Thesis Project PM
Thesis Project PM
AUTHORS:
Thomas Filippa
Mohamad Mroue
Jisil Rishmawi
Group 12
Tutor:
Prof. Manuel Merchan
Madrid,
Spain June
2019
Abstract
rural areas. Therefore, JMT International has developed a construction project to build a
Healthcare Centre in Aldea el Rosario, since this village needs several health treatments.
The clinic will positively impact the lives of approximately 4,200 people, both in El Rosario and
nearby villages such as: Santo Domingo, La Union Otuta and Agua Caliente.
The essence of this project is managing, constructing and delivering the health Centre within the
constraints set. The project will have a duration of 1 year starting from the approval to the
It will be sponsored by USAID, JICA, Government and Rotary International. It will offer
primary medical services such as: general medicine, X-Ray services, obstetric, respiratory
Index of Figures
Project Sponsor:
The following were identified for the funding for the project,
Honduran Government
Rotary International
Project Client:
The project´s clients after completion are going to be the Municipality of Santa Rita de
Copán.
Project Justification:
The objective of the project is to provide health care services to the remote community
of Aldea El Rosario – Honduras. The citizens have experienced health care shortage due
to the absence of public facilities in the rural areas, as it takes up to two hours to reach
the closest clinic/hospital by walking distance, since none of the people in El Rosario
it is estimated that the network of services of the Ministry of health covers 60%,
The Social Security Institute covers 18%, a 5% the private sector, and the
1
Project Description
to all areas of the country. Due to this problem, the decision to build a health center
will help the citizens to have a closer medical assistance whenever they need it. It will
be located in rural community in El Rosario, Santa Rita de Copan that can be accessed
by children, women, men and senior citizens, some of the characteristics that the health
Diagnosis
Observation
Consultation
Treatment
Intervention
General Medicine
Obstetric
Respiratory
Emergency
The high level requirements that will be needed for the project are specified on Table 1.
Table 1: High Level Requirements
Activity Requirements
Construction Permits - Land use license
- INSEP permit
- Environmental standard according to ISO
- ACI Code
area
- Damage or theft of equipment and tools – Since 2010, Honduras has had one
Project Cost:
After analyzing all the activities, the proposed budget for the project is shown in table 2.
Activity Cost
Food $ 13,000
Transportation $ 10,800
Miscellaneous $ 5,000
Contingency 10 % $ 93,806
Project Schedule:
Total duration of the project will be of 1 year, and starting from January 1st, 2019.
- Medical employees
- Health Ministry
- Construction Firm
Approval:
The purpose of this project is to help the locals in Aldea El Rosario in their struggle to
have an accessible medical facility. Currently, there are no available healthcare services
and families have to travel to another town for assistance. The situation was reported
then Health Ministry but due to several problems they could not provide a solution. Our
project is to build a clinic to provide fast and high quality health assistance to all the
2.1.2 Methodology
The methodology in this project is going to take a Waterfall Methodology, being that
all the planning must be done at the initial part of the project due to the construction, it
follows a sequential guideline to plan, construct, test, and implement and there is no
2. The design specifications are created and evaluated on how the final result is
4. Testing - Once the construction has been finished, the final tests for delivery.
5. Delivery - The product is when the deliverables are made and submitted by the
team
2.1.3 Structure
The structure of this business case will consist in several stages consisting:
a) Definition of the case: First we describe the current situation in the health sector
in Honduras, to analyze the business needs and the project ticket request.
b) Definition of the strategic plan in how the project will operate which will help us
d) Definition of the triple constraint, the project cost, schedule and scope are
defined
f) Risks analysis
Rosario, we are going describe the health system in Honduras and how does that impact
The health sector consists of two subsectors. A public sub sector composed by
the Ministry of health (signal) corresponds to which the controller, guiding role
and provision of health services to the entire Honduran population and the
it is estimated that the network of services of the Ministry of health covers 60%,
The Social Security Institute covers 18%, a 5% the private sector, and the
(p.30)
there are challenges in the provision of basic health services to residents. Additionally,
most common health problems in the rural areas that are found are “infectious diseases,
diarrhea, adolescent pregnancy, chronic and respiratory diseases are also health
The health system in Honduras is going difficulties on its capacity to provide all citizen
with medication, resources and access to health this problems evidence in different
Médica, 2017),
- The fragmentation of the health system, without control over the coverage
and without dimensioning how much of the fundamental efforts are being made
types and amounts of resources needed to promote the service model, without the ability
to change the methods of recruitment, hiring and remuneration in force and to interlink
the recognition of individual performance with the institutional one and finally
contributed by the households and of them, the poorest suffer greater financial risk since
the direct payment to obtain health services comes from their pockets.
Medical Brigades
Being Honduras a third world country, it is difficult to the health system to provide
all citizens with medication, resources and access to health, especially in the rural
Honduras:
estimated that there are 10.1 doctors per 10,000. Data by departments showed
that Francisco Morazán had 23.8 doctors per 10,000 inhabitants while Lempira
and Santa Barbara each had 2 doctors per 10,000 inhabitants. None of the 18
as indicated by the regional human resources target and in contracting with the
average of the region of the Americas there is an unequal gap (20.8 physicians
Per 10,000).
Aldea El Rosario is located on Santa Rita in the department of Copan with an area of
314 km² and with a population of 31,829 and the families do not have an immediate
access to a healthcare facility: It takes them up to three hours to the next town to have
medical assistance. Moreover, the quality of the medical service is not always
the closest hospital to Aldea el Rosario does not have adequate equipment for the best
2.5.1 Mission
To provide to the locals living in Aldea El Rosario access of medical services, resources
and doctors with the construction of a Medical Healthcare Center sponsored by NGO
2.5.2 Vision
To improve the health condition and reduce the percentage of diseases of all the families
living in nearby villages that does not have access to medical assistance.
2.6 Values
For a successful project, the cores values in which are going to rely are:
3. Efficiency: Having the proper metrics in each aspect of the project will help us
determine how effectively and efficiently our team is performing in base of the
members and stakeholders, it results in a more effective project and can manage
The construction of the healthcare center id a Strategic Project due that has long
project on budget.
economic environment, inflation risks will be taken in account to make sure that
In terms of operational Objectives during the project, the operational objectives are
Reduce waste by 10% over the project life: Reducing environmental impact
usage.
operational costs.
Improve and maintain workplace safety: Comply with health and safety
and law.
work together productively. Cultural and language factors will be taken into
considerations.
The stakeholders that are going to be involved through the whole project are:
The citizens have experienced health care shortage due to the absence of public
facilities in the rural areas, as it takes up to three hours to reach the closest
immediate assistance. Moreover, the quality of the closest hospital is not as high as in
other parts of Central America. The medical clinic, in which the families have access,
can only provide medical attention to 1 or 2 persons at the same time, which makes
The clinic will improve the life of local people in Aldea el Rosario and neighbor
communities. It will provide immediate medical support to patients and will be able to
treat the whole community (estimated to be 4,200 considering the growth factor of 25
years).
The clinic will offer good medical assistance due to the investment being made and it
will consist with 7 exam rooms, 1 minor procedure room and X-ray facilities, in which
will make the waiting period shorter and faster. It will also have a pharmacy which
will have a supplied storage so that there always will have a good medicine inventory
The clinic will offer the basic medical services such as: of general medicine, X-Ray
The Smart Objectives identified for the project are shown in table 5
Provide medical assistance to local Medical records of each patient Ongoing process
years)
health ministry
The high level requirements are presented in order to meet the project, business and
Materials
Professional and
Nurses
18
2.14 Selection and Description of Optimal Solution
After analyzing the alternatives for solutions of the business needs, the Construction of
the healthcare center will have more impact on El Rosario and the nearby villages on
the health situation. Even though is going to have a higher cost at first than the other
options, it will not depend on environmental or transport problems. In the social factors,
with the Health center, the people will receive a more complete medical examination to
approximately 4,200 citizens and comparing with the medical brigades and offering
only the transportation to the nearest clinic, it will only impact around 400 people
The total duration of the project will be of 1 year, and starting from January 1st,
19
Painting September 7, 2019 September 27,
2019
Plumbing July 6, 2019 August 5, 2019
Figure 1 shows a visual representation of the time-line of the project. It will be further
The estimated budget for the construction of the healthcare center will be $1,135,053,
Description Cost
Start up $ 10,000
Food $ 13,000
Transportation $ 10,800
Miscellaneous $ 5,000
Contingency 10 % $ 93,806
There were several risks identified during each phase of the project. According to
Table 10, natural disaster and health and safety issues might represent a high risk.
The risk score was found by combining the impact and the probability on the risk matrix
Below is shown the actions to mitigate these risks. The risks are detailed on the table
Probability
Activities Associated Risk(s) Severity Risk Score Method(s) to Manage the Risk
Construction of the
Health and safety issues – not Strict supervision on site – make sure
clinic Critical Medium High
complying with regulations workers have insurance
23
Table 11: Risk Matrix
Severity
NEGLIGIBLE MARGINAL CRITICAL CATASTROPHIC
Small/unimportant Minimal importance; Serious/important; Maximum importance;
Not likely to have a Has an effect on the Will affect the operation of the Could result in disaster/death;
major effect on the operation of event but event in a negative way. WILL affect the operation of
operation of the event. will not affect the event the event in a negative way.
outcome.
25
2.18 Definition of Indicators, Measurement Systems, Targets and Control
To understand the efficiency and productivity of the project, the following variables are taken
into account. Then to control and monitor these variables, the KPIs that will be implemented are
Productivity of employees Number of hours to complete a task vs. Hourly salary per
employee
CV, CPI
being managed
SPI, SV
Quality Number of accidents on site
approved/unapproved orders)
Fatalities
QA&QC
The health system in Honduras is struggling to provide healthcare in all the country due
to poor management of resources and unequal financing on the health sector by the
Government. This results in insufficient medical care in the rural areas where the locals
do not have access for medical attention and medicines, which oblige them to walk a 3-
After analyzing the solutions through multi-criteria and the relative risks of the project,
the optimal solution is to build a healthcare center In Aldea el Rosario. This will
positively impact the lives of approximately 4,200 people, both in El Rosario and the
neighbor villages such as: Santo Domingo, La Union Otuta and Agua Caliente.
The project will have duration of 1 year starting from the approval to the delivery of the
JICA, Government and Rotary International. It will offer primary medical services such
as: general medicine, X-Ray services, obstetric, respiratory emergency and pharmacy that
The Scope Management Plan presented on this document shows how the project and
Product scope will be defined, validated, and controlled. For the Scope Management to be
1. Define High Level Requirements: This was used in order to complete the
Requirement Traceability Matrix with the project, business and product objectives
framework in which the project work will be performed and includes all the
3. Create WBS: The Work- Breakdown Structure was created which helps to a
better monitoring and controlling the project with its detailed work packages for
each deliverable and activity for each component for the WBS.
3.2 Requirement Traceability Matrix
The implementation of a requirements traceability matrix helps ensure that each requirement adds business value by linking it to the
business and project objectives. (Project Management Institute, 2017). The requirements Matrix are described in table 14.
5 Construction Team Medium Project NGO Hire a contractor company Signed agreement
6. Health Standards High Product NGO Operate with all health requirements Health Ministry
inside the clinic approval
7. Equipment Medium Product NGO Operate will all the necessary equipment
8. Medical Materials Medium Business NGO Have all graduated and experienced personal Signed Agreement
9 Suppliers Medium Business NGO Identify medical and disposable materials Signed Agreement
10 Professional Medics Medium Business NGO Have all graduated and experienced personal Signed Agreement
and nurses
Source: The authors
30
3.3 Product Scope Description
The clinic will offer medical services to the citizens of Aldea el Rosario and neighbor villages. These
people have difficulties in getting medical treatment, as the closest medical center is located 3 hours
away. The clinic will offer diagnosis, medical consultation and treatments of disease, illness, injury and
The main services that we offer vary from primary care, obstetric services and emergency treatment
(1) Pharmacy
(1) Laboratory
(4) Bathrooms
Design Layout :
The figure 2 below represents the architectural design layout for the health care that will be executed
accordingly, based on this design we were able to quantity survey and derive the resources,
durations and estimated cost for the project further in the document.
31
Figure 2: Architectural Design Layout
Project Deliverables
Project Charter
Business Case
Design Tender
Human Resources
HRMS
ISO QMS
Construction
Mobilization
Site Preparation
Soil Reports
Excavation
Demobilize
Project Controls
Deliverables Check
Approvals
Safety
Safety Plan
Safety Documents
Project Exclusions
Initially, the clinic only provide the basic medical care for the citizens, which will exclude secondary,
tertiary or quarterly medical care. However, negotiations are open for another project to expand the
Project Constraints
Project Assumptions
1. Sponsors will deliver the funds 2 months before the beginning of the project. This will allow us
to start ordering materials and equipment as well as closing the contract with the construction
company.
4. Approximately 4200 people per year will benefit from the project.
The WBS is a hierarchical decomposition of the total scope of work to be carried out by the
project team to accomplish the project objectives and create the required deliverables. The WBS
organizes and defines the total scope of the project and represents the work specified in the
The Work- Breakdown Structure (WBS) is shown in figure 3, which shows a limited version, to view
the entire structure; it has been created on www.wbstool.com. In order to consult it, enter the following
credential:
Email: [email protected]
Password: 123456789
Figure 3: Work-Breakdown Structire (WBS)
36
3.5 WBS Dictionary
To understand the Work – Breakdown Structure of the project, the WBS dictionary has
been made as well, in which it “describes each component of the WBS with milestones,
deliverables, activities, scope, and sometimes dates, resources, costs, quality” (Casagrande,
37
Duration: 7
Acceptance Criteria: Metrics
Resources: Business Analyst; Project Manager
1.1.2 Scope Management Plan Description: Establishes how the scope will be defined,
developed, monitored, controlled, and validated.
Duration: 5
Acceptance Criteria: Deliverables
Resources: Project Manager; Contracts Manager
1.1.3 Schedule Management Plan Description: Establishes the criteria and the activities
for developing, monitoring, and controlling the
schedule.
Duration: 5
Acceptance Criteria: SPI
Resources: Project Manager; Planning Engineer
1.1.4 Cost Management Plan Description: Establishes how the costs will be planned,
structured, and controlled.
Duration: 5
Acceptance Criteria: CPI
Resources: Project Manager; Cost Engineer; Planning
Engineer
1.1.5 Quality Management Plan Description: Establishes how an organization´s quality
policies, methodologies, and standards will be
implemented in the project.
Duration: 5
Acceptance Criteria: QUALITY METRICS &
MEASURE
Resources: Project Manager; Quality Engineer
1.1.6 Resource Management Plan Description: Provides guidance on how project
resources should be categorized, allocated, managed,
and released.
Duration: 5
Acceptance Criteria: Fulfills Requirements and
Specifications
Resources: Project Manager; Procurement Engineer;
Cost Engineer; Planning Engineer
1.1.7 Communication Management Description: Establishes how, when, and by whom
Plan information about the project will be administered and
disseminated.
Duration: 5
Acceptance Criteria: Network Channels
Resources: Project Manager
1.1.8 Risk Management Plan Description: Establishes how the risk management
activities will be structured and performed.
Duration: 5
Acceptance Criteria: Significance of risk
Resources: Project Manager; Planning Engineer; Cost
Engineer
1.1.9 Procurement Management Plan Description: Establishes how the project team will
acquire goods and services from outside of the
performing organization.
Duration: 5
Acceptance Criteria: Fulfills Requirements and
Specifications
Resources: Project Manager; Procurement Engineer;
Cost Engineer; Planning Engineer
1.1.10 Stakeholder Engagement Plan Description: Establishes how stakeholders will be
engaged in project decisions and execution, according
to their needs, interests, and impact.
Duration: 5
Acceptance Criteria:
Resources: Project Manager; Stalk holders
The construction of the Health Clinic in El Rosario will take a year, being this is a long
project it is necessary to be monitoring and controlling the entire project since the initiation
until closure.
With the information provided, the scope will be monitored throughout the whole project
by using variance analysis which will be used to compare the baseline to the actual results
The results will also include “the number of change requests received, the number of
requests accepted, and the number of deliverables verified, validated, and completed”
The schedule management plan is created to establish all the criteria’s for developing,
monitoring and controlling all the activities on the construction for the Healthcare Center in
el Rosario.
The Schedule Management plan is created to establish all the criteria’s for developing,
monitor and control all the activities for the construction of the Healthcare Center in El
Rosario. (Project Management Institute, 2017) Defines Schedule Management Plan as:
The tool used to determine the schedule plan is Project Management Software Project (MS
Project) , which is “a tool for project managers that helps develop a schedule, assign
resources to tasks, track the progress, manage the budget and analyze workloads for an
A milestone list is created by the Project Manager of this project and its team where it
represents a time where the team has achieved an important event of the project. . To have a
list identifies all project milestones and indicates whether the milestone is mandatory, such
The activity list includes the schedule activities required on the project. This list provides
as many details as possible to make it easier to for the project management team to access
though the schedule during the whole project duration. The activity list for the whole
Is the tool that communicates what work needs to be performed, which resources of the
organization will perform the work and the timeframes in which that work needs to be
performed. The project schedule should reflect all of the work associated with
The project complete schedule of the project is shown on the figures 4, 5, 6 and 7 which
logically, due to the difficulty of presentation the schedule below will be divided on
different pages showing all activities (Task Name), durations, start and finish dates, in
addition to the critical path and milestones highlighted in yellow under the (Task
Name).
Figure 4: Project Schedule A
59
Figure 5: Project Schedule B
Controlling the schedule involves to monitor the status of the project activities and to update the
project progress throughout the entire schedule, the result of this process is that the schedule baseline
is maintained.
To keep control of the schedule performance during the project, the schedule variance and cost
Schedule Variance
between the planned values. It is the amount by which the project is ahead or behind the
Cost Variance
Cost variance (CV) is the amount of budget deficit or surplus at a given point in time,
expressed as the difference between earned value and the actual cost. It is a measure of cost
63
4.6 Critical Path
The Critical Path is a method that controls the calculated start or finish date of the project. The
“Estimate the minimum project duration and determine the amount of schedule flexibility on the
logical network paths within the schedule model. This schedule network analysis technique
calculates the early start, early finish, late start, and late finish dates for all” (Project Management
Institute, 2017)
Figure 8, 9 and 10 shows the critical path for the project which presents all the activities on the MS
Project that cannot be delayed to maintain the project schedule. Any delay affecting he activities
highlighted in red will be managed by the project manager according to the change management plan
65
Figure 9: Critical Path B
budgeting, financing, funding, managing, and controlling costs so that the project can be
According to the PMBOK (2017), the Project Cost Management processes are:
2. Estimating Costs
3. Determine Budget
4. Control Costs
For example, limiting the number of design reviews can reduce the cost of the project but
For example, the cost of an acquired item may be measured when the acquisition decision
is made or committed, the order is placed, the item is delivered, or when the actual cost is
68
5.2 Plan Cost Management
To plan the Cost Management plan, will be needed the following inputs:
a) Project Charter:
This will be helpful to assess the scope of the project and the total gross budget. The wider
the scope, the less accurate the cost estimates. Thus, we have developed a specific and
narrow scope to minimize uncertainty. In fact, our project charter includes information such
as project description & justification, high level requirements, risk analysis, gross budget
Another important input to develop an accurate plan cost management is the analysis of the
The schedule management plan establishes the criteria and the activities for developing,
monitoring, and controlling the schedule. The schedule management plan provides
processes and controls that will impact cost estimation and management (PMBOK, 2017).
The risk management plan provides the approach for identifying, analyzing, and monitoring
risks. Therefore, it can positively contribute to the identification of the processes to control
cost estimations. Refer to the risk management document to see the full risk matrix.
5.3 Risks Costs Identification
The Risk Cost Identification shows the most important risks of the project. The costs to
manage these risks can be calculated by identifying the salary per hour of the person in
charge of managing these risks and the total hours needed to do so.
The total risk cost identification will be $10, 032.50, which is illustrated in Table 18
- The Salary per hour taken by dividing the annual salary with 52 weeks of
work.
- Total is the product of the salary per hour and the total hours.
Table 18: Risk Cost Identification
Labor shortage/low skills workers. As Mitigate -Outsource part of the construction HR department
Economic $ 22.05 130 $ 2,866.50
we operate in a very isolated area phase - running a strict recruitment process (2 people)
Project Architectural - Civil - MEP design Prevention: Early design phase and multiple
Consultants $ 15.00 75 $ 1,125.00
Management defaults revisions with external consultants
Source: The authors
71
5.4 Cost Estimations
The cost estimates will be reviewed and refined during the project to reflect additional
detail as it becomes available and assumptions are tested. The accuracy of a project
estimate will increase as the project progresses through the project life cycle. The project in
its initiation phase may have a rough order of magnitude (ROM) estimate in the range of
−25% to +75%. Later in the project, as more information is known, definitive estimates
The first input would be the Plan Cost Management described in the previous sections. This
is because the unit of measures, the level of accuracy and precision are essential to
estimates costs.
Another important input is the Quality Management Plan. In this document, we have
identified quality requirements and/or standards for the project and its deliverables. We also
documented how the project will demonstrate compliance with quality requirements and
how we manage and control quality. Examples include ACI code for construction
specifications, ISO for the PMO quality standards and ISO for accessibility. Regarding
managing and controlling quality, we are going to use tools such as inspection checklists,
Therefore, the Quality Management Plan is an essential input to estimate costs, as these
Finally, another vital management plan to use for cost estimates is the Scope Baseline. This
72
is because the wider the scope, the higher the costs. Therefore, we have developed a
specific project scope statement and a detailed WBS with approximately 150 deliverables.
Each deliverable is associated with specific resources. In this way, it would be easier to
estimates costs. Moreover, we have also developed a WBS dictionary in which we describe
the work to do in each WBS component. This will provide additional details to develop a
Analogous cost estimating. Since the team has had experiences in the construction
industry, analogous estimating is one of the most appropriate methodologies for our
project. It uses values and attributes of a previous project that are similar to the current
one. Values and attributes of the projects may include but are not limited to: scope, cost,
budget, duration, and measures of scale. Comparison of the values of the previous project
becomes the basis for estimating the same parameter or measurement for the current
project.
In the project will be using the parametric estimating to identify a relationship between
relevant data and other variables to calculate a cost estimate for project work.
Also, a reserve analysis is made to estimate the contingency reserves to account for cost
uncertainty. Contingency reserves are the budget within the cost baseline that is allocated
for identified risks. Given the results of the nature of the project and the risk matrix, the
The cost key requirements that have been identified are shown on Table 19.
(Sponsor approval)
Parametric Estimation
To determine the budget is the process of aggregating the estimated costs of individual
activities or work packages to establish an authorized cost baseline. The key benefit of this
process is that it determines the cost baseline against which project performance can be
monitored and controlled. This process is performed once or at predefined points in the
project.
A project budget includes all the funds authorized to execute the project. The cost baseline
is the approved version of the time-phased project budget that includes contingency
The budget items have been divided according to the following description:
1) Material
2) Subcontractors/Suppliers
3) Equipment/Vehicles
4) Running costs
5) Mobilization and site off costs
6) Indirect staff
7) Direct staff
8) Contingency
Table 20 presents a budget description for each item which will be used throughout the
project.
Table 20: Budget Description
a) Sponsors Contribution
The Sponsors contribution for the project according to the budget is shown on table 21.
construction project:
1) Mobilization Plan: Containing the costs of both direct and indirect staff divided
monthly
2) Equipment Costs: Containing all the costs of the machines used during the project
divided monthly
3) Material Costs: Containing specific material items and the relative unit of measure,
Direct Manpower
Supervisor $ 12,000
Foreman $ 9,600
Labors $ 36,400
Carpenters $ 28,500
Steel Fixers $ 21,000
Scaffolders $ 15,000
Electricians $ 14,400
Riggers $ 15,600
Surveyors $ 16,200
Plumbers $ 14,400
Source: The authors
Direct and Indirect costs were estimated according to the histogram in Figure 11 based on
40
35
30
25
20
Indirect Staff
15 Direct Staff
10
The running costs of the project are shown in table 23 based on the histogram on Figure 12
of the mobilization and demobilization of manpower and equipment of the whole project.
Running Costs
Food $ 15,150
Transportation $ 12,625
Housing $ 14,760
Miscellaneous $ 5,000
Travel Expenses $ 15,000
Manpower 5% $ 22,609
Contingencies
Source: The authors
8
No. of Equipments
7
6
5
4
3
Equipments
2
1
0
Date
e) B.O.Q
By using the architectural design layout and the Activity list of Table 17, the estimations
Mobilization
Cabin Total Unit 2 $ 2,310 $ 4,620
Toilette Total Unit 1 $ 450 $ 450
Offices Total Unit 1 $ 1,500 $ 1,500
Warehouse Total Unit 1 $ 5,000 $ 5,000
Temporary Fancies L.M 146 $5 $ 730
Temporary L.S 1 $ 2,500 $ 2,500
parking
Small cafeteria Total Unit 1 $ 800 $ 800
Earth works - Gatch M3 120 $3 $ 372
Fill
Concrete works M3 0
Foundations M3 55 $ 104 $ 5,720
Columns M3 9 $ 104 $ 936
Beams M3 33 $ 104 $ 3,432
Slabs M3 180 $ 104 $ 18,720
Concrete Grouting L.S 1 $ 5,000 $ 5,000
& Acc.
Reinforcement steel Tons 30 $ 640 $ 19,200
Masonry Total Unit 11,500 0 $ 5,175
Plastering works M2 1,000 $3 $ 3,000
Painting works M2 1,000 $ 14 $ 14,000
Tiling Works M2 380 $ 35 $ 13,300
HVAC VRV System Total Unit 1 $ 25,000 $ 25,000
Electrical works LS 1 $ 30,000 $ 30,000
Plumbing works LS 1 $ 10,000 $ 10,000
False Ceiling M2 360 $ 20 $ 7,200
Waterproofing M2 360 $ 35 $ 12,600
works
Solar panels Total Unit 1 $ 15,000 $ 15,000
Medical Equipment Total Unit 1 $ 250,000 $ 250,000
Aluminum louvers Total Unit 32 $ 18 $ 576
Wooden doors Total Unit 25 $ 60 $ 1,500
Fire System LS 1 $ 15,000 $ 15,000
Alco bond M2 250 $ 12 $ 3,000
Generators Total Unit 1 $ 8,000 $ 8,000
Parking and M2 400 $ 36 $ 14,400
landscape
Ambulance Total Unit 1 $ 40,000 $ 40,000
Porta Cabin Offices Total Unit 15 $ 2,000 $ 30,000
Consumables L.S 1 $ 2,500 $ 2,500
Tools L.S 1 $ 4500 $ 4,500
Safety Tools L.S 1 $ 3000 $ 3,000
Running Cost L.S 1 $ 6500 $ 6,500
Lab Testing & Third L.S 1 $ 12000 $ 12000
Parties
Source: The authors
Note: M: Meters, M2: Meters Squared, M3: Meters Cube, L.S: Lump sum
Control Costs is the process of monitoring the status of the project to update the project
costs and managing changes to the cost baseline. The key benefit of this process is that the
The following activities will be executed during the cost control process:
- Identifying the factors that create changes to the authorized cost baseline;
- Ensuring that cost expenditures do not exceed the authorized funding by period, by
- Monitoring cost performance to isolate and understand variances from the approved
cost baseline;
- Preventing unapproved changes from being included in the reported cost or resource
usage;
- Informing appropriate stakeholders of all approved changes and associated cost; and
One of the analysis selected to control cost is the earned value analysis. It compares the
performance measurement baseline to the actual schedule and cost performance. Earned
value management (EVM) integrates the scope baseline with the cost baseline and schedule
Finally, two important metrics to control costs are the schedule performance index (SPI)
The work performance information covers the project’s past performance and any
information that could impact the project in the future EACs are typically based on the
actual costs incurred for work completed, plus an estimate to complete (ETC) the remaining
A construction project in a remote area such as Aldea el Rosario can face many challenges
due to the uncertainty of factors such as local regulations, cultural differences, labor
shortages and unknown site conditions. The levels of responsibilities are high in each part
of the project, in which the opportunity to increase social value and improve the wellbeing
of many people. Therefore, the purpose of this quality management plan is to minimize
The Project Quality Management processes that are going to be presented in this document
the project and its deliverables, and documenting how the project will demonstrate
responsibilities
b) Manage Quality: The process of translating the quality management plan into
executable quality activities that incorporate the organization’s quality policies into
the project.
c) Control Quality: The process of monitoring and recording the results of executing
the quality management activities to assess performance and ensure the project
For quality improvement in the project, the following actions are going to be implemented
Compliance:
Identify what quality standards and processes we are going to use and in
Identify the desired levels of performance for the product and its
components.
following report.
Defects:
Communication:
Environment:
Identify a HRMS for the HR department for employees to avoid risks and
Testing:
Closing:
Collect lessons learned and update current plans for coming projects.
The American Concrete Institute (ACI) promulgates ACI 318-83, "Building Code
Requirements for Reinforced Concrete, “the aim of building codes is to provide the
minimum public safety criteria, and this is the principle followed in the preparation of the
ACI Building Code. The code sets out appropriate techniques to design and construct
According to (Standards Stores), ISO 9001 “is the Quality Management System (QMS)
continuously”
c) ISO/IEC Guide 71:2014 Standards and regulations.
The (International Organisation for Standadization) describes the ISO / IEC JTC 1 as “a
joint technical committee of the International Organization for Standardization (ISO) and
the IEC. Its aim is to create, preserve and encourage IT and Information and
d) IEC 60364-5-51
provide for the safety of persons, livestock and property against dangers and damage which
may arise in the reasonable use of electrical installations and to provide for the proper
During projects, making sure that people are on the same page and understanding how they can
alignment on achieving the vision of the project are critical to ensure success (Kovacevic, 2018)
The following table describes the role and responsibilities of the stakeholders involved in the
project. Moreover, the table reveals the frequency of each activity and who is charge of approving
it.
Table 26: Roles and Responsibilities
- Supervision of Quality Assurance and control on site. - Once Quality Assurance Manager
W Project Manager - Develop of Quality Management Plan - Once Sponsor and Client approval
- Project documents updates (Lessons learned register, - Every two weeks - Quality Assurance
Requirements traceability matrix, Risk register, - Every two weeks - Quality Assurance Manager
- Quality Task Review, deliverables and process - As Needed - Quality Assurance Manager
Approval
89
Name Role - Responsibility - Frequency Acceptance criteria
M Technical Supervision of Quality Control at the design - During the design none
Manager
Q Safety Engineer - Monitor the respect of safety rules on site, so you must - Ongoing Quality Assurance Manager
The Organizational Chart on Figure 13 shows the hierarchical structure of the NGO, which illustrates the relationships between the
Once the Plan Quality Management phase is completed, it is vital to understand how to manage
quality during the project. The main inputs during this phase are:
2) Project Documents
During the project in data gathering, checklists will be used in every step, which is a “structured
tool, usually component-specific, used to verify that a set of required steps has been performed or to
check if a list of requirements has been satisfied” (Project Management Institute, 2017)
Based on the project’s requirements and practices, the checklist that is going to be implemented in
our project will be used during the inspections requests for information regarding site work (civil,
mechanical & electrical), material and safety, which is presented on Figure 14.
92
Figure 14: Inspection Request
Date:
El Rosario Health Clinic Time
IR No:
INSPECTION REQUEST FOR SITE WORK
Item description:
Coordination
Technical
Survey Electrical Mechanical
Construction Drawings No:
Comments
Inspection Result
QC / Approved
Consultant
Approve
d as noted
Civil Electrical Mechanical
Name
Signature Disapproved.
Date