Client: Nlcil Subject: Quality Assurance Plan For Side Drain (Rev-00)

This document outlines a quality assurance plan for a side drain project with the following key points: 1. It lists 4 main items to be checked - survey, surface dressing, PCC work, and RCC work. 2. For each item, it specifies the type of check, extent of checking, acceptance criteria, records to be maintained, and responsibilities of contractor and client. 3. It emphasizes 100% checking of critical activities like survey, concrete pouring and mixing through visual checks and documentation of test reports, with oversight shared between contractor and client.

Uploaded by

Sasanka Sekhar
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
144 views2 pages

Client: Nlcil Subject: Quality Assurance Plan For Side Drain (Rev-00)

This document outlines a quality assurance plan for a side drain project with the following key points: 1. It lists 4 main items to be checked - survey, surface dressing, PCC work, and RCC work. 2. For each item, it specifies the type of check, extent of checking, acceptance criteria, records to be maintained, and responsibilities of contractor and client. 3. It emphasizes 100% checking of critical activities like survey, concrete pouring and mixing through visual checks and documentation of test reports, with oversight shared between contractor and client.

Uploaded by

Sasanka Sekhar
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 2

QUALITY ASSURANCE PLAN

CLIENT: NLCIL
SUBJECT: QUALITY ASSURANCE PLAN FOR SIDE DRAIN (REV- 00)

Records to Agency
Sl. No Item Category Type / Method of check Extent of Reference Acceptance Format of record be Remarks
check document norms
furnished CONTRACTOR CLIENT
A B C D E F G H I J K

1 Survey

Co-ordinates / Levels of
a) Bench Mark recoding of Critical Visual checks 100% Approved Drg. As per approved Drg. Joint Record Yes P W Site Verification/Review
all effected working area

Checking of invert levels


& Alignmnets by TS Verifiaction of Calibartion Joint Record of bottom/invert
b) Critical 100% Approved Drg. As per approved Drg. Yes P W Site Verification/Review
system & Auto level as certifiacte level of Drain
per approved Drg. Wise

Checking of Calibration
Verifiaction of Calibartion
c) report for both machine Critical 100% Approved Drg. As per approved Drg. Calibration report Yes External Agency W Site Verification/Review
certifiacte
& prizom

2 Surface dressing

Specifications/ Specifications/
a) Checking for layout Major Dimensional check 100% Joint Records Yes P RW Site Verification/Review
Methodology Methodology

Breaking with proper


Specifications/ Specifications/
b) side slopes, Shoring Major Visual Checks 100% Joint Records No P RW Site Verification/Review
Methodology Methodology
Removing of Water, etc.

Checking location, firm


Specifications/ Specifications/
c) bed, levels, free from Major Visual Checks 100% -- yes P RW Site Verification/Review
Methodology Methodology
slush

Disposal/proper stacking
Specifications/ Specifications/
d) of breaking materials in Minor Visual Checks 60% -- No P RW Site Verification/Review
Methodology Methodology
demarked area.

3 PCC M 15 (1:2:4)/M 10 (1:3:6) Grade of Concrete as per approved Drg.

Free fall Height should


Lab Test report with proper
be mainted at site for
Pouring of Concrete MTC reqd . (NC, setting time
Specifications/ As per IS 456, IS avoiding any kind of
a) thickness as per Critical Visual Check 100% of Cement, Compressive Yes External Agency RW
Methodology 4031 & IS 10262 Seggregation. Reports
approved Drg. Wise Strength, Soundness &
are submitted before
Fineness Test of Cement)
working at site.

Checking of vibrating by
Site Verification/Review
neddle / plate Vibrator, if Specifications/
b) Critical Visual Check 80% As per IS 2505/2506 -- No P RW & minimum 14 days
reqd. as per site situation Methodology
Curing reqd.
basis

4 RCC M20/M25/M30 Grade of Concrete as per approved Drg. (If reqd.)

Lab Test report with proper


MTC (for cement only) reqd . Free fall Height should
(NC, setting time of Cement, be mainted at site for
Compressive Strength, avoiding any kind of
As per IS 456, IS Soundness & Fineness Test of Seggregation. Reports
4031 & IS 10262- Cement as per IS 4031 Part 1 to are submitted before
2019. For Agg. Part 6) & detailed Mix Design working at site. Also
Before Pouring of Visual Check, batch report of
Specifications/ Mechnaical report with trial mix. Also Agg. mechanical properties of
a) Concrete thickness as per Critical concrete must be checking 100% Yes External Agency RW
Methodology properties IS 2386 Mechanical properties Agg. As per IS 2386 Part
approved Drg. Wise reqd. as per IS 4925 wise
Part 1 to Part 4 & IS (Crushing value, Impact Value 1, Part 3 & Part 4
383-2016 Table 7 & with Combined Flakieness & checking reqd. & for
Table 9 reqd. Elongation index, Gradation of Fine pariticales Silt
10 mm,20mm & Sand Zone II) content with Gardation
must be mentioned in Desin test reqd. as per IS 383-
Mix report as per IS 383 - 2016 2016 Table 9 wise.
wise

Checking vibrating
needle/plate vibrator Specifications/
b) Critical Visual Check 100% As per IS 2505/2506 -- No P RW Site Verification/Review
before & during the Methodology
pouring of concrete

Cube sampling & testing


Visual Check as per IS 456 & Specifications/ As per IS 456 & IS Compressive strength checking
c) after the pouring of Critical 100% Yes P RW Site Verification/Review
516 part 1 wise Methodology 516 at 7 & 28 days basis.
concrete

Checking the Slump randomly


for Ajax or Transit mixer for
Slump test/ Consistency
every time of casting as per
Test of Concrete during Visual Check at site with Specifications/ As per IS 1199 Part 1
d) Critical 100% approved design mix; with Yes P RW Site Verification/Review
& before the pouring of Slump cone appratus Methodology & 2-2019 wise
tolerence as per IS 4925 & IS
concrete
4926 wise, also slump test
register reqd. at site

5 Reinforcement (Fe-500 D) (If reqd.)

Lab Test report with proper


Checking of
Visual Check with dimensions Specifications/ As per IS 1786-2008 MTC (BendTest, Rebend Test,
a) reinforcement (Fe-500D) Critical 100% Yes External Agency RW Site Verification/Review
as per approved BBS Methodology & IS 2502 Carbon Content & UTS with
& BBS
YS & Elongation)

6 Shuttering for Raft & Wall with checking of alignments


Shuttering stripping time must
be maintained as per IS 456
Shuttering of Raft & Dimensional checking reqd.
Specifications/ As per IS 456 & IS (Clause 11) wise, for better
a) Wall Critical by tape measurement 100% Yes P RW Site Verification/Review
Methodology 14687 wise stability purpose MS shuttering
according to approved Drg.
boards (plate thickness 3.5 mm)
may be used at site

Checking of top &


Checking reqd. by TS
bottom level of Raft as Specifications/ Specifications/
b) Critical system/Auto level to ensuring 100% Joint Records with sketch reqd. Yes P RW Site Verification/Review
per approved Drg. To Methodology Methodology
proper alignmnent with Slope
ensure the Slope

7 Curing (Water Ponding/Sparying with Hessian cloths)

Minimum 28 days reqd.


unless any other special
Curing is essential for 28 Specifications/ cases curing must be
a) Major Visual Check 100% As per IS 456 As per site surveillance wise Yes P RW
days minimum Methodology maintain 14 days as per
decide the EIC of
NLCIL.

8 Brick Work

Brick work (Brunt Clay Testing of bricks


bricksas per BOQ wise) reqd. as per IS 3495
Visual Check, before start of
where ever reqd. as per Part 1 to Part 4 wise, Joint Records (All relavant test
the Brick Works, it must be in Specifications/
a) site basis, with Cement Critical 100% Specification reqd. as reports of Bricks reqd. as per IS Yes External Agency RW Site Verification/Review
staturated condition based by Methodology
Mortar (1:4), Inside & per IS 1077 wise or code 3495)
water sprinking
outside plastering with as per mentioned in
same ratio BOQ

Specifications/ Specifications/ Minimum 07 days (as


b) Curing of Brick work Critical Visual Check 100% - Yes P RW
Methodology Methodology per IS 2212) reqd.

9 Back filling if applicable as per approved Drg.

Filling and compaction


in layers not more than
a) Critical Visual Checks 100% Specifications Specifications - Yes External Agency RM Site Verification/Review
300mm & CBR value
not less than 4

Filling & Compaction of


b) sand & aggregate around Critical Visual Checks 100% Specifications Specifications - Yes P RW Site Verification/Review
the PVC pipe

c) Check for final level Critical Visual Checks 100% Drawings Drawings - Yes P RW Site Verification/Review

10 Hume Pipe NP 4 Grade laying

Specially in joint portion


Visual Checking in joint of Hume pipes; Wire
NP 4 grade of Hume As per IS 458- As per IS 458-2003, Joint Records (MTC of Hume
portion for per Caulking Space mesh reqd. with rich
a) Pipe installed reqd. at Major 100% 2003, specifiaction specifiaction Pipe reqd. with mentioned the Yes P W
as per IS 458-2003 & Flush cement mortar as per
joint portion followed followed relavant parameters)
joints satndard specifiaction
wise

Legends: P PERFORM
R RANDOM
W WITNESS
RW RANDOM WITNESS
RM RANDOM MONITORING
MPDD MODIFIED PROCTOR DRY DENSITY
SPDD STANDARD PROCTOR DRY DENSITY