0% found this document useful (0 votes)
124 views1 page

FGD Project at 2X 525 MW MPL: Document Title: Gypsum Storage Shed Sizing Calculation

This document provides calculations for sizing a gypsum storage shed for a flue gas desulfurization (FGD) project at a power plant with two 525 MW units. It was prepared by Thermax Limited's Enviro Division for Tata Power and gives details on the gypsum production rate assumptions, storage time calculations, and resulting minimum required shed area. The document has gone through several revisions to address comments from stakeholders.

Uploaded by

Piyush Malviya
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
124 views1 page

FGD Project at 2X 525 MW MPL: Document Title: Gypsum Storage Shed Sizing Calculation

This document provides calculations for sizing a gypsum storage shed for a flue gas desulfurization (FGD) project at a power plant with two 525 MW units. It was prepared by Thermax Limited's Enviro Division for Tata Power and gives details on the gypsum production rate assumptions, storage time calculations, and resulting minimum required shed area. The document has gone through several revisions to address comments from stakeholders.

Uploaded by

Piyush Malviya
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

THE TATA POWER COMPANY LIMITED

FGD PROJECT AT 2X 525 MW MPL

Doc No. PE00659-V001-00-M-


Doc No._E306046A62
THERMAX LIMITED – ENVIRO DIVISION CA-011

Rev __7____ Rev _H___

Page 1

FGD PROJECT AT 2X 525 MW MPL

Document Title: GYPSUM STORAGE SHED SIZING CALCULATION

Document No: PE00659-V001-00-M-CA-011

Approvals
Revision Date Description Prepared Checked Approved
By By By
A 19-01-2020 Issued for Review & Comment PKM DB DSG
B 13-03-2020 Revised as per internal discussion PKM DB DSG
& comments received from MPL
C 02-04-2020 Revised as per internal discussion PKM DB DSG
& comments received from MPL
D 24-06-2020 Revised as per internal discussion PKM DB DSG
& comments received from MPL
E 23-07-2020 Revised as per internal discussion PKM DB DSG
& comments received from MPL
F 22-09-2020 Revised as per comments PKM DB DSG
G 16-10-2020 Revised as per comments PKM DB DSG
H 17-03-2021 Revised as per comments PKM PKM DB