Modifying Production Line For Productivity Improvement: A Case Study of Vision Lens Factory
Modifying Production Line For Productivity Improvement: A Case Study of Vision Lens Factory
Original Article
2
Engineering Program in Engineering Management,
Kasetsart University, Chatuchak, Bangkok, 10900 Thailand.
Abstract
This study aimed to modify the plastic vision lens production line CR39 in order to improve its productivity. Work
study and line balancing techniques were employed in order to improve the bottleneck point in the manufacturing process.
Standard time was measured. The result shows that productivity increased by 1,257 pieces per day and labor productivity
increased from 82 to 88 pieces per man-hour. However, this improved production capacity was still below the target capacity.
Therefore three additional alternatives were proposed. A simulation model was employed in order to analyze these alterna-
tives. The results found that, by using the lowest unit production cost scenario, additional labor and machines were added
into the bottleneck point of the production line. The productivity was then increased by 7,738 pieces per day or a 44%
improvement, which reached the target productivity, and the average resource utilization was 89%, which satisfied the objec-
tives.
3. Case Study
Table 1. Resources allocation. where ti is time for task i, j is the number of tasks, Cd is cycle
time, and
Workstation No. of Staff No. of Machines
(4.35+22+10.9+3.13+11.6) 51.98
N= = =2.36 3 workstation .
Mould Inspection 4 - 22 22
Mould Assembly 10 10 In this case, the number of workstation should be
Gasket Assembly 2 - reduced from 5 to 3 is to increase the production line effi-
Spring Assembly 2 - ciency according to the concept of expert line balancing
Filling Monomer 10 10 system (ELBS).
Summary 28 20 In this stage, standard time is calculated using work
study. Line balancing is then conducted by reducing the
number of workstation to three stations by combining the
mould assembly and filling monomer into one station. Gasket
(1) Mould Assembly with Machine: This process assembly, spring assembly, and filling monomer are also
starts at the mould inspection station. Moulds are then sent grouped together as a single station. By doing so, the
to the mould assembly station and the filling station respec- distance of movement is decreased. One piece flow produc-
tively. tion can be implemented and the batch size of mould inspec-
(2) Mould Assembly with Gasket: This process starts tion station is reduced by half as shown in Figure 7.
at the mould inspection station and then the mould is After the workstations are combined, some unneces-
assembled with a gasket. A spring is added to the mould at the sary activities can be removed and, hence, the standard times
spring assembly station. Moulds are then sent to the same of some assembly steps are decreased. The standard time of
filling station as in mould assembly with a machine line. The improved line is presented in Figure 8.
resources allocation is shown in Table 1. From a method and According to the improvement, the workstations of
time study, the standard time can be calculated as shown in mold assembly operation and filling monomer operation
Figure 6. are combined into new workstation. The total number of
machines required by the new workstation is eighteen. Ten
4. Methodology of them are for the mold assembly operation and eight of
them are for the filling monomer operation. Also, the work-
4.1 Work study method stations of gasket assembly operation, spring operation, and
filling monomer operation are combined into the new
The analysis of the production improvement use workstation. Here, the total number of machines required is
several performances measured to compare the results which two. They are for the monomer filling operation. From the
are productivity and efficiency. From the data in Figure 6, the improved standard time, resources allocation can now be
job time for mould assembly is equal to 22 seconds. The modified as shown in Table 2. From the line balancing and
number of workstation can be calculated from equation (1) improved working method, production layout can be
j improved as shown in Figure 9.
ti The efficiency for the production line calculated from
N i 1 (1) Equation 2:
Cd
Figure 6. Value stream mapping of current line and standard time of workstations of the current line.
R. Pisuchpen & W. Chansangar / Songklanakarin J. Sci. Technol. 36 (3), 345-357, 2014 349
[(2)-(1)]
KPI (1) (2) *100 =
(1)
Before Improvement After Improvement % of Difference
No. of Staff 28 28 -
Productivity (pieces/day) 18,344 19,601 7%
Productivity (pieces/hr/man) 82 88 7%
Utilization Average (%) 80% 85% 6%
Total Efficiency (%) 47.25% 78% 55%
j
fore, an additional improvement is needed in order to reach
ti the target. It is worth noting that the above analysis is
E= i=1 (2)
NCa studied with average values only. The result might be differ-
ent if data with variances are considered here. Thus it is
where ti is time for task i, j is number of tasks, Ca is actual necessary to conduct a computer simulation in order to verify
cycle time, N is the number of workstation, and the correctness of the experiment and to analyze the amount
(4.35 22 10.9 3.13 11.6) of WIP. Moreover, different line balancing scenarios can be
E 0.4725 . simulated in order to obtain the optimal solution for the
(5*22)
production line by considering system throughput, work in
The result shows that the efficiency for the current process and production cost per unit.
production line is 47.25%. Table 3 shows the operation
performance results both before and after the improvement. 4.2 Simulation model by ARENA
From the above results, the production capacity
increased by 1,257 pieces per day. However this capacity is Figure 10 shows the simulation flow diagram of the
still below the target value of 25,000 pieces per day. There- studied production line.
An input analyzer was used in order to measure the From the Kolmogorov-Smirnov Test, the results in Table 4
statistical dispersion of data. The Kolmogorov-Smirnov Test show that the p-value >0.15. Therefore, we fail to reject the
with a sample size N=30 was conducted under a 95% confi- null hypothesis (H0). The data is the representation of the
dence interval (significant level = 0.05). The null hypotheses real processing time. The simulation model based on the
will be accepted if P-Value >0.05. The input distribution input data can be constructed as illustrated in Figure 11. The
processing time of each workstation is represented in Table 4. simulation model was used to find the productivity, work in
Figure 11. Simulation model of the assembly and filling stations of the current line.
352 R. Pisuchpen & W. Chansangar / Songklanakarin J. Sci. Technol. 36 (3), 345-357, 2014
process, number of operators and machines, and utilization (FGB). In this department, the two of same production type
percentage both before and after the improvement had been will be batched together permanently using batch module
made. before assembling in process module. Batches of 180 pieces
In the simulation model, the raw materials are created will be delivered to the spring department. After that batches
into the system using separate module. The raw materials are of 100 pieces will be transferred to the fill monomer. In fill
created into the system every two minutes 240 pieces with monomer operation, the batches will be separated in pieces
a total of 50,000 pieces per day to produce 25,000 finished and processed with filling machine using process module.
products per day. The finished products consist of two raw The finished products leave the system by the dispose
materials. The assign module is used to distinguish the type module.
of raw materials. The decide module is used to separate 70% Figure 12 represents the model concept of expert line
of raw materials for inspection mould and 30% of raw balancing system (ELBS). The number of workstation is
materials for gasket assembly. The raw materials will be reduced from 5 to 3. The gasket assembly operation, spring
batched into 180 pieces using batch module before sending operation, and filling monomer operation are combined with
them to different departments. At the destination depart- no batch size during workstations with initiating the one-
ments, the batches will be separated using separate module piece flow continuous process as seem by using three
and followed by process module. process modules in the model.
For example, after inspection mould workstation, the The simulation model is run as a terminating system
batch module will be used to batch the products with batch starting from 8:00-17:00 (8 hrs) without a warm up period.
size shown in Figure 9. At the following station, mould An initial run is used to obtain the half-width for the confi-
assembly station, the products will be separated by separate dence interval to consider the number of replication. The
module. The decide module separates lenses into finished- appropriate number of replication can be calculated from
lenses and semi-lenses. The subclasses for finished-lenses Equation 3 when R0 is an initial number of replication, h 0 is
are finished lens assembly TS machine(FTS), finished lens the half-width from the initial run, and h is the required half-
assembly TP machine(FTP), and finished lens assembly TJ width.
machine(FTJ). The subclasses for semi-lenses are semi lens
assembly TS machine(STS) and semi lens assembly TJ
h o2
R Ro (3)
machine(STJ). The percentages for each type of lenses are h2
shown in Figure 10. The batch module is used to permanently The initial run with ten replications results in an h 0 of 17,365
batch the products before assembling in process module. ±75 pieces/day. The half-width (h) of 50 required R = 23
After mould assembly station, the products are temporary replication from Equation 3. The research sets the number of
batched again for 100 pieces before sending them to filling replication of 30 to reduce the error variance. The validation
monomer. of the simulation model is completed by comparing the
As the job in gasket assembly, decide module will be throughput of the actual system with the simulation system.
used to separate lenses to be finished lens assembly gasket The hypothesis testing for comparing mean is conducted at
type A (FGA) and finished lens assembly gasket type B = 0.05 using MINITAB14.
Figure 12. Simulation model of assembly and filling station of improved line.
R. Pisuchpen & W. Chansangar / Songklanakarin J. Sci. Technol. 36 (3), 345-357, 2014 353
In Figure 13, the p-value of 0.105 implies that we fail scenarios as shown in Table 7.
to reject the null hypothesis at = 0.05. The data from the
current production and from the simulation model are Alternative 3: Resources allocation
normally distributed. The throughput from both systems is Alternative 3 employs the concept of expert line
not significantly different. Therefore, the simulation model balancing system (ELBS) which is the simulation model as
can be used to represent the current production system. shown in Figure 12. The resource allocation of each process
was established so that the production capacity reaches
Production Line Improvement Alternatives 25,000 pieces per day. A process analyzer was also used.
Resources are control variables. System output and utiliza-
Alternative 1: Work study and line balancing tion are responses. Alternative 3-1 is performed what-if
In this alternative, a work study and line balancing analysis for batch size. Alternative 3-2, is performed what-
concept were employed as described above. The simulation if analysis for resource allocation. Alternative 3-3 is the
model is presented in Figure 12. analysis of the combination of both parameters from what-if
analysis.The simulation model of the assembly and filling
Alternative 2: Production batch size stations of the improved line was run and analyzed for 22
In this alternative, the batch sizes between stations scenarios.
are adjusted using current layout. The optimal batch size was
calculated using the process analyzer in ARENA13. Batch 5. Results
size is considered as a control variable. Responses are seven
types of work in process which are finished lens assembly 5.1 Production improvement through line balancing:
gasket type A (FGA), finished lens assembly gasket type B Alternative 1
(FGB), finished lens assembly TJ machine(FTJ), finished lens
assembly TP machine(FTP), finished lens assembly TS The results of improvement alternative 1 are shown
machine(FTS), semi lens assembly TJ machine(STJ), and in Tables 4 and 5. The average resource utilization and pro-
semi lens assembly TS machine(STS) as well as the output ductivity increased by 7% and 9% respectively. Moreover,
system. The simulation model of the assembly and filling WIP also decreased by 12%.
stations of the current line was run and analyzed for five
[(2)-(1)]
Entity Name (1) (2) *100 =
(1)
Current Model Alternative 1 % of Difference
Mould 3,405 3,363 1.2%
FGA 84 33 60.7%
FGB 84 20 76.2%
FTJ 53 1 98.1%
FTP 57 1 98.2%
FTS 63 1 98.4%
STJ 84 2 97.6%
STS 61 1 98.4%
354 R. Pisuchpen & W. Chansangar / Songklanakarin J. Sci. Technol. 36 (3), 345-357, 2014
[(2)-(1)]
KPI (1) (2) *100 =
(1)
Current Model Alternative 1 % of Difference
No. of Staff 28 28 -
Productivity (pieces/day) 17,400 19,003 9%
Labor Productivity (pieces/man/hr) 78 85 9%
Utilization Average (%) 72% 78% 8%
WIP (pieces) 3,899 3,422 -12%
5.2 Production improvement through optimal batch size: alternative 1. This scheme includes scenario 1, 2, 3, and 4.
Alternative 2 Alternative 3-2: The batch size remains unchanged and
resource allocation is modified from alternative 1. This
The results are shown in Table 7. Batch 1 is the batch scheme includes scenario 5, 6, 7, 8, 9, 10, 11, 12, and 20. Alter-
transshipped from the mould assembly station to the filling native 3-3: Both batch size and resource allocations are
monomer station and from the gasket assembly station to the modified from alternative 1. This scheme includes scenario
filling monomer station. Batch 2 is the batch transshipped 13, 14, 15, 16, 17, 18, 19, 21, and 22. Table 9 summarizes the
from the inspection mould station to the mould assembly additional number of machines and operators required in
station and from the gasket assembly station to the spring each process.
assembly station. The simulation model was then run with overtime
As can be seen from Table 7, the optimal batch size is being considered. The new output was used in order to
in scenario 5 (Batch 1=10, Batch 2=30) which resulted in a calculate the cost per unit. Filling machines cost is 1,000,000
16% reduction in WIP. Moreover, the system output Baht per machine and the cost for new layout design is
increased by 2.84%. 100,000 Baht. Therefore, as in scenario 17, the total set up
cost for four machines is 4,100,000 Baht. In this study, annual
5.3 Production improvement through resource allocation: worth criterion is employed. Operational cost per day (OC) is
Alternative 3 computed from the cost of machine per day plus labor wage
per day (LC) and can be presented as follows.
Alternative 3 can be divided into three schemes as
follows. Alternative 3-1: The batch size is modified and OC = LC+[Machine Cost (A/P, 10%, 5)/
production resource allocation remains unchanged from number of operating days per year] (4)
R. Pisuchpen & W. Chansangar / Songklanakarin J. Sci. Technol. 36 (3), 345-357, 2014 355
Resource
Scenario
No. of Staff Tapping TJ Machine Tapping TP Machine Tapping TS Machine Fill Machine
Scenario 1 0 0 0 0 0
Scenario 2 0 0 0 0 0
Scenario 3 0 0 0 0 0
Scenario 4 0 0 0 0 0
Scenario 5 1 0 0 1 0
Scenario 6 2 0 0 2 0
Scenario 7 3 0 0 3 0
Scenario 8 5 0 0 4 0
Scenario 9 4 0 0 4 0
Scenario 10 5 0 0 4 1
Scenario 11 3 0 0 4 0
Scenario 12 4 0 0 4 0
Scenario 13 3 0 0 3 0
Scenario 14 3 0 0 3 0
Scenario 15 4 0 0 3 0
Scenario 16 3 0 0 4 0
Scenario 17 3 0 0 4 0
Scenario 18 4 0 0 4 0
Scenario 19 3 0 0 4 0
Scenario 20 6 0 0 5 0
Scenario 21 6 0 0 5 0
Scenario 22 7 1 0 5 0
356 R. Pisuchpen & W. Chansangar / Songklanakarin J. Sci. Technol. 36 (3), 345-357, 2014
Model No. of OTCost NT Cost Labor Cost/ Annual Worth/ Total Cost/ Output system
Staff (Baht) (Baht) Day(Baht) Day(Baht) Unit(Baht) (pieces)
Current 28 - 8,400 8,400 - 0.4828 17,400
Current + OT 28 6,300 8,400 14,700 - 0.6851 21,457
Policy 1 28 - 8,400 8,400 - 0.4420 19,003
Policy 1+OT 28 6,300 8,400 14,700 - 0.6628 22,179
Policy 2 28 - 8,400 8,400 - 0.4694 17,894
Policy 2+OT 28 6,300 8,400 14,700 - 0.6718 21,880
Policy 3-1 28 6,300 8,400 14,700 - 0.6623 22,197
Policy 3-2 31 - 9,300 9,300 2,170 0.4572 25,088
Policy 3-3 31 - 9,300 9,300 2,170 0.4563 25,138
It can be seen that alternative 3-3, adding workers capacity is still below the target capacity. An additional
into the production line is necessary as in Table 9. The improvement alternative was proposed in order to increase
output reached the goal of 25,000 pieces per day. The best the utilization percentage to 100% or full capacity. In this
scenario is scenario 17 which adds 31 workers and gains 89% third alternative, additional operators and machines were
utilization. This means that the unit manufacturing cost is added to the bottleneck point of the process. The best
lowest and the production capacity reaches the target. scenario 17 with the lowest unit production cost provided a
44% increase of production capacity. This means that the
5.4 Comparison of operational performances of the capacity increased to 25,138 pieces per day or increased by
improvement alternatives (without overtime) 7,738 pieces per day from the current production line, which
reached the target capacity. The average utilization percent-
Table 11 compares the operational performances of age is 89% which satisfied the objectives. The economic
the current model and the improved models. analysis for alternative 3 shows the payback period of 2.33
years. This is an interesting option to apply to the production
6. Conclusions and Recommendations line with high possibility to be implemented and reached
customer needs and company policy to increase the produc-
All three improvement alternatives provided better tivity of the mean production line. The further research can
production performances. Alternative 1 used line balancing consider other types of costs as factors in production line
and work study concepts. The batch size was decreased by and can apply to similar case study.
half. The production capacity increased from 17,400 to
19,003 pieces per day which means the capacity increased by References
1,603 pieces per day. Moreover, labor productivity increased
from 78 to 85 pieces per man-hour. Resources utilization Duran T., Selcuk, K., Ertan, G. and Baykoc, O.F. 2008. Simple
improved by 8% and WIP decreased by 12%. In alternative and U-type assembly line balancing problems with a
2, small lot size production was implemented. As a result in learning effect. Applied Mathematical Modeling. 32,
Scenario 5, WIP decreased by 16% and the production 2954–2961.
capacity increased from 17,400 to 17,894 pieces per day Hadi, G., Kursat,A.,Cevriye, G and Emel, K. 2005. A shortest
which means the capacity increased by 494 pieces per day route formulation of simple U-type assembly. Applied
or 2.84%. The production resources of both alternatives Mathematical Modeling. 29, 373-380.
remained unchanged. However, this improved production
R. Pisuchpen & W. Chansangar / Songklanakarin J. Sci. Technol. 36 (3), 345-357, 2014 357
Keytack, H.O. 1997. Expert Line Balancing System (ELBS). Resnick, M.L. and Zanotti, A. 1997. Using Ergonomics to
Computers and Industrial Engineering. 33, 303-306. target Productivity Improvement. Computers and
Khalid, S. and Saleh, A. 2011.Productivity improvement of Industrial Engineering. 33, 185-188.
a motor vehicle inspection station using motion and Savsar, M. and Jawini, A.Al. 1995. Simulation analysis of
time study techniques. King Saud University – Engi- just-in-time production. International Journal of
neering Sciences. 23, 33-41. Production Economics. 42(1), 67-78.
Mikell, P.G. 2008. Automation,Production System, and Com- Shuang, L., Wang, X. and Lixin, M. 1997. Optimization of
puter – Integrated Manufacturing. Pearson Education Assembly Line Based on Work Study. Harbin Univer-
Inc., New Jersey, U.S.A. sity of Commerce, Harbin, P.R. China.
Raymond, G. 2010. Leveraging new SEMI standard to reduce
waste and improve flow for Semiconductor manu-
facturing. Simulation Modeling Practice and Theory.
26, 658–664.