Method Statement External Application of Corrosion Inhibitor
Method Statement External Application of Corrosion Inhibitor
No: SITE-001
Date: METHOD STATEMENT
Revision: 0 External application of Corrosion inhibitor
Page: 1
Of: 4
Project : EPC WORK FOR PERMANENT STAFF ACCOMMODATION Contract No.: OGC/14/2017
MS prepared
QA/QC Manager Signature
by: Date:
MS
Implemented Construction Manager Signature
on site by: Date:
MS
Implemented HSE Advisor Signature
on site by: Date:
MS
OGC ACCEPTANCE
Revision: 00
RESPONSIBILITIES
Contracts Manager shall review contract documents with senior management and ensure that all
necessary resources are made available throughout the construction period by proper planning
Contracts
and ordering material ahead of the activities. He shall have overall responsibility for carrying
Manager
out the works and he shall ensure that the works are carried out as per all necessary QHSE
requirements and to the required specification.
Reviews documents with senior management and ensure that the latest revision is being used by
Document Control system. He shall ensure that suitable resources are available & issue day to
Construction
day instruction to the Site team. Inspect the work periodically to ensure that the Method
Manager
statement, Inspection & Test Plan and Risk assessments are adhered at site. Monitor, Review &
Revise the Method Statement if and when required.
Ensure the work is carried out as per the requirement and in a safe manner. Ensure all people at
Site site adhere with HSE requirement.
Engineer/Per Commence work after ensuring a Valid Work Permit, Approved Method Statement, ITP and Risk
mit Applicant Assessment Plan are in place. Inspection of setting out prior to start the works. Inspection of
incoming materials and review of test certificates to ensure the quality of materials used for
construction.
Foreman / Assigning and controlling the team involved in the activity. Preparation of work site and
Permit Holder organising required equipments and machinery. Ensuring that the works are implemented in a
safe manner as described in the Method statement and Risk Assessment Plan and a valid work
permit in place by referring the document prior to execution of work.
Giving safety TBT and TRIC to the workforce before the commencement of the activity.
Organising equipments and tools, maintaining all safety precautions and shifting materials to the
site. Ensure that all personnel involved with Tiling work are wearing the correct PPE and are
carrying out their duties in a correct and safe manner by Supervision.
Review method statement to complete the risk assessments and give safety tool box talk to the
site team and site management. Monitor all works to ensure they are being carried out in a
correct and safe manner.
HSE Advisor Ensure that all Plant and Equipment operators are qualified and licensed to operate the
equipment by checking prior to induction. Ensure activity specify risk to personnel involved are
assessed and hazard analysis is carried out, and men involved are briefed in Tool Box Talks.
Monitor, Review & record Safety findings.
Monitor the execution of the works to confirm the Contractor’s compliance with the
QA/QC specification, approved drawings, method statement, ITP’s, etc & maintain the records of
Inspector Quality Control check lists / formats using contract filing system.
This method statement is applicable for application of External corrosion inhibitor application in the
previous concrete wherever suspecting/no evidence of MCI in the fresh concrete concreted location
and provides details pertaining to working methods to be adopted, activities involved, responsibilities,
documentation & to identify the hazards associated and how to mitigate these hazards associated with
this work.
2. Materials Used
All the materials used for external CI work shall be approved by the company prior to start of the work
4. Reference Documents
Approved MAS (ACO-2-2001-304-T7-4-A)
Technical Data sheet of Sika Ferrogard-903.
Contract Quality Plan.
Contract Safety Plan.
5. Work Methodology
With the executed concrete records Sr.Construction Engineer/Sr QC Inspector shall prepare and
mark the locations where suspecting/no evidence of MCI added in the concrete and the same shall
be marked in the latest approved IFC drawings.
Obtain approval from OGC QC representative and CSR thru RFIW.
The substrate shall be cleaned free from dirt,dust,oil ,grease and other foreign materials.
Any small concrete repair/fin hole packing shall be carried out with approved fair face mortar.
5.4 Application:
As per the Manufacture recommendation temporary movable shed arrangement shall be prepared
and placed in the application location to avoid application in direct sunlight.
Sika Ferrogard-903 material first coat shall be applied in the concrete surface by roller or brush
application uniformly covered in all surfaces of concrete.
The required coverage rate shall be of not less than 0.30kg/m2,if the coverage rate found low one
more coating shall be applied in the concrete.
Necessary pre and post weight shall be checked to ensure the required coverage rate of the
material.
The painted surface shall be dampened twice in a day upto three days from the date of
application.
The area shall be protected to the traffic or other further works upto three days from the
completion of CI application.
Shall obtain final approval from OGC QC thru RFIW.
6. Safety
A) HSE Procedures
All the critical tasks involved in this work shall be listed out and appropriate Procedures shall be
followed stringently during the execution of the work. In addition to this, Job Safety Plan
pertaining to every activity will be prepared by the Permit Holder and applied during the course of
the activity. Also, Activity Hazard Control Register is available as a supplementary HSE document
for guiding the Supervisors for safe work.
Site specific Emergency response procedures & emergency response team shall be developed &
relevant information shall be made available to all employees. Regular emergency drills, based on
various emergency scenarios shall be conducted in accordance with HSE activity matrix. SHOC /
MSDS shall be readily available at site in order to handle the chemicals safely.
Employees shall be trained in Industrial First Aid and will be available to meet the requirement of
one first aider in each crew of 20 employees. When less than 20 people are working at a particular
location, at least one person per shift is to be competent First Aider with access to suitable First
Aid kits. Additional trained first aiders will be introduced in case of increase in manpower.
Refresher training will be imparted to the first aiders on expiry of the validity of their certificates.
Adequate identification marks/stickers shall be made for easy identification of first aider at site.
Daily toolbox talk will be given by the foreman in a language that the work force understands prior
to the risks associated with the activity for that day.
Minimum PPE requirement shall be implemented throughout the whole work site. List of minimum
PPE requirement intended for this method statement are hard hat, safety shoe, hand gloves
(Rubber / Cotton), ear plug, safety goggles, high visibility jacket ,nose masks, safety overalls &
Gum boots. Any other PPE that may be further required shall be made available to site as and when
required.
7. Documentation
CI application Checklist
Request for Inspection of Work (RIW)
Approved AFC drawings and Approved Shop Drawings