QAQC Report Mara

This quality assurance and quality control report is for a project to prepare a second tender proposal for the construction of permanent buildings at the MARA Mukah Vocational College in Sarawak, Malaysia. The report outlines the quality assurance plan, quality control implementation system, and relevant construction guidelines. It also provides details on the project site layout, contract particulars such as scope of work, quality assurance team, construction drawings, method statements, inspection forms, and material approval log. The objective is to ensure the highest quality and efficiency in executing the project according to JKR construction standards.

Uploaded by

Kevin Chang
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
445 views11 pages

QAQC Report Mara

This quality assurance and quality control report is for a project to prepare a second tender proposal for the construction of permanent buildings at the MARA Mukah Vocational College in Sarawak, Malaysia. The report outlines the quality assurance plan, quality control implementation system, and relevant construction guidelines. It also provides details on the project site layout, contract particulars such as scope of work, quality assurance team, construction drawings, method statements, inspection forms, and material approval log. The objective is to ensure the highest quality and efficiency in executing the project according to JKR construction standards.

Uploaded by

Kevin Chang
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 11

MARA

Version 0
Date : 18.06.2020

MAJLIS AMANAH RAKYAT

QUALITY ASSURANCE QUALITY CONTROL


REPORT
[ NOVEMBER ]

Title of Project: Menyiapkan Projek Sakit Bagi Tender Kali Kedua Cadangan
Pembinaan Bangunan Kekal Giatmara Mukah, Lot 5907, Blok 48, Mukah Land
District, Mukah, Sarawak

Prepared by:
APPL ENGINEERING SERVICES SDN. BHD.
Prepared By: Reviewed By: Acknowledge By:
Kevin Chang Wei Kiat Wallace Chong

1
MARA
Version 0
Date : 18.06.2020

Introduction
The objective of the Quality Assurance and Quality Control Report is to ensure that the
project is well executed with the highest level of quality and efficiency. This report is
purposely to clarify the work has done to follow the JKR standard of work. This report also
shows the area that was inspected through the “Inspection Form” (IF), test report, data
collective such as necessary form and site photo.

Quality Assurance Plan


A quality assurance plan is a document, constructed by the project team, meant to ensure
the final products are of the utmost quality. A quality assurance plan contains a set of
documented activities meant to ensure that customers are satisfied with the goods or
services a company provides.

Quality Control Implementation System


The QAP content are consisted on general information of the project, project team
responsibilities and construction procedure. When an effective construction QAP is
applied to a Project, it provides confidence and assurance that the quality of
workmanship and materials incorporated into the project comply with requirements and
specifications of the plan. This type of assurance is necessary in every construction
process.

Guidelines
The standard guidelines that will be used in preparing this QAP so that it can easily to
refer and any changes can be done during the process of test or inspections in uniform
manner.

Any references need to be stated so there are no confusions and difficulties during
alteration of the standard work during project commencement as stated below;

 Jabatan Kerja Raya, Standard Specification for Building Works 2014

 Jabatan Kerja Raya, Standard Specification for Road Works

 Jabatan Kerja Raya, Specification for Occupational Safety and Health for
Engineering Construction Works 2011

 General Specification for Watermain Construction

 Specification for Mechanical Services Works

 Specification for Electrical Services Works

2
MARA
Version 0
Date : 18.06.2020

Project Site Layout

3
MARA
Version 0
Date : 18.06.2020

Contract Particulars

1. Contract Title : Menyiapkan Projek Sakit Bagi Tender Kali Kedua


Cadangan Pembinaan Bangunan Kekal Giatmara
Mukah, Lot 5907, Blok 48, Mukah Land District,
Mukah, Sarawak

2. Client : Majlis Amanah Rakyat (MARA)

3. Contract Sum : RM 9,335,497.80

4. Contract No. : MARA 200-3/2/32/(68)

5. Superintending Officer : Majlis Amanah Rakyat (MARA)

6. Letter of Acceptance Date : 28th May 2020

7. Contract Commencement : 18th June 2020


Date

8. Contract Completion Date : 4th November 2021

9. Contract Period : Eighteenth (18) months

10. Defect Liability Period : Twelve (12) months

11. Time Extension Approved : Nil

12. Revised Contract : Nil


Completion Date

4
MARA
Version 0
Date : 18.06.2020

Scope of Work
A. Preliminaries Work
1. Site Survey
2. Shop Drawing, Calculation Etc
3. As built drawing
4. Safety measure
5. Programme of Work
6. Progress Report and photograph
7. Insurances
8. CIDB levy
9. Contractors storage, welfare and site accommodations
10. Site office and equipment
11. Hoarding
12. Security on site
13. Quality assurance plan
14. Safety and health
B. Piling Works
1. Test piles
2. Load test
3. Pile integrity test
4. 200mm x 200mm Precast reinforced concrete
5. Bakau Piles
C. Building Works
1. Blok Pentadbiran
2. Bengkel Pendawaian Elektrik
3. Bengkel Teknologi Kimpalan dan Fabrikasi Logam
4. Blok Transit Lelaki
5. Blok Transit Perempuan
6. Pusat Sampah
D. External works
1. Site Clearance and Earthwork
2. Road and Carpark
3. Reinforced Concrete Slab
4. Drainage Works
5. Sewerage Drainage
6. External Water Reticulation
7. Turfing
E. Built in Furniture
F. Landscaping
G. Signages
H. Mechanical and Electrical Services

5
MARA
Version 0
Date : 18.06.2020

Contract’s Quality Assurance Team

6
MARA
Version 0
Date : 18.06.2020

List of Construction Drawing

7
MARA
Version 0
Date : 18.06.2020

List of Method Statement

8
MARA
Version 0
Date : 18.06.2020

Request of Request For Information (RFI)

9
MARA
Version 0
Date : 18.06.2020

List of Request for Inspection Form /Pre-concreting Form

10
MARA
Version 0
Date : 18.06.2020

List of Material Approval Status Log

11