without any
hang over potential encumbrances from the design or construction team.
• The design and construction team must be able to use the project as a facility which they have no
hesitation in describing or showing to prospects and current clients.
• A well closed project is insurance of future good relations with specialty contractors on the job as
subcontractors of the prime contractors.
• The properly closed project makes no unreasonable or unpredictable demands on the design and construction
staff subsequent to the close out
The close out process does not start as the construction phase is being completed but long before. Gosing out is
an ongoing action. Throughout all phases of the job the experienced
construction team studies the documents and the work SO as to set how each element can best be turned over to
the owner in accordance with the contract.
Some of the many steps to be taken to properly close out a project are given below. The list is for all parties
to the contract, since most are involved in the close out phase. Parties indicated in ( ) are those most
concerned with the item. Where multiple parties are indicated it does not necessarily indicate the parties
must participate together in the action. .
The list is at random. (Note: This list will be arranged by categories as items are added)
1. Prepare a construction record package. This set of documents was formerly called the as built drawing set.
(contractor)
2. Obtain, where appropriate, a certificate of occupancy, or equivalent document, from the local building
department, or other regulatory and enforcement agency. (owner, architect/engineer, contractor)
3. Prepare, distribute and have approved by the owner, the architect/engineer and the contractors, a punch
out procedure. (contractor, architect/ engineer, owner) ..."J
ho 323 - December, 93
Ralph J. Stephenson PE PC
Consulting Engineer
4. Punch out the project and complete the punch list requirements within an agreed upon time frame.
(architect! engineer, contractor, owner)
5. Prepare, submit and accept the operating and maintenance manuals for the total project. (contractor,
owner)
6. Clear final payments on the project and obtain proper waivers of lien. (contractor, owner)
7. Provide the owner with a proper set of construction documents for reference use. (contractor, owner)
8. Collect and store job logs, diaries, daily reports, test reports and all other documentation generated by the
job activities. (contractor, owner, architect/engineer)
9 . Bring all meeting minutes and record files up to date so as to permit easy use and retrieval of needed
information. (contractor, owner, architect/engineer)
10. Collect and bind all official and unofficial project photos. (contractor, owner, architect/engineer)
11. Collect and record all project network plans, schedules and bar charts by issue number, subject and date.
(contractor, owner)
12. Oose out and store all correspondence and other record files. (contractor, owner, architect/engineer)
13. Assemble and properly store all shop drawings and other job related submittals. (contractor, owner,
architect / engineer)
~ 14. Request the architect/engineer of record to make an inspection resulting in the granting of a certificate of
substantial completion. 'This may be required to to obtain a certificate of occupancy. (contractor, owner)
15. Plan and implement grand opening or preview festivities for major team members, company principals
and others contributing to the planning, design and construction of the facility. (owner, contractor)
16. Each party should conduct their own job critique during which responsible parties to the project meet and
identify points of strength and weaknesses in carrying out the job. One major product of this critique should
be a set of recommendations for improvement of future performance, and documentation of the problems
encountered and how they were resolved. (contractor, owner, architect/engineer)
17. Relinquish, or account for, all client owned tools, spare parts, and extra stocks of materials, rightfully
the property of the owner. (contractor, owner)
18. Provide the owner copies of all releases, including final inspection certificates, occupancy permits,
operating certificates, health department approvals and permits, and all other similar documents to allow
the owner to occupy the building under full understanding of the conditions of the turnover. (contractor,
owner, architect/engineer)
19. Label all electrical panel boxes, plumbing lines, valves and equipment as required for proper operation
and maintenance. (contractor)
21. Submit a final statement of accounting, as required, to the owner and the architect/engineer. (owner,
contractor, architect/engineer)
ho 323 - December, 93
RalphJ. Stephenson PE PC
Consulting Engineer
22. Obtain, prepare or issue a final change order reflecting adjustments to the contract sums not previously ,J
made by change orders. (contractor, architect/engineer, owner)
23. Send sincere thank you letters as appropriate to the owner, to the design team and to various contractors
involved on the job. (contractor, architect/engineer)
24. Provide the owner a complete list of contractors and vendors participating in the job and indicating their
installation responsibilities. (contractor)
25. Insure the owner is placed on the marketing call list, mailing list and other action tickler files as
appropriate. (contractor, architect/engineer)
26. Arrange for such open house activities as may be desired or required (owner, contractor,
architect/engineer)
27. Insure that your company identification is shown somewhere in the building if permitted. (owner, ale
and contractor)
28. Insure the project is as clean or better than called for in the specifications when your staff moves off the
job. Don't lose the good will of the owner by leaving him a dirty job. (contractor)
29. Properly train and turn over the facility to the owner's representatives. Depending on the size and
complexity of the project, the training process should begin from one to three months before occupancy.
(owner, contractor)
30. Establish and approve the start of all warranty and guarantee periods for all material and equipment on J
the job prior to owner making the facility operative. (owner, contractor, architect/engineer) ,.""
31. Prepare and submit to the owner a Construction Record Package. This package should contain the
following: (contractor)
32. Submit a final billing to the owner containing a list of all incomplete items and a properly assigned cost
to each item. (contractor)
33. Advise the owner of any insurance changes over existing or past requirements or dates. (contractor,
architect/engineer)
34. Complete all pre start up testing, run in and instruction along with submission of operating and
maintenance manuals. (contractor, owner)
N.Q..re: All pre start up and start up requirements should be ful1y described in the contract documents and
clearly referenced to the warranty period.
35. Submit final meter readings for utilities, and measured records of stored fuel at the time of substantial
completion. (contractor) ..J
ho 323 - December, 93
Ralph J. Stephenson PE PC
Consulting Engineer
36. Submit to owner, the consent of surety to final payment if required. (contractor)
37. Have final inspection made by an experienced exterminator to rid the job of rodents, insects or other
pests. (contractor, owner)
38. Read the full contract document requirements (drawings, Specifications, and contract) for closing out the
job. (contractor, owner, architect/engineer)
39. Provide the owner a certification as to the building area calculations including gross square footage
.leasable square footage, and area use assignments.
ho 323 - December, 93
RalphJ. Stephenson, P.E.
Consulting Engineer
• Project Partnerlng for the Design and Construction Induslly Ralph J. Stephenson, P.E.
John Wiley and Sons, Inc.
New York, New York
Payment or money flow on a construction project can be just that· a line of strength that
can preserve the life, vigor and integrity of a project, or a line of weakness that can cast the
project adrift.
Successful firms are not often heard complaining about payment. This oddity bears close
examination from those seeking to emulate them.
II. General nature of cash flow in the construction industry
A. Legal background for progress payments
1. Governed by the doctrine of conditions
Doctrine of conditions says that a party should not have to perform its promise
without obtaining the other party's promised performance. The principle is
central to any discussion of progress payments..
2. Who is required to perform first?
Common law requires that performance of services precede payment.
B. Role and obligations of the payer
1. To maintain strong financial position that allows prompt payment when deserved
a) Makes people want to work for you
b) Improves potential for future reductions in proposal prices
2. To pay promptly and within the context of the contract
C. Role and obligations of the payee
1. To perform well and in accordance with your contract
2. To bill accurately and promptly
3. To follow the ground rules by which payments are to be made
4. Frequently the payee holds the key to successful payment for the work
5. Points for the payee to consider
Too often we in the construction industry blame everyone but ourselves for not
being paid what we think is owed us promptly.
Many times the cause of slow or reduced payment lies with the payee, not the
payer.
III. Conditions surrounding collections and payments
A. Unsuccessful collections & payments often result from
1. Mistrust· Inability to work honestly with unwritten standards
2. Cupidity· Inordinate desire to get something for nothing
3. Doubtful risk taking· A high risk has a corresponding high penalty
4. Ultra conservatism· Excites suspicion and slows cash flow
5. Incompetence· Produces a lack of desire to payor work· no incentive
6. Claim prone environment
The contested claim brings out the worst in everyone, and most particularly
makes the payer reluctant to pay.
Understanding how to reduce the dust, noise and confusion that surround
contested claims often can encourage prompt payment even in difficult conflicts.
a) Common causes of contested claims and their frequency are
(1) Directed change - 48%
(2) Constructive change - 42%
(3) Defective or deficient contract documents - 41 %
(4) Delays - 41%
(5) Constructive acceleration - 35%
(6) Maladministration - 33%
(7) Differing site conditions - 31 %
(8) Impossibility of performance - 18%
(9) Superior knowledge - 18%
(10) Termination - 7%
7. Stubbornness - A balky mule cannot be depended on to pull the wagon
8. Dishonesty - Destroys incentives to play fair and pay promptly!
B. Successful collections & payments
1. Trustful relations
Construction is a give and take situation. By the end of the job the gives and takes
must balance out. The construction machinery is lubricated by the exchange of
small favors.
2. Honesty
Honest people select their business associates carefully. Those who pay for
services rendered generally recognize honesty in a company or an individual if
they themselves are honest.
3. Competence
Competent people recognize competence in others. On most jobs, given the
presence of a reasonable number of high value factors, the competent payee will
be compensated fairly and promptly. Financial check and balance systems ask too
many "why" questions to allow competent parties to remain unrewarded.
4. A willingness to give and take
All taking and no giving by either the payer or the payee will sink a project in a
swamp of paper and a sea of red ink. The mistrust that results from this lack of
informal give and take will grow to a monster unless it is replaced by a mutual
confidence by the parties to the situation.
IV. Retentions
A. Often used for doubtful reasons
1. As a club to assure proper completion
2. To save interest payments for 10% of the job cost
3. To insure construction damage to completed work is repaired
4. To pay for anticipated contested claims
B. The problems of retention are old and will probably remain problems until
1. Properly addressed by the parties involved
2. There is agreement among like parties as to its impact
3. All parties to a contract behave according to their contract
C. Attitudes and realities about retention
1. In 1976 a survey was made of the American Subcontractors Association (ASA)
a) Showed average retention among members was $200,000
b) Members said would reduce bid price 3.7% if retention was eliminated
9.¢.0
b) Of 200 respondents
(1) 89% said they give better bids to generals regularly or occasionally
(2) 90% did so because the general had prompt payment policies
(3) 91 % said not paid within 3 days of billings
(4) 69% said not paid within 7 days of billings
3. Policies on retention
a) Recent AGC, ASC and ASA policy calls for payment within 7 days of billing
b) In 1974 GSA went to zero retention
c) At one time Department of Defense eliminated retentions
d) EPA once wrote retention requirements out of its grants
e) About 1984 Michigan Dept. of Msm. & Budget adopted zero retention
(1) Was required by the legislature
(2) Department had 2 choices
(a) Putmoneyinescrow
i) Problem - couldn't use state treasury for holding vehicle
ii) Problem - private holding would have too complicated
(1) Would have thousands of accounts
(2) Prohibitively expensive and cumbersome
(b) Adopt a policy of total payment for completed line items
i) Each line item was to be explicit
(1) On recent $2,000,000 job
(a) Had about 1100 line items
(b) Listed on 27 pages
(c) Ranged in cost from $100 to nearly $70,000
(3) Adopted zero retention route
(a) Some state officials like it, some hate it
(b) Some contractors like it, some hate it
f) In 1983 the Office of Federal Procurement Policy decided that
(1) A uniform government wide policy should be implemented
(2) Retainage was not to be used as a substitute for good contract management
(3) An agency cannot withhold funds without good cause
(4) Determinations on retainage are to be made on the basis of
(a) Contractor's past perfonnance
(b) Likelihood that such performance will continue in the future
(5) Suggested that
(a) Retainage not exceed 10%
(b) That it be adjusted downwards as the contract approaches completion
(c) When contract is complete all retainage be paid promptly
4. Summary - there is no single attitude or reality re retentions!
V. Collections, or better yet, payments
A. Direct payment from the owner
1. Conventional method on self financed projects
2. Success of method depends on the integrity and competence of the owner
Example: the withholding of payment because the contractor did not submit a
a) Infeasible schedules
a) Personal integrity
b) Business integrity
c) Funding sources
(1) Individuals
(2) Syndicates
(3) Trust funds
(4) Pension funds
(5) Political entities
d) Payment method
2. B. Assign values to the client and the project which you are proposing upon
a) Values should be from one to ten
(1) One - Client and project produce worst pay potential situation for factor
(2) Ten - Client and project produce best pay potential situation for factor
3. C. Multiply the factor weight by the value to get a profile number
4. Example of profiling
How you miiWt profile the payment potential of a new pros.pect.
Total = 529 out of a total possible of 740, or a 71 % potential for good payment
relationship.
VIn. Rules for getting paid promptly
A. Be certain of your agreement and understand what it says
B. Be honest in your dealings and your intent
C. Fulfill your contract
D. Avoid legal entanglements and tlueats
E. Be willing to use the lubricating oil of small favors exchanged
IX. If you aren't entitled to it don't try to get it!
X. ho 259 - March 1996
As your comments are received, and as the check list sees use on actual projects I shall further
elaborate on each of the five major generic work phases use presently. These are front end work
(fen), programming (pgm), designing (des), constructing (con), and following up (fo1).
Additions to the work phase list will be made as they are suggested and appear useful and
appropriate for achieving the major uses of the check list.
II. Background
The pm master check list originated as a tabulation of construction activities that might be
encountered in the network planning of a development, design, or construction project. As the list
has been used by various practitioners items have been added, and the use of the list has been
expanded. It can be used for making selective runs by:
• work phase
• csi codes
• general information
• responsibility codes
• submittal requirements
• who is responsible
• who is doing the work
• who is in charge
• who is liable
• target dates
• actual dates
III. Format for data runs - fields as of 12104197
A. Data type - describes the use of the record in relation to the management of
the project of which it is a part.
1. abbreviations (abb)
Key abbreviations used for descriptive purposes - limited where possible to three
characters.
2. action (act)
The basic name and description of what is being identified in the key fields.
3. participants (par)
The individuals or organizations responsible for carrying out the activities on the project.
Usually participants will be designated by a specific code number as they become part of
the project team.
B. Sequence #; - describes the work phase by number when the action, subject or
meaning occurs or is used in the project line of action.
The sequence # identifies the places in the general sequence of work in which design and
construction professionals often visualize actions occurring in an improvement program.
Often an action item normally encountered during the program phase will have to be
deferred until the design phase because adequate information is not available at the earlier
program phase. For instance reciprocal easements at a site may not be totally defined until
some design and poSSibly construction begins.
Usually the construction work phase can be broken in to several well defined parts of the
building or environment. These might include the items listed below. Building parts are
designated in the master pm check list as components and are defined in the component
field or column (cmpt).
a) 05.01 - caw - construction contract award
b) OS.02 - ga - general conditions
c) 05.03 - siw - site work
d) 05.04 - sbw - substructure work
e) OS.OS - ssw - superstructure work
o OS.06 - esk - exterior skin work
g) 05.07 - irw - interior rough work
h) OS.08 - ifw - interior finish work
j) OS.09 - usy - unit systems work
j) OS.10 - clo - close out work
k) OS.11 - war - warranty work
page 2 date printed: 12/4/97
Check list information Ralph}. Stephenson, P.E.
Consulting Engineer
01 - General (gen)
03 - Program (pgm)
04 - Design (des)
05 - Construction (con)
06 - Follow up (fol)
14
par 1011 ROWNG CURTAIN CONTRACTOR 10 081 genl genlFllpl
~OOANGCONTRACTOR
0011 genl
genl
gentrapl
gen/npl
19 lpar toll 0071
Ipar 1011 !,-ONCRETE CONTRACTOR ooal genl gen/npl
20
!
pagel
R.al.ph J. Stephet'lllOll, P.!!., p.e.
Muter Project Management Check List - d608 -listed by seq, data type &: cmpt Consulting Engineer
data
..,. type IIiIq ..:IImI, oubject 01'-'-1 wkphue cmpt
36
par ~11 MISCELLANEOUS IRON CONTRACTOR 0051 genl !senlnpl
56
par ~11 SIGNAGE CONTRACTOR 0101 genl gen/l'llpl
61
.., 041051
101/02103/ BUS - BUSINESS NEGOTIATIONS
04/051
gm/desl
genlfenl bus!
pgmldesl
~ 101/021031 COE CODE &: ORDINANCE WORK gen/fenl [cdel
.., ~4/051
101/02/031 CMPT-COMPONENT
pgmldesl
genlfen! emptl
64
.., 041051
~1/02/031
041051
COS -COST &: ESTIMATING WORK
des/pgml
_emen/p cosl
gm/des/c
~ 101/021031 CTR CONTRACT PREPARATION AND EXECUTION WORK gen/fent drl
.., ~4/051
01102/031 £AS - EASEMENT WORK
pgm/desl
gen/fen! easf
.., 041051
~1/02/031 FEN - FRONT END WORK
pgm/de.'
gen/fenl lenl
041051 P8m/desf
68 ~ ~1/02/03/ f- MKT - MARKET CONSIDERATIONS :~n/fenl ~ktl
69
.., 041051
[01/021031 REG REGULATORY WORK
gm/desl
gen/fenl regl
.., ~"OSI
[01102/031
~14I0SI
RES - REAL ESTATE
pgm/desl
gen/fenl resl
pgm/desl
page 2
Ralph J. St<!pheMon" P .E., P.c.
Muter PmJect MiIJUIgement Check List - diG8 ·Illlied by seq, data type &. CUlpa Consulting Engineer
data
. ., type II1II ....... tuhjector-ms wkphue aapt . .pcode
71
feb 01/02/031 GEN • GENERAL CONSTRUcnON RELATED genlfenl ~ql
04105 pgm/desl
~~
72
85
feb 1011041 DES - DESIGN WORK ,eD/desl des/
86
feb 011041 DES-DESIGN sen/desl desl
geDldesl prr.1
87
abb 01/041 PRG • PROJECT DESIGN PROGRAM WORK
89
feb 01104/05/ COD -CONTRACT DOCUMENTS sen/deslc cod/
01'11
i 1011051
page 3
date ptillled:1214191
Ralph J. Sleph_1I,. P.E., P.c.
Muter Project M ......ement Check List • d&08 • listed by -... data type Ie c:anpt Consulting Engineer
data aI
lie' .,.,
type aide wk phue ....pt ... pallle
107
.,., 01105/ SSW- SUPER STRUCTURE WORK gen/conl I-w/
110 ad
reM - PROGRAM
fen/plml fin/fen/pg
de/llcon/ mldes/con
111 ad 02/03/0(1 REPARE PRO FORMA COST ANALYSES fen/plm! ~finlfen
Iet"' Plm/desl
112 ad 1021031041 SELICI' CONSTRUCI'ION ADVISORS OR CONSULTANTS AS fen/plml fen/des/pg
REQUIRED deal ml
146 ad
r 02103/041 SELECT GEOTECHNICAL ENGINEER
051
02/03/041 NSURE INTERNAL STAFF WAGE AGREEMENTS ARE IN PLACE
fen/Plm/ fen/plmld
des/conl eslconl
fen/pgml en/pgmld
051 des/conl ea/con/ad
:act 102/03/041 APPLY FOR .. OBTAIN ENVIRONMENTAL PERMITS REQUIRED 0011 fen/plml fen/plmld
14' 05 des/conl eslcon/env
148 act 102/03/041 IDENTlF\'ULTIMATE DECISION MAKER fen/nm/ ~en/pgmld
051 des/conl IH/con/mgt
149 ad 102/03/041 DENTIFY RELATIONS AMONG PARTIES fen/pgml fen/nmld
051 ides/conl es/con/mgt
150 ~ 102/031041 SET PROJECT MISSION, GOALS 8t OBJECTIVES fen/paml fen/pamld
~51 ideslconl eslcQn/mgt
~2/03/04.1 REVALIDATE YOUR FIRM'S ABlLITYTO DO TREJOB fen/pgml fen/pgmld
151 ad
051 dea/conl es/con/mgt
ad 02/031041 DECIDE ON PROJECT DELIVERY SYSTEM TO BE USED fen/plml fen/plmld
152
051 des/conl lea/con/mgt
ad 02/03/041 APPLY FOR 8t OBTAIN WATERWAY WORK PERMITS fen/pgml fen/pgmld
153
051 ides/CQnl ea/cQn/per
154 ad 02/031041 IOBTAIN PERMITS FROM CORPS OF ENGINEERS AS REQUIRED fen/paml fen/plmld
05 ideslcQnl ~slcQn/per
ISS act 02/031041 IOBTAIN TEMPORARY 8t PERMANENT FINANCING fen/paml fenlpgmlfi
051 !de./conl n/des/conl
02/03/041 DETERMINE FINANCIAL SOUNDNESS OF CLIENT ien/pgml tenlpamlfi
156 ad
051 ides/coni n/desfconl
157 act 02/03/041 IOBTAIN INTERIM FINANCING fen/pgml fenlpgmlfi
051 ides/conl n/des/cQnl
158 ad 02/031041 rPREPARE 8t SUBMIT ENVIRONMENTAL IMPACT STATEMENT 0011 fen/paml ~enlpgmlr
05 des/cQnl egienY/de.
ad 02/031041 PREPARE AND SUBMIT TRAFFIC STUDIES OF SITE AREA fen/paml fen/pamlt!:
159
05 ide./con' f/slt/des/co
160 ad 02/03/041 IOBTAIN OR PREPARE ALL EASEMENTS FOR STREET fen/Plml fen/reg/eas
051 RELOCATION deslcQnl I/desicon/p
161 ad 02/03/041 IREVIEW 8t APPROVE ENVIRONMENTAL IMPACT STATEMENT roOl / fen/pgml fen/reg/en
os de./cQn/ v/desiconf
02/03/041 I'-HECK ALL ASSESTS AND RESOLVE OUTSTANDING LIABILITY fen/pgm! ten/reslpg
162 ad
051 COMMITMENTS des/conl mldes/con
fen/pgml empt
163 :utl 02/03/041 UTL - UTILITY WORK
051 ides/conl
ad 021041 ~PPLY FOR AND OBTAIN SITE PLAN APPROVAL fen/desl fenlslt/des
164 II
~DENTIFY
EASEMENTS .. RESTRICTIONS THAT IMPACT ON fen/deslc leasllen/des
165 lad 02/04/051
~LDWORK Qn/ Iconl
02/041051 IOBTAIN NOTICE TO PROCEED IF APPROPRIATE DOl! fenldeslc fenladm/d
166 ad
~n/ ~./con/
02/04105 IREVIEW APPLICABLE LIEN LAWS .. CONVEY INFORMATION TO 0011 fen/desll: fen/adm/d
167 lad ani ea/conl
1m0SECONCERNED
02/04105 IOBTAIN HIGHWAY PERMITS FOR ROAD IMPROVEMENTS 0011 fen/deslc fen/con/pe
168 ad on/ rldesl
EXECUTE CONSTRUCTION CONTRACTS WITH CLIENTS 0011 fen/deslc fen/ctr/des
169 ad 02/04/05 onl ile 0'11 I
170 KI: 02/0 4/051 PREPARE LIST OF ALLOWANCES AND REVIEW WITH PROJECT 0011 fenldeslc fenldeslco
STAFF ani nl
ad 02/04/051 MAKE FULL REVIEW OF CONSTRUCTION DRAWINGS fen/deslc fenldeslco
I'll ani nl
ESTABLISH AND TABULATE KEY PROJECT DATES, AND REVIEW 0011 fen/deslc fenldeslco
172 ad 02/04/051 ani nl
WITH PROJECT TEAM
IDENTIFY NATURE OF LABOR FORCE FOR PROJECT fen/deslc fenldes/co
173 <lct 02/04/05 onl nl
ad 102/041051 E .. SUBMIT APPROVAL PROCEDURES TO BE USED fenldeslc fenldeslco
1'4 anI nl
~2104/051 ESTABLISH PLAN ROOM PROCEDURES FOR PROJECT 0011 fen/deslc fenldeslco
1'5 fact onl 1n'
dare prillled:12/4/97
Ralph J. Stepk_1I, P.E., P.c.
Muter Project Management Check List - d6G8 - listed by seq, ~toI type ... c:mpt Consulting Engineer
data csI
reel type axle
116 act U2/04/05 ARRANGE FOR AND MAKE VIDEO ... SOUND RECORDS fen/deslc fenldeslco
anI nl
171 act ,,2/041051 MAKE VIDEO TAPE RECONASSAINCE OF SITE BEFORE 0011 lenldeslc fenldeslco
STARTING DESIGN ... CONSTRUCTION ~nl n/gcr!
118 act 02/04/051 SET PROCEDllKES FOR ALL}OB RELATED MEETINGS fenldesle fenldes/co
onl n/mgt!
179 act 02104/05 OBTAIN SOIL BORINGS AND SUBSOIL ANALYSES ~O21 (en/deslc fenldes/co
'onl n/.bw!
180 ad 02104105 !MAKE PRECONSTRUCTION SITE RECONNAISSANCE - PHONE, 0011 {en/deslc fenldeslco
SOUND, TV ani n/sUl
181 act 02/04/05 fAPFLY FOR TEMPORARY UTILITY SERVICES 0011 fen/deslc fenldes/utl
anI conI
182 act 112104/051 DETERMINE APPUCABLE UTILITY EASEMENTS ... CONFIRM 0011 !e:Jdeslc fenl_/dft
CLEARANCE TO START WORK nl Iconl
183 ad !02/04/0S = N E SITE ACCESS REQUIREMENTS DURING 0011 fen/deslc fen/gcrlsll
NSTRUCTION ani des/con
184 act 102/04/051 VAUDATE YOUR FIRM'S ABILITY TO MEET INSURANCE 0011 fen/deslc fenlinsldft
REQUIREMENTS ani con/adml
185 ~ ,,2104105 DENTIF\' RELATIONS AMONG PARmS DURING fenldeslc fenlmltlde
CONSTRUCTION fonl 's/conl
186 ~ ~2/04l05! READ CONSTRUCTION SPECIFICATIONS AND CONTRACTS 10011 fen/deslc fenlmgtlde
ani slconl
181 act !02I04/0S APPLY FOR PERMANENT UTILITY SERVICES 1001 !fertldell/c fenlutl/des
onl conI
188 lid 02/051 PREPARE BLANKET PURCHASE ORDER SYSTEM 10011 fen/coni adm/fen/d
elconl
189 ad 02/051 REPARE MASTER LABOR,. MATERIAL BUDGETS f0 011 ffen/conl conlfen/co
51
190 ad 02/051 !pREPARE'" DISTRIBUTE BUy-otJT ESTIMATE AS REQUIRED 0011 fenlconl conlfen/pt
01
191 ad 02/051 IREVIEW BULLETIN, CHANGE ORDER ... FIELD ORDER 0011 fen/coni len/adm/t
PROCEDURES WITH SUBCONTRACTORS anI
192 ad 021051 IPREPARE SCHEDULE OF VALUES FOR PAYMENT REQUESTS 0011 fen/conl fenladmlc
ani
193 ad 021051 IREVIEW EMPLOYEE SITE CONDUCT GUIDELINES WITH 0011 fen/conl fen/adm/c
SUBCONTRACTORS anI
194 act 021051 !OBTAIN EMERGENCY PHONE NUMBERS FOR 0011 en/conl fen/adm/t
SUBCONTRACTORS ionl
195 ad 1121051 OBTAIN FIELD ornCE PHONES AND DISTRIBUTE NUMBER 0011 enlconl fen/adm/c
onl
196 ad 1021051 REVIEW BlLUNG PROCEDURES WITH SUBCONTRACTORS 0011 fen/conl fen/.dm/c
'on I
191 <let 1021051 !DETERMINE SCOPE ... NATURE OF LABOR AGREEMENTS ... 0011 tenlconl ten/..dmlc
DISCUSS WITH PROJECT TEAM onl
198 ad 1021051 NOTIFY FIELD STAFF AND OTHERS CONCERNED REGARDING 0011 fen/conl fenladmlc
ALTERNATES SELECTED onl
199 ad 1021OS1 !OBTAIN BUILDER'S RISK AND LIABILITY INSURANCE 0011 fen/conI fenl.dmlc
lon/insl
200 ad 102/051 OBTAIN FIRE AND THEFT INSURANCE 0011 fenlconl fen/adm/c
onllnsl
~ 10 21051 PROVIDE OWNER WITH INSURANCE CERTIFICATES AS 10011 fen/conI fen/ad.m/c
REQUIRED ~n/lnsl
202 lact 1021051 OBTAIN SUBCONTRACTOR INSURANCE CERnFICATES 0011 fenlconl fen/adm/c
on/insl
ad 102/051 SET ... IMPLEMENT SAFETY PROGRAM 001/· fen/coni fenladmlc
onlregl
204 ad 02/051 PREPARE ... DISTRIBUTE CONSTRUCTION JOB SITE PLAN 0011 fen/conI fenladmJsl
Igcr/conl
20S <let ,,2/051 NSPECT JOB SITE BEFORE MOBILlZE ... MOVE IN !D021 fenlconl fenlconl
206 ad 021051 OBTAIN ALL SITE CLEARANCES NEEDED TO BEGIN AND ro021 len/coni fen/conl
MAINTAIN CONSTRUCTION WORK
201 ad 1021051 PROVIDE NOTICE OF START OF WORK AS REQUIRED roOtl fen/con/ fen/coni
208
ad 021051 REPARE AND DISTRIBUTE SUBCONTRACTOR UST 0011 fenlconl fen/coni
ad 02/0S1 SET ... HOOK UP JOB SITE CLOTHES CHANGING FACILITIES FOR 0011 fen/coni fen/conl
TRADES
210 ad 02/0S1 SET UP FIELD BANK ACCOUNTS AS NEEDED 100ti fenlconl en/conl.. d
ml
act ~2/051 pBTAIN BONDS, INSURANCE 6: UCENSES AS REQUIRED 0011 fenlconl ~eD/eon/ad
211
ml
211 act 021051 REVIEW EMPLOYEE SITE CONDUer GUIDWNES WITH 0011 fen/conl fen/con/.ad
INTERNAL STAFF 'ml
213 act 021051 ARRANGE FOR 6: TAKE ONGOING CONSTRUCTION PHOTOS 001 fenleonl fen/eon/ad
ml
214 act &. HOOK UP JOB SITEOmCES 0011 fen/conl fealeon/ge
rl
215 act 02/051 SET &. HOOKUP JOB SITE STORAGE FACILITIES 10011 fen/coni fen/con/ge
rl
216 ~ 02/051 DENTIFY ALL GENERAL REQUIREMENTS &. CONDmON ITEMS 10011 fealeon/ge
rl
217 act 102/05/ NSTALL JOB SITE PHONES roOll enleon/ge
rl
218 act 1021051 REVIEW SITE PLAN AND SITE SPACE ALLOCATION WITH !OOll fenlconl Ifealconlait
SUBCONTRerORS IIgerl
219 act 102/051 ~NSTALL JOB SITE TEMPORARY WATER 0011 fenlconl fen/con/aU
Igcrl
220 act 021051 INSTALL JOB SITE TEMPORARY TOILETS 0011 fen/conI fen/con/ut
II
221 act 1021051 PROVIDE CONSTRUCTION SUPTWITH SUBCONTRAer 1"011 enlconl fenleotlad
PURCHASE ORDERS SHOWING WK SCOPE OF SUBCONTRACTS mfconl
~31
m SSEMBLE AND ORGANIZE PROJEer CONSTRUerION TEAM fen/coni fen/mgt/eo
fnl
223 FEN - FRONT END WORK fenl fteql
~HECK PARKING REQUIREMENTS
224 act 1031041 pgm/deal cde/pgmld
esl
225 act 03/041 MAKE PHEUM CODE REVIEW OF EARLY DESIGN PACKAGES pgm/desl cdelpgmld
~.I
226 act 03/041 NEGOTIATE AND EXECUTE CONSTRUC. TION ADVISOR Ipgm/desl elr/pgmlde
CONTRAerS AS REQUIRED 81
227 ~ 103/041 IKEVIEW PROJEer PROGRAM NEEDS AND DESIRE WITH OWNER pgm/desl pgmldesl
228
act 103/041 !SELECT CONSTRUCTION DESIGN CHARACTERISTICS &. SYSTEMS pgm/des' pgmldesl
230 act 10 3/041 IREVIEW PROJEer PROGRAM NEEDS AND DESIRES WITH pgm/d.sl pgmldes/
ARCfHTEerlENGINEER
231 lact 103/041 [DETERMINE SCOPE OF WORK FOR ALL OFF SITE 10021 pem/deal pgmldesl
CONSTRUCTION REQUIRED
m act 103/041 DETERMINE ELEVATOR REQUIREMENTS pem/des' pgmldesl
236 ~
103/041 ~ETERNnNEPHONEDEMANDLOADS 0161 Plm/desl pgmldes/u
~II
~ 244
245 act
M"fI.5I ESTABLISH SCOPE OF OFF-5ITE WORK REQUIRED BY YOU AND
BY OTHERS
3/041051 IDENTIFY LONG LEAD OR HARD TO PROCURE ITEMS AND
DISCUSS WITH PROJEer STAFF
Plm/deal Pimldea/e
conI on/of.t.lw
Pim/desl Plmldu/e
conI onlprol
data
246 ad 103/0 4/051 PREPARE & SUBMIT VALUE ENGINEERING ANALYSIS roOll pgm/desl pgmldesle
conI !onlvenl
ad 103/011051 IREMOVE CONTAMINANTS FROM SITE AS REQUIRED roOll p,m/de.' re"psmld
247 coni esJabalcon
abb 10 41 DES-DESIGN delll leeql
248
ad 1041 IAPPLY FOR & OBTAlN PLAN CODE IlEVIEWS REQUIRED 1001 idesl cde/delJl
249
261
ad 1041 PREPARE DESIGN DEVELOPMENT PACKAGE dell
262 ad
ad
041
041
PREPARE PRELIMINARY DESIGN PACKAGE
265 ad 041 CHECK SCHEMATIC DESIGN PACKAGE FOR CONSTRUCTIBILITY desl desl
ad 10 41 PREPARE & SUBMIT PERFORMANCE SPECS FOR LIFE SAFETY desl idesl
AND AUTOMATION SYSTEMS
267 ad 10 41 PREPARE & ISSUE £LEVATOR ENTRANCE AND CAB DESIGN 0141 dell dell
269 ad 1041 PREPARE & ISSUE DESIGN DEVELOPMENT PACKAGE desl Idesl
270
ad 10 41 REVIEW & APPROVE DESIGN DEVELOPMENT PACKAGE desl desl
276 ad 1041 REVIEW & APPROVE CONTRACT DOCUMENT PACKAGE 1001 desl idesl
277 ad 10 41 PREPARE AND SUBMIT EARLY DESIGN STUDIES TO CITY FOR desl deslcdel
COMMENT
278 fact 10 41 RETAIN WINDOW WASHING CONSULTANT des des/cot I
date prWe4:12/4/97
Rafph r. Steph-, P.£', P.c.
Master Project Management Check Llat • d608 ·Ilated by seq.. data type a. cmpt Consulting Engineer
data aI
...." type mde wit pb.ue cmpl NIp aide
281 ad 10 41 ....ONPIRM OWNER OR END USER TIME TABLE FOR DESIGN 001 'des! ~slpu
API'ROPRlAT~ d"'''''''~
298
lid 104/051 ESTABUSH PROJECT DESIGN 6: CONSTRUCTION COST ACCTG 001
SYSTEM AND ACCOUNT NUMBERS
299 ad 104/1151 SET STORAGE" INSURANCE REQUIREMENTS FOR MATERIAL 6: 0011
EQUIPMENT FURNISHED BY OTHERS
300 ad 104/1151 ...,.AR, AND l'UBUSII. AS
ClUTIQUE 6: DEBRIEFING
RJu. "OlEO ""
I
ad 104/051 IDENTIFY EQUIPMENT 6: MATERIAL FURNISHED BY OTHERS 6: 01111 des/conI con/prolde
301
REVIEW WITH PROJECT STAFF .1
fact 104/1151 ....ONPIRM OWNER'S BUDGET RELATIVE TO THE PROJECT 01111 des/conl cos/des/co
302
DELlVEllY SYSTEM SELECTED nl
ad 10 41051 ESTIMATE COSTS OF REVISIONS TO WORK 0011 des/conl cos/des/co
nl
304 lad 1041051 PREPARE BASE COST ESTIMATES TO CORRELATE WITH DESIGN 0011 des/conl cos/des/co
PKOGRAM nl
305 fact 10 41115 / PREPARE 6: EXECUTE ALL LICENSE AGREEMENTS 10011 des/conI dr/des/con
I
ad 104/051 NEGOTIATE 6: EXECUTE AGREEMENT ON TRAFFIC des/conl dr/des/eon
SIGNALIZATION I
ad 104/1151 EOTECHNICAL ENGINEER CONTRACT des/conl dr/des/con
307 /
ad 104/051 NEGOTIATE AND EXECUTE GUARANTEED MAXIMUM PRICES des/coni dr/des/con
AS REQUIRED I
lad 104/051 NEGOTIATE AND EXECUTE DESIGNlBUILD CONTRACTS AS des/coni drldeslcon
REQUIRED I
ESTABLISH" PUBLISH OPERATING &: MAiNT MANUAL (OMM) 0011 des/eonl desldolco
:nO fact 104/051
SUBMITTAL PROCEDURES nl
fact 104/051 DEFINE JOB CONDmONS TO BE MET FOR SUBSTANTIAL 0011 deslcon! dell/dolco
311
COMPLETION nl
STABLISH AND PUBLISH WARRANTY PROCEDURES 01111 deslconl des/dolwOl
312 rlconl
!;-t4/051 PREPARE 6: SUBMIT DAILY REPORTS 0011 Ides/conI deslconl
313
ad 04/051 ...HECK FINAL DESIGN PACKAG:E FOR CONSTRUCTIBILITY 0011 des/coni deslconl
314
act 041051 TABULATE ACCEPTED ALTERNATES '" INSURE APPLICABLE des/conl des/coni
DRAWINGS ARE AVAILABLE
act 041051 rrABULATE ALL BID QUALIFICATIONS'" REVIEW WITH PROJECI ~es/con' des/conl
STAFF
act 04/011 IESTABLISH'" PUBLISH SUBMllTAL PROCESSING PROCEDURES 0011 ~e./conl des/conl
324
32S lid 041051 IPREPARECONTRACT AWARD TABLATION SHEET WHERE 0011 des/conl des/con/
APPROPRIATE
326
329 ad
lid 041051
04/051
lESTABUSH PHOTO TAKING RESPONSmILITIES AND
PROCEDURES ON PROJECT
IPREPARE CONTRACT DOCUMENT MATRIX
des/conl des/coni
de./conl des/cofll
des/conI des/conl
act 041051 fLABEL'" SAFELY STORE INTACT BID SET OF CONTRACT 0011 des/conI Ides/conl
DOCUMENTS
act 04/051 ~DENTIFY ALL ALLOWANCE ITEMS &: DISTRIBUTE LIST TO 0011 des/conl Ides/conl
331
rtuosE CONCERNED
lad 104/051 VICES REQUIRED 0011 Idevconl des/cofll
~ 1041051 [REVIEW '" DISTRIBUTE ALL SUBSOIL REPORTS AS REQUIRED des/conl de./conl
345 .act ~4/051 APPLY FOR &: OBTAIN EROSION CONTROL PERMITS 0021 delleonl des/con/en
vlperl
act ~4/051 DESIGN, FABRICATE AND ERECT SITE IDENTIFICATION SIGN 10011 dealcon/ge
rl
347 act 1041051 DETERMINE LOCATION OF STORAGE, OFFICE, CONST ROADS, 0021 dealconl des/conlge:
STOCKPILE, PARKING, TRAILERS,&.: FAB AREAS rlsltl
~41051 PREPARE &.: SUBMIT ELEVATOR STUDIES des/conI des/eonllp
i
act ~4/051 OBTAIN REQUIRED APPROVALS OF WORK PLANS AND 0011
tol
!des/conl des/conlplI
349
SCHEDULES sl
350
act ~4/051 REVIEW WORK PLAN AND SCHEDULES WITH 10011 des/conl des/conlp.
SUBroNTRACTORS 81
Y. rr
JWph J. StepheMOll,. P.E., P.c.
Muter Project Management Check List - d608 -listed by eeq, data type 4: anpt Consulting Ensineer
dat.t
_. type oeq ......... lUbjector-mg wlcphMe anpl
3S1 act 10 4/05 / !pREPARE SUMMARY & DJrrAILED NETWORK MOBELS OF WORK 1001 / ~es/conl Ides/conlpa
rroBEDONE sl
352
~ 10 41051
IfILE CONTRACT DOCUMENT BUILDING PERMIT SET IN SAFE, 0011 des/conl ideS/conipe
\.
353
PROTECTED BUILDING
LABEL & SAFELY STORE INTACT PERMIT SETS OF DRAWNINGS 10011
rl
des/conI des/conlpe
EE=
rl
354 IAPPLYFOR & OBTAIN ELECTRICAL PERMITS !O161 des/conI des/conlpe
rl
355 !APPLYFOR&OBTAlNDEMOLlTIONPERMITS 0011 des/conl des/conlpe
rl
356 act 1041051 IAPPLY FOR 4: OBTAIN MECHANICAL PERMITS 015/ des/coni des/con/pe
rl
357 act 1041051 IAPPLY FOR & OBTAIN STREET RESTRICTION PERMITS 0011 deS/conlpe
rl
358 act 04/051 APPLY FOR 4: OBTAIN HEALTH DEPARTMENT PERMITS 0011 des/conI deS/conlpe
rl
359 act 04/051 APPLY FOR Ie OBTAIN SITE WORK PERMITS 0021 ides/conI
II'I
360 act 041051 APPLY FOR Ie OBTAIN FULL BUILDING PERMIT 0011 Ides/conl Ides/conlpe
rl
361 act 04/051 APPLY FOR Ie OBTAIN FOUNDATION PERMITS 0011 ides/coni Ides/conlpe
rl
361 act 041051 !APPLY FOR Ie OBTAIN CURB CUT PERMITS 0021 Ides/conl ldeS/conipe
II
363 act 04/051 !APPLY FOR Ie OBTAIN FOOD SERVICE PERMITS 001/ ~es/conl Ides/conlpe
rl
364 act 041051 APPLY FOR AND OBTAIN ALL SIGN PERMITS 0011 ides/conI des/conlpe
r/
365 act 041051 IAPPLY FOR Ie OBTAIN SITE UTILITY PERMIT 0021 Ides/conl des/conlpe
rl
36(i act 04/051 IAPPLYFOR & OBTAIN SITE IMPROVEMENT PERMIT 0011 Ides/conl des/conlpe
rl
367 act 1)4/051 APPLY FOR Ie OBTAIN SOIL EROSION PERMITS 0021 deslt:on/ des/eonlpe
rl
368 act 104/051 IOBTAIN FULL BUlLDlNG PERMIT 0011 ides/conI deslconlpe
rl
369 act 104/051 pBTAlN FOUNDATION PERMITS 0011 fdesJconl des/conlpe
fl
pBTAlN ELECTRICAL PERMIT 001/0161 des/conI deslconlpe
370 ~ 104/051
rl
pBTAlN PLUMBING PERMIT 001/0151 deslconl deslconlpe
371 ~ 104/051
rl
act 1041051 pBTAlN CURB CUT PERMITS 10011 deslconl des/conlpe
372
rl
~
APPLY FOR Ie OBTAIN HIGHWAY RIGHT OF WAY WORK 10011 des/conl des/conlpe
373
PERMITS rl
pBTAIN SITE WORK PERMITS 1001/0021 deslconl des/canipe
374
rlsltl
SJrr NORMAL. EXPEDITED AND SPECIAL SUBMITTAL 0011 deslconl des/con/pf
375
TURNAROUND TIMES TO BE USED 01
act 04/051 IDENTIFY ALL OWNER FURNISHED EQUIPMENT ITEMS Ie 0011 deslconl des/con/pr
376
DISTRIBUTE TO THOSE CONCERNED 01
act 041051 IOBTAIN '" DISTRIBUTE APPROVED LONG LEAD ITEM COLOR 4: 1D011 des/conl des/con/pr
377
iFINISH SCHEDULES '01
act 1041051 DETERMINE WAREHOUSING NEEDS AND OBTAIN SPACE 10011 des/coni des/con/pr
378
~I
act 104/051 IOBTAIN DELIVERY DATES FOR MATERIAL Ie EQUIPMENT 0011 Ides/coni des/con/pr
379 01
FURNISHED BY OTHERS
act 104/051 ESTABLISH FORMAT AND CONTENT OF PROCUREMENT LOGS 0011 fdes/conl ~es/con/pr
380
!pI
DESIGN, SUBMIT AND APPROVE CONCRJrrE MIXES 0031 des/conl des/con/pr
381 01
PREPARE Ie ISSUE ELEVATOR PROPOSAL PACKAGE OU( deslconl deslcon/pr
382 01
IVALUATE ELEVATOR PROPOSALS AND AWARD CONTRACT 0141 ~es/conl ~eslcon/pr
383 oleotl
04/051 DJrrERMINE MOCK UPS REQUIRED AND MAKE 0011 deslconl Ideslcon/pr
384
ARRANGEMENTS FOR THEIR DESIGN AND CONSTRUCTION ~/mupl
act 041051 FOLLOW UP AND RECEIVE TEMPORARY UTILITY SERVICES 0011 deslconl [des/con/pf
385 olutll
act 104/051 REVIEW TESTING NEIDS AND OBTAIN TESTING SERVICES 10011 des/conl des/conltel
prof
act 104/051 OBTAIN INFORMATION ONTKASH COMPACI'OR OUf des/conl detJIcon/us
yl
act 104/051 OBTAIN INFORMATION ON PALLE1T STACKER ro131 detJIconl detJIcon/us
11'
389 act 104/051 OBTAIN INFORMATION ON BALER IOUI detJIconl ldeslcon/us
11'
390 lad 104/051 DETERMINE RECIPROCAL EASEMENTS 6; CONFIRM CLEARANCE ides/coni !euldetJIco
TO START WORK ttl
391 ad 104/051 DETERMINE MAINTENANCE EASEMENTS AND CONFIRM 0011 ides/coni euldes/co
CLEARANCE TO START WORK ~I
act 04/051 IfOLLOW UP WITH PUBUC RELATIONS CALL AFTER Ides/conl ~kt/del/co
392
CONSTRUCI10N 1\1
393 act 04/051 IFOLLOW UP AND OBTAIN REGULATORY APPROVALS aetJIconl ret/des/co
..
nl
394 act 04/051 !RETAIN CURTAIN WALLITESTING CONSULTANT detJIconl esldeslcon
Iprol
395 051 CON -CONSTRUCI10N < coni seq
act IOSI OBTAIN AND DISTRIBUTE SITE ADDRESSES 0011 !conI adm/COllI
!act 10 51 SET UP FIELD PETTY CASH ACCOUNT 6; PROVIDE CASH TO FIELD 0011 ani admlconl
STAFF
act 10 51 ESTABLISH PROJECI' CONST COST ACCI'G SYSTEM AND 0011 coni fadm/coni
ACCOUNT NUMBERS
fad IOS( SET 6; IMPLEMENT SUB CONTRACI' PAYMENT PROCEDURES 0011 olll adm/con.!,
!crt
ad IOS( SET PROJECT CLOSE OUT PROCIDURES 10011 conI c
act 051 pBTAIN PROJECI' OPERATING AND MAINTENANCE MANUALS 0011 conI laIcani
410 KI 051 PREPARE AND SUBMIT CONST DOCUMENT RECORD SET 0011 conI dolconl
(FORMERLY CALLID THE AS BUILT RECORD SET)
411 act 051 pBTAIN WARRANTIES 0011 coni loleon
416 ad 051 !'oLEAR FINAL PA¥MENT ON PROJECI' AND OBTAIN PROPER 001 conI dolconl
WAIVERS OF LIEN
417
ad OSI [pROVIDE OWNER AND USER WITH AN UP-TO-DATE SET OF 001 0
CONSTRUCI10N DOCUMENTS FOR REFERENCE USE
418 ad OSI !'o0LLECT, RECORD, AND STORE JOB LOGS, DIARIES, REPORTS, 001 conI dolconl
AND OTHER PROJECI' DOCUMENTATION
ad OS( BRING ALL MEETING MINUTES AND RECORD FILES UP-TO-DATE 00l coni dolconl
419
420 act 105/ ....OLLECT AND BIND ALL OmCIAL AND UNOFFICIAL PROJICI' 00l COlli do/conl
PHOTOS
421 ~d 051 .....OLLECT AND RECORD ALL PROJECT NETWORK PLANS. 0011 coni do/coni
SCHEDULES, AND BAR CHARTS
\.,. t22 ~ ~Sl .....LOSE OUT AND STORE CORRESPONDENCE AND OTHER
RECORD FILES
0011 conI dolconl
W ~ ~51 ASSEMBLE AND PROPERLY STORE ALL SHOP DRAWINGS AND 0011 onl ~Io/conl
OTHER JOB RELATED SUBMIlTALS
424 ~ 051 REQUEST ARCHlENGR OF RECORD TO MAKE CERTIFICATE OF DOlI Icon I do/coni
SUBSTANTIAL COMPLETION INSPECTION
425 ad 051 PLAN AND IMPLEMENT GRAND OPENING OF PROJECT AS 10011 conI dolconl
REQUIRED
426 ad 051 \..ONDUCT INTERNAL PROJECT CRITIQUE AND MAKE 0011 conI do/conI
RECOMMENDATIONS FOR IMPROVEMENTS
427 ad 051 ACCOUNT FOR ALL CUENT-OWNED TOOLS, SPARE PARTS. AND 0011 conf dolconl
EXTRA STOCKS OF MATERIALS
t28 51 PROVIDE OWNER COPIES OF ALL RELEASES THAT ALLOW 0011 conI dolconl
OCCUPANCY
m .id IOSI LABEL ALL ELECT PANEL BOXES, PLMBG, VALYES AND EQUIP
FOR PROPER OPERATION AND MAINTENANCE
015/0161 conI dolconl
431 ad IOSI SUBMIT FINAL STATEMENT OF ACCOUNTING AS REQUIRED, 0011 !Coni do/con
TO OWNER AND ARCHlTECTIENGINEER
432
ad IOSI LCHANGE ORDER 0011 coni do/coni
ONTRACT AMOUNTS
433 ad 10 51 SEND DESERVED THANK YOU LEITERS TO THE OWNER, 0011 conI do/conI
DESIGNERS, AND CONTRACTORS INVOLVED
434 ad ~51 fl'ROVIDE OWNER WITH COMPLETE UST OF CONTRACTORS 0011 coni dolconl
AND VENDORS ON JOB AND WHAT THEY DID
~RRANGE FOR SUCH OPEN HOUSE ACTIVITIES AS MIGHT BE coni dolconl
435 !ad 10 51 0011
DESIRES
\Jd 051 ~NSURE THAT YOUR COMPANY IDENTIFICATION IS SHOWN 0011 conI do/coni
436
SOMEWHERE IN THE BUILDING IF PERMIlTED
437 ad 051 INSURE THE BUILDING IS AS CLEAN OR CLEANER THAN DOlI Iconl do/conl
SPECIFIED WHEN YOU MOVE OUT
438 ad 05/ PROPERYTRAIN AND TURN OVER THEFACIUTYTOTHE DOlI !conI dolconl
OWNER'S REPRESENTATIVES
439 ad 051 ESTABLISH START OF ALL WARRANTY AND GUARANTEE 0011 coni do/conI
PERIODS PRIOR TO OWNER MAKING JOB OPERATIVE
440 adl 051 PREPARE AND SUBMIT TO THE OWNER SPECIFIC WARRANTIES 0011 feonl clo/conl
AS SPECIFIED
441 ad 051 PREPARE AND SUBMIT TO THE OWNER WORKMANSHIP OR 0011 onl dolconl
MAINTENANCE BONDS REQUIRED
4t2 ad 051 PREPARE AND SUBMIT TO THE OWNER MAINTENANCE 0011 onl do/conI
AGREEMENTS AS SPECIFIED
443 ad 051 PREPARE AND SUBMIT TO THE OWNER DAMAGE AND 0011 conI do/conI
SElTLEMENT SURVEYS OF THE SITE AND FACILITIES
444 lad 051 REPARE AND SUBMIT TO THE OWNER FINAL PROPERTY 0011 coni do/conI
SURVEYS OF THE SITE
445 lad 051 SUBMIT FINAL BILLING TO OWNER FOR ALL IMCOMPLETE 0011 iConl do/conl
ITEMS AND A PROPER COST ASSIGNED TO EACH
051 ADVISE OWNER OF ANY INSURANCE CHANGES OVER 0011 [conI dolconl
446 lad
EXImNG OR PAST REQUIREMENTS OR DATES
SUBMIT FINAL UTILITY METER READINGS, AND RECORDS OF 0011 lConl dokanl
447 ad 051 STORED FUEL AT TIME OF SUBSTANTIAL COMPLETION
448 ad ~WNER CONSENT OF SURETY TO FINAL PAYMENT 0011 coni dolconl
RID JOB OF ALL RODENTS, INSECTS. AND OTHER PESTS BY AN 0011 conI dolconl
449 ad 051 EXPERIENCED EXTERMINATOR
tl'
\..AREFULLY READ THE FULL CONTRACT DOCUMENT CLOSE 10011 conI dolconl
4SD
OUT REQUIREMENTS
51 MAINTAIN INVENTORY OF TOOLS &: EQUIPMENT 10011 conI conladml
451
ad ~51 PREPARE EMPLOYEE SITE CONDUCT GUIDELINES 0011 conI conladml
4S2
~51 ASSIGN CONSTRUCTION JOB NUMBERS conI con/adml
4S3 lad
~ c..f
Ralph J. Stephenson, P.E., P.e.
Muter Project Management Check Llat - d608 - listed by aeq, data type Ie anpt Consulting Engineer
clata col
..... type CDIIe wk phase anpl ...pcode
459 lad ~Sl NSTALL COMPACTOR AND BALER EQUIPMENT 0111 onl con/lfwl
on/lfwl
465 ad 051 NSTALL TRAFFIC DOORS 0101 !coni
ad 051 INSTALL CERAMIC TILE WALLS AND FLOORS 0091 !coni on/lfwl
471 lad 10 51 NSTALL HANGERS Ie GRID FOR ACOUSTICAL CElUNG 0091 conI on/ifwl
472 lad ~SI SET FOOD SERVICE EQUIPMENT 0111 onl coniIf wI
coni con/lfwl
475 ad 10 51 NSTALL IN RACK SPRINKLER PIPING AND HEADS 0151
484
ad 051 rr APE Ie SAND WALL GYP BOARD 0091 coni con/lfwl
494 ad 051 ....OMPLETE HOOK UP !LEVATOR AND EQUIPMENT ROOM 014{ onl !c0nfifwl
MACJUNERY
OS{ INSTALL FIRE EXTINGUISHERS
495 ad 0101 coni on/ifwl
500 fad 10 51 APPLY PLASTER SKIM COAT TO INTERIOR WALLS 0091 onl con/ifwl
S02
ad IOSI NSTALL HOISTWAYWIRING aUI ~onl cORfifwl
S04 ad 10 51 INSTALL MARBLE FOOOR AND WALL FINISHES 0041 conI conlffwl
S07
ad 051 INSTALL DRAPERIES 0121 coni con/ifwl
SOlI
ad 051 APPLY GYPSUM FLOOR TOPPING 0031 coni oR/ifwl
S09 lad
05/ NSTALL ACOUSTIC CEILING PANELS 00911 anI con/ifwl
510 >ad 051 INSTALL INTERIOR BUILDING PAVERS 10091 conI ~nlifwl
5U >ad 051 APPLY PLASTER BROWN AND SCRATCH COAT TO INTERIOR 0091 coni cORlifwl
WALLS
513 lad 051
HOOK UP &; TEST FIRE PROTECTION 3RD PARTY SUPERVISORY 015/0llil onl con/ifwl
SYSTEM
514 ~d 051 IINSTALL ELEVATOR EQUIPMENT ROOM MACHINERY 0131 onl conllfwl
515 ad 051 !,-OMPLETE HOOK UP !LEVATOR AND EQUIPMENT ROOM 10141 anI 'con/ifw'
MACHINERY
511i lad
05/ INSTALL !LEVATOR RAIL BRACKETS &; CAR &; 0141 coni conlifwl
COUNTERWEIGHT RAILS
517 ad 051 INSTALL ELEVATOR PIT EQUIPMENT 10141 conI con/ifwl
518 fad 051 SPRAY ON FIREPROOFING AT INTERIOR STRUCT STEEL 10071 conI con/ifwl
MEMBERS
519 lad
051 SPRAY ON FIREPROOFING AT PERIMITER STRUCT STEEL 0011 conI conlifwl
MEMBERS
~NSTALL INSULATION AT EXTEIOR WALL SPANDRELS 0011 onl con/ifwl
520 ad OS!
526 lIA:t 051 INSTALL ELEVATOR ENTRANCES (MINUS DOORS) 0141 conI lconllEwl
529 ad 051 ROVIDE TEMPORARY PERMANENT POWER TO MACIDNE 0161 coni conlifwl
ROOMS FOR ELEV INSTALLATION
lld 051 INSTALL DRAPERY TRACKS 0121 !conI conlifwl
531 lld 051 IERECT ELEV SHAFT STUDS, IN WALL WORK'" DRY WALL TO f00910151 Icon I con/lfwl
PART ENCLOSE SHAFTS 0161
ad 051 INSTALL ELECTRICAL POWER EQUIPMENT DISCONNECTS 0161 Iconl on/lfwl
539 ~ IDSI NSTALL ABOVE CLG INTERIOR ROOF DRAIN LEADER 0151 conI con/irwl
~"
NSTALL ABOVE CLG SHEET METAL DUCTWORK FOR HVAC 0151 coni !conlirwl
051 NSTALL AND TEST ABOVE FLOOR FIRE SPRINKLER RISERS 0151 coni con/irwl
ad 051 INSTALL ABOVE CLG ELECTRICAL DISTRIBUTION CONDUIT 0161 conI con/ltwl
545 lld 051 INSTALL HOLLOW METAL DOOR FRAMES 0081 coni c
547 \\Id 051 ULL ELECTRICAL DISTRIBUTION WIRE IN CONDUIT 016/ conI conllrwl
lIA:t 051 NSTALL AND TEST ABOVE FLOOR FIRE SPRINKLER LATERALS 0151 onl on/irwl
AND DROPS
549 act 10 51 INSTALL ABOVE CLG INTERIOR DOMESTIC SEWER PIPING 0151 conI con/irwl
550 ad 051 INSTALLABOVECLG INTERIOR DOMESTIC WATER PIPING 0151 onl con/lrwl
552 ad 051 NSTALL HARD CEILING SUSPENSION AND FRAMING 0091 coni con/irwl
lld 051 ~NSTALL BORROWED LIGHT HOLLOW METAL FRAMES 0081 coni onltrwl
553
554 ad 051 INSTALL ABOVE CLG SUPPORTS FOR FOLDING PARTITIONS 005/0061 coni on/irwl
5SS lld 051 ERECT METAL WALL STUDS FOR DRY WALL PARTITIONS 10091 onl con/trwl
556 ad 051 INSTALL BELOW FLOOR ELECTRICAL ROUGH INTO ABOVE 0161 conI conlil'wl
FLOOR EQUIPMENT
ad 051 ~NSTALL IN WALL ROUGH DOMESTIC PLUMBING WORK 10151 coni conlirwl
557
558 ad 051 INSTALL IN WALL ROUGH HVAC WORK J:: onl conltrwl
SS9 ad 051 NSTALL IN WALL ROUGH ELECTRICAL CONDUIT AND FEEDERS 0161 conI con/irwl
ad 051 NSTALL IN WALL ROUGH MEDICAL GAS PIPING 10151 feonl con/irwl
date p"nted:12/4/97
RalphJ. Stephen80n. P.Eo, P.c.
Muter Project Management Chedt Lut • dliOS • luted by seq, cb!hI type &: c:mpt Consulting Engineer
data col
feC' type mde wk phue cmpt
565 act 051 REQUEST AND IMPLEMENT SPECIAL INSPECTIONS OF PROJECT 0011 coni Iconlillpl
567 ad !OSI PREPARE PROJECT CONSTRUCTION NETWORK MODEL 0011 ~onl Icon/pasl
568 ad ~SI APPLY FOR &: OBTAIN TEMPORARY PARKING PERMITS 0011 (:0111 conlperl
S70 fld 051 IREVIEW AND EVALUATE CONST SUB CONTRACT PROPOSALS 0011 onl con/prol
~
ad 051 EXPEDITE ALL DEUVERIES [0011 coni conlprol
578 051 IFAB &: DELIVER ELEVATOR PLUNGER CASINGS 0141 coni conlprol
579 f1d
ad 051 IFAD " DELIVER ELEVATOR BRACKETS" RAILS [0141 coni conlprol
580
051 FAB &: DELIVER ELEVATOR ENTRANCES 0141 leonl con/prol
581 ad
ad 051 SOUCIT Ie RECEIVE ELEVATOR PROPOSALS 0141 Iconl on/prol
582
585 ad 051 AD" DELIVER ELEVATOR CAB INTERIOR FINISHES 10141 coni con/prol
587 ad 051 AI" DELIVER ELEVATOR MACHINE ROOM EQUIPMENT 0141 !conI conlprol
ANCHOR BOLTS
588 ad 051 AD" DELIVER ELEVATOR PIT TIE DOWN STEEL" EMBEDS 10141 !coni con/proJ
conI con/pro/co
589 ~d
051 SOUCIT Ie RECEIVE CONST SUB CONTRACT PROPOSALS !OOll
tI
f1d 051 REP Ie ISSUE SUB CONTRACTOR CONSTRUCTION CONTRACTS 0011 conI con/pro/co
590 II
"PO'S
f1d 05/ RECEIVE AND FILE ALL EXECUTED SUB CONSTRACTS 10011 tonI ton/pro/co
591 tl
~51 REPARE UST OF EARLY SUBMITTALS NEEDED AND ASSIGN TO 10011 conI con/proillu
592 ad PROJECT STAFFFOR DOING pI
ad ~Sl REVIEW &: APPROVE ELEVATOR PIT TIE DOWN STEEL Ie EMBEDS 0141 onl on/pro/llu
593 pI
SHOP DRAWINGS
~ ad ~51 REPARE Ie SUBMIT ELEVATOR PIT TIE DOWN STEEL 80; EMBEDS 0141 conI con/profsu
594 SHOP DRAWINGS bl
595
Lei REVIEW Ie APPROVE CONTRACTOR DRAWINGS OF £LEVATOR 0141
DOORS, FRAMES 80; CABS
coni onIprolsu
1:>1
596 act ~51 PREP" SUBMIT CONTRACTOR DWGS FOR ELEV FIXTURE 0141 Iconl ~n/prolsu
DESIGN, MTLS" COLORS hi
59'1 act ~51 REVIEW" APPROVE CONTRAcrOR DWGS FOR ELEV FIXTURES nUl conI ~on/prolsu
hi
598
act ~51 PREPARE" SUBMIT ELEVATOR MAClDNE ROOM ANCHOR 0141 onl on/pro/au
BOLT SHOP DRAWINGS hI
599 lad 051 REPARE" SUBMIT CONTRACTOR DRAWNGS OF ELEVATOR 0141 conI ~on/pro/.u
DOORS, FRAMES" CABS hi
600 ad 051 REVIEW" APPROVE ELEVATOR MACHINE ROOM ANCHOR 0141 coni con/pro/au
BOLT SHOP DRAWINGS hI
act 051 DPARE" SUBMIT ELEVATOR HOISTWAY, PIT" MACHINE 0141 coni on/prolau
ROOM SHOP DRAWINGS hI
act 051 REVIEW" APPROVE ELEVATOR HOISTWAY, PIT "MACHINE 0141 coni con/pro/au
ROOM SHOP DRAWINGS hi
603 ad 051 REVIEW" APPROVE CONTRAcrOR DWGS FOR ELEVATOR 10141 onl con/prolau
ENTRANCES bl
604 act 05/ OLLOW UP AND RECEIVE PERMANENT UTILITY SERVICES 10011 conI con/prolut
II
605 ~ 10 51 ~CAVATE, FORM, REINFORCE, POUR "STRIP EXT WALL&; COL 0031 iconl con/abwl
fF'rGS
act 10 51 EXCAVATE, FORM, REINFORCE, POUR" STRIP INTERlOR COL j0031 conI con/sbwl
RXmNGS
607 act IO S{ SET EMBEDS IN SUBSTRUCTURE WALLS AS REQUIRED ~3101SI ic onl con/.bwl
0161
act IDSI ORM, RElNF, POUR" STRIP COL FOOTINGS PIERS 0031 Iconl I:On/sbwl
610 ~ ~51 LAY OUT COLUMN LNES" INTERIOR ELEVATIONS 001{ 'coni l:On/sbwl
act ~51 EXCAVATE, FORM, REINFORCE, POUR &: STRP EXT WALL" COL 0031 Iconl I:On/abwl
611
FTGS
612 act 051 POISON SUBBASE 0021 iconl con/abwl
613 act ~SI BACKFILL INTCOL FOOTINGS" PIERS 002/ ic on/ conJabwl
614 act 051 DRILL AND FILL COLUMN CAISSONS 0021 Iconl con/llbwl
615 act 051 FILLL" FINE GRADE FOR INTERIOR SLAB ON GRADE 0031 coni con/abwl
616
act 051 SET IN FLOOR WORK FOR INTERIOR SLAB ON GRADE 0031 conI con/sbwJ
617 act 051 POUR OUT INTERIOR SLAB ON GRADE 0031 coni con/abwi
618 act 051 ICURE SLAB ON GRADE TO ALLOW CONSTRUcrION TRAFFIC 0031 conI on/sbwl
619
ad 051 SAW CUT SLAB ON GRADE 0031 onl con/shwl
ad 051 SEAL SLAB ON GRADE SAW CUT JOINTS 0031 conI con/sbwl
act 051 BACKFILL EXT COL &: WALL FOOTINGS" PIERS 0021 conI !con/sbwl
621
act 051 [DRIVE TEST PILING" LOAD 10021 conI !con/sbwl
act 051 [DRIVE AND BRACE SOLDIER BEAMS AND INSTALL LAGGING 10 021 coni con/sbwl
624 act 051 RUB EXPOSED FOUNDATION CONCRETE 0031 coni con/sbw'
act OS{ [DRIVE &: FILL STEEL SHELL PILES 0021 conI lcon/abwl
625
~ 1051 ORM. REINFORCE &: POUR FILE CAPS 1D031 I<:oltl !am'.bwl
~ 051 LAY AND PART BACKFILL FOOTING DRAIN TILE 10021 teonl !con/sbwl
act 051 BLAST ROCK AND REMOVE AS REQUIRED 10021 !coni con/sbwl
~ 051 IMOBILJZE AND MOVE DRIVING RIG ON SITE ~021 conI con/.bwl
~51
637 BRACE JASEMENTWALLS FOR EARLY BACKFILLING AS 002f conI con/sbw/
REQUIRED
~51 fMASS EXCAVATE FOR SUBSTRUCTURE WORK 0021 anI con/sbwl
639 act 051 APPLY WATERPROOFING TO EXTERIOR FOUNDATION WALLS 0071 onl con/sbwl
640 !act 051 SET ANCHOR BOLTS IN FOOTINGS, PIERS AND WALLS 0031 anI coltl.bwl
641 act 051 NSTALL WATER STOPS IN SUBSTRUCTURE WALLS AS 10031 conI con/sbwl
REQUIRED
act 051 EXCAVATE, FORM, REINFORCE, POUR AND STRIP GRADE 100 3/ coni con/sbwi
BEAMS
act 051 STABILJZE son 0021 conI con/sbwl
!act IDSI BACKFILL AND COMPACT AT EXTERIOR OF SUBSTRUCTURE 10021 onl con/abwl
WALLS
649 ~ 10 51 LAY VAPOR BARRIER FOR SLAB ON GRADE 10071 conI on/sbw!
ad IOSI FORM, REINFORCE. POUR 6: FINISH CONCRETE TRUCK APRONS 10021 conI con/siw/
657 lad IOSI FORM, REINFORCE, POUR 6:FINJSH CONCRETE SIDEWALKS 1D021 eonl con/siwl
ad 051 FORM, REINFORCE, POUR &: FINISH CONCRETE CURBS &: 0021 conI c:on/siwl
t.iU 11 J:;!(b
669 .act ~Sl ~ONSTRUcr SERVICE AREA ENCLOSURE 002/0031 feonl con/siwl
0041
670
act ~SI ~LEAR &: GRUB SITE 0021 feonl con/siwl
671 act 051 SEET HOlUZ &: VERTICAL CONTROLS 0021 conI con/siwl
672 act 051 CUT &: FILL MAIN BLDG AREA TO FINAL SUB GRADE 0021 ~onl con/siwl
ELEVATION
673 act 051 STOCKPILE EXCAVATED MATERIAL 0021 coni on/siwl
679 act ~SI ~NSTALL CURB CUTS &: APRONS 0021 iconl con/siwl
680
act ~SI ~NSTALL ACCELERATION &: DECELERAnON LANES ON 0021 coni con/siwl
ADJOINING ROADS
act ~SI ~NST ALL TRAFFIC SIGNALS &: CONTROLLERS 0161 coni on/siwl
681
act 051 ~NSTALL SITE DITCH DRAINS &: CULVERTS 0021 feonl !c0n/siwl
682
683 act 051 STRIPE VEHICLE &: PEDESTRIAN AREAS 0091 coni con/siwl
684 act 051 REMOVE EXISTING CONCRETE FOUNDATIONS 0021 coni con/siwl
685 act 051 MASS EXCAV, INSTL UNDERGRD UTIL &: GRADE FOR POOL 0021 coni con/siwl
SPRAYED CONC
act 051 APPLY SPRAYED CONCRETE FOR POOL BASIN 10031 coni con/siwl
687 act 051 FILL &: FINE GRADE FOR POOL PERIM DECK 10021 onl on/siwl
688 act 051 POOR OUT POOL PERIM SLAB ON GRADE DECK 10031 coni con/slwl
690 !.act 051 INSTALL FLAG POLE FOUNDATION 0021 coni con/siwl
691 act 051 FORM, REINFORCE &: POUR TRANSFORMER BASES 0021 onl on/siwl
692 act 051 EXCAVATE, INSTALL &: BACKFILL LIGHT POLE BASES 10 161 coni con/slwl
693 act 051 NSTL &: LAMP SITE LIGHT FIXTURE 0161 onl con/slwl
694 act 10 51 FINE GRADE SITE AREAS TO BOTTOM OF BASE PAVING COURSE 0021 conI con/slwl
695 !.act ~SI EXCAVATE, INSTALL, TEST &: BACKFILL SITE UG GAS LINES 0021 conI con/slwllu
til
~ct 10 51 REMOVE EXISTING BELOW GRADE CONCRETE AS REQUIRED 0021 coni con/siw/de
696
ml
act 10 51 ~NSTALL TELEPHONE CABLE TO BUILDING 0161 conI con/slw/ut
697
II
698 act ~SI EXCAV, INSTL &: BACKFILL SITE ELECT &: TELEPHONE CONDUIT 0161 coni con/slw/ut
II
I?: (,. ?
llaIphJ. StepheftllOlI, P.£. P.c.
Muter Pl'Ojed: Management Check List - d608 -listed by seq, d.Ua type Ie cmpt Consulting Engineer
~51 IEXCAVATE. INSTALL, TEST &; BACI<FILL SITE UG SANITARY 0011 !conI ~on/siw/ut
191 lad 1
SEWER LINES II
~ct ~SI ~CAVATE.INSTALL, TEST Ie BAClCFILLSlTE USDOMESTlC 0021 !conI ~n/slw/ut
\. '7Il2
193 ~ ~51
WATER LINES
EXCAVATE, INSTALL Ie BACKFlLLSlTE UGHTlNGCONDVIT ~1" conI
II
mn/stw/ut
1/
ad ~51 SET TRANSFORMERS ON BASE 0161 !Con! con/stw/ut
704
II
70S ad 051 PULL PRIMARY CABLE AND CONNECT TRANSFORMER 0161 onl mnlsiw/ut
1/
706 ad OS! ORM, POUR Ie STRIP EXTERIOR COLUMNS 0031 coni conlaswl
701 ad 051 pmE &; STRIP CONCRETE CORE WALLS 0031 ~onl con/sswi
198 ad 051 ERECT STRUCT STEEL AND JOISTS 0051 ~on' conlsswl
709 ad 051 PLUMB, BOLT Ie DETAlL STRUCTURAL STEEL It JOISTS 0051 coni con/sswl
711 ~ 10 51 FORM, REINFORCE &0; SET IN FL WORK FOR SUPPORTED ~31 coni con/sswl
CONCRETE DECKS
ad 10 51 GROUT BASE PLATES i0031 conI ~onJsawl
712
713 ~ct fII S1 POUR CONC SLABS AND CURBS ON METAL DECK 0031 coni con/sswl
717 act ~51 STRIP It RESHORE SUPPORTED CONCRETE DECK .~031 !coni on/.swl
i
~NSTALLSHEARSTUDS f0 051 con/sswl
718 !tct fII S1 !coni
719 ~ 051 POUR OUT SUPPORTED CONCRETE DECKS 0031 coni con'sswl
ad ~51 IROUGH WOOD FRAME WALLS AND FLOOR SYSTEM 006' coni con/owl
720
ad ~SI !fORM, REINFORCE. POUR It STRIP CONCRETE SHAFT It SHEAR OOll Iconl ~n's.wl
721
iwALLS TO FLOOR DECK ABOVE
ad ~51 pIKE SUPPORTED CONCRETE DECK TO POST TENSION 0031 Iconl con/sswl
722
724 ~ 051 ORM, REINFORCE Ie POUR CONCRETE COLUMNS 0031 conI con/sswl
act fIIS 1 IFORM &0; SET IN FLOOR WORK FOR SUPPORTED CONCRETE DECK 10031 conI ~on/sswl
72S
~ 051 FURE SUPPORTED CONCRETE DECK TO STRIP ItRESHORE ~031 icon I con/s.wl
726
727 !tel fII S1 [fOTAL STRIP SUPPORTED CONCRETE DECK 0031 ani con/.swl
ad 051 ORM, REINFORCE AND POUR CONCRETE CORE WALLS 0031 conI con/owl
728
729 !tel ~sl [ERECT UGHT GAUGE STEEL WALLS AND SUPPORTED DECKS 0051 onl onlsswl
ad 051 ORM, REINFORCE. POUR It STRIP COLS TO FLOOR DECK ABOVE 0031 onl con/sswl
730
ad ~sl IFORM, REINFORCE, POUR It STRIP CONCRETE SUPPORTED 0031 conI conlsswl
731
DECKS ON WOOD FORMS
ad ~Sl IRUB EXPOSED CONCRETE SURFACES ON SUPPo.RTING ~O31 coni con/owl
732
STRUCTURES
ad ~SI SET EMBEDS IN SUPPORTED CONCRETE DECK 0031 ~onl con/s.wl
733
73(j .a ~S/ NSTALL ELEVATOR FIRE COMMAND ROOM 0161 Ic°nl Icon/usyl
737 act 051 NSTALL DATA PHONE SYSTEM 10161 onl !conillsyl
act 051 ~NSTALL ELEVATOR LIFE SAFETY SYSTEMS iO U /0161 ~onl ~on/llsyl
740
act 051 ~NSTALL '" WIRE GUARD STATION PANEL" EQUIPMENT 0161 onl on/u8yl
741 act 051 [fRAiN STAFF ON FOOD SERVICE EQUIPMENT USE AND 0111 coni con/usyl
MAINTENANCE
742 act 051 INSTALL ELEVATOR CONTROL SYSTEMS OUI conI con/usyt
743 ad 051 ORDER, DETAIL, APPROVE, FAI '" DELIVER EL'EVATOR Ot41 coni con/uy/pr
01
7"
ad !OSI ORDER, DETAIL, APPROVE. FAB" DELIVER EMERGENCY
GENERATOR
10161 conI Icon/llsy/pl
01
745
act 10 51 NSTALL JOB SITE TEMPORARY POWER 0161 I«:onl con/utl/.U
{
746 ~d ~51 INSTALL JOB SITE TEMPORARY PERMANENT POWER 10161 IConl !COn/utl/slt
I
747 ~ 10 51 PROVIDE FIELD WITH FIELD BUDGErS 10011 IConl !cos/conI
748 act 051 IPREPARE FIELD COST, HOUR, QUANTITY BUDGErTARGETS 0011 Ic:onl cos/conl
749 ~ 051 IPREPARE AND MAINTAIN PAST" CURRENT FIELD LABOR fOOll Iconl cos/conI
ANALYSES
7SO act ~SI IPREPARE" MAINTAIN PAST 6; CURRENT ADMINISTRAIVE 0011 coni cos/coni
LABOR ANALYSES
751 ad 05/ PREPARE'" MAINTAIN GENERAL CONDmONS MATERIAL DOt/ 'coni cos/conl
ANALYSES
752 act 05/ PREPARE OVERIUNDER ANALYSIS OF PROPOSALS AND BUY 0011 onl cos/con/pr
OUT 01
ad 05/ !DEMOUSH 6; REMOVE ALL IOOSTING ABOVE GRADE 0021 coni demlcon/s
OBSTRUCTIONS AS REQUIRED itt
act 051 !DEMOLISH AND REMOVE ALL BELOW GRADE OBSTRUCTIONS 0011 conI demlcon/s
AS REQUIRED Itl
755
.a 051 ILOCATE,. REMOVE. RELOCATE,. CAP ALL IOOSTING SPECIAL USE 0011 onl demlcon/s
UTILIllES AS REQUIRED it/uti I
act 05/ LOCATE,. REMOVE. RELOCATE ALL lOOSTING ELECTRICAL LINES 0021 coni demitORls
ASREQURIED Itlutll
757 act 051 LOCATE,. REMOVE, RELOCATE,. CAP ALL EXISTING WATER LINES 0021 conI idemlconls
AS REQUIRED itlutll
ad 051 LOCATE, REMOVE, RELOCATE ALL EXISTING CABLE TV UNES AS 001/ anI dem/con/.
REQUIRED itlutll
759 act 051 LOCATE, REMOVE, RELOCATE ALL EXISTING PHONE UNES AS 0021 coni idem/conls
REQUIRED it!uUI
760 act 051 LOCATE,. REMOVE, RELOCATE OR CAP ALL EXISTING GAS LINES 0021 conI idemlcon/s
AS REQUIRED itlutl!
761 ~ 051 LOCATE, REMOVE, RELOCATE, CAP ALL EXISTING STORM LINES 0021 eonl demlcon/s
AS REQUIRED it/uti!
762 ~ 051 LOCATE, REMOVE, RELOCATE, CAP ALL lOOSTiNG SANITARY 0021 !conI ~emleon/.
UNES AS REQUIRED WuUI
763 ad ~51 DEMOUSH EXISTING STRUCfURES AS REQUIRED 0021 !coni demlsit/co
rtl
764
.a ~51 INSTALL SUOING METAL FIRE DOORS 10081 coni esk/conl
765
ad ~Sl ....AULK EXTERIOR PRECAST PANELS 10071 coni esklconl
~d ~SI INSTALL ROOF DRAINS AND OVERFLOW DRAINS 015/0071 eonl esk/conl
date prillled:12/4/97
Ralph J. Stephel'llOJ\. P.E., P.C
Muter Projed MlIIUIgement Check List - d608 - listed by.eq, dab type '" anpt Consulting Engineer
data cal
.... type mde wk phue Gl\pt
T11 act 051 LAY SINGLE PLY ROOF MEMBRANE 0071 conI
m !ad 051 INSTALL SHEET METAL RooFFLASlDNGS AND TRIM 00'11 coni eak/conl
776 act 051 r--AULK STOREFRONTS AND ENTRIES 0081 coni leak/conI
777 ad ro SI INSTALL STOREFRONT '" ENTRY ALUM FRAMING 10 081 coni leak/conl
7110 let 0 51 NSTALL BUILDING MOUNTED SECURIT\' CAMERAS 0161 conI eak/conl
781 let 051 NSTALL EXTERIOR MAN DOORS 0081 conI e.k/conl
7112 let 051 NSTALL LOUVERS IN EXTERIOR WALLS 0101 conI (15k/conI
783 act 051 INSTALL DOCK SEALS AND BUMPERS 0111 'conI (15k/conI
784 act 051 ~NSTALL BUILDING MOUNTED SECURIT\' UGlITlNG 0161 ~onl eak/conl
785 act 051 APPLY PLASTER TO EXTERIOR SURFACES 0091 onl esk/conl
787 act 051 !SET, AUGN, &; SECURE EXTERIOR PRECAST PANELS 003/0051 anI !esk/con/
ad 051 ~NSTALL EXTEROR HARD CEILING SOFFIT FRAMING 0091 coni leak/conI
788
791
act 10 51 INSTALL ROOF FLASlDNGS &; TRIM 007/ Oft/ leak/coni
795 act 10 51 fAPPLYEXTERIOR INSULATION AND FINISH SYSTEMS (DRYVIT 100'11 conI leak/coni
AND OTHERS)
act 1051 ,-AULK EXTERIOR SASH 10081 conI e.k/conl
796
797
51 CAULK EXTERIOR MASONRY !IIO'11 anI e8k/conl
051 INSPECT &; APPROVE ELEVATOR CAR OPERATION 10141 conI reg/con/us
803 \td
yl
act 051 PREPARE &; SUBMIT SUMMARY CONSTRUCTION REPORTS 10011 conI replconl
\. 804
80S ad 051 iREVIEW SUBMITTAL PROCESSES WITH SUBCONTRACTOR &; 10011 onl !sublconl
OBTAIN THEIR AGREEMENT
dale prinled:12l4llJ7
Jtalph). Stephenaon. P.E., p.e
Millllter Project Management Check List - d608 • listed by seq. data type ok anpt Consulting Engineer
data
•• type IIIq ....... aabjectOJ'--. wit,......, ClllpI
807
808
war 051
ad 05/061
FOL - FOLLOW UP
emp.'
~lo/con/fol
ACTION TICKLER LISTS AS APPROPRIATE mktl
809 ad 051061 OLLOW UP ON CORRECTIVE WORK REQUIRED DURING 0011 con/foil conldo/wa
WARRANTY PERIOD rlfol!
<late printed:12l4/97
Ralph J. Stephenson ,P.E., P.C.
Consulting Engineer
The starting point of most construction related claims is when one of the parties
involved feels they have been harmed in some manner by the actions of
another involved party. Of course there are many variations on this basic
theme. Due to the number, complexity and combinations of circumstances
under which a contested claim may arise, let us first take a specific set of project
delivery criteria and examine the steps that might be followed in resolving a
typical dispute.
Assumptions - The project is a hard money, fixed time job in which the
construction firm doing the work is considered a prime contractor, with a
conventional construction contract with the owner. The owner has had his
design team prepare a relatively complete set of contract documents from which
contractor selection was made by competitive bidding from a short list.
Further assume that at some point in the construction process the owner takes
an action that seems to interfere with the right of the contractor to enjoy a
maximum profit from his construction efforts (sometimes called
maladministration), while, in the contractor's opinion, he is still performing in
accordance with his contract obligations.
To describe an instance where this could actually happen, suppose the contract
calls for completion of the total facility by September 1st with no specified
intermediate dates for owner occupancy of the facility. Part way through the job
the owner makes it known to the contractor that he wants the upper floors
delivered by July 1st, but will still take the lower floors on September 1st. The
owner says this should be at no additional cost to him since the contractor was
planning to be done about that time anyway. The contractor proceeds to try and
accommodate the owner.
Clearly, where the financial and other losses of the contractor, real or imagined,
is sizable, another method of approaching a settlement must be found.
Now, the first step in a formal resolution takes place· making a decision on the
preferred or specified method to use to settle. Usual methods are:
• Administrative settlement
• Mediation
• Arbitration
• Modifications or combinations of the above
There may be considerable variation in the sequence in which the steps are
taken. However at some time in the process each of the following actions must
be considered, and if appropriate, taken. The steps are lettered for convenience of
reference, but are not necessarily listed in the sequence in which they may be
taken.
• Step A - The need for a claim emerges and the parties involved discuss the
matter. There is either a resolution, a decision to pursue the matter further
administratively, or a decision to file for formal action resulting from the
discussions.
• Step 0 - The contractor through his legal advisors, then actually files for
litigation. This is a complex and formal process, a description of which is beyond
the scope of this essay.
• Step E - As the petition for litigation is being filed, the contractor selects the
issues to be addressed that have contributed to the claim, and the level of
documentation he and his technical and legal counsel feel appropriate.
If the nature of the claim is such that many complex and obscure factors have
contributed to the claimed loss, or the proof of loss appears excessively complex,
the contractor may call in an outside qualified and objective expert to help
assemble the documents, the facts and the amounts to be claimed.
contractor.
• Step I - As discovery proceeds, the parties to the dispute should be, and usually
are, trying to agree on an administrative settlement as the various claims and
counter claims statements emerge.
Also, during the discovery period face to face attempts to uncover evidence are
accomplished most commonly by deposition. The deposition consists of
testimony and questioning, again aimed at evidence location. The deposition
period will usually continue over a period specified loosely by the governing
judicial body in the matter.
• Step I - At some point, usually determined by the governing legal body, the
discovery period is declared closed and formal legal hearings now begin. By this
time a selection and settlement on the type of litigation decision making process
has been made. The two most common methods are the bench trial and the jury
trial.
A bench trial is conducted by a judge only, and he makes the decision in the
matter after the hearings have been completed. The jury trial uses a jury of lay
individuals to hear the testimony and to judge the merits of the case.
• Step K - During the formal trial process the parties to the contested claim
page 4 ho 320 Derember 1997
Ralph J. Stephenson ,P.E., P.e.
Consulting Engineer
During the hearing process many people may be called to the witness stand to
answer questions. Those who have given depositions may be closely questioned
on statements made by them during the deposition, particularly in relation to
additional information that has come out during subsequent depositions,
interrogatories or in court.
• Step L - Once the governing legal body declares the trial completed, the case is
closed and either the judge, in a bench trial, or the jury, in a jury trial, retire to
review the evidence, think about the testimony and the evidence, and to make a
decision from the choices presented during the triaL
?-17
Ralph J. Stephenson PE PC
Consulting Engineer
Iechnography
The practice of preparing displayed and structured meeting
notes and related material as discussions proceed
• Overview
Current popular equipment such as the Kodak and the Sharp, use a compact flat
transparent display which rests on the light bed of an overhead transparency
projector, and shows the computer screen image on a conventional projector screen.
3.) A meeting leader who can either accurately type or draw, or have typed or drawn,
the main thought flow of the meeting.
4.) Key people who can participate in the session and produce a desired end product.
The process objective is to generate an ongoing set of notes from which all people in
the gathering can obtain information and to which they can provide input. The end
product of a technography session is a complete, accurate and accepted (accepted does
not necessarily mean approved) hard copy report of the proceedings for immediate
distribution and use.
• Advantages
• Documentation from the session can be printed at any point in the -session,
and duplicated and distributed to the group to permit reviewing material
covered to that point.
• Where there is disagreement about an issue, the entire range of conflict can
be recorded for all to see. Thus points of view that may normally be obscured
are often encouraged and displayed to the group.
The benefit here is that participants know that through such displayed material
there are improved probabilities that the true goals and objectives of the group
will be achieved. Everybody works to the same agenda and from the same set of
notes.
• Ideas are captured while they are still fresh in the minds of the originator.
• Details can be added to earlier topic discussions as the meeting progresses.
• At the close of the meeting those at the meeting know what they and the
others have agreed on and who is to do what.
;-.71
Ralph J. Stephenson PE PC
Consulting Engineer
• Suggestions
Some suggestions to help you to get a good start in using displayed stenography are
given below:
2. Use good hardware and software that allows all participants to clearly view
the screen display.
3. Recommended software for note taking includes one of the standard word
processors such as MacWrite or Microsoft Word. Other word processing
programs that are easily used in technography include outlining programs such
as Think Tank or More. Software for graphic and tabular displays includes ....J
standard project planning, data base, free graphics and spread sheet programs
such as MacProject, Micro File, MacPaint, MacDraft and Excel.
4. If you cannot do the typing, thinking, leading and operational job yourself
the meeting to record the main body of material, while you apply your talents
to the special leadership and display work required by other than the note
taking process.
For example, if you are conducting an initial design and construction project
planning meeting, the various information you might wish to gather could
b. Author of notes
e. Those involved in the total effort - this information and other material
that is revised and updated continually as the project moves along is
usually kept in a general section that is constantly updated to reflect the
latest data available.
g. Documents used for reference in the sessions and on the project Includes
plans and schedules in effect, contract documents currently in effect, special
reports and material referred to in the meeting, and other similar items of
reference importance.
1. Responsibility codes
O. Abbreviations
p. Mission statements
q. Project characteristics
r. Agenda
s. General notes
l) pro - procurement
m) riw - rough interior work
w) t/ r - time restraint
(1) Faces on 20th Street, access to Lohngren on west and Mill Run on east
b) Philosophy
(1) To constantly maintain an attractive, safe retail environment during const
c) Existing enclosed mall shopping center
(1) Built about 1971
(2) Gross existing building area =150,000 sq. ft
(3) Parking spaces = 1,000
(4) Anchors
(a) Travelers Merchandise - general department store
i) Strong store
(b) Robertson Company - catalog outlet
(5) 25 tenant spaces in addition to anchors
(6) Areas presently unoccupied and available for construction use
(a) col. lines 22 to 25/A to D
(b) Col. lines 5 to 6/D to D.5
e) Problems to be resolved
f) Laundry lists
b) 2.02 - Prep smry netwk model for dp1, 2, 3 & 4 to confirm current key dates
f) 2.06 - Prep network models for elect and mech remodeling under dp4
a) 03.01 - Design
(1) 03.0101 - All intermediate design package production dates being met
(2) 03.0102 - Need cost data on alternate roofing details for dpl
b) 03.02 - Construction
b) 06.02 - Carlsbad agreed to review T & J sub prices & release appvl promptly
(1) 6.0301 - For names 1st letter of 1st name and 1st two letters of last name
(2) 6.0302 - Traditional abbreviation to be maintained
03. Clearly identify at the beginning of the form, who originated the form and to
whom it is addressed.
04. Provide a date prepared, date sent and date received space on the form.
06. Provide enough space to record the information needed. If the form is to be
handwritten it will require more space than if to be typed.
02. Briefly describe what the form is to accomplish - what is its mission?
04. Review description & rating in steps 1,2 and 3, and determine if form is
truly needed. If not don't prepare it.
05. If form is needed, list, at random, all information items needed to fulfill the
mission.
10. Prepare a dummy of the form, make copies and test it a few days in actual use
if at all possible.
Be certain to explain its purpose and use.
11. Revise the form as needed and have it printed, padded and put into use.
12. Revaluate the form regularly for improving or for discard when no longer
needed.
Situation #3 - General contractor - As the project manager for the general contractor
on a new 5 story office building you are responsible for keeping the official
construction meeting minutes at job meetings with the owner, the
architect! engineer and the major sub contractors. You feel it might be well to devise
a standard form to use for each meeting so you are certain to include all the agenda
items necessary to cover at each meeting. Design an outline form on which you
could hand write the minutes directly and efficiently for later typing by the field
office receptionist.
ho 2% December 1997
RalphJ. Stephenson, P.E.
Consulting Engineer
communications so you can operate effectively. Design a form that will indicate the
proper flow of information between you and the other parties where owner input is
essentiaL
Situation #6 - Pesip bulld - You are the vice president of operations of a moderate
size design build firm. The company is being asked with increasing frequency to
evaluate potential sites that might be available to your clients and prospects for
building, or to you to add to your own property portfolio. Design a site survey and
information form that will give you the information needed to quickly and
thoroughly locate a site with given characteristics and allow you to quantitatively
evaluate its value for a given use.
You are a developer currently building a small residential subdivision containing 15 single
unit homes. Your firm, Newland Estates, is a quality developer of residential properties
averaging about 200 living units per year put in place. You market the properties as they
are improved.
This current project of 15 homes is a high priority program since it is the first of several
hundred modest two story colonial homes you intend to put on a recently acquired site. The
site work for the first part of the development was completed about 2 months ago and you
are anxious to get the first 15 units built and sold to help your cash flow.
The individual units occupy lots with dimensions of about 120' x 400' each. The houses are
2 story plus full basement with a footprint of about 35'x40'. Taps for utilities are to the
The houses each have a moderate sized front porch, a 10'x20' patio at the rear, a two car
garage and a full apron driveway from the front to the garage at the rear.
The structure is conventional stick framing with prefab wood roof trusses. The exterior skin
is board and insulation with brick veneer at the first floor and wood sheathing at the
second floor and attic space. Exterior sash is pre glazed and all exterior millwork &:
Interior finishes are conventional with gyp board ceilings and walls painted or textured.
Most light fixtures and mechanical trim are surface mounted. Floors are generally finished
Basement areas are unfinished. The furnace is gas heat with cooling and heating air
The houses are fully landscaped and ready for owner move in upon completion.
Because of the key position of the early units you wish to plan their construction well and
sequence them on a clearly defined tumover cycle of one unit per week. All permits have
been obtained, most materials are either on site or available and the area of the first 15
- About how many working days should construction of one unit take?
- What is the implication of a turnover cycle of 5 working days on the crew sizes needed?
P: 91
32323103333 4
1113 1/141/15 1/181/19 1/191/25 1/271/28 2/1 2/2 2/5
3 0
I 02·Z I I 05·A I I 07·B I I 09·S I I 11·V I I 15·0 I 2/5 2/5
111
1/18 1/191/20 1727 2/2 2/4 2/5 2/10 '\..
o 7 /3 4 2~0 2 2 3 0 3 ~ 2
ua 1/12 1/13 1/18 1/21lt28 1121 2/1 2/3 2/8 2/10 2/11 2/12
-..
I 01·T/R TO I 1r----,0"",3-=.T,..--.... ,-.--:-,0:::"".-::u~-,1 1ft 12-0 I 1 16·F I I 19-H I 21·Q
START OF
PROJECT
'\~3
1121
1 0
1/131/14
,5
f/281128
1122
2/5 21 2/10 2/11 T12
~~5 4
2/18
--.
04·L 06-C 22-M
~
'-Il 1/13 m31/n 1/211/22 1/22 718
~ 3 3
2/3 2/4
1,...·-....>.'"""'18:::"".":'.:x--'11. . .- ""2""O.-:'N:----'
D
41 46
41 47 NETWORK MODEL
43 48 Issue ##1 - January 13, 1998
44 49 FOR EXERCISE #2
45 50 Latest Start Latest Finish exercise ##2
WEX PM 99 Project Team
Ian 01
ban 11
ACTIVITY LEGEND
Ralph 1. Stephenson P.E.
Consulting Engineer
323 Hiawatha Drive
Note: Mt. Pleasant, Michigan 48223-9096
Float time shown in this network model is for the sole use of
the WEX PM 99 project team. Use of float time by others
is to be only by written permission of the WEX PM 99 team Sheet #1
bo #517 management
l l l
RALP1I J. ST1I:PBJeN80N, P. E.. P. C.
MIND PROBER OO• •'CT&/I'DI'G ~GDI • • •
Agree Disagree
Talkative - chatty, always speaking
Egotistic - self-centered, individualistic
Empathetic - aware of another, compassionate
Apprehensive - fearful, worried, afraid
Unconventional - unusual, not the norm, rebellious
Kind - gentle, considerate, warmhearted
Rigid - still, unchanging, inflexible
I Impatient - excitable, unable to wait
Sympathetic - comforting, understanding
Reserved - restrained, self-controlled, shy
Adventuresome - daring, willing to take chances
Uncaring - lacking in warmth or sympathy
Quiet - still, silent, not talkative
, Sarcastic - joking in a biting or cynical way
1 Concerned - aware, caring, interested
.
! Distant - remote, inaccessible, removed
I Competitive - seeking to win, ambitious, achieving
i
Apologetic - sorry, regretful, makes excuses
OutgOing - sociable, friendly
I Independent - self-reliant. autonomous
! Sensitive - perceptive, touchy, nervous
Meek - humble, submissive, patient
I Meticulous - extremely careful, scrupulous
I !
Suspicious - doubtful, distrust, uncertainty
I Fun-loving - playful, carefree, spontaneous
Help-seeking - looking for assistance or comfort
! Charitable - generous, kind, giving
Neighborly - friendly, amicable. familiar
Achieving - accomplishing, persevering, striving
Approval-seeking - wanting acceptance and praise
Self-blaming - guilt, fault finding
Precise - clearly defined, exact
-o Guarded - kept safe. prot~cted, watched over
f Carefree - free of worry or responsibilities
Dependent - needing aid or assistance
Comforting - soothing, relieved, consoling
Hlo 2Sj
Pg. 1
11m PROBER RALPH J. STEPHK:f80N. P. E.. P. C.
OoaraVlll'Dro c.onulI••
Agree Disagree
Affiliative - associated, connected
Ambitious - enterprising, striving, eager
Status-conscious - attentive to position and wealth
Humble - reserved, self-conscious, modest
Accurate - correct, clear-cut, beyond doubt
Defensive - protective, shielded, careful
Joking - witty, wisecracking, jesting
Defenseless - unguarded, unprotected. needing shelte
Consoling - solace, to cheer up
Hospitable - welcoming, warm, receptive
Goal-oriented - seeking success and achievement
Seeks Attention - wanting to be noticed
I Obedient - compliant, amenable, dutiful
!
Responsible - accountable, trustworthy
Wary - cautious, watchful, on guard
Playful - impllsh, mischievous, frivolous
Trusting - confident, committed
Protective - defended, guarded, careful
J
I
I Loyal - steadfast, faithful, devoted
•
! Striving - contending, exerting effort
Seeks Recognition - wanting to be praised
Yielding - deferring, relenting, gives in
Tidy - neat, orderly, clean
S~cretive - covert, underhanded, concealed
I
!
Pleasure-seeking - seeking gratification or delight
I nsecure - inadequate, unsure, shaky
.
Nurturing - nourishing, supporting, fostering
I ndividualistic - one-of-a-kind, independent
Accomplishing - successful, to bring to completion
Socially Striving - seeking respectability
H/o 25;
Pg. 2
SECTION 9
University
This sampler consists, first of a short essay on "Use of Float Time in Project Planning",
followed by a series of 11 other essays on various planning, design and construction
subjects. The hope is that you or any of your professional associates or friends will use
this material for the benefit our respective professions -- but I request users to please
give the authors credit.
Of course, I'm always happy to hear from you, so please don't hesitate to drop an e-line.
Cordially and sincerely, with hope that you'll respond
Table of Contents
Introduction and Table of Contents................................................ pages i to iii
Dear Friends:
Happy Millennium! (For men it starts this year; for women, next).
I'm offering a small sample of what I'm thinking about with a short essay on
"Use of Float Time in Project Planning." The idea is that anyone may use this
material for any reason so long as it benefits our professions but I would like
users to give the authors credit, please.
Of course, I'm always happy to hear from you, so please don't hesitate to drop
me an e-line. Cordially and sincerely (with hope that you'll respond)
What is float time? It is a number of working days determined by the total plan of
work, and mathematically set by the logic of the network plan, by the durations
assigned to each task, and by the completion date set for the project and its component
parts.
Float is the amount of time between the earliest date an activity can start, according to a
given plan of work, and the latest date it can start according to the same plan of work.
Float time occurs in a task when the activities that restrain it are able to be completed
before the latest date by which the restrained task must start, as determined by the
latest allowable finish date of the project or project component.
Float time is not assigned by the planner, nor is it automatically allocated to activities
that are traditionally critical.
Because of the nature of the construction business in which many normally unrelated
organizations and individuals are brought together by agency and contract
arrangements to do a job, float or discretionary time is potentially valuable to all parties
to the job. Thus ownership of float time often becomes a subject of dispute and
controversy.
A few guidelines which have seen general acceptance and some legal concurrence in
practice are given below:
1. In a hard money fixed time contract the float time within the contract boundaries
belongs to the contractor.
2. Ownership of float time should be established very early in a project. Where some
question of ownership exists, the ownership rights should be noted on the plans and
schedules of work prepared by the contractor.
3. On negotiated projects, where there may be a cost and time span to be mutually
agreed on by the contracting parties as the project gets under way, ownership of float
time is usually a matter to be worked out in advance as job conditions demand.
4. Relative to subcontractors, the ownership of float time within a hard money, fixed
cost subcontract is usually set by implied consent, but normally rests with the prime
contractor under which the subcontractor is working. In situations where there is very
little interface between a prime contractor's tasks and his subcontractor's tasks, it is
possible that ownership of self contained float may remain with the subcontractor.
5. Ownership of float time does not release a contractor from the obligation to provide a
high quality service to the client. Where poor use of float time to the detriment of the
job is encountered, fault for the poor performance will usually temper the ownership of
the float.
* * *
In general most problems with float occur where approval delays are encountered,
where intermediate project dates are not specified but are desired and imposed, when
poor performance pushes tasks beyond scheduled end dates, or where uncontrollable
obstacles to meeting project contract obligations appear.
Control of the span of management is one of the largest and most serious
problems encountered by the emerging manager. He or she so often feels
able to manage the world, but, in truth and practice, these individuals are
delegating that operation to those within their span of management who they
can influence most effectively. That span of management can be anywhere
between six and thirty, depending totally on the amount of interaction
expected among those being managed.
Let me know what you think about this ...write me if you've experienced it
yourself. Those other Construction University students (an elite group)
receiving these essays might well like to hear your story. Send it to me and
we'll see what happens. ...After all Construction University is the locus of
common sense!
Span of Management
-- 1299 words December 30, 1999
-- Reading time approximately 6 minutes
Carrie is a very bright lady, a university graduate with writing, publishing and
management skills and aspirations. A year ago Carrie accepted a very responsible
position with Xeno Development. Xeno is an international urban planning, design and
construction firm specializing in the development and ownership of integrated
commercial enterprises and related sports facilities.
Her immediate superior, Helen Ralon, vice president of staff operations, immediately
spotted Carrie's talents and gave her a clearly defined departmental management
assignment including responsibility for publishing the monthly Xeno newsletter for
commercial and sports facility owners. Current staff of the department in addition to
Carrie was two full-time writers, one proof reader / graphic designer and one computer
operator.
Carrie quickly assembled this group into a effective team whose performance was good
enough to lead Helen to add another supervisory task to Carrie's assignments-
preparing all proposal letters for presentation to prospective clients. Carrie was
delighted by the challenge, and soon hired, with Helen's support, two additional
engineering and architectural professionals to provide technical strength to the
operation.
Helen soon noticed that Carrie was spending more overtime, was looking tired and
harassed; she also was losing her normal good natured rapport with others. Most
seriously, her work quality and management abilities were visibly deteriorating.
After some serious thinking, Helen decided Carrie's problems might stem from a too
rapid and too-large expansion of her span of control. This very common ailment affects
many managers today, and the failure of them and their superiors to recognize the
problem is often the cause for promising careers ending up in frustration and failure.
Continued later. As to the details - read on!
Span of management can be defined as the number of people whose activities you are
able to manage and supervise by relatively continuous contact. Relatively continuous
contact is direct communication on a day-to-day basis that allows you to evaluate
performance at desired and needed intervals. Usually, direct management implies a
closely spaced geographic relation to those being managed.
1.) The degree of need for those you manage to communicate with each other.
2.) The amount of time required to be spent by you with each of those you manage,
and
3.) The effort required of you by your subordinates to assist them to work well with
those outside your direct management system.
If there is a large degree of intercommunication between those you manage with each
other, and with you, an effective span of management is usually limited to from four to
six persons. Where there is little or no intercommunication among those under your
direct management, you may be able to manage 20 to 30 people. Such a number is not
arbitrary: many years ago social scientists studied Sear's stores' middle management.
The Sear's researchers found that where department managers had little if any contact
with each other that store managers could properly handle the responsibility for as
many as 30 of these isolated managers and still be profitable and effective.
If two-way links must be maintained among you and among your subordinates within
a managerial span of control of four, you are now managing 20 paths. Still not too
many, provided anyone link or set of links does not require excessive time.
If you are managing 20 people with links limited to one from them to you and none
from them to others, you are only managing 20 x 2 =40 communication channels. If
you must manage total linkage among 20 subordinates you will find yourself trying to
keep in touch with so many communication channels that you never can gain
permanent control of the management process.
The span of management has many historical precedents that have repeatedly proved
the difficulties in trying to directly manage too many people. One of the earliest
examples of formal span of control analysis is found in the Bible. Exodus 18:12 - 27 tells
of Jethro warning his son in law, Moses, that he has stretched his span of management
too far and is in danger of losing control of the Exodus mission, leadership, and quality.
Military management for thousands of years has proven that careful attention must be
paid the span of control to maintain safety and effectiveness of troops being managed.
Today's managers in all fields of construction (for example Helen and Carrie in our case
study) find their span of control measurement is far more complex than that of the
traditional internal manager. This is primarily due to the need for the manager in
construction to be responsible for, and have authority over, many parties outside the
organization. In addition he or she often does not have strong, well-defined, formal
organizational clout and must exert direction through technical excellence, persuasion,
fairness, firmness and good judgment.
This is possible for the experienced and excellent manager, but is hardly ever achieved
by the emerging manager without help from his or her superior management staff and
the company executive staff.
Keeping the span of management to a controllable size is the responsibility of both top
and middle management, both the managed and the manager.
* >I- >I-
Carrie needs to groom one or more of her subordinates to manage some of Xeno's
operations, allowing Carrie to be most effective on the heavy-hitting projects while
permitting her to keep her hard-won authority (and responsibility).
The following essay is the result of my participation in a seminar by the Michigan and
Detroit chapters of the Associated General ContractorsJ entitled AGC
Student/Contractor Awareness Night (SCAN) in October of 1999. My friend Dick
Brunvand of the Michigan Chapter of the AGC asked me to expand on my panel
comments. This brief essay is the answer to his request.
As alwaysJ the materials from the Construction University are for your use as long as
that use is intended to benefit the professions. It would be niceJ too, if you give the
various authors credit as you reuse these materials.
1405 words
approximate reading time =10 minutes
Are you ethical? -- Am I ethical? -- Are they ethical (and who are they, anyway)? The
professional designer and constructor face these questions and dozens of others related
to behavior day in and day out. We'll assume you are ethical and let's assume I am, too.
But do we mean the same thing? Will we use the same criteria in an ethical situation
that involves both of us? Can you see the need for both of us to share a definition?
J'If language is not correct, what is said is not what is meant: What ought to be done
remains undone: Morals deteriorate: Justice will go astray: And the people will stand
about in hopeless confusion."
Civilizations and their disciplines of good, evil, moral duty and standards of conduct,
commonly called ethics, are faced ultimately with hard decisions about what they
believe in and what they wish for the future. Similarly, the design and construction
professions face the need to transfer into words and deeds what is healthy to believe in
and what is healthy to do. A very simple anecdote illustrates the principles of proper
behavior in a startlingly clear mode as presented in the world of words. Let us call this
story the "Case of the Invisible Sprinkler Lines."
A young journeyman sprinkler fitter named Fred, just 22 years old, is working on a
medium-sized school job in Lansing, Michigan. Fred's approved shop drawings show a
sprinkler main running above the ceiling from the riser to the branch line in a small,
enclosed storage area on the first floor. Two sprinkler heads are to be located in the
storage room.
Fred has found sheet metal ductwork and water piping that interfere with this line,
making it difficult to install without redesigning the sprinkler distribution system. Fred
flags down George, his supervisor, and asks him what to do. George, a seasoned
tradesman and field manager with almost 30 years experience looks over the situation
and tells Fred -- 'forget the runs and just install dummy heads in the storage area after
the ceiling is in. Nobody will notice it or check it anyway. Arguments with the owner,
the architect and the engineer about who's going to pay for correcting the interferences
Fred disagrees but does not have time to voice his feelings because George is already
The president of Fred's company, Tom Halstead, happens to be at the project for a job
meeting. Fred sees him some distance away as he is told by George to ignore the
interference. George has left the area without seeing Mr. Halstead, and the president is
walking toward Fred, obviously with the intent of saying hello and seeing how things
are going.
What should I say, if anything, to Mr. Halstead about the sprinkler heads?
This, in miniature, is what many of us encounter as we try to make ethical, moral, and
civilized decisions about the problems and temptations facing us in our personal and
on-the-job lives.
There are some easily applied systems that can help you arrive at quick but sound
ethical decisions. For instance, the three-question technique proposed by Kenneth
Blanchard and Norman Vincent Peale in their book The Power of Ethical Thinking
suggests you answer three questions:
1. Is my decision legal?
• Does it violate civil law or company policy?
2. Is my decision balanced?
• Is it fair to all concerned in the short and long term situation. Does it avoid sum-zero
situations? (In a sum-zero situation there is a winner and loser with the winner taking
everything the loser loses.)
In Fred's situation the legal answer is apparent. Doing what his superior, George,
suggests is clearly a violation of the law and probably of company policy. Further, a
decision to install the dummy heads is a disservice and a danger to those who must
occupy the completed school.
Installing the dummies creates an automatic adversarial situation in which there are
losers: those using the building and depending on the life-safety systems. There are
dubious winners: the contractors on the job. There is another loser, Fred. He will
probably lose his job unless he can think of a way to a winning solution, one in which
all parties win.
The third consideration is more complex and personal but is probably the easiest to
answer. Your feelings are best known to yourself, and your answer will mirror your
ethical capacity to exist in a working group that values a high trust of others in that
group.
We have seen in the sprinkler story an example of the formal ethic where Fred's
refusal to install the dummy sprinkler heads is readily recognized as ethical by the law
and by well-accepted standards of good conduct.
Blanchard and Peale are superb as far as they go, but for those of us in the construction
professions there is yet another form of ethic: paramount respect for public health,
safety, and welfare. As an illustration consider a situation where life safety is at stake
and you must make decision in which only the end result is the measurement of ethical
performance. For instance, suppose that you, as a project manager on a busy highway
job, must suddenly shut down a critical interchange at morning rush hour due to an
unexpected gas leak. The end result -- a safe journey for the users - will be the final
criterion of ethical action, rather than the shut down and its delay to motorists at the
start of the work day.
In our second example above situational ethics determine what rules of law and
behavior can be safely broken to arrive at course of action that at its completion is
considered ethical. Here is where professional designers and constructors must be at
their best. Perhaps the most reliable and straightforward ethical guidelines I have
received were those given to me many years ago by Clement Freund, Dean of
Engineering at the University of Detroit. I had asked for his guidance in considering a
structural design revision that in my opinion could be safely done, but would possibly
violate a required code. He told me about a simple test of ethical priorities, and how to
apply it to actions that must be taken as we make ethical decisions. IIYour actions",
Dean Freund said, IIshould be given the following order of consideration:
• Your first priority is -- to protect the health, welfare and safety of the public.
• Your second priority is -- to protect the interests of your client or employer.
• Your third priority is -- to protect the interests of your peers.
Although there may be no single acid test of ethical, moral, and civilized behavior, the
considerations outlined above certainly contain the essence of generally accepted civil
and professional action to achieve such behavior. Their incorporation into your
thinking and reasoning in design and construction matters will give you added
confidence in the validity of your design and construction choices.
Regards,
- 1,623 words
-- Approximate reading time - 8 minutes
(Every man and woman is satisfied that there is such a thing as truth or they
would not ask any questions - paraphrased from Charles Sanders Peirce>
Over the years I have been impressed by the amount and quality of information some
professionals in the design and construction business are able to acquire in a very short
time. After much watching, listening, reading and thinking I have concluded that this
information is a direct result of their use of a talent. .. the talent of intelligent
questioning. Part of this talent grows out of a sincere interest in what others think; the
other part is learned.
used.
This event happened several years ago on the construction of a large discount
store in Chicago upon which I was engaged as a consultant. My responsibility
was to regularly inspect, evaluate, and report on construction progress of the job
to the owner.
The general contractor's field superintendent on the job, Linton (not his real
name), was originally a farmer, and a good one. He had earned an architectural
degree from an excellent Midwest university and had received his professional
architectural registration. Linton had learned, as do many farmers, to keep his
mouth shut except when he added value by opening it.
I came to the job about nine o'clock in the morning and checked in at the field
office. Linton was occupied but told me to go ahead and tour the job and he
would catch up later.
Site grading was in work for a major share of the parking areas and the
foundations for the building were substantially complete. I noticed that building
work and site grading were meeting planned dates between early and late starts
and finishes. However, several trenched utility excavations were standing open
and empty.
It was not a serious schedule problem at the time, but with wet, cold weather in
the forecast, the open excavations might force a site-work cost overrun for my
client.
Linton caught up with me just as I was heading back to the shanty to review job
progress with him. On our way I asked--"Linton, do you have all your building
permits," knowing that Linton, an ho:nest person, would quickly explain why he
wasn't installing site utilities in the open trenches. However, Linton responded
with a terse one-word answer: "yes."
trailer. Once in a warm and relatively comfortable work place, I said to Linton,
"If you have all your permits ... and knowing from my inspection that you have
the underground pipe and conduit on the job ... why aren't you installing the
Linton told me quickly and impatiently that I had asked him if he had all his
building permits--not all of his construction permits. He said he did have a full
building permit, but that his site work permit was still pending and would be
So, Linton felt that he would have been lying--and rightly so--if he had told me
The lesson learned: Don't ask the Lintons of this world a yes or no question
unless you are totally satisfied that a yes or no will provide you with all the
correct information you need. Linton had given me a right answer to a wrong
question.
Questions stimulate the mind. Most active, interested people love to answer a
professionals, must understand that although there are fifteen or twenty kinds of
questions in common use, most of these are either open or closed. This two-part
choose to ask.
*A closed question is one that can be answered with a yes or no, or with a simple
statement of fact:
narrow down a group to those individuals who probably know something about
a particular subject.
.. An open Question is one that cannot be answered with a yes or no, nor with a
topic.
Notice the question is devoid of specific details. Instead, Fred has allowed the
audience members to provide their ideas about what he is asking. This
stimulates the group to supply their own interpretation about what Fred wants
and to give answers that will help direct the discussion into more specific
channels.
Lisa raises her hand, answers "yes" to Fred's closed question, and begins to
converge the discussion by asking Fred another closed question: "Are you
looking for experience with interior design narrative programs for facility
support areas?"
Others who answered Fred's opening question are now also asking both closed
and open questions to further narrow down what it is that Fred is really trying
to find from the group. At the same time, Fred is gathering information about
the people who will probably prove valuable as he makes design-team
management assignments.
permanently:
.. Their proposal includes several options we want but you have excluded - can
.. What does the group think about design/build? Tony, how about you?
.. What do you mean when you say we should start our cost estimates by
.. Are you aware of the business risks you are taking with our client by using
.. When did you first realize how good that glass system really was?
... How has the use of commissioning improved your project costs?
respective offices?
This is by no means an exhaustive list of the types of questions that are out there
and there will be more to follow in the next Construction University paper.
As always, your input and questions are welcomed! I'd especially like to hear
about any times when your questions led to... hmmm ... interesting answers.
Here are some references I suggest if you want to know more about questions
and questioning:
The Nine Master Keys of Management by Lester R. Bittel - McGraw Hill Book
Company
He and I have been looking at the makeup of our classes at the U. of W. for many years
and we agreed about four years ago that Phil should write a paper with his views of a
peculiar phenomenon--the existence of a hole in the age spectrum that had certain
characteristics, and, within some groups, had produced a vacuum in information
transfer. You can read all about it below.
The essay is long and meaningful, meant to be read at your leisure. And, naturally, we
hope you will send your comments.
This essay is the fifth in the Construction University series. If for any reason you did
not receive and want any of the earlier mailings, just let me know. Here's what we've
sent so far: Float Time (CU #001), Span of Control (CU #002), Ethics (CU #003); and
Using Intelligent Questioning (CU #004). As well, if you would like to address an
essay to this audience of dedicated professionals, drop me a line.
Cordially,
Century?
by Philip M. Bennett
Architect and Professor
University of Wisconsin
~ -5,338 words
-Approximate reading time =25 minutes
The construction industry is presently undergoing a change in the experiential
backgrounds of many of the members of its professional work force. u.s.
demographics and insurance studies show that as we neared the year 2000
approximately 60 percent of the experienced work force in America would be retiring.
The legendary construction professionals who had many years of technical skills are
now retired or retiring. The magnitude of the knowledge base being lost to retirement
has yet to be realized. Many individuals who are retiring after 40 or 50 years of
experience will take with them several critical areas of information necessary to
maintain continuity and the integrity of the departments that they leave.
Their leaving has created a void ... a gap. Somebody--many somebodies, actually-- have
to fill it, but how can we remedy the lack of preparation that accompanies new
members of our fields? Even more serious, there is now a lack of people in the 35-45
year-old age range ... a time, traditionally, when many construction professionals were
moving into middle management. It is these people who would have been training
new entrants to the professions and these same people, historically, would be getting
A host of issues--the high costs of construction, limited time for training, and larger
construction demands--have opened this gap and it's up to us--those of us who are not
yet retired (even some who are but remain active in the professions) and who can see
the problem--to address the issue. My hope is that everyone in the construction
industry will reevaluate organizational and individual deficiencies and then direct
training efforts toward improving industry performance.
The Problem
The gap hasn't happened all at once. We've been watching during the past twenty-five
years as economic and time constraints have pushed many organizations and
companies to place less emphasis on training and mentoring to replace a growing
number of retirees. Add to all that, with the onset of downsizing, rightsizing, and
company buy-outs, many individuals have been forced into alternate career paths that
have limited the depth of experience they might have gained by staying in just one
position. This fragmentation in training has produced large numbers of individuals
who have limited skills in the specialty and general areas needed to satisfy the needs of
the construction industry.
Major changes in construction and related manufacturing sectors in the 1980s have
further reduced the number of midrange-age individuals in the work force. As a result,
middle management has been decimated. We now are feeling the effects of limited
leadership to take over many organizational programs. There is little discernible
leadership continuity in the overall work force coming from the Gap Group - and
that's something we desperately need.
Let's start by taking a closer look at the reasons we face this problem:
Seemingly, organizations are no longer willing to train individuals in the basic skill
areas required for success of their projects.
As we've seen a downturn in training numbers, we have also seen an increase in the
number of construction problems and deficiencies resulting from poorly organized and
inadequately written legal documents. Basic technical skills are still required to
successfully solve construction industry problems.
Automation Technology
During the mid-1970s and through the 1980s, automation technology was implemented
in a number of organizations and companies across the U.s. As the automation world
developed, more and more companies became proficient in many applications
associated with their production activities. The automation world became a part of
everyone's life and proficiency and production has increasingly affected the overall
structure of the work force.
Economics
During the past 15 years, many organizations and companies have been faced with
cutting overall production and operational costs. The need to reduce costs has greatly
affected the work force and many individuals in upper and middle management.
Realigning staff to meet production needs while cutting costs has tended to decrease
the number of individuals in the middle-age range of the work force.
In an effort to reduce production costs and realign with public needs, many companies
have been downsizing in an effort to cut costs in addition to realigning their staff to
meet overall demands.
For some organizations, this has been termed as a process of rightsizing the production
staff to meet the goals of the organization while serving the overall marketplace. These
Specialization
As our world has become more complex, many disciplines have become more
specialized. Larger projects, more sophisticated automation technology, construction ,J
technology change, and the overall demands for production have created a demand for ...."
individuals who specialize in their educational and experiential development. An
individual no longer comes into an organization and works through a whole series of
areas before reaching a high level within the company. It is now difficult to find
individuals who understand a process from beginning to end; that's a radical departure
from past practice.
Worker Mobility
During the past 15 years, many changing job opportunities and downsizing have
caused the work force to become more mobile, thus producing fragmentation of
learning experiences. One now finds very few individuals who have had a long-term
continuity of learning within one organization. Individuals tend to spend only a few
years in a particular learning experience before moving on to some entirely different
job. Such mobility amplifies the fragmentation of experience. The gap in educational
and experiential backgrounds is increasing at a rapid rate because of mobility and
limited job tenure opportunities for continuity in the organizational structure.
Temporary Attitudes
We no longer find organizations that have a family-type work force of long standing.
Tenure on a job tended to strengthen the quality of production--the overall attitudes
being positive and the final product one that pleased the public. Many individuals
have acquired an attitude that "I'm only here for a short time, so my experiences will be
limited by my exposure to the company or organization." These attitudes tend to
decrease the valuable experiential gain from exposure to limited processes within the
organiza tion.
As a result, we find many companies and organizations that are constantly dealing
with new people to train who have limited backgrounds and understanding of overall
organizational goals. When the individuals in the work force reach a certain point, they
decide to quit and move on to another organizational structure thus causing major gaps
within the continuity of the work force. Production goes down while the quality of the
product also goes down. The customer ends up the loser.
During the past 10 or so years, many organizations have altered their planning process
from long-range to very short-range, and, in many cases, day-to-day.
This shift results in reduced training, reduced employee allegiance to the organization,
and undermines the good features of longevity. Many individuals know from the
outset that their jobs will only last as long as the projects are funded. With many
organizations working on a project-by-project basis, it tends to cause a fragmentation of
the learning process and produces a sense of insecurity on the part of the worker.
Lack of continuity in the work force, a loss in the experiential base through retirement,
and the mobility of the work force have caused many organizations to place little
emphasis on the historic database necessary to make improvements and refinements to
their overall production process. The expected results can be more trial-and-error
decision-making activities, greater risk to the owner-clients, and repetition of many
mistakes. The end result will be higher costs, lower quality, and reduced fulfillment of
user needs.
Surveys have shown that few organizations are taking advantage of their history ... that
is, using their historic data as a basis for decision making. Lacking a strong information
database will create major gaps in training and experiential backgrounds of their
employees (especially new employees). The weakness in limited informational
databases of historic data will result in higher cost decision-making while at the same
time increasing and magnifying the risk of poor decisions being made.
As a result, many companies face more down time in bringing new people on board
and in bringing them up to speed in their job performance. Therefore, it is becoming
very important to develop career-path training and good exposure to field mentoring in
an effort to reduce training costs while improving the future production from the
employee.
altered their career development programs that were considered basic and essential in
maintaining skill levels. With a lack of continuity in training, hiring and developing
career-path programs, the nation will be faced with increasing cost to achieve the
quality expected by the general public. Random surveys in professional development
programs indicate the gap in age range and experience hinders continuity in expertise.
Informal class surveys of professionals in many fields and representing many different
industries have indicated a major gap in the age range of their employees and also in
the experience base for future leadership. Fellow workers and employees agree that the
United States is facing a major problem in developing strong continuity in leadership
and decision making because we do not have good continuity of training within most
organiza tions.
Experiential Deficiencies
Are your projects getting out of hand? Are there to few people who know what needs
to be done to bring the project in profitably? Are bad decisions being routinely made
without being recognized?
With older generations retiring, the experiential level within an organization declines
rapidly. This decline leaves many deficiencies in the potential for management,
procedural activity, and overall technical experience to effectively solve critical
problems. With a major gap in the middle-aged range and experience level, companies
must search for younger people to pick up the slack, and in many cases, to bring back
retired individuals as consultants. If not filled, the educational and experiential gap
will cause the overall quality of decision making and leadership to decline rapidly.
Limited experience in the project management field has already caused many projects
to get out of hand with very high cost overruns and major losses to owner-clients. We
can attribute this to the decline in leadership and judgment that has accompanied the
replacement of experienced project managers with those who are much less
experienced. As a result of the lack of quality education and good experiential
backgrounds, one finds the leadership and decision-making in question.
Surveys taken over the last several years in a professional developmen t program
focusing on contract documents shows a steady decline in the quality of these
documents. The number of errors, deficiencies, and overall problems associated with
many construction projects tends to be increasing rather than decreasing. Also, fewer
people are able to judge whether documents and reports are sufficient; they just don't
know! Our surveys have shown that this decline is continuing to grow at a more rapid
pace as we move into the 21st century.
As these programs were dropped, there was an increase in the number of problems
associated with development of construction documents the actual project construction
in the field.
For those organizations that have already recognized the problem they will have the
l
advantage of an early recovery, which will allow them to still select from a greater
resource pool of skilled individuals. Those organizations that have not recognized the
problem and are hoping everything somehow will be resolved will face greater
problems in the future because they will have fewer people to select from to create
strong production and administrative programs.
result, many organizations suffer from discontinuity in age range and shallow
experiential depth.
Surveys have shown that an employee can be advanced three to five years ahead of his
or her underdeveloped capabilities for problem solving simply by attending continuing
education programs. Sharpening skills through both formal and informal training can
add great value to an organization's experiential base. Professional development
attendees have indicated that some programs can give them educational insights to
help them solve problems that would have been far more costly to resolve if they had
not attended a continuing education program. Personal discussions with employees
and informal surveys have shown that companies active in internal and external
training programs have generally operated with a higher level of success and have
produced more quality projects than those who have not encouraged employee career
development.
Improve Mentoring
Careful planning and staff organization can create mentoring programs that do not
reduce overall production or alter decision making, but, instead, enhance the end
product through more effective working relationships. Teaming up a younger person
with an older, experienced staff member can bring many benefits to the organization. It
allows the more experienced person to take advantage of the younger person's fresh
technical skills and incorporate them into the problem-solving process. At the same
time, this can better integrate the experienced individual's knowledge of the process
and the overall goals established by the organizational structure. The exchange of
ideas, the application of technology, and the extension of the younger generation's
experience provides an overall successfulleaming environment that produces better
problem solving, and saves time and money in the delivery process.
In the future, more internal training will help organizations fill the educational gap and
overcome many of the problems that come from potentially fragmented training off
site.
As a result of the current situation, some organizations are beginning to request in
plant or in-house training programs to bring staff members into a position where they
can perform more effectively in a limited time frame. These special programs focus on
critical task performance requirements and critical company demands. Benefits from
in-house training appear to far outweigh the limited training of a few individuals being
sent to off-site training centers. In particular, in-house training programs give rise to
organizational representatives who become more effective team players as well as focus
on the thinking process necessary to streamline many organizational structures.
Nor does all the in-house training have to come from outside: in many organizations,
there are very talented people who have not been given an opportunity to conduct or
present seminars or in-house training programs for the benefit of less-experienced
individuals. Great opportunities exist for developing ongoing in-house training
programs that build on experienced individuals' knowledge obtained through years of
experience as well as from attending outside professional development programs.
Complex demands of many of our design and construction projects require that heavy
emphasis be placed on team interaction and decision making in an effort to maintain
quality controL Organizations are beginning to recognize that the complexity of
technology and the demands of current projects are requiring more and more
specialists working in a team setting to solve complex technical problems.
Organizations can exploit this situation by teaming up younger, inexperienced
individuals with older more experienced specialists who can share good technical
knowledge. This is not necessarily a mentoring arrangement, but it may well lead to
one. Teaming also provides the opportunity for younger people who are more
proficient and skilled in automation areas to pass on their learning experiences and
knowledge to the less-skilled older generations.
valuable to their employer. Cross training also allows individuals to cover for each
other during vacations and employment declines as well as handling peak loads where
multiple talents are required. By creating cross-training programs, organizations can
reduce the impact of losses through retirees and provide cover for individuals who are
absent from the middle-age range of experiential backgrounds.
The development of effective operational and training manuals can be the beginning of
a strong educational development process. Good manuals and procedures will enable
younger employees to better understand the company or organizational program as
well as the standardization required to maintain specific levels of production and
quality. Training manuals are especially important where projects rely on critical
decision making through a series of problems whereby experience can be captured and
transferred to younger team members. Case studies, good examples, things-that-work
manuals, and quality decisions for specific problems can enhance the training potential
for new employees.
can provide valuable information for project start-ups, thereby reducing costs, time,
and labor resources while maintaining quality decision making.
Under his direction, annual continuing education programs have been developed and
presented on working drawing production, CADD management, specification writing,
construction contracts, construction inspection and field administration, project and
construction management, housing and building inspection, planning and zoning for
community land use management, effective zoning administration, integrated mining
and land reclamation, and design of functional research and development laboratories.
Please take some time as it becomes available and give me your comments,
revisions and additions on the list below. I will, in turn, try to incorporate your
suggestions in future Construction University materials.
Regards and good luck (with a dash of skill) in closing out your next project.
Sincerely yours,
Ralph
The process of closing out a construction project has emerged as one of the most
important sequence of events a project team may encounter during the course of
the project. Reasons for this are:
• The close out process usually results in a formal and legal acceptance of the
page 35 ho 323 date printed: 12/6/0
Construction University Ralph J. Stephenson, P.E.
CU #006 - Oosing Out A Construction Project Consulting Engineer
facility by the owner or occupant. Thus responsibility for the correctness of the
work passes from the design and construction team to the owner. The transition
must be clear and indisputable to avoid contested claims and residual obligations. ~
• The conditions imposed by the warranties on workmanship, systems and
equipment must be clearly defined and accepted by all concerned if adequate
guarantees of performance are to be placed in force .
• The design and construction team must have a definitive point in time where
their contractual obligations have been fulfilled and they can consider their legal
relations closed out so far as project design and construction administration and
operations are concerned.
• The owner must have a specific point in time where he can consider the project
legally his without any hang over potential encumbrances from the design or
construction team.
• The design and construction team must be able to use the project as a facility
which they have no hesitation in describing or showing to prospects and current
clients.
The close out process does not start as the construction phase is being completed
but long before. Closing out is an ongoing action. Throughout all phases of the job
the experienced construction team studies the documents and the work so as to set
how each element can best be turned over to the owner in accordance with the
contract.
Some of the many steps to be taken to properly close out a project are given below.
The list is for all parties to the contract, since most are involved in the close out
phase. Parties indicated in ( ) are those most concerned with the item. Where
multiple parties are indicated it does not necessarily indicate the parties must
participate together in the action.
The list is at random. (Note: This list will be arranged by categories as items are
added)
3. Prepare, distribute and have approved by the owner, the architect/engineer and
4. Punch out the project and complete the punch list requirements within an
5. Prepare, submit and accept the operating and maintenance manuals for the
6. Clear final payments on the project and obtain proper waivers of lien.
(contractor, owner)
7. Provide the owner with a proper set of construction documents for reference
8. Collect and store job logs, diaries, daily reports, test reports and all other
architect / engineer)
9. Bring all meeting minutes and record files up to date so as to permit easy use
10. Collect and bind all official and unofficial project photos. (contractor, owner,
architect/ engineer)
11. Collect and record all project network plans, schedules and bar charts by issue
12. Close out and store all correspondence and other record files. (contractor,
13. Assemble and properly store all shop drawings and other job related
14. Request the architect/ engineer of record to make an inspection resulting in the
15. Plan and implement grand opening or preview festivities for major team
members, company principals and others contributing to the planning, design and
16. Each party should conduct their own job critique during which responsible
parties to the project meet and identify points of strength and weaknesses in
carrying out the job. One major product of this critique should be a set of
of the problems encountered and how they were resolved. (contractor, owner,
architect/ engineer)
17. Relinquish, or account for, all client owned tools, spare parts, and extra stocks
18. Provide the owner copies of all releases, including final inspection certificates,
permits, and all other similar documents to allow the owner to occupy the
19. Label all electrical panel boxes, plumbing lines, valves and equipment as
21. Submit a final statement of accounting, as required, to the owner and the
22. Obtain, prepare or issue a final change order reflecting adjustments to the
23. Send sincere thank you letters as appropriate to the owner, to the design team
24. Provide the owner a complete list of contractors and vendors participating in
25. Insure the owner is placed on the marketing call list, mailing list and other
26. Arrange for such open house activities as may be desired or required (owner,
contractor, architect/engineer)
27. Insure that your company identification is shown somewhere in the building
28. Insure the project is as clean or better than called for in the specifications when
your staff moves off the job. Don't lose the good will of the owner by leaving him
29. Properly train and turn over the facility to the owner's representatives.
Depending on the size and complexity of the project, the training process should
30. Establish and approve the start of all warranty and guarantee periods for all
material and equipment on the job prior to owner making the facility operative.
31. Prepare and submit to the owner a Construction Record Package. This package
should contain the following: (contractor)
32. Submit a final billing to the owner containing a list of all incomplete items
and a properly assigned cost to each item. (contractor)
33. Advise the owner of any insurance changes over existing or past requirements
or dates. (contractor, architect/engineer)
34. Complete all pre start up testing, run in and instruction along with submission
of operating and maintenance manuals. (contractor, owner)
Note: All pre start up and start up requirements should be fully described in the
contract documents and clearly referenced to the warranty period.
35. Submit final meter readings for utilities, and measured records of stored fuel at
the time of substantial completion. (contractor)
37. Have final inspection made by an experienced exterminator to rid the job of
rodents, insects or other pests. (contractor, owner)
38. Read the full contract document requirements (drawings, specifications, and
contract) for closing out the job. (contractor, owner, architect/engineer)
39. Provide the owner a certification as to the building area calculations including
gross square footage leasable square footage, and area use assignments.
A few years ago I was asked by a structural steel fabricator in Grand Rapids,
Michigan to summarize some informal remarks I had made about why the
planning, design and construction profession is so significant.
At first I thought it would be a difficult request to fill. How wrong I was! The
summary was easy to write and it stimulated some ideas that had been rattling
around in my mind for a long time. The essay is no intellectual masterpiece and
was written from memory about the off-the-cuff remarks I had made at the
evening program on which I had appeared.
In reading the essay the other day it seemed to me that the content of the paper
might be of value to today's construction professional. Perhaps you will agree.
Comments and essays about our business and profession are always welcome.
Please write and send them along.
Regards,
Ralph
-- 1074 words
-- approximate reading time - 5 minutes
Five ingredients are critical to good thinking and effective management in design
and construction.
• Importance!
• Responsibility!
• Excitement!
• Contribution!
• Methodology!
These rewards enrich professional life, and are won as we become aware of how
the five act in our daily work.
1. Importance!
The design and construction professional contributes greatly to the quality of our
total environment. This contribution of knowledge, skill, ingenuity, ethical
behavior, and sound moral outlook makes the generic construction practitioner a
front line battler for good. It identifies the professional as being an important
individual. It makes the organization within which he or she works a significant
vehicle for societal good.
2. Responsibility!
In the work place, some may have a flawed perception of what constitutes a
mistake by the skilled professional. This is a risk all professionals, credentialed or
not, must take. We cannot transfer that risk to others who are not so fortunate or
knowledgeable, nor as able to carry the burden of such risk.
Feeling responsible for a job is often as great a reward as is feeling you have
contributed to that job's success
Taking the risk of being responsible generates the next reward element of our
business life - Excitement.
3. Excitement!
Excitement is the process of experiencing the ups and downs that accompany any
contribution to society's well being. It is the barometer that measures the pressure,
or lack of, to do well.
The reward of excitement is frequently found in both the action and the result.
When we are about to accomplish something significant, excitement mounts.
When we have accomplished something significant, excitement is heightened by
what the accomplishment means to those for whom we took the action.
Excitement must be one of the driving forces for a professional who desires
excellence. However, the project must be worthy of that excitement and the
participants must be willing to join in. This leads to our next significant
ingredient - Contribution.
4. Contribution!
If you don't care who gets the credit you can accomplish anything.
Believing this brings into view a vast array of rewards and benefits to the
professional practitioner. Credit is a tool to encourage improvement and learning.
If you are a real pro at what you do, and you want the results of your work to bring
about truly constructive change, then by contributing and transferring credit you
can often gain rewards far beyond a direct credit benefit to yourself!
When you contribute what you can without concern for being given credit, you
gain benefits that encourage you and those being given the credit, to become even
better.
Interestingly, a direct gain for another by your efforts, usually results in a gain for
you, often from unidentifiable sources. Many times this unexpected bonus comes
from those who have been credited and their supporters.
Even if the rewards of giving don't result in a credit to you, don't worry - your
store of gifts for others won't ever run out. Giving encourages giving.
5. Methodology!
Often the secret of doing something well is first doing it poorly -- knowing some
degree of failure. We must all experience failure to understand what success
means. Patterns of success seen through the traps of failure help us develop better
methods of doing things.
These are then merged into habits and processes that encourage the elements of
successful action to be continually duplicated and evaluated, and when necessary,
changed or discarded.
Every exceptional professional has built a variety of procedures that serve well
and hold failure at bay. The reward of using these procedures is the gift of success.
When you have learned to use good procedures well, when not to use them, and
when to adapt them to a different situation, you will have built a dependable
professional methodology.
dilemma in which ratings, rankings, and listings must be applied to a set of factors,
weights, and attributes to determine what the best combination of all of these is for
The various theories of probability can be of help in resolving many of the problem
not always have the technical knowledge to work comfortably with formal
statistical or probability methods. Therefore I offer the following essay, the eighth in
the series of Construction University papers to help the practitioner make good, and
ranking choices when several factors may influence the decision as to which are the
best.
Please let me know of your own experiences with decision making tool and with
your permission we will pass them along to others in the construction industry.
Construction University
--712 words
The purpose of decision making for the responsible project manager is to insure
decisions of the project manager to a decision in line with what the upper
1. Select, write down, and verify the various decisions possible. What courses of
action are available?
It is essential to realize that the factors selected and screened for use must all be
of relative importance and that the assignment of weights should spread from
one to ten. A help in doing this properly is to determine the most important and
critical of the factors and assign it a value of eight to ten. Next select the least
important factor and give it a weight of from three to one. The remainder
should fall somewhere in between. Remember more than one of the factors
being weighed can receive the same number. You are not ranking the factors,
you are weighing them.
4. Assign a value to each potential course of action or each decision possible for
each of the factors selected and weighed. If there are three courses of action
possible, and you have selected five factors by which these are to be judged, you
will have to assign 3 x 5 = 15 values to the entire array. This can be seen in the
following matrix example where alternative project delivery systems for
constructing a warehouse are being considered.
The three delivery systems under consideration are 1.) an award of a hard money
contract from a full set of contract documents; 2.) retention of a non liable
construction manager to run the project; or 3.) the use of a liable general
contractor involved early as a construction consultant and providing iterative
estimating leading to submission and acceptance of a guaranteed maximum
price.
Project delivery systems being considered & their value in satisfying the
Factors Values
The selection analysis above indicates the best delivery method of the three
being considered is a progressive pricing system leading to submission of a
guaranteed maximum price for which the contractor will construct the project.
It should be emphasized that the validity of factor selection, the factor weighing,
the selection of alternatives and their valuing depend totally on the exercise of
sound judgments by those making the analysis. Usually for each decision to be
made such an analysis as above is made by several qualified staff. Some may not
even be associated with the project directly but only acquainted with the key
demands of the project program and mission. This wider range of views and
ideas often lends strength to the recommendations.
Ralph
May 15,2000
CU #009 below is one of the more complex views of the project and program
management systems that we have included in the CU series. The process described
below is designed to help both new and experienced managers get a firm handle on
what it is that he or she is expected to manage. The process likewise can help show
those on the project or program team what role they are to play in achieving the
vision and mission of the entire action effort.
As usual, comments, rebuttals and new ideas are welcome, along with your
permission to include them in future Construction University essays. Let us hear
from you!
We will soon be collecting comments received so far and will incorporate them into
a future CU.
Keep in touch!
Regards,
Ralph J. Stephenson
-- 1271 words
-- Approximate reading time - 10 minutes
Since the start of the American Industrial Revolution in the late 1700s and
continuing through the 19th, 20th and into the 21st centuries, entrepreneurs have
wrestled with defining what they do, what they would like their future to be, and
how they could reach a desired goal through effective management of their
organizations.
You, who practice management for a livelihood, have probably wondered if there is
a pattern for success in the application of philosophies that have seemingly driven
business planning over the past 200 or more years.
While recently reviewing various concepts of words and their meanings I came to a
somewhat fuzzy, inconclusive conclusion that there are five words that have
permanent significance in defining how a business or enterprise becomes and stays
successful. The five might be incorporated into a single sentence entitled UHow to
be Successful." -- but more about that shortly.
We live in two worlds, the world-of-words and the world of non-words. The
world-of-words is that in which we live by simulating actions through words and
other symbols that describe events that could or actually do happen. Let me give
you an example.
The world of non-words is that in which we live and cause things to happen by our
actual presence and physical actions. A world-of-words model such as described
above is only a guide to the physical construction of the project. We build the actual
project in the world of non-words.
By this brief essay I shall attempt to show how the manager can start building a
sound action plan in a world-of-words using key descriptive elements that are
critical to the plan. Then we can relate this plan model to the world of non-words
showing how the manager can simulate various alternatives while translating his
or her model into a real set of actions.
Suppose we want to design and build a new library and remodel an adjoining
existing library. The process of planning to build can be described in seven steps:
1. First determine what our grand plan of action will require. We will need -
• Management - The act and manner of defining, assembling and directing the
application of resources to achieve our mission and specific goals and objectives.
Now we subtract the components one by one from our model and evaluate what
happens when that component is removed.
By removing vision from the model we blur the meaning of the project or
program, and raise serious questions about why we ever embarked on this course of
action anyway: the removal produces action paralysis and confusion about desired
results.
We have now removed a vital link between the foresight to visualize and the
Now, we have either extended or reduced the time from stating our mission to
defining our objectives to a degree where we may lose the action time sense needed
to proceed in a realistic manner.
We now have no engine or rudder left on our ship by which we can achieve our
vision through the use of the model objectives, goals, and mission .
... ...
The above model and the brief analysis-by-subtraction shows how critical the major
components of our model are: how they help us to reach our vision while fulfilling
our mission. We can summarize this essay in a single sentence entitled "How to be
Successful"
''You improve your chances of success in any endeavor by applying a vision (what
you see in your future), understanding your mission {the primary achievements
you must reach), setting your goals (targets, not yet quantified, but at which you are
aiming), incorporating your goals into a set of objectives (quantified targets), all
designed so you can provide a solid business plan, molded by whatever
management form you feel best fits your abilities."
* * *
CU #009 glossary of terms
• Management - The act and manner of defining, assembling and directing the
application of resources to achieve specific goals and objectives .
• World of non-words - The world in which we live and cause things to happen by
our actual presence and physical actions.
When you work with other organizations, their management and their staff,
you can gain much business-useful knowledge by observing critical elements
of that organization's operations. Those that may contribute to the success, or
lack of success, in people, management, and marketing relations include:
• How the organization functions,
• How successful the organization is as measured by your standards,
• What techniques the various departments and divisions use to maintain
their organizational and management effectiveness,
• What they do, or don't do, that lowers or improves their potential for
succeeding,
One of the most important of these elements is the nature of the organization as
defined by the words "conservative" and "forerunner" (not to be intermingled
with the meanings of politically oriented conservative and liberal). The
following benchmarking essay may help you discover how the match between
you and a work place plays a vital role in your future, particularly in the
planning, design and construction profession.
* * * *
Managed Organizations
(For definitions of words in bold, underlined type see the glossary of terms at the
end of this essay).
Let us start by testing a few of the characteristics that influence what kind of
organization these words seem to describe .
• It is critical to understand that both types of organizations can be, and often are
successful or unsuccessful. The style of forerunner or conservative is merely an
indication of the way the organization achieves its successes or goes through the
twinges of its failure.
- Dependable,
- Predictable,
He has a strong drive to take good care of his family and to insure that they
benefit from his short and long term professional efforts.
caring for the public health, welfare and safety of his community.
The organizational structure of his employer's firm, Johnston and Sons, P.e.
is rather rigid and in Adam's opinion a tad too highly regimented. However
he appreciates the need for a relatively predictable structure to allow for a
feeling of comfort and security that will allow planning properly for the
future of both the company and the employees.
You are a trusted friend of Adams and considered by him as a coach and
mentor. He has just asked you in a social setting what kind of organizations
Page 55 ho 315 12/6/0
Construction University Ralph J. Stephenson P.E., P.c.
CU #010- Forerunner & Consulting Engineer
Conservatively Managed Organizations June 11,2000
he should plan to be with during the various stages of his career. He has
phrased the query as an open question, and is obviously interested in what
you have to say. You judge that he will listen, but might be inclined to tailor
his opinions and decision to fit what words he wants you to use.
What career paths would you recommend Adam Jay follow over the next 10
years?
services, and practices you employ against your toughest competitors, and
practice leaders .
• Employee security - That benefit gained by one who works for another and
enjoys freedom from risk, danger, doubt, anxiety, or fear.
• Leveraging - The effective use of vested and earned authority and resources
to solve problems and achieve goals and objectives.
• Liberal - Generally favoring proposals for reform, open to new ideas for
• Positive change - Change that is managed so its control and use raises the
potential for individuals or organizations to succeed at being excellent.
• Politically liberal- Of, pertaining to, or dealing with the structure or affairs
of government in the private, public or volunteer sectors of our society, and
not limited to or by traditional, orthodox, or authoritarian attitudes or
dogmas. Generally favoring proposals for reform, open to new ideas for
progress, and tolerant of the ideas and behavior of others; broad-minded.
Subject: CD #011 - Close out list for Community Medical Center Tenant
Improvements
June 30, 2000
"Feel free to use the close out check list for any training programs for CU e-mails.
Please give credit to:
Phone: 770-263-3733"
-- so, his check list constitutes CU #OIl, this addition to our ongoing close out
essays.
Please let me know if you are still receiving the CU series of essays and please feel
free to submit any material you would like to see in print to me for potential
Keep in touch!
Regards
Ralph
Courtesyo£
Collins Project Management
5996 Peachtree Parkway
Norcross, Georgia 30092
Phone: 770-263-3733
--834 words
--approximate reading time - 5 minutes
17. Acoustical ceiling lay-in panels - furnish at least 5 percent of total product
installed maintenance stock
18. Exposed ceiling suspension members - furnish at least 2 percent of total
product installed for maintenance stock
19. Resilient tile flooring - furnish at least 10 percent of each variety installed for
maintenance stock
20. Resilient base - furnish at least 10 percent of each variety installed for
maintenance stock
21. Resilient sheet flooring - furnish at least 10 percent of each variety installed,
in full roll width, for maintenance stock
22. Paint Maintenance Stock - furnish not less than one labeled and sealed 1
gallon can of each type of finish coat and color
23. Wall Coverings Maintenance Stock - Vinyl - 2 percent of the number of rolls
installed
24. Wall Coverings Maintenance Stock - Wallpaper - 2 percent of the number of
rolls installed
25. Plastic Laminate Lockers - turn keys over to the owner
26. Accordion Folding Partitions - 2 year warranty
27. Accordion Folding Partitions - maintenance materials
28. Accordion Folding Partitions - demonstrate operation procedures
29. Medical Equipment - demonstrations, warranty cards and instruction
booklets
instruction
maintenance contract
49. Nurse/Patient Communications Network - train all staff receiving the new
equipment
50. Nurse/Patient Communications Network - as built drawings of all network
components and associated wiring
51. Motor Controls and Wiring - test all overload relay control circuits
Technology in Construction
Operations?
At the beginning of the design and construction electronics age in the mid 1950's
contractors' technical needs were filled at a pace that allowed even the most
cautious professionals to see the resulting benefits and to gradually fold the systems
into their daily operations. Examples of this early embracing of technology could be
seen in the widespread use of estimating systems using computers and spreadsheets
(1960), and critical path planning using early CAD systems and computational
systems (1955).
Today, the pace of new entries into the electronic design and construction market
make it almost impossible for any but a few users of these systems to keep up with
new developments and new products. The result is often chaos in and among
firms, and within the industry disciplines. New professional graduates are bringing
academically learned, cutting-edge programs to the field where they are promptly
put at odds, and often invidiously compared, with other operational systems ...both
old and new.
Let's face it: not every professional can know every program and every
platform...nor does he or she want to!
There is an even more fundamental acceptance and learning problem. It deals with
our assessment of just what it is that we seem to need to effectively and profitably
design, engineer, and construct.
To help bring into focus what this means to the professional constructor let's first
examine four factors that determine how well we will be doing business and
constructing facilities during the current booming technological expansion.
Factor #2. Basic technological systems that are used to meet these needs.
Factor #3. Problems resulting from failure to match the tools available to meet
these needs.
Factor #4. Solving the problems caused by not meeting operational needs.
Once we have a clear understanding of these four factors, and how they affect our
organization and our profession we can apply the results to planning how we can
best use the evolving technology to achieve success. Let's first prepare a check list of
the factors in a specific program of improvement...for instance gaining excellence in
the preparation of useful project plans and schedules.
• Knowing how to manually prepare network plans & critical path diagrams.
• Understanding the difference between planning and scheduling.
• Properly using workable expediting systems.
• Knowing the yardsticks by which to measure project success.
• Understanding the concept of program management.
• Understanding and properly using project delivery systems.
• Knowing how to keeping accurate records.
• Preparing and using check lists of design and construction actions to be taken.
• Knowing how to, and, then, properly processing revisions.
• Implementing principles of good field inspection for the project team.
• Knowing how to manage a project or a program.
Factor #3 - Types of problems often resulting from failure to match the tools
available to the needs to be satisfied.
Comment #1 - We are not following evaluation systems that provide rational and
objective arguments for adopting, rejecting or revising the bewildering array of
Comment #2 - We are wasting enormous amounts of time that could be best spent
in becoming better builders on substitution of eye-catching graphics for
understandable explanations of the new technological systems. ("If it's pretty it
must be right, accurate and sufficient.")
Comment #4 - In our rush for volume (too often at a sacrifice of quality and profit)
we do not take adequate time to fully understand the actual operational techniques
needed to build properly.
Planning is to define project actions and their relations with each other in a
Comment #8 - We don't see what it is that makes problems for others on the
project team. We are frequently so concerned with ourselves and our jobs that we
exclude any attempt to understand what's going on around us. The result is that we
needlessly cause problems for others.
Comment #10 - We often resist learning how to use new systems because they seem
to pose a threat to our career by putting us at a disadvantage with the younger, more
knowledgeable practitioners. Therefore we fight the new techniques, the new
systems; we fail to be effective construction professionals ... and, we fail to help
others do what we actually believe is needed to improve our industry.
In sum, I would assess our situation this way: Technology is not bad -- we merely
use it poorly. We.J:9!l do better.
Comments?
Regards,
Ralph