QAQC Report Mara
QAQC Report Mara
Version 0
Date : 18.06.2020
Title of Project: Menyiapkan Projek Sakit Bagi Tender Kali Kedua Cadangan
Pembinaan Bangunan Kekal Giatmara Mukah, Lot 5907, Blok 48, Mukah Land
District, Mukah, Sarawak
Prepared by:
APPL ENGINEERING SERVICES SDN. BHD.
Prepared By: Reviewed By: Acknowledge By:
Kevin Chang Wei Kiat Wallace Chong
1
MARA
Version 0
Date : 18.06.2020
Introduction
The objective of the Quality Assurance and Quality Control Report is to ensure that the
project is well executed with the highest level of quality and efficiency. This report is
purposely to clarify the work has done to follow the JKR standard of work. This report also
shows the area that was inspected through the “Inspection Form” (IF), test report, data
collective such as necessary form and site photo.
Guidelines
The standard guidelines that will be used in preparing this QAP so that it can easily to
refer and any changes can be done during the process of test or inspections in uniform
manner.
Any references need to be stated so there are no confusions and difficulties during
alteration of the standard work during project commencement as stated below;
Jabatan Kerja Raya, Specification for Occupational Safety and Health for
Engineering Construction Works 2011
2
MARA
Version 0
Date : 18.06.2020
3
MARA
Version 0
Date : 18.06.2020
Contract Particulars
4
MARA
Version 0
Date : 18.06.2020
Scope of Work
A. Preliminaries Work
1. Site Survey
2. Shop Drawing, Calculation Etc
3. As built drawing
4. Safety measure
5. Programme of Work
6. Progress Report and photograph
7. Insurances
8. CIDB levy
9. Contractors storage, welfare and site accommodations
10. Site office and equipment
11. Hoarding
12. Security on site
13. Quality assurance plan
14. Safety and health
B. Piling Works
1. Test piles
2. Load test
3. Pile integrity test
4. 200mm x 200mm Precast reinforced concrete
5. Bakau Piles
C. Building Works
1. Blok Pentadbiran
2. Bengkel Pendawaian Elektrik
3. Bengkel Teknologi Kimpalan dan Fabrikasi Logam
4. Blok Transit Lelaki
5. Blok Transit Perempuan
6. Pusat Sampah
D. External works
1. Site Clearance and Earthwork
2. Road and Carpark
3. Reinforced Concrete Slab
4. Drainage Works
5. Sewerage Drainage
6. External Water Reticulation
7. Turfing
E. Built in Furniture
F. Landscaping
G. Signages
H. Mechanical and Electrical Services
5
MARA
Version 0
Date : 18.06.2020
6
MARA
Version 0
Date : 18.06.2020
7
MARA
Version 0
Date : 18.06.2020
8
MARA
Version 0
Date : 18.06.2020
9
MARA
Version 0
Date : 18.06.2020
10
MARA
Version 0
Date : 18.06.2020
11