Pipeline - Lessons Learned
Pipeline - Lessons Learned
PIPELINE PROJECT
GROUP 02
10 GANESHA STREET
TH
MARCH 8
TH
, 2021
1
TABLE OF CONTENTS
INTRODUCTION.....................................................................................................................................3
LESSONS LEARNED APPROACH................................................................................................................3
LESSONS LEARNED FROM THIS PROJECT....................................................................................................4
LESSONS LEARNED KNOWLEDGE BASE / DATABASE....................................................................................6
LESSONS LEARNED APPLIED FROM PREVIOUS PROJECTS..............................................................................6
PROCESS IMPROVEMENT RECOMMENDATIONS..........................................................................................6
2
INTRODUCTION
Capturing lessons learned is an integral part of every project and serves several purposes.
While the finalization of a formal lessons learned document is completed during the project
closeout process, capturing lessons learned should occur throughout the project lifecycle to
ensure all information is documented in a timely and accurate manner. The lessons learned
document serves as a valuable tool for use by other project managers within an organization
who are assigned similar projects. This document should not only describe what went wrong
during a project and suggestions to avoid similar occurrences in the future, but it should also
describe what went well and how similar projects may benefit from this information. This
document should be communicated to the project sponsor and Project Management Office
(PMO) for inclusion in the organizational assets and archives as part of the lessons learned
database. If the organization does not have a PMO then other, formal means of communicating
the lessons learned should be utilized to ensure all project managers are included.
The purpose of the lessons learned document for the Pipeline Project is to capture the project’s
lessons learned in a formal document for use by other project managers on similar future
projects. This document may be used as part of new project planning for similar projects in
order to determine what problems occurred and how those problems were handled and may
be avoided in the future. Additionally, this document details what went well with the project
and why, so that other project managers may capitalize on these actions. Project managers
may also use this document to determine who the project team members were in order to
solicit feedback for planning their projects in the future. This document will be formally
communicated with the organization and will become a part of the organizational assets and
archives.
3
The lessons learned from the Pipeline Project are compiled from project journal entries
throughout the project lifecycle. Lessons learned were also be gathered from both realized and
unrealized risks in the project risk register as well as through interviews with project team
members and other stakeholder as necessary. The lessons learned from this project are to be
used as references for future projects and contain an adequate level of detail so that other
project managers may have enough information on which to help base their project plans. The
lessons learned in this document are categorized by project knowledge area. These knowledge
areas consist of: procurement management, risk management, integration management,
quality management, time management, cost management, scope management, human
resource management, and communications management. NOTE: some knowledge areas may
not contain lessons learned if none were documented throughout the project lifecycle.
The following chart lists the lessons learned for the Pipeline project. These lessons are
categorized by project knowledge area and descriptions, impacts, and recommendations are
provided for consideration on similar future new construction projects. It is important to note
that not only failures or shortcomings are included but successes as well.
4
project.
Scope Scope Creep Stakeholders The PM did not have a The PM must have
Management continuously tried plan for addressing an approval process
adding to the project scope creep and for any proposed
scope throughout the allowed some scope changes and
project lifecycle. requirements to be communicate this
added until the process to all
sponsor stopped it. stakeholders.
Overall project delay
of 3 weeks was the
result.
Quality Building A process for This allowed the Always plan quality
Management Material determining project team to work standards and
acceptable building with the contractors allowances into the
material quality was to smoothly ensure all project plan. This
planned into the materials were of helps avoid delays
project. acceptable quality and and cost overruns.
avoided any re-work
and delays associated
with substandard
material.
Risk Zoning A risk was identified Impact was minimal Always consider
Management Approval that there may be because the PM external impacts on
delays in receiving included potential the project cost and
approval from the zoning delays into the schedule. This must
county zoning board. project schedule. be continuous
This was a success throughout the
because it was project lifecycle.
identified early and
planned for.
5
learned knowledge/databases contain large amounts of information, so it is important that
there is a system for cataloging this information.
The lessons learned for the Pipeline Project will be contained in the organizational lessons
learned knowledge base maintained by the project management office (PMO). This
information will be cataloged under the project’s year (2021) and the type of project (New
Construction) for future reference. This information will be valuable for any project manager
assigned to a new construction project in the future.
The Pipeline Project utilized several lessons learned from past projects:
1. The addition of a risk associated with planning cost and schedule based on external
dependencies (i.e. zoning approvals) was determined during the planning process by
consulting the lessons learned.
2. The planning of acceptable quality standards was based on lessons learned from the
XXX. By planning for quality standards the project team was able to avoid schedule and
cost overruns by clearly communicating acceptable quality standards to all contractors
involved with the project.
As indicated in the lessons learned chart above, the Project Project did not have a process for
reviewing and approving requested changes in requirements or project scope. Not only is this a
lesson learned for similar future projects; but the organization must ensure that all project
managers are aware of the need for this process to be included in the planning of all future
projects. Therefore, it is recommended that prior to work beginning on any new project, the
project manager must brief the project sponsor on the process for requesting and approving
changes to project scope.