Estimate For Concrete Work of M15 (1:2:4) : (I) Estimating Work Volume

The document estimates the materials, costs, and total budget for concrete work using M15 grade concrete with dimensions of 0.8m x 0.8m x 0.8m. It calculates that 0.512 cubic meters of concrete will be needed, requiring 3.16 bags of cement, 0.15 cubic meters of sand, and 0.29 cubic meters of stone or brick chips. The total material costs are estimated at Rs. 3433.89 with stone chips and Rs. 2658.99 with brick chips. Additional costs include Rs. 1700 for labor, 3% of materials for overhead, 2% for equipment, and 10% profit. The total estimated rates are Rs. 5903.97 with stone

Uploaded by

mtuanlatoi9704
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
1K views1 page

Estimate For Concrete Work of M15 (1:2:4) : (I) Estimating Work Volume

The document estimates the materials, costs, and total budget for concrete work using M15 grade concrete with dimensions of 0.8m x 0.8m x 0.8m. It calculates that 0.512 cubic meters of concrete will be needed, requiring 3.16 bags of cement, 0.15 cubic meters of sand, and 0.29 cubic meters of stone or brick chips. The total material costs are estimated at Rs. 3433.89 with stone chips and Rs. 2658.99 with brick chips. Additional costs include Rs. 1700 for labor, 3% of materials for overhead, 2% for equipment, and 10% profit. The total estimated rates are Rs. 5903.97 with stone

Uploaded by

mtuanlatoi9704
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 1

Estimate for concrete work of M15 (1:2:4)

L
(i) Estimating Work Volume
Length, L = 0.8 m B
Width, B = 0.8 m
Height, H = 0.8 m
H

Volume of Work, V = 0.512 m3

(ii) Estimation of Materials

Dry Work Volume = 0.768 m3

Cement = 157.99 Kg
= 3.16 Bag

Sand = 0.15 m3
= 5.17 cft

Aggregate = 0.29 m3
= 10.33 cft

(iii) Cost of Materials (with stone chips)

Item Quantity Unit Unit Rate Total (tk.)


Cement 3.16 Bag 490 1548.29
Sand 5.17 cft 45 232.47
Stone 10.33 cft 160 1653.13
Total = 3433.89

(iv) Cost of Materials (with brick chips)

Item Quantity Unit Unit Rate Total (tk.)


Cement 3.16 Bag 490 1548.29
Sand 5.17 cft 45 232.47
Stone 10.33 cft 85 878.23
Total = 2658.99

(v) Total Cost Calculation


with stone with brick
1. Material Cost = 3433.89 2658.99
2. Labor Cost (1 Mason, 2 Helper) = 1700.00 1700.00
3. Overhead Cost (3%) = 154.02 130.77
4. Equipment and tools (2%) = 102.68 87.18
5. Profit (10%) = 513.39 435.90
Unit Rate/Item = 5903.97 5012.83