ENMG698c Lecture3

Uploaded by

Joli Smith
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
66 views62 pages

ENMG698c Lecture3

Uploaded by

Joli Smith
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 62

Lecture 3

The Risk Management Process per PMBOK Standards

ENMG 698c: Special Topics - Project Risk Management - Dr. Rayan Khraibani

Copyright © 2020-2021, American University of Beirut, All Rights Reserved


Outline
▪ Overview of the PRM processes
▪ Plan risk management
▪ Identify risks
▪ Analysis
▪ Responses
▪ Monitoring
▪ Conclusion

ENMG 698c: Special Topics - Project Risk Management - Dr. Rayan Khraibani
2
Copyright © 2020-2021, American University of Beirut, All Rights Reserved
Overview of the PRM Processes

ENMG 698c: Special Topics - Project Risk Management - Dr. Rayan Khraibani
3
Copyright © 2020-2021, American University of Beirut, All Rights Reserved
ENMG 698c: Special Topics - Project Risk Management - Dr. Rayan Khraibani
Project Risk Management - Introduction
4
Copyright © 2020-2021, American University of Beirut, All Rights Reserved
Project risk management
▪Objective
▪ Optimize the chance or project success
▪ Ensure that project stays on track
▪ Seize opportunities
▪Included in
▪ Planning, executing, and monitoring & controlling parts of the
project life cycle

ENMG 698c: Special Topics - Project Risk Management - Dr. Rayan Khraibani
5
Copyright © 2020-2021, American University of Beirut, All Rights Reserved
Seven processes

ENMG 698c: Special Topics - Project Risk Management - Dr. Rayan Khraibani
6
Copyright © 2020-2021, American University of Beirut, All Rights Reserved
A broad definition of risk
▪Uncertainty
▪ Positive and negative risks
▪Variability
▪Pro-activity
▪ Response plan vs. contingency reserve
▪Unpredictability
▪Issues

ENMG 698c: Special Topics - Project Risk Management - Dr. Rayan Khraibani
7
Copyright © 2020-2021, American University of Beirut, All Rights Reserved
A unified framework

ENMG 698c: Special Topics - Project Risk Management - Dr. Rayan Khraibani
8
Copyright © 2020-2021, American University of Beirut, All Rights Reserved
Plan Risk Management

ENMG 698c: Special Topics - Project Risk Management - Dr. Rayan Khraibani
9
Copyright © 2020-2021, American University of Beirut, All Rights Reserved
Plan risk management process
▪ Consists of defining how to conduct risk management activities

▪ Once or at pre-defined milestones during the project

ENMG 698c: Special Topics - Project Risk Management - Dr. Rayan Khraibani
10
Copyright © 2020-2021, American University of Beirut, All Rights Reserved
ENMG 698c: Special Topics - Project Risk Management - Dr. Rayan Khraibani
11
Copyright © 2020-2021, American University of Beirut, All Rights Reserved
Inputs
▪Project Charter
▪ High-level description, scope and requirements
▪Project Management Plan
▪ Coordination and consistency
▪Project Documents
▪ Information (e.g. stakeholders risk attitude)

ENMG 698c: Special Topics - Project Risk Management - Dr. Rayan Khraibani
12
Copyright © 2020-2021, American University of Beirut, All Rights Reserved
Inputs

▪Enterprise Environmental Factors

▪Organizational Process Assets


▪ e.g. risk policy, templates (registers & reports), roles and
responsibilities, authority levels, lessons learned

ENMG 698c: Special Topics - Project Risk Management - Dr. Rayan Khraibani
13
Copyright © 2020-2021, American University of Beirut, All Rights Reserved
Tools and techniques
▪Expert judgement
▪Data analysis
▪Meetings, workshops

▪ Understand the context


▪ Elicit risk attitude
▪ Tailor
▪ Promote team work and communication

ENMG 698c: Special Topics - Project Risk Management - Dr. Rayan Khraibani
14
Copyright © 2020-2021, American University of Beirut, All Rights Reserved
Output: the risk management plan
▪ General risk strategy

▪ Methodology

▪ Roles and responsibilities

▪ Funding and contingency protocol

▪ Activities and timing

ENMG 698c: Special Topics - Project Risk Management - Dr. Rayan Khraibani
15
Copyright © 2020-2021, American University of Beirut, All Rights Reserved
Output: the risk management plan
▪ Risk categories

▪ Probabilities and impact definitions and matrix

▪ Reporting formats

▪ Tracking

ENMG 698c: Special Topics - Project Risk Management - Dr. Rayan Khraibani
16
Copyright © 2020-2021, American University of Beirut, All Rights Reserved
A risk breakdown structure
Requirements
Estimates
Technical risk
Processes
Technology
Organization
Management risk Resourcing
Risk categories Global risk Communication
Procurement
Commercial risk Suppliers
Sub-contracts
Legislation
External risk Exchange rates
Competition
ENMG 698c: Special Topics - Project Risk Management - Dr. Rayan Khraibani
Project Risk Management - Introduction
17
Copyright © 2020-2021, American University of Beirut, All Rights Reserved
A scale definition table

ENMG 698c: Special Topics - Project Risk Management - Dr. Rayan Khraibani
18
Copyright © 2020-2021, American University of Beirut, All Rights Reserved
A probability and impact matrix
Implement
Plan response response

4
Probability

Monitor 1
1 2 3 4 5
Impact

ENMG 698c: Special Topics - Project Risk Management - Dr. Rayan Khraibani
19
Copyright © 2020-2021, American University of Beirut, All Rights Reserved
Probability/impact scores

ENMG 698c: Special Topics - Project Risk Management - Dr. Rayan Khraibani
20
Copyright © 2020-2021, American University of Beirut, All Rights Reserved
Identify Risks

ENMG 698c: Special Topics - Project Risk Management - Dr. Rayan Khraibani
21
Copyright © 2020-2021, American University of Beirut, All Rights Reserved
Identify risk process
▪ Consists of identifying and documenting sources of risk

▪ Iterative process over the project life cycle – frequency to be


determined in the risk management plan

▪ Many participants (project manager, operations, final users,


experts…)

ENMG 698c: Special Topics - Project Risk Management - Dr. Rayan Khraibani
22
Copyright © 2020-2021, American University of Beirut, All Rights Reserved
ENMG 698c: Special Topics - Project Risk Management - Dr. Rayan Khraibani
23
Copyright © 2020-2021, American University of Beirut, All Rights Reserved
Inputs
▪Identify elements that are at risk
▪ Project management plan (WBS, requirements, schedule, costs,
quality, resources, scope,…)
▪ Project documents (estimates, lessons learned)
▪ Agreements
▪ Procurement documentation
▪Use organizational history and resources
▪ Enterprise environmental factors
▪ Organizational process assets
ENMG 698c: Special Topics - Project Risk Management - Dr. Rayan Khraibani
24
Copyright © 2020-2021, American University of Beirut, All Rights Reserved
Tools and techniques
▪ Expert judgement
▪ Data gathering (brainstorming, checklists, interviews)
▪ Data analysis (root cause, assumptions & constraints, SWOT,
documents)
▪ Team skills
▪ Prompt lists
▪ Meetings

ENMG 698c: Special Topics - Project Risk Management - Dr. Rayan Khraibani
25
Copyright © 2020-2021, American University of Beirut, All Rights Reserved
Output: the risk management plan
▪ General risk strategy

▪ Methodology

▪ Roles and responsibilities

▪ Funding and contingency protocol

▪ Activities and timing

ENMG 698c: Special Topics - Project Risk Management - Dr. Rayan Khraibani
26
Copyright © 2020-2021, American University of Beirut, All Rights Reserved
Output: the risk register
▪Contains the details of the identified risks and the results of
their analysis at the activity level
▪Events and changes are recorded during the project life
cycle
▪ List of risks / importance
▪ Risk owners
▪ Potential responses
▪ Risk status

ENMG 698c: Special Topics - Project Risk Management - Dr. Rayan Khraibani
27
Copyright © 2020-2021, American University of Beirut, All Rights Reserved
Output: Project documents updates

▪Relevant project documents are updated during the life


cycle of the project, e.g.:
▪ Assumption log
▪ Issue log
▪ Lesson learned register

ENMG 698c: Special Topics - Project Risk Management - Dr. Rayan Khraibani
28
Copyright © 2020-2021, American University of Beirut, All Rights Reserved
Analysis

ENMG 698c: Special Topics - Project Risk Management - Dr. Rayan Khraibani
29
Copyright © 2020-2021, American University of Beirut, All Rights Reserved
Perform qualitative risk analysis process

▪ Consists of assessing characteristics of project risks (probability,

impact) and classifying them (priority)

▪ Helps in identifying focus

▪ Subjective assessments based on beliefs and perceptions

ENMG 698c: Special Topics - Project Risk Management - Dr. Rayan Khraibani
30
Copyright © 2020-2021, American University of Beirut, All Rights Reserved
ENMG 698c: Special Topics - Project Risk Management - Dr. Rayan Khraibani
31
Copyright © 2020-2021, American University of Beirut, All Rights Reserved
Tools and techniques
▪ Expert judgment
▪ Data gathering
▪ Data analysis
▪ Team skills
▪ Risk categorization
▪ Data representation
▪ Meetings

ENMG 698c: Special Topics - Project Risk Management - Dr. Rayan Khraibani
32
Copyright © 2020-2021, American University of Beirut, All Rights Reserved
Example: subjective probability assessment

wet black

dry white

ENMG 698c: Special Topics - Project Risk Management - Dr. Rayan Khraibani
33
Copyright © 2020-2021, American University of Beirut, All Rights Reserved
Example: Graphical representation

ENMG 698c: Special Topics - Project Risk Management - Dr. Rayan Khraibani
34
Copyright © 2020-2021, American University of Beirut, All Rights Reserved
Perform quantitative analysis process
▪ Consists of assessing characteristics of project risks using
mathematical models
▪ Helps in assessing global exposure
▪ Provides quantitative risk information to support risk response
planning
▪ Specialized software
▪ Usually performed for large complex projects or high priority risks

ENMG 698c: Special Topics - Project Risk Management - Dr. Rayan Khraibani
35
Copyright © 2020-2021, American University of Beirut, All Rights Reserved
ENMG 698c: Special Topics - Project Risk Management - Dr. Rayan Khraibani
36
Copyright © 2020-2021, American University of Beirut, All Rights Reserved
Tools and techniques
▪ Expert judgment

▪ Data gathering

▪ Data analysis

▪ Team skills

ENMG 698c: Special Topics - Project Risk Management - Dr. Rayan Khraibani
37
Copyright © 2020-2021, American University of Beirut, All Rights Reserved
Tools and techniques
▪Representation of uncertainty
▪ Probability distributions
▪ Probability trees
▪Data analysis
▪ Sensitivity analysis
▪ Monte-Carlo simulation
▪ Decision trees
▪ Influence diagrams

ENMG 698c: Special Topics - Project Risk Management - Dr. Rayan Khraibani
38
Copyright © 2020-2021, American University of Beirut, All Rights Reserved
Example: Probability distribution

Construction
costs

ENMG 698c: Special Topics - Project Risk Management - Dr. Rayan Khraibani
39
Copyright © 2020-2021, American University of Beirut, All Rights Reserved
Example: a Tornado diagram

ENMG 698c: Special Topics - Project Risk Management - Dr. Rayan Khraibani
40
Copyright © 2020-2021, American University of Beirut, All Rights Reserved
Example: a decision tree

ENMG 698c: Special Topics - Project Risk Management - Dr. Rayan Khraibani
41
Copyright © 2020-2021, American University of Beirut, All Rights Reserved
Example: Monte-Carlo simulation

ENMG 698c: Special Topics - Project Risk Management - Dr. Rayan Khraibani
42
Copyright © 2020-2021, American University of Beirut, All Rights Reserved
-800
-600
-400
-200
0
200
400
600

-1200
-1000

-1400
Cash flows / 2005
Cash flows / 2007
Cash flows / 2009
Cash flows / 2011
Cash flows / 2013
Cash flows / 2015
Cash flows / 2017
Cash flows / 2019
Cash flows / 2021
Example: trend chart

Cash flows / 2023


Cash flows / 2025
Cash flows / 2027
Cash flows / 2029
Cash flows / 2031
Cash flows / 2033
Cash flows / 2035
Cash flows / 2037
Cash flows / 2039
Cash flows / 2041
Cash flows / 2043
Cash flows / 2045
Cash flows / 2047
Cash flows / 2049
Cash flows / 2005 to Cash flows / 2060

Cash flows / 2051


Cash flows / 2053
Cash flows / 2055
Copyright © 2020-2021, American University of Beirut, All Rights Reserved

Cash flows / 2057


ENMG 698c: Special Topics - Project Risk Management - Dr. Rayan Khraibani

Cash flows / 2059


Mean
5% - 95%
+/- 1 Std. Dev.

43
Responses

ENMG 698c: Special Topics - Project Risk Management - Dr. Rayan Khraibani
44
Copyright © 2020-2021, American University of Beirut, All Rights Reserved
Plan risk response process
▪ Consists of developing options and deciding on actions and
strategies to address project risk (negative or positive)

▪ Responses should be adapted to the importance and impact of


risks and be cost effective (strategic decision making)

▪ May include more than one level of contingency planning

ENMG 698c: Special Topics - Project Risk Management - Dr. Rayan Khraibani
45
Copyright © 2020-2021, American University of Beirut, All Rights Reserved
ENMG 698c: Special Topics - Project Risk Management - Dr. Rayan Khraibani
46
Copyright © 2020-2021, American University of Beirut, All Rights Reserved
Tools and techniques
▪ Expert Judgment
▪ Data Gathering
▪ Team skills
▪ Strategies (threats, opportunities, contingent responses)
▪ Data Analysis (alternative, cost-benefit analysis)
▪ Decision Making (risk/return, multicriteria)

ENMG 698c: Special Topics - Project Risk Management - Dr. Rayan Khraibani
47
Copyright © 2020-2021, American University of Beirut, All Rights Reserved
Outputs

▪Change Requests

▪Updates
▪ Project management plan
▪ Project documents

▪Risk register, risk report

ENMG 698c: Special Topics - Project Risk Management - Dr. Rayan Khraibani
48
Copyright © 2020-2021, American University of Beirut, All Rights Reserved
Example: risk register update

Risk Probability Impact Importance Preventive Contingency Owner


measures measures
Delay in 0.25 -2M Selection, Alternative X
procurement monitoring supplier
Devaluation 0.5 -1M hedging Additional Y
funding
Major 0.1 -50M Preventive Repairs & Z
breakdown maintenance
reschedule

ENMG 698c: Special Topics - Project Risk Management - Dr. Rayan Khraibani
49
Copyright © 2020-2021, American University of Beirut, All Rights Reserved
Implement risk response process
▪ Consists in implementing agreed-upon risk response plans

▪ Belongs to the execution group

▪ Can result in a change of schedule (activities, cost, resources)

ENMG 698c: Special Topics - Project Risk Management - Dr. Rayan Khraibani
50
Copyright © 2020-2021, American University of Beirut, All Rights Reserved
ENMG 698c: Special Topics - Project Risk Management - Dr. Rayan Khraibani
51
Copyright © 2020-2021, American University of Beirut, All Rights Reserved
Monitoring

ENMG 698c: Special Topics - Project Risk Management - Dr. Rayan Khraibani
52
Copyright © 2020-2021, American University of Beirut, All Rights Reserved
Monitoring risk process
▪ Consists of tracking the identified risks, monitoring the
implementation of the response plans, and evaluating the risk
management process effectiveness

▪ Uses performance information generated during project execution

ENMG 698c: Special Topics - Project Risk Management - Dr. Rayan Khraibani
53
Copyright © 2020-2021, American University of Beirut, All Rights Reserved
ENMG 698c: Special Topics - Project Risk Management - Dr. Rayan Khraibani
54
Copyright © 2020-2021, American University of Beirut, All Rights Reserved
Tools and techniques
▪Data analysis
▪ Risk reassessment
▪ Variance and trend analysis (technical performance, costs,
resources)
▪Audits
▪Meetings

ENMG 698c: Special Topics - Project Risk Management - Dr. Rayan Khraibani
55
Copyright © 2020-2021, American University of Beirut, All Rights Reserved
Example: burn-down chart

ENMG 698c: Special Topics - Project Risk Management - Dr. Rayan Khraibani
56
Copyright © 2020-2021, American University of Beirut, All Rights Reserved
Conclusion

ENMG 698c: Special Topics - Project Risk Management - Dr. Rayan Khraibani
57
Copyright © 2020-2021, American University of Beirut, All Rights Reserved
Specific R.M. documents
▪ Risk register
▪ In table form, contains information on individual project risks
▪ List, impact, probability, importance, responses, status, owner
▪ Risk report
▪ Higher level summary, contains strategic information
▪ Threats and opportunities, risk management results, strategies

ENMG 698c: Special Topics - Project Risk Management - Dr. Rayan Khraibani
58
Copyright © 2020-2021, American University of Beirut, All Rights Reserved
Organizational memory
▪ Issue log
▪ Lesson learned register

ENMG 698c: Special Topics - Project Risk Management - Dr. Rayan Khraibani
59
Copyright © 2020-2021, American University of Beirut, All Rights Reserved
Emergent practices
▪ Non-event risks
▪ Project resilience
▪ Value of flexibility and team work
▪ Integrated risk management
▪ Agile environments
▪ Frequent reviews – risks are identified and discussed in regular meetings
▪ Tools: risk burndown charts, Kanban boards, impact matrices

ENMG 698c: Special Topics - Project Risk Management - Dr. Rayan Khraibani
60
Copyright © 2020-2021, American University of Beirut, All Rights Reserved
Readings
▪ A guide to the PMBOK, Chapter 11

ENMG 698c: Special Topics - Project Risk Management - Dr. Rayan Khraibani
61
Copyright © 2020-2021, American University of Beirut, All Rights Reserved
Assignment
▪ Form teams for the final presentation
▪ 11 teams, 7 students per team
▪ Write a one-page proposal

ENMG 698c: Special Topics - Project Risk Management - Dr. Rayan Khraibani
62
Copyright © 2020-2021, American University of Beirut, All Rights Reserved