RCDC-IRCWE-7195-001 Inspection Request - Ceiling, Wall Enclosure

Download as xls, pdf, or txt
Download as xls, pdf, or txt
You are on page 1of 2

PMD 09-004 / Rev.

RIDER HUNT LIACOR, INC.


INSPECTION REQUEST
REQUEST FOR CEILING / WALL CLOSURE
PROJECT : CONTRACTOR :
LOCATION : DATE :
CLIENT : BUILDING ID :

MATERIALS DESCRIPTION
AREA(S) TO BE INSPECTED LOCATION
CEILING/WALL FRAMING
ACTION CODE:
Approved
Approved subject to comments, work may proceed.
For reinspection
Disapproved, works cannot proceed

CONFIRMATION:

PARTICULARS RHLI REMARKS

LAYOUT

FRAMING/ SUPPORT

ELECTRICAL WORKS ROUGHING -INS

MECHANICAL WORKS ROUGHING- INS

SANITARY/ PLUMBING ROUGHING- INS

FIRE PROTECTION ROUGHING-INS

AUXILLARY

INSULATION

SERVICE & MAINTAINANCE ACCESS

INITIAL HYDROSTATIC PRESSURE TEST

INITIAL FLOW TEST

SPECIALTY WORK

OTHERS, PLS. SPECIFY

REQUESTED BY: INSPECTED BY :

CONTRACTOR'S REPRESENTATIVE RHLI - SITE ENGINEER

APPROVED BY:
I.S.O. 9001:2000
CONTROLLED COPY

CONSTRUCTION MANAGER
RCDC-IRCWE-7195-001

INSPECTION REQUEST - CEILING & WALL ENCLOSURE

PROJECT : CONTRACTOR :
LOCATION : DATE :
CLIENT : BUILDING ID :

MATERIALS DESCRIPTION
AREA(S) TO BE INSPECTED LOCATION
CEILING/WALL FRAMING ACTION CODE:

Approved

Approved, subject to comments, work may proceed

For reinspection

Disapproved, works cannot proceed

CONFIRMATION:

PARTICULARS CHPBCC REMARKS

LAYOUT

FRAMING/ SUPPORT

ELECTRICAL WORKS ROUGHING -INS

MECHANICAL WORKS ROUGHING- INS

SANITARY/ PLUMBING ROUGHING- INS

FIRE PROTECTION ROUGHING-INS

AUXILIARY

INSULATION

SERVICE & MAINTAINANCE ACCESS/ HANDHOLES/ MANHOLES

INITIAL HYDROSTATIC PRESSURE TEST

SPECIALTY WORK

OTHERS, PLS. SPECIFY

REQUESTED BY: INSPECTED BY :

CONTRACTOR'S REPRESENTATIVE CHPBCC - SITE ENGINEER

APPROVED BY:

CHPBCC - CONSTRUCTION MANAGER