Pt. Duta Utama Tehnik Abadi: Blasting & Painting

This document is an inspection report for blasting and painting work at a compressor room workshop. It summarizes the surface preparation including abrasive cleaning method, paint products and specifications. Weather conditions during blasting and each painting coat are reported. Dry film thickness measurements for the primer, second and finish coats are within specifications. The final inspection found the work to be acceptable.

Uploaded by

marifa tullah
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLS, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
664 views3 pages

Pt. Duta Utama Tehnik Abadi: Blasting & Painting

This document is an inspection report for blasting and painting work at a compressor room workshop. It summarizes the surface preparation including abrasive cleaning method, paint products and specifications. Weather conditions during blasting and each painting coat are reported. Dry film thickness measurements for the primer, second and finish coats are within specifications. The final inspection found the work to be acceptable.

Uploaded by

marifa tullah
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLS, PDF, TXT or read online on Scribd
You are on page 1/ 3

BLASTING & PAINTING

PT. DUTA UTAMA TEHNIK ABADI


MECHANICAL -ELECTRICAL - CONSTRUCTION

INSPECTION REPORT
Project No. :
PROJECT : New Compressor Room
Doc. Number :
Location Blasting & Painting : Workshop PT. DUTA
Owner : PT. Vopak Terminal Merak
: -
ITEM NAME :
LOCATION : Jl. Raya Merak Km. 3. Kel. Gerem
Appropriate Drawing
Mark No. / Item No. Profile Material Quantity
Length Thickness

CLEANING
SURFACE PREPARATION : DATE COLOUR OF PAINT
METHOD
Anchore Profile Primer Coat :
Type of Abrasive Cleanliness
2.0 - 3.0 mils (50 - 75 μm) Dry Blasting Second Coat :
Finish Coat :
PAINT PRODUCT NAME / TYPE OF PAINT
MANUFACTURE PRIMER COAT SECOND COAT FINISH COAT

Weather Condition of Blasting & Painting



PAINTING
st nd rd
1 2 3
Time
Wet Bulb (ºC)
Dry Bulb (ºC)
Relative Humidity (%)
Dew Point (ºC)
Steel Temperature (ºC)
DRY FILM THICKNESS REPORT Reference :
1 2 3 4 5
No DESCRIPTION AVERAGE DFT OF PER COAT DATE REMARKS
DFT (μm) DFT (μm) DFT (μm) DFT (μm) DFT (μm)
1 PRIMER COAT
2 SECOND COAT
3 FINISH COAT

RESULT : √ Accepted Rejected


Table 1 Painting
NOTE : Only for Type of Abrasive to be Reference WI-DUTA-Paint-01 Specification
FINAL INSPECTION :

PT. DUTA UTAMA TEHNIK ABADI PT. Synthetic Rubber Indonesia


PREPARED & CHECKED BY : APPROVED BY :
PT. DUTA UTAMA TEHNIK ABADI PICTURE OF INSPECTION (BLASTING)
MECHANICAL -ELECTRICAL - CONSTRUCTION

PREPARED & CHECKED BY : CHECKED BY : APPROVED BY

SUWARNO
HAFID QUALITY CONTROL
PT. DUTA UTAMA TEHNIK ABADI PT. DUTA UTAMA TEHNIK ABADI PT. Vopak Terminal Merak
PHOTOGRAPH
PT. DUTA UTAMA TEHNIK ABADI
FOR
MECHANICAL -ELECTRICAL - CONSTRUCTION
DRY FILM THICKNESS (DFT)

(3 COAT SYSTEM)

Primer Coat
84.5 µm 82.8 µm 78.7 µm 81.4 µm 77.4 µm

Second Coat
215 µm 208 µm 216 µm 218 µm 202 µm

Finish Coat
298 µm 264 µm 282 µm 306 µm 257 µm

Judgment √ Acceptable Unacceptable


PT. DUTA UTAMA TEHNIK ABADI PT. Vopak Terminal Merak