Designof PVSystemas Alternate Source
Designof PVSystemas Alternate Source
net/publication/275567857
CITATIONS READS
2 2,456
1 author:
SEE PROFILE
Some of the authors of this publication are also working on these related projects:
All content following this page was uploaded by Christian Kwaku Amuzuvi on 06 February 2019.
Email address:
[email protected] (C. K. Amuzuvi), [email protected] (C. K. Amuzuvi)
Abstract: This paper seeks to emphasise the tendency of the use of solar energy as an alternative source of energy for
today as far as the lighting needs of a particular infrastructure is concerned. It compares the use of a Photovoltaic (PV)
System and an existing 60 kVA generator that powers a premise. The paper provides a general understanding of a solar
energy (renewable energy) and how photovoltaic technology can be practically applied to power the lighting needs of the
premise. Analysis of the site, weather data, and the design predicted the value of the photovoltaic system as an economic
investment. We present the analysis undertaken using the PVSYST software package to optimize the system design for the
premise. The simulation and calculation was done with the consideration of a PV array’s tilt and direction and economic
considerations. The proposed photovoltaic system for the premise, with 30 units of battery capacity of 17850 Ah, an
inverter size of 132 kW and a minimum number of 8 modules at 12.53 kWp was sufficient for the proposed design. The
output analysis when implemented will result in a substantial lifetime energy savings, improving reliability and provide a
great impact on the environment. It is therefore worthwhile to invest in photovoltaic renewable energy systems to augment
the energy needs of locations where its use is viable.
clouds, oceans and land masses [8]. The spectrum of solar Figure 2 shows a typical solar photovoltaic plant.
light at the Earth’s surface is mostly visible and near infrared
ranges with a small part in the near-ultraviolet [9]. The total
solar energy absorbed by the earth’s atmosphere, oceans and
land masses is approximately 3,850,000 exajoules (eJ) per
year [8]. The amount of solar energy reaching the surface of
the planet is so vast that in one year, it is about twice as much
as will ever be obtained from all of the earth’s non-renewable
resources of coal, oil, natural gas etc. Solar energy can be
harnessed at different levels around the world mostly
depending on the distance from the equator [10].
and metal. An outer frame is used to house the module to example curve is where the voltage is 17 volts, and the
increase mechanical strength, and to provide a way to mount current is 2.5 amps. Therefore the maximum power in watts
the unit. This package is called a module or panel. The is 17 volts times 2.5 amps, equaling 42.5 watts.
amount of current produced is directly proportional to the The power, expressed in watts, at the maximum power
cell’s size, conversion efficiency, and the intensity of light. point is described as peak, maximum, or ideal among other
For example, groups of 36 series connected PV cells are terms. The current-voltage (I-V) curve is primarily based on
packaged together into standard modules that provide a the module being under standard conditions of solar
nominal 12 volt (or 18 volts at peak power) [2]. radiation and module temperature.
a high quality inverter, which converts DC power from the photovoltaic conversion are solar panels, batteries,
solar array into AC power that conforms to the grid’s regulators/controllers, invertors and load as summarized in
electrical requirements. the block diagram of Figure 8. For a reliable generation
During the day, the solar electricity generated by the system that can function independent of the utility grid,
system is either used immediately or sold off to electricity batteries may be a viable component to the total system [14].
supply companies. In the evening, when the system is unable Back-up generators may be included in a system to provide
to supply immediate power, electricity can be bought back power when the PV system is not operating, and are
from the network as shown in Figure 5. generally included when systems are not grid connected.
2.4.2. Stand-Alone Systems
PV systems not connected to the electric utility grid are
known as off grid PV Systems and also called stand-alone
systems. Direct systems use the PV power immediately as it
is produced, while battery storage systems can store energy
to be used at a later time, either at night or during cloudy
weather conditions. These systems are used in isolation of
electricity grids, and may be used to power radio repeater
stations, telephone booths and street lighting. Figure 6
shows a typical off grid PV systems.
temperature. The output result is used to directly compare approach with a guide in the development of this paper
with electricity bills paid monthly to the ECG. providing results in the form of a full report, specific graphs
and tables. Figure 10 shows the circuit diagram of the
3.2. Load Data proposed PV design using the PVSYST V5.0 software.
Eight (8) hours of operational time was chosen for each The hardware components include; the PV modules,
illuminant. The number of lamps in the various parts of the battery, charge controller, inverter, wires and cables and
premise and the total energy consumption of each type of other safety and auxiliary components. The main purpose of
lamp were analysed. The total daily energy utilization of the a charge controller is to prevent the battery from being
premise for eight hours is 3348 Wh. With the load under- or overcharged.
assessment detail in hand, the total Watt-hours per day The inverter is also used in the system where AC power
needed from the PV modules was calculated by multiplying output is needed. The input rating of the inverter should
the daily energy utilized (DEU) per day by 1.3 (this is the never be lower than the total wattage of the appliances to be
standard energy lost in a PV system taking into account the used. The inverter must have the same nominal voltage as
wasted energy from wiring, charge controllers, batteries and the battery with the size 25-30% bigger than the total watts
inverters) to get the total Watt-hours per day which must be of the appliances [18].
provided by the panels [17]. Therefore, 3348 Wh/day×1.3 = All inverters have a continuous rating and a surge rating.
43534.4 = 43.53 kWh/day. The surge rating is usually specified at so many watts for so
many seconds. This means that the inverter will handle an
overload of that many watts for a short period of time. This
surge capacity will vary considerably between different
types of inverters, even within the same brand. Generally, a 3
to 15 second surge rating is enough to cover 99% of all
appliances.
The wires and cables used in this design must be in
compliance with the National Electrical Code with color
codes to designate its function and use. The conductor
material was copper which is the most common with
thermoplastic being the insulation material.
3.4. Sizing of Components and System Design
3.4.3. Battery Sizing output. The green bars in the graph represent the monthly
The batteries must be able to store the total daily load, in energy demands of the premise with the red bars
addition to the extra energy lost by inverting from DC to AC. representing the amount of energy that can be produced by a
With the help of the software, 30 batteries (6 in series × 5 in 12.53 kWp system. It can clearly be seen that the design
parallel) of a 12 V battery with capacity of 17850 Ah were produces enough electricity to fully offset the lighting load
required. These batteries will provide adequate storage to of the premise. The energy demand is 43.55 kWh per day
meet the daily energy requirements, operating temperature whereas the systems mean daily available output is 60.4
effects of 50°C, 4 days of autonomy, which is the number of kWh per day. Excess energy is produced, except the month
days the battery sustains its charge with no sunshine to of June, July, August and September which produces
recharge it, and 5% of loss of load (LOL), which is the relatively less energy in excess.
probability time fraction at which the battery is disconnected
due to the “low charge” regulator security.
3.4.4. Controller Sizing
From standard practice, the sizing of the solar charge
controller is to take the Isc of the PV module and multiply it
by a factor of 1.56 and the number of panels [19]. Therefore,
5.1 A × 1.56 × 8 = 63.65 A.
3.4.5. Inverter Sizing
In the sizing of the solar inverters, it should be noted that
the inverter should be 25-30% bigger than the total Watts of
all appliances that are to be powered by the system. It must
also be able to handle the expected surge or in-rush of Figure 11. Graph Showing Available Solar Energy and User’s Needs by
current that some large loads draw upon. The method for Mean Monthly Output of the Proposed PV System.
estimating surge requirements is simply to multiply the total
AC watts by three at realistic conditions where household Figure 12 also shows the average state of charge of
loads do not surge. The main criterion was to match the batteries and the probability of LOL by mean monthly. The
inverter’s input voltage with the nominal battery voltage and state of charge of batteries is the actual capacity of the
choosing the desired AC output voltage of 240 VAC. The battery, which is defined at nominal current, but varies with
total AC load is approximately 44 kW which must be the the discharge current level and temperature. It was however,
inverter size and therefore equal to the minimum inverter noted from the graph above that June, July, August and
continuous watt rating. The minimum surge rating will be September had less probability of LOL.
44 kW × 3 = 132 kW.
3.5. Safety Regulations
3.7.1. Life Cycle Cost for Proposed Design Table 4. General Comparison between the Proposed Design and the 60 kVA
The life cycle costs (LCC) are the sum of the equipment generator
(initial) costs and operational costs arising during the project
Factors Solar (PV) 60 kVA Generator Set
until the end of the project horizon, which is usually set
between 20 and 30 years [15]. Resource Sunlight readily
Fuel is expensive and can be
The equipment costs are the initial costs incurred at the Availabilit available
scarce
beginning of the PV system electrification whilst the y
operational costs include the running costs, maintenance and Mode of
Simple Complicated
Operation
replacement costs. Tables 1 and 2 below represents the
Reliable power all month
initial and maintenance cost respectively for a period of 20 Relatively Cheap provided fuel is available
years and at a rate of 5%. Silent Generator not restricted to
Merits
Very long system lighting circuits alone but
Table 1. Initial Installation Cost Analysis for the Proposed Photovoltaic lifespan powers all load at the
System premise
LCC
Unit Price
PV Components Quantity Price (GH¢)
(GH¢) Relatively higher Low installation but high
Solar PV Module 8 1,000.00 8,000.00 installation cost but low maintenance and operation cost
maintenance and
Environm
Battery 30 390.00 11,700.00 operation cost
e-ntal and
No pollution Air Pollution
Inverter 1 6,504.70 6,504.70 Social
Impact
Controller 1 3,000.00 3,000.00 • Poor system output
from June to September • Environmental and Noise
Labour and Miscellaneous - - 10,000.00 Demerits due poor sun exposure pollution
Total Initial Cost (GH¢) 28,674.70 • System was limited to • Relatively Simple installation
lighting circuits
Table 2. Maintenance Cost Analysis for the Proposed Photovoltaic System
4. Conclusion and Recommendations
Maintenance Cost
4.1. Conclusion
Energy Cost (GH¢/hour) 1.78
Annuities and Maintenance (GH¢) for 20 years 14,460 Ghana is endowed with solar and other renewable energy
resources that can contribute immensely to residential and
Total Life Cycle Cost 43,134.70
industrial energy needs for the country. This paper reveals
the appropriateness of the generation of electric power using
3.8. Comparison between the Proposed PV Design and the solar renewable energy compared to the use of a diesel
60 kVA Generator generator. The proposed photovoltaic system for the premise
Before the comparisons and projections were made, the life required a 30 unit of battery capacity of 17850 Ah, an
cycle cost of the 60 kVA generator was also obtained as inverter size of 132 kW and a minimum number of 8
indicated in Table 3. Table 4 also show the general modules at 12.53 kWp for the design. The design achieved
comparison between the proposed design and the 60 kVA all the set goals relating to reliability, efficiency, adequacy,
generator. cost-effectiveness and environmental impact issues albeit
Table 3. General Comparison between Proposed Design and 60 kVA
limited to only the lighting circuits of the premise.
generator
4.2. Recommendations
Initial Cost Price (GHc)
The following are recommended from the proposed
Cost of generator 39,200 design:
Installation Cost 11,478 Hybrid system of renewable power generation should
be considered to further improve the reliability,
Total Initial Cost 50,678
efficiency, adequacy, cost-effectiveness and
Annual Maintenance Cost environmental impact issues of electricity provision;
Servicing; GHc400 for every 3 months 1600 The PVSYST software and other simulation programs
should be used as a tool to assist individuals and other
Diesel pricing; GHc162 for 90 litres full tank 1000
researchers in the optimization of the design of PV
Total Annual Maintenance Cost 2600 systems and
Total Maintenance Cost for 20 years 52,000 Government policies should be geared towards
Total Life Cycle Cost of Generator 103,356 encouraging individuals and investors to consider
investing in renewable energy.
16 Christian Kwaku Amuzuvi and Emmanuel Effah: Design of a Photovoltaic System as an Alternative Source of
Electrical Energy for Powering the Lighting Circuits for Premises in Ghana
[6] Aryeetey, E. (2005), “Guide to Electric Power in Ghana”, [17] Anon (2010), “Renewable Energy Potential - Country Report
Resource Center for Energy Economics and Regulation, Ghana (RECIPES)”, Technical Report on Developing
University of Ghana, Accra, 67 pp. Renewables, Amsterdam, 29pp.
[7] Amuzuvi, C. K. and J. C. Attachie (2013), Effective Power [18] Joe, X. (2007), “MPPT Inverters and Charge Controller
Management in Homes and Premises in Ghana. Research Algorithms for Solar Tracker”, International Journal of
Journal of Applied Sciences, Engineering and Technology, Electrical & Electronics Engineering, IJMME-IJENS, Vol.
6(03): 354-360. 10 No. 1, pp. 13-18.
[8] Sauder, E. M. (2008), “Development of an appropriate Solar [19] Aldous, S. (2009), “How Solar Cells Work”
and Wind Hybrid Charging Station for Electric Vehicles in www.howstuffworks.com/solar-cell.htm. Accessed: July 14,
Developing Countries”, Unpublished MSc Thesis Report, 2012.
Pennsylvania State University, USA, 81pp.