Project Master Schedule Pekerjaan Pembangunan Jetty Port & Conveyor System Pltu Tanjung Balai Karimun Sektor Kepulauan Riau

This project schedule outlines the tasks for constructing a jetty port and conveyor system for a PLTU power plant in Tanjung Balai Karimun, Riau Islands province from March 2018 to March 2020. The key tasks include preparation from September 2018 to March 2019, engineering from November 2018 to May 2019, procurement from May 2019 to December 2019, construction from July 2019 to February 2020, commissioning in February 2020, training in late February 2020 and obtaining a turn over certificate on March 3rd 2020 upon completion of the project.

Uploaded by

Cubzlook
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
121 views1 page

Project Master Schedule Pekerjaan Pembangunan Jetty Port & Conveyor System Pltu Tanjung Balai Karimun Sektor Kepulauan Riau

This project schedule outlines the tasks for constructing a jetty port and conveyor system for a PLTU power plant in Tanjung Balai Karimun, Riau Islands province from March 2018 to March 2020. The key tasks include preparation from September 2018 to March 2019, engineering from November 2018 to May 2019, procurement from May 2019 to December 2019, construction from July 2019 to February 2020, commissioning in February 2020, training in late February 2020 and obtaining a turn over certificate on March 3rd 2020 upon completion of the project.

Uploaded by

Cubzlook
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

PROJECT MASTER SCHEDULE

PEKERJAAN PEMBANGUNAN JETTY PORT & CONVEYOR SYSTEM PLTU TANJUNG BALAI KARIMUN SEKTOR KEPULAUAN RIAU
ID WBS Task Name Start Finish Duration 21 April 01 September 11 January 21 May 01 October
1 1 PEKERJAAN PEMBANGUNAN JETTY Mon 03/09/18 Tue 03/03/20 548 days?
2 1.1 PORT & CONVEYOR
Contract Effective SYSTEM
Date PLTU Mon 03/09/18 Mon 03/09/18 0 days 03/09
3 1.2 Preparation Sun 09/09/18 Wed 03/07/19 298 days
13 1.3 ENGINEERING Fri 09/11/18 Thu 30/05/19 203 days
14 1.3.1 CIVIL / STRUCTURE ENGINEERING Fri 09/11/18 Thu 23/05/19 196 days
19 1.3.2 DOCUMENTS ENGINEERING
MECHANICAL Sat 17/11/18 Sun 26/05/19 191 days
24 1.3.3 DOCUMENT ENGINEERING
ELECTRICAL Fri 03/05/19 Thu 30/05/19 28 days
30 1.3.4 DOCUMENT
INSTRUMENT ENGINEERING Fri 10/05/19 Sun 26/05/19 17 days
35 1.4 DOCUMENTS
PROCUREMENT Tue 14/05/19 Fri 06/12/19 207 days?
105 1.5 CONSTRUCTION Thu 04/07/19 Tue 04/02/20 216 days
230 1.6 COMMISSIONING Wed 05/02/20 Tue 03/03/20 28 days
236 1.7 Others (Training) Wed 26/02/20 Tue 03/03/20 7 days
237 1.8 Turn Over Certificate (TOC) Tue 03/03/20 Tue 03/03/20 0 days

Task Project Summary Manual Task Start-only Deadline Progress


PREPARED BY :
Split Inactive Task Duration-only Finish-only Critical Manual Progress
CONSORTIUM ETI - PDP Milestone Inactive Milestone Manual Summary Rollup External Tasks Critical Split
Summary Inactive Summary Manual Summary External Milestone Baseline