Petrochina International Jabung Ltd. Job Safety Analysis: Put On Ppe Required For A Safe Job

This document provides a job safety analysis for stringing pipe 6" at Sabar#2 PAD. It outlines 4 basic job steps: 1) Teamwork and communication to prevent miscommunication and ensure all workers understand emergency response plans; 2) Preparing documents, tools, and equipment while taking care and paying attention; 3) Securing the work area by barricading it and posting warning signs to prevent unauthorized personnel; and 4) Unloading material pipes from a trailer by taking safety precautions to prevent pipes from falling. The analysis identifies potential hazards at each step and lists the required personal protective equipment and safe work procedures to complete the job safely.

Uploaded by

Yosua Situmorang
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
72 views3 pages

Petrochina International Jabung Ltd. Job Safety Analysis: Put On Ppe Required For A Safe Job

This document provides a job safety analysis for stringing pipe 6" at Sabar#2 PAD. It outlines 4 basic job steps: 1) Teamwork and communication to prevent miscommunication and ensure all workers understand emergency response plans; 2) Preparing documents, tools, and equipment while taking care and paying attention; 3) Securing the work area by barricading it and posting warning signs to prevent unauthorized personnel; and 4) Unloading material pipes from a trailer by taking safety precautions to prevent pipes from falling. The analysis identifies potential hazards at each step and lists the required personal protective equipment and safe work procedures to complete the job safely.

Uploaded by

Yosua Situmorang
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 3

HSE-ICG/PCJ-3075-CA/JSA.

002
Date:
PetroChina International Jabung Ltd. Job Safety Analysis Tanggal :

Job: Stringging Pipa 6” Sabar#2 PAD Title of person Analyzed by:


who does the job: Operator, HSE, Supervisor, Rigger,
Flag Man

Work Crew Leader


Department : Section: Reviewed by: Approved by:
PT. IndoCipta Gemilang Construction Work Crew Supv: Area Supv: F/S Supv:

Construction Manager

Personal protective equipment (PPE) : Write down correct specifications of personal



Put on PPE required for a safe job. protective equipment required (Consult HSE Dept) :
1. Safety hat / helmet √ 6. Face shield 11. SCBA 16. Safety shoes / boots √
2. Safety glasses √ 7. Ear plugs / muffs 12. Gloves – Ordinary 17. Rubber boots
3. Goggles – ordinary √ 8. Dust mask 13.Gloves - Chemicals 18. Prot. Clothing /
Apron
4. Goggles – tinted 9. Air-purifying respirator 14. Gloves – Thermal 19. Body harnesses, L-
lenses line
5. Goggles – Chemicals 10. Air-line respirator 15. Rubber gloves 20. Life vest
Sequence of Basic Job Steps Potential Hazards Protective Equipment Safe Procedures
1) Team Work & Communication  Misscommunication  Pre – Job safety meeting
 Missunderstanding  Discuss JSA to workers before job
 Failure  Discuss emergency respons
preparedness to workers if emmergency
situation happen
 Good Communication with personel
 Everyone has permission to stop the job
 Melakukan rapat keselamatan sebelum
melakukan pekerjaan
 Kesalahan komunikasi
 Membicarakan JSA kepada pekerja
1) Kerjasama dan Komunikasi  Kesalahpahaman
sebelum bekerja
 Terjadi kegagalan
 Membicarakan tanggap darurat ke
pekerja jika terjadi situasi darurat
2) Prepare Document, Tools and  Pinch Point  Use hand Gloves  Be careful when pick up tools
Equipment  Miss Comunication  Every one must pay attention at all
 Missunderstanding times
 Failure  Stay focused
 Ensure tools ready to use
 Ensure all document already accepted
and reviewed by PCI
2) Mempersiapkan dokumen dan alat –  Terjepit  Gunakan Sarung Tangan  Berhati – hati ketika mengambil
Page 1 of 3
alat  Miskomunikasi peralatan
 Kesalahpahaman  Setiap orang harus memperhatikan
 Terjadi Kegagalan pekerjaannya dan lingkungannya
setiap waktu
 Tetap fokus
 Memastikan semua peralatan siap
untuk digunakan
 Memastikan semua dokumen telah
disetujui dan dan ditinjau kembali
oleh pihak PCI
3) Secure area  Unauthorized personel  Barricade tape/safety line  Supervisor must know area for work
 Other activity in the same area  Warning sign  To ensure area safe for work
 Barricade area with tag line and give
warning sign for unauthorized
personel
3)Mengamankan area kerja  Personil tidak berkepentingan  Garis barricade  Supervisor harus mengetahui area
 Kegiatan lain di area kerja  Tanda bahaya kerja yang akan dikerjakan
 Memastikan area kerja aman untuk
bekerja
 Barrikade area dengan garis barikade
dan tanda bahaya
4) Unloading material pipe 6” from trailler  Pipe fall  Stopper  Install stopper so the pipe are not
by long arm excavator  Sling broke up  Barricade lose and fall from trailler
 Trailler reversed  Hand gloves  Ensure unauthorized personel do not
 Pinch by pipe at work location
 Excavtor Collapse  Make sure sling refer to safe load
 Make sure hand position do not pinch
point
 Make sure position of trailler and
excavator on safe location
 Make sure the material is tied
properly
 Ensure unloding pipe 6” is directed by
personel trainned
4) Menurunkan material pipa 6” dari  Kejatuhan material  Stopper  Pasang stopper pada pipa
Trailler menggunakan Long Arm  Sling putus  Barricade  Pastikan tidak ada pekerja yang tidak
Excavator  Terbalik  Sarung tangan berkepentingan
 Terjepit  Pastikan kekuatan sling aman untuk
 Excavator Amblas/Terperosok digunakan dan tidak melebihi beban
 Tangan tidak berada pada titik jepit
 Trailler dan Excavator diposisikan di
tempat aman dan rata
 Pastikan material terikat dengan
benar
 Memberikan tug line untuk memandu
Page 2 of 3
mengarahkan pipa
 Pastikan penurunan pipa 6” material
diarahkan oleh personel yang terlatih
5) Stringging pipe 6” schedule 40 on its  Pinch of pipe  Hand Gloves  Make sure hand position do not under
position  Hit by pipe the pipe
 Sling Broke Up  Use sand bag to blocks to prop
 Wear hand gloves
 Ensure the workers are at safe distance
 Workers unauthorized are not allowed
at lifting radius
5) Menempatkan pipa 6 “ schedule 40 pada  Terjepit pipa  Sarung tangan  Pastikan posisi tangan tidak di bawah
tempatnya  Tertimpa pipa pipa
 Sling Putus  Gunakan karung pasir sebagai ganjal
 Gunakan sarung tangan
 Pekerja berada dalam jarak yang aman
 Pekerja yang tidak berkepentingan
tidak diperbolehkan berada di radius
pengangkatan
6) Housekeeping  Garbage  Trash bag  Ensure there is no trash
 Ensure the worker use handgloves
Ensure work area is clean from trash.
Separate organic non-organic and
Dangerous goods waste
6) Merapikan area kerja  Sampah  Tempat Sampah  Pastikan tidak ada sampah
 Pastikan pekerja menggunakan sarung
tangan
 Pastikan area kerja bersih dari sampah
dan memisahkan sampah organic, non
organic dan B3.