Project Master Schedule Pekerjaan Pembangunan Jetty Port & Conveyor System Pltu Tanjung Balai Karimun Sektor Kepulauan Riau
Project Master Schedule Pekerjaan Pembangunan Jetty Port & Conveyor System Pltu Tanjung Balai Karimun Sektor Kepulauan Riau
PEKERJAAN PEMBANGUNAN JETTY PORT & CONVEYOR SYSTEM PLTU TANJUNG BALAI KARIMUN SEKTOR KEPULAUAN RIAU
ID WBS Task Name Start Finish Duration 21 April 01 September 11 January 21 May 01 October
1 1 PEKERJAAN PEMBANGUNAN JETTY Mon 03/09/18 Tue 03/03/20 548 days?
2 1.1 PORT & CONVEYOR
Contract Effective SYSTEM
Date PLTU Mon 03/09/18 Mon 03/09/18 0 days 03/09
3 1.2 Preparation Sun 09/09/18 Wed 03/07/19 298 days
13 1.3 ENGINEERING Fri 09/11/18 Thu 30/05/19 203 days
14 1.3.1 CIVIL / STRUCTURE ENGINEERING Fri 09/11/18 Thu 23/05/19 196 days
19 1.3.2 DOCUMENTS ENGINEERING
MECHANICAL Sat 17/11/18 Sun 26/05/19 191 days
24 1.3.3 DOCUMENT ENGINEERING
ELECTRICAL Fri 03/05/19 Thu 30/05/19 28 days
30 1.3.4 DOCUMENT
INSTRUMENT ENGINEERING Fri 10/05/19 Sun 26/05/19 17 days
35 1.4 DOCUMENTS
PROCUREMENT Tue 14/05/19 Fri 06/12/19 207 days?
105 1.5 CONSTRUCTION Thu 04/07/19 Tue 04/02/20 216 days
230 1.6 COMMISSIONING Wed 05/02/20 Tue 03/03/20 28 days
236 1.7 Others (Training) Wed 26/02/20 Tue 03/03/20 7 days
237 1.8 Turn Over Certificate (TOC) Tue 03/03/20 Tue 03/03/20 0 days