Document Control
1 Contact Information............................................................................................................6
1.1 Design Scope of Work............................................................................................................. 6
2 Defects Liability...................................................................................................................6
2.1 List of All Equipment Covered By Warranties..........................................................................6
2.2 List of Any Spares and Special Tools Supplied Under the Contract........................................6
3 WAC Information................................................................................................................6
3.1 WAC and Construction Drawings Location..............................................................................6
5 Operation Procedures..........................................................................................................7
5.1 Description of Assets Operation.............................................................................................. 7
6 Asset Equipment..................................................................................................................8
6.1 Equipment Technical Data Tables........................................................................................... 8
6.3 Drawings................................................................................................................................. 9
6.3.1 Pumps................................................................................................................... 9
6.3.2 Motor (for non-submersible pumps)......................................................................9
9 Document Control..............................................................................................................11
1 Contact Information
Fax
Email
Project or Job Number
2 Defects Liability
List of Any Spares and Special Tools Supplied Under the Contract
1. #########
2. #########
3. #########
4. #########
Electrical 1.
#########
2. #########
3. #########
4. #########
5. #########
Design Report 1. #########
2. #########
3. #########
4. #########
5. #########
Installation/Construction 1.
Method Statement
2.
3.
4.
Other Relevant 1.
Information
Commissioning Process
System Overview
5 Operation Procedures
Isolation Procedures
Emergency Procedures
System Operation and Control Schematics Indicating major items of equipment and parts
that are essential to the operation of the system
Keeping and compiling records is a valuable part of an efficient operation and maintenance of the
system. The following should be included in the manual:
Daily logs, maintenance records, laboratory records, monthly reports, monitoring reports,annual
reports, operating cost reports, accident reports, and safety surveys.
A listing of acceptable international/national Standards and procedures for testing and
commissioning.
An operation plan for emergencies and the procedures to be followed until normal operation can be
resumed. This plan should include personnel assignments, emergency equipment inventory, and
emergency vendors/supplier support numbers. The emergency call up list should identify, in ranked order,
the system/equpment personnel responsible for making decisions in specific situations. This list should
include the department, job title, office phone number, email address and etc. for all Supplier/Vendor or
personnel.
Contingency Plan
A Contingency Plan should also be made to insure proper operation of system even in adverse
conditions. This plan should describe conditions and procedures for putting standby and
emergency sources into active service. Procedures for notifying customers, the local safety and health
jurisdiction of noticeable health and safety problems.
Safety Procedures
Safety Procedures should identify work space hazards for the system. Potentialhazards include
mechanical equipment, electrical, explosion and fire, and any material of the system. The manual should
provide information on how to do the following tasks;
6 Asset Equipment
Refer to Appendix 3. Technical Data Tables for data tables at commissioning. Refer to TFMS for
approved equipment data for the subject of this Manual:
Details
Catalogues of all installed material, system and equipments (This shall have an accompanying summary
chart indicating approved material, system and equipment information against actually installed).
Endorse copy of all test results(includes test result log sheet) and Installation
supervision certificates (Approval letter and Certificate of accredited testing
laboratary/authority pertaining to the project)
Drawings
As built drawings and existing information of the project if applicable. Note: All as built drwgs should be
endorsed by relevant authority.
Architectural Drawings
Civil and Structural Drawings
Mechanical Services Drawings
Electrical Services Drawings
Equipment Layout plan & detail drawings
General Arrangements
Sectional Arrangements
Operation Description
Functional Specification
Refer to Appendix 3. Technical Data Tables for data tables at commissioning. Refer to detailed design
report/drawing or interface requirements for equipment data.
Maintenance Information
Troubleshooting Instructions for Large Components (eg. pump and motors etc).
Maintenance Scheduling
9 Document Control