Revenue Recognition: Long Term Construction

Download as docx, pdf, or txt
Download as docx, pdf, or txt
You are on page 1of 2

REVENUE RECOGNITION: LONG TERM CONSTRUCTION

Question 10: XI - Incomplete Data


In 20x4, Joey Building Inc. began work on a four-year construction project The contract price is P300
million. Joey uses the overtime/percentage-of-completion method accounting. At the end of 20x5, the
following financial statement information indicates the results to date for Cincy One:
Income Statement:    
Gross profit (before taxes) recognized in 20x4 P 22
 
million
Balance Sheet:    
Accounts Receivable from construction billings P14
 
million
Construction in progress P 66 million  
Less: Billings on construction (75 million)  
Net billings in excess of construction in progress   P 9 million
Cash Flow Statement    
Cash Collection P 46
 
million

Required: Compute the following, placing your answer in the spaces provided and supporting
computations below:
1. 3Cash collected by Joey on Cincy One during 20x4
2. Actual costs incurred by Joey on Cincy One during 20x4
3. On December 31, 20x4, the estimated remaining costs to complete
4. The percentage of Cincy One that was completed during 20x4

Question 11: XII - Incomplete Data


In 20x4, Johnson Builders began construction work under a three-year contract at a price d
P7,525,000. The firm uses the overtime/percentage-of-completion method for finances accounting
purposes. The income to be recognized each year is based on the proportion of cost incurred to the
total estimated costs for completing the contract. The financial statement presentations relating to this
contract on December 31, 20x4, are:
Balance Sheet:    
Accounts Receivable   P 150,000
Construction in progress P  
602,000
Less: Progress billings 562,000 40,000
Income Statement    
Gross profit on construction contracts   P 301,000
 
Required: Determine the:
1. Cash collected in 20x4.
2. Estimated income on the construction contract.

You might also like