Formwork supports fresh concrete until it gains strength and includes shuttering, centering, and staging. Shuttering supports horizontal surfaces like beams and slabs. Centering supports vertical surfaces like columns and walls. Staging supports both shuttering and centering using materials like wooden ballies, pipes, props, and jacks. Formwork can be removed after 24 hours if adequately supported. The term 'staging' refers to formwork that is built up progressively from one floor to the next. Removal of forms must ensure complete stability of the structure. Formworks support fresh concrete.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
57 views1 page

15 8 Questionnaire

Formwork supports fresh concrete until it gains strength and includes shuttering, centering, and staging. Shuttering supports horizontal surfaces like beams and slabs. Centering supports vertical surfaces like columns and walls. Staging supports both shuttering and centering using materials like wooden ballies, pipes, props, and jacks. Formwork can be removed after 24 hours if adequately supported. The term 'staging' refers to formwork that is built up progressively from one floor to the next. Removal of forms must ensure complete stability of the structure. Formworks support fresh concrete.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 1

1. Is any arrangement done to support the fresh 8.

Provided that the structure is adequately


concrete to attain its strength and structure. supported, after how many hours may the forms
a) Shuttering be removed?
b) Centering a) 48 hours
c) Staging b) 24 hours
d) Formwork c) 12 hours
d) 72 hours
2. Is a formwork which supports the horizontal
surface such as beams and slab bottoms. 9. Fill in the blank: The term ______ is applied
a) Shuttering as it is built up in stages from one storey to the
b) Centering next floor.
c) Staging a) Shoring
d) Formwork b) Staging
c) Framing
3. Is a formwork which supports the vertical d) Scaffolding
surface such as columns and walls.
a) Shuttering 10. Fill in the blank: The removal of forms shall
b) Centering be done in such a manner as to insure complete
c) Staging ________ of the structure.
d) Formwork a) Rigidity
b) Stability
4. Are materials such as wooden ballies, pipes, c) Safety
props, jacks, H-frames which support both d) Durability
shuttering and centering.
a) Shuttering 11. What do formworks support?
b) Centering a) Fresh concrete
c) Staging b) Scaffolding
d) Formwork c) People
d) Platforms
5. Is a more substantial framework progressively
built up as tall building rise up.
a) Scaffolding
b) Framework
c) Staging
d) Formwork

6. Which of the following is not included in the


different parts of staging:
a) Vertical Support
b) Woorden Ballies
c) Horizontal Braces
d) Base Support

7. Which of the following is not included in the


materials used in staging:
a) Props
b) Woorden Ballies
c) Base Support
d) Jacks