Chapter 4 Wcu
Chapter 4 Wcu
Chapter 4 Wcu
CHAPTER FOUR
4. COLLECTION AND DISTRIBUTION OF WATER
4.1 Intakes.
Intakes are devices or structures in a surface water source to draw water from this source and
then discharge in to an intake conduit through which it will flow in to the water works
system.
An intake consists of:
The opening, strainer, or grating through which the water enters, and
The conduit conveying the water, usually by gravity, to a well or sump.
From the well the water is pumped to the mains or treatment plant. Intakes should be so
located and designed that possibility of interference with the supply is minimized and where
uncertainty of continuous serviceability exists, intakes should be duplicated.
The following must be considered in designing and locating intakes:
a) The source of supply, whether impounding reservoirs, lakes, or rivers (including the
possibility of wide fluctuation in water level).
b) The character of the intake surroundings.
Depth of water
Character of bottom
Navigation requirement
The effect of currents floods and storms up on the structure and in scouring the
bottom.
c) The location with respect to sources of pollution; and
d) The prevalence of floating materials such as ice, and vegetation
1
Wachemo University- Department of Civil Engineering
CHAPTER FOUR collection and distribution
by gate valves on short lengths of pipe. Where the dam is of masonry, the intake may be a well
in the dam structure itself, also with openings at various heights.
Or
Figure 4.1b Tower water intake for a lake or reservoir water supply
ii) River Intakes
Where rock foundations are available, some cities have built elaborate river intakes, resembling
bridge piers with ports at various depths, to allow for great fluctuations in river stage. Small
cities may use pipe intakes similar to those described under lake intakes. The bottom must be
sufficiently stable. And the water deep enough to allow for a submergence of at least 1m at all
times with a clear opening beneath the pipe so that any tendency to form a bar is overcome.
2
Wachemo University- Department of Civil Engineering
CHAPTER FOUR collection and distribution
The inlet end of the pipe is provided with an enlarged bell mouth, to which is fixed a
hemispherical fine screen which prevents floating materials from entering the intake pipe. Also,
there is a coarse screen provided so that big floating particles are excluded. The water from the
out let of the intake pipe is led to a sump well or supply.
3
Wachemo University- Department of Civil Engineering
CHAPTER FOUR collection and distribution
v) Infiltration Galleries
Infiltration galleries are widely used many monsoon countries, such as India, to abstract water
from river- bed deposits where surface flow disappears during the dry period but subterranean
flow continues. A large diameter concrete caisson or ‘wet well’ is sunk in the river bed
sediments. The infiltration galleries comprise porous, perforated or un- jointed concrete or
asbestos-cement pipes, usually 200-300mm diameter, laid in gravel filtered trenches cut in the
river-bed sediments, connected to the wet well in which the pumps are sited. The galleries, of
which there may be several many meters long, extend cross- River or up-river to places where
it is thought will best pick up the main subterranean flow.
4
Wachemo University- Department of Civil Engineering
CHAPTER FOUR collection and distribution
1. Gravity Distribution. This is possible when the source of supply is a lake or impounding
reservoir at some elevation above the city so that sufficient pressure can be maintained in
the mains for domestic and fire service. This is the most reliable method if the conduit
leading from source to city is adequate in size and well safeguard against accidental breaks.
High pressure for fire fighting, however, may be obtained only by using the motor pumps
of the fire department.
2. Distribution by means of pumps with storage. In this method the excess water pumped
during periods of low consumption is stored in elevated tanks or reservoirs. During periods
of high consumption the stored water is drawn up on to augment that pumped. This method
allows fairly uniform rates of pumping and hence is economical, for the pumps may be
operated at their rate capacity. Since the water stored furnishes a reserve to care for fires
and pump breakdowns, this method of operations fairly reliable. Motor pumpers must
ordinarily be used for higher fire pressure, although it is possible to close the valves leading
to the elevated storage tanks and operate a fire pump at the pumping plant.
5
Wachemo University- Department of Civil Engineering
CHAPTER FOUR collection and distribution
3. Use of Pumps with out storage. In this method the pumps force water directly in to the
mains with no other outlet than the water actually consumed. It is the least desirable system,
for a power failure would mean complete interruption in water supply. As consumption
varies, the pressure in the mains is likely to fluctuate. To conform to the varying
consumption several pumps are available to add water output when needed, a procedure
requiring constant attendance. The peak power consumptions of the water plant is likely to
occur during periods of otherwise high current consumption and thus increase power cost.
An advantage of direct pumping is that a large fire service pump may be used which can
run up the pressure to any desired amount permitted by the construction of the mains.
4.3.1 Functions
It is seldom possible or economic for a source to give a fluctuating out put in step with demand.
Filtration plants need to be run 24 hours a day with only infrequent, carefully controlled
changes of out put. Pumps need to be run near their design point for maximum efficiency,
whilst electricity tariffs may influence their running times; it is not economical for a long
supply main to have an overlarge capacity simply to meet the peak demand of a few hours
duration. A technical and economic study of the capital and operating costs of the various
options available, including possible silting for a service reservoir is necessary before deciding
service reservoir requirements.
During the summer months the evening peak may be higher and more prolonged due to garden
watering. There will be a slightly different pattern of demand at weekends and on holidays. In
6
Wachemo University- Department of Civil Engineering
CHAPTER FOUR collection and distribution
the winter there will also be a higher rate through out if a severe frost causes many pipes burst
on consumers’ premises.
The elevation at which it is desirable to position a service reservoir depends up on both the
distance of the reservoir from the distribution area and the elevation of the highest building to
be supplied.
If the distribution area varies widely in elevation it may be necessary to use two more service
reservoirs at different levels, so that the lower area do not receive an unduly high pressure.
Wherever possible the use of non-stand pipes for high pressures should be avoided as such
pipes are expensive.
Pressure control valves are some times installed in inlet mains from service reservoirs in order
to reduce the pressure to low laying zones, or to limit increase of pressure at night to reduce
leakage. In making a decision to install pressure control devices it should be borne in mind that
if the device fails to operate, which it will do if the equipment is not properly maintained, then
the downstream mains will be subjected to a sudden increase of pressure and may burst. In
addition, excessive wastage of water may also take place through consumers’ ball valves
unaccustomed to working at high heads.
Break pressure tanks give better protection to low laying zones and are preferable to pressure
reducing devices; however the use of them or pressure reducing valves in pumping schemes
represent a direct wastage of pumping energy and more economic alternative should be sought.
7
Wachemo University- Department of Civil Engineering
CHAPTER FOUR collection and distribution
MANHOLE
LADDER
WATER LEVEL INDICATOR
INFLOW PIPE
OUTLET PIPE
DITCH
8
Wachemo University- Department of Civil Engineering
CHAPTER FOUR collection and distribution
Equalizing or operating capacity can be obtained from a mass curve of water consumption rates
and pumping supply rates.
1) The capacity can be analytically determined by finding out maximum cumulative
surplus during the stage when pumping rate is higher than water consumption rate and
adding to this maximum cumulative deficit which occurs during the period when the
pumping rate is lower than the demand rate of water.
2) The above figure can be obtained by drawing mass curves of water consumption rates
and water pumping supply rates.
Determine the capacity of a service reservoir if pumping is done 24 hours at constant rate.
Solution
Water supply = 150l/c/d
Total water demand = demand * population = 150*1600 = 240,000liters
Rate of pumping = 240,000/24 = 10,000lit/hr = 30,000lit/3hr
Solution.
Total water demand = 240,000lit/hr
9
Wachemo University- Department of Civil Engineering
CHAPTER FOUR collection and distribution
Case II
10
Wachemo University- Department of Civil Engineering
CHAPTER FOUR collection and distribution
B) Graphical Method:
MASS CURVE
300000
200000
150000
MAX DEFICIT
100000
Max Surplus
50000
0
0 2 4 6 8 10 12 14 16 18 20 22 24 26
TIM E (HOURS)
11
Wachemo University- Department of Civil Engineering
CHAPTER FOUR collection and distribution
A. Depth
There is an economical depth of service reservoir for any given site. For a given quantity of
water either a shallow reservoir having long walls and a large floor area may be constructed or,
alternatively. A deep reservoir may be constructed with high retaining walls and a smaller floor
area. Depths most usually used are as follows:
B. Shape
Circular reservoir is geometrically the most economical shape, giving the least amount of
walling for a given volume and depth: it has the attraction of allowing construction of a thin
reinforced concrete dome shaped roof, free of all supporting columns, resting on ring beam
fixed to the top of the wall for diameters of up to about 60m.
However, this shape is seldom adopted. It is unsuitable for division in to two compartments,
which would allow one half to be drained for maintenance without taking the whole reservoir
out of service.
Its shape frequently does not permit best use of available land, and
Problems of design will arise if it is to be partially buried in sloping ground
A rectangular reservoir with a length to width ratio 1.2 to 1.5:
Usually proves most economical when division walls are incorporated
Floors and roof should be sloped to not flatter than 1:250 for drainage ( such slopes
should be parallel to maintain uniform column and wall heights)
The total depth of the reservoir must be sufficient to allow the maximum inflow
assumed in the design calculation to pass over the over flow weir, with a safety
margin of at least 150mm below the under side of roofing beam.
It is good practice to set the over flow weir slightly higher, say by 50mm, than the top
water level at which the supply is cut off by a ball valve or an electrode.
12
Wachemo University- Department of Civil Engineering
CHAPTER FOUR collection and distribution
Disadvantage
The breakage of this pipe is large
Carrying capacity decreases with increase in life
The pipes become heavy and uneconomical when their sizes increase (especially
beyond 1200mm)
13
Wachemo University- Department of Civil Engineering
CHAPTER FOUR collection and distribution
Disadvantage
14
Wachemo University- Department of Civil Engineering
CHAPTER FOUR collection and distribution
2
1. Darcy –Weisbach formula; h f fLV
2 gD
2. Hazen-Williams formula; Q 0.278CD 2.63S 0.54 , S h f
L
3. Manning’s Formula; 1AR 2 / 3 S 1 / 2
Q
n
* The most common pipe flow formula used in design and evaluation of a water distribution
system is the Hazen-Williams’ formula.
The water supply pipes sizes available are given in the following table:
Metric sizes 10 20 25 30 40 50 60 80 100 150 200 250 300 350 375 400 450 500 525 600
(mm)
English (In) 1/2 3/4 1 11/4 11/4 2 21/2 3 4 6 8 10 12 14 15 16 18 20 21 24
Solution
Total flow, Q = Demand* Population = 150*80,000 = 12x106 lit/day
12 X 10 6
0.1389m 3 / sec
(24 * 60 * 60 *10 3 )
Required pipe area, A Q D Q D 4Q 0.1389 * 4 343mm
2
V 4 V V 1.5 *
But the pipe size available on the market is 300mm & 350mm, then take D = 350mm
Example-2
A town has a population of 100,000 persons. It is to be supplied with water from a reservoir
situated at a distance of 6.44km. It is stipulated that one-half of the daily supply of 140lit/capita
should be delivered in 6 hours. If the loss of head is estimated to be 15m, calculate the size of
pipe. Assume f = 0.04.
Solution
Total daily supply = 100,0003 *140 14,000m 3
10
Since half of this quantity is required in 6 hours
Maximum flow = 14,000
0.324m 3 / s
(2 * 6 * 60 * 60)
According to the Darcy-Weisbach formula:
15
Wachemo University- Department of Civil Engineering
CHAPTER FOUR collection and distribution
fLQ 2
hf Where, hf = 15m,f = 0.04, L= 6440m
12.1d 5
b) What size of pipe line (L = 1000m) should be used to supply 100l/s so that the head loss
does not exceed 10m. Use both the three formula, C= 100, n = 0.013, f = 0.035, find also the
velocity.
1) Darcy-Weisbach formula
fLV 2
hf
2 gD
Where, hf = head loss (m)
F = friction factor (which is related to the relative roughness of the pipe material &
the fluid flow characteristics)
L = length of pipe (m)
V = velocity of flow (m/s)
D = diameter of pipe (m)
G = Acceleration due to gravity (9081m/s2)
The term hf represents the energy loss that occurs in any distribution system. The major
loss of energy is due to friction between the moving water and pipe material; however,
energy losses also occur from flow disturbance caused by valves, bends in pipes line, and
changes in diameter.
Exercise-1. Calculate the head loss in 600mm pipe , 1500m long smooth walled concrete
( = 0.001) pipe line carrying a water of 0.30m3/s [Ans, hf = 2.43m)
16
Wachemo University- Department of Civil Engineering
CHAPTER FOUR collection and distribution
Cast Iron
Cement lined 130 – 150
New, unlined 130
5years-old, unlined 120
20 years old, unlined 100
Concrete 130
Copper 130 - 140
Plastic 140 -150
New welded Steel 120
New riveted Steel 100
Nomographs shown in fig – solve the equation for C = 100.Given any two of the parameters
(Q, D, hf or V) the remaining can be determined from the intersections along a straight line
drawn across the nomograph.
Exercise -3
For Q = 30l/s, D = 200mm,C = 100,L = 1500,Find hf.
Solution
From nomograph, hf = 12.15m
Using the formula, hf = 12.30m
2 / 3 1/ 2
3) Manning’s Formula; Q 1AR S , R = D/4, S = hf/L
n
Where, n = Coefficient of roughness depending on pipe material, usually
n = 0.013 GI pipes
n = 0.009 Plastic pipes
n = 0.015 Clay concrete pipes
Exercise 4.
For Q = 30l/s, D = 200mm,n = 0.013,L = 1500
hf 10.936n 2 Q 2 10.936n 2 Q 2 10.936(0.013) 2 (30 / 100) 2
S hf * L *1500 12.550
L D16 / 3 D16 / 3 200 / 100016 / 3
From Nomograph, hf/L = 0.00825
= 0.00825*1500 = 12.38m
Valves. Used to isolate and drain pipe line sections for test, inspection, cleaning and repair
i) Gate valves. Are installed in every main and sub-main to isolate a portion of the
network system during a repair.
ii) Check-valves (Non-Return valves). Are generally used to prevent reversal of flow
when a pump is shot down
iii) Air-Relief Valves. In long pipes lines air will accumulate in the high points (summits)
of the line and may interfere with the flow. It is necessary, therefore, to place air relief
valves at those points where trouble is expected.
17
Wachemo University- Department of Civil Engineering
CHAPTER FOUR collection and distribution
iv) Pressure regulating valves. These valves automatically reduce pressure on the d/s side
to any desired magnitude and are used on lines entering low areas of a city, with out
such reductions pressures would be too high.
v) Sluice Gates. Are vertically sliding valves which are used to open or close openings in
to walls.
Fire hydrants. It is used on mains to provide a connection for fire hazards to
fire fighting
Water meters. In most cities, the water furnished to a consumer is measured,
and the consumer charged accordingly to the amount of water
consumed.
DEAD-END
MAIN
SUB-MAIN
Advantages
The design calculations are simple
Cut off valves required are comparatively less in number
The system is cheap and economical
Laying the water pipes is simple
Disadvantages
During repair, a large portion of the distribution system is affected
The pipes terminate at the dead-end and no circulation of air (due to stagnation,
pollution may occur)
Common in small scale rural water supply schemes
2. Grid Pattern. In this pattern, the main, sub-mains and branches are interconnected with
each other.
18
Wachemo University- Department of Civil Engineering
CHAPTER FOUR collection and distribution
LOOP
Advantages
Flow can occur in more than one direction and stagnation does not occur
In case of repairs, a very small portion of the distribution area will be affected
When a fire occurs plenty of water is available for fighting purposes.
Disadvantages
The cost of laying the system is high
The procedure for calculating the sizes of pipes and for working out pressures
are complicated
A large number of valves are required.
Pipe networks (Grid Pattern)
A group of interconnected pipes forming several loops or circuits is called a network of pips.
Such networks of pipes are commonly used for municipal water distribution systems in cities.
The main problem in a pipe network is to determine the distribution of flow through the various
pipes of the network such that all the conditions of flow are satisfied and all the circuits are
then balanced.
The conditions to be satisfied in any network of pipes are as follows:
1. According to the principle of continuity the flow into the junction must be equal to the
flow out of the junction.
2. In each loop, the loss of head due to flow in clock wise direction must be equal to the loss
of head due to flow in anti-clock wise direction.
3. The Darcy – Weisbach equation must be satisfied for flow in each pipe.
Minor losses may be neglected if the pipe lengths are large. However, if the minor
losses are large , they must be taken into account by considering them interims of the
head lost due to friction in equivalent pipe lengths
according to Darcy- Weisbach equation the loss of head hf though any pipe
discharging at the rate of Q can be expressed as:
H L KQ n -------------------- (1)
Where K = proportionality factor which can be determined for each pipe, knowing the friction
factor f, length L, and the diameter D of the pipe.
fL
K ----------------------- (2)
12.1D 5
n = an exponent having a numerical value ranging from 1.72 to 2.0.
For any pipe if Qo is the assumed discharge and Q is the corrected discharge, then:
Q Qo Q ---------------------- (3)
and the head loss for each pipe is
19
Wachemo University- Department of Civil Engineering
CHAPTER FOUR collection and distribution
Q
KQo n
hL ------------------ (9)
KnQo n 1
hL
n ( )
Q
In the above expression for the correction the denominator is the sum of absolute terms
and hence it has no sign.
Further if the head losses due to flow in the clock wise direction are more than the head
losses in the due to flow in the anti-clock wise direction, then according to the sign
convention adopted, Q will be negative and hence it should be added to the flow in the
anti-clock wise direction and subtracted from the flow in the clock wise direction.
For pipes common to two circuits or loops a correction from both the loops will be
required to be applied.
With the corrected flow in all the pipes, a second trial calculation is made for all the
loops and the process is repeated till the correction becomes negligible.
20
Wachemo University- Department of Civil Engineering
CHAPTER FOUR collection and distribution
Water is supplied from a reservoir at an elevation of 200m. The elevations of various points in
the pipe line are given in brackets. Design the pipes RA, AA2and AB. Assume the minimum
pressure in pipes in resident area to be 35m of water and in business districts 50m of water.
R
ELE.
200m
Q=1000l/s,
L=3200m A
(100) Q =180l/s.
A1 L =1300m A2 (90m)
Q=600l/s,
L=2000m
B1 B(70m) B2
Q = 430l/s
L = 1200m
C1 C(55m) C2 Business
District
D1 D(54m) D2
Exercise-2 Find the floe distribution in the gravity supply system through the following pipe
network shown below. Use Hazen – Williams formula (C= 100) . If the pressure at point A is
490.5 KPa, find the pressures at points B & C. Assume all pipe junctions are at the same
elevation.
250l/s
F
A 45 l/s
B
45 l/s 75l/s 75l/s
30l/s
100l/s
LOOP II
LOOP I
10l/s
10l/s
D C
E
80 l/s 40l/s
40 l/s
21
Wachemo University- Department of Civil Engineering
CHAPTER FOUR collection and distribution
Solution
250l/s
F
A 45 l/s
B
45 l/s 75l/s 75l/s
30l/s
100l/s
LOOP II
LOOP I
10l/s
10l/s
D C
E
80 l/s 40l/s
40 l/s
22
Wachemo University- Department of Civil Engineering
CHAPTER FOUR collection and distribution
Exercise-2
C = 100
1st Correction loop I
Pipe Diameter Length Flow Slope Head loss hL/Q
D(mm) L(m) Q(l/s) (m/1000m) hL= S*L (m)
AD 250 1000 100 0.025 25.483 0.255
DE 150 2000 10 0.004 8.628 0.863
EF 200 1000 -30 -0.008 -8.127 0.271
FA 250 2000 -75 -0.015 -29.916 0.399
-3.933 1.787
Q11 = hL/1.85(hL/Q)
1.189
Q11 = hL/1.85(hL/Q)
3.755
Q21 = hL/1.85(hL/Q)
0.488
2ndCorrection loop II
Pipe Diameter Length Flow Slope Head loss hL/Q
D(mm) L(m) Q(l/s) (m/1000m) hL= S*L (m)
AB 250 2000 78.755 0.016 32.749 0.416
BC 200 1000 33.755 0.010 10.111 0.300
CD 100 2000 -6.245 -0.013 -25.997 4.163
DA 250 1000 -97.435 -0.024 -24.285 0.249
-7.423 5.127
Q22= hL/1.85(hL/Q)
0.783
23
Wachemo University- Department of Civil Engineering
CHAPTER FOUR collection and distribution
Q31 = hL/1.85(hL/Q)
0.099
3rd Correction loop II
Pipe Diameter Length Flow Slope Head loss hL/Q
D(mm) L(m) Q(l/s) (m/1000m)hL= S*L (m)
AB 250 2000 79.537 0.017 33.354 0.419
BC 200 1000 34.537 0.011 10.549 0.305
CD 100 2000 -5.463 -0.010 -20.289 3.714
DA 250 1000 -97.140 -0.024 -24.150 0.249
-0.535 4.687
Q32= hL/1.85(hL/Q)
0.062
4th Correction loop I
Pipe Diameter Length Flow Slope Head loss hL/Q
D(mm) L(m) Q(l/s) (m/1000m)hL= S*L (m)
AD 250 1000 97.240 0.024 24.196 0.249
DE 150 2000 11.777 0.006 11.681 0.992
EF 200 1000 -28.223 -0.007 -7.258 0.257
FA 250 2000 -73.285 -0.014 -28.662 0.391
-0.044 1.889
Q41 = hL/1.85(hL/Q)
0.013
Q42= hL/1.85(hL/Q)
0.005
24
Wachemo University- Department of Civil Engineering
CHAPTER FOUR collection and distribution
Q51 = hL/1.85(hL/Q)
0.001
5th Correction loop II
Pipe Diameter Length Flow Slope Head loss hL/Q
D(mm) L(m) Q(l/s) (m/1000m) hL= S*L (m)
AB 250 2000 79.605 0.017 33.406 0.420
BC 200 1000 34.605 0.011 10.587 0.306
CD 100 2000 -5.395 -0.010 -19.829 3.675
DA 250 1000 -97.185 -0.024 -24.170 0.249
-0.006 4.649
Q52= hL/1.85(hL/Q)
0.001
Q61 = hL/1.85(hL/Q)
0.000
Q52= hL/1.85(hL/Q)
0.000
25
Wachemo University- Department of Civil Engineering
CHAPTER FOUR collection and distribution
26
Wachemo University- Department of Civil Engineering
CHAPTER FOUR collection and distribution
27
Wachemo University- Department of Civil Engineering
CHAPTER FOUR collection and distribution
28
Wachemo University- Department of Civil Engineering
CHAPTER FOUR collection and distribution
Figure 4-7 Nomograph for Manning formula, for circular pipes flowing full based on n=0.013
29
Wachemo University- Department of Civil Engineering