Estimate
Estimate
Estimate
THICKNESS OF PLASTER
MIXTURE CLASS
8mm 12mm 16mm 20mm 25mm
A 0.144 0.216 0.288 0.360 0.450
B 0.096 0.144 0.192 0.240 0.300
C 0.072 0.108 0.144 0.180 0.255
D 0.060 0.090 0.120 0.150 0.188
SAND (m3) 0.008 0.012 0.016 0.020 0.025
MIXTURE CLASS D
THICKNESS OF PLASTER 16mm
CEMENT AREA per
AREA (bags) SAND (m3)
face
FRONT (exterior & interior) 19.11 2.29 0.31 9.56
LEFT (exterior & interior) 41.24 4.95 0.66 20.62
BACK - T&B Area (exterior & interior) 15.58 1.87 0.25 7.79
BACK - Firewall (exterior & interior) 11.68 1.40 0.19 5.84
RIGHT (Common wall) 23.24 2.79 0.37 23.24
Septic Tank 7.26 0.87 0.12
Kitchen Sink 0.63 0.08 0.01
Catch Basin 0.86 0.10 0.01
TOTAL 110.86 14.35 1.91
TABLE 2-2 QUANTITY OF CEMENT AND SAND FOR CHB MORTAR PER SQUARE METER
MIXTURE CLASS D
Size of CHB 4"
CEMENT
AREA (bags) SAND (m3) CHB (pc)
FRONT 10.69 3.505 0.465 133.57
LEFT 22.19 7.277 0.965 277.32
BACK (T&B Area) 8.38 2.750 0.365 104.79
BACK (Firewall) 7.18 2.354 0.312 89.71
RIGHT (Firewall) 25.65 4.206 1.116 160.29
Septic Tank 7.26 2.381 0.316 90.75
Kitchen Sink 0.63 0.207 0.027 7.88
Catch Basin 0.86 0.283 0.038 10.80
TOTAL 82.83 22.96 3.60 875.11
TABLE 1-2 CONCRETE PROPORTION
GRAVEL
MIXTURE CEMENT SAND GRAVEL
QUANTITY VOLUME BEDDING
CLASS (bags) (m3) (m3)
(m3)
Footing A 5 0.072 3.240 0.180 0.360 0.090 3.099
Wall Footing A 1 1.278 11.502 0.639 1.278 0.426
Column A 1 0.696 6.261 0.348 0.696
Beam A 1 0.189 1.701 0.095 0.189
Flooring C 1 2.927 17.563 1.464 2.927 1.371
Service Entrance C 1 0.238 1.425 0.119 0.238
TOTAL 41.69 2.84 5.69
Dimension
15.457373
1 A'-B-3
0.5 B-1-3
TABLE 3-6 LENGTH OF REINFORCING BARS FOR CHB IN METERS
HORIZONTAL
VERTICAL REINFORCEMENT
SPACING (cm) REINFORCEMENT PER
PER SQUARE METER (m) SQUARE METER (m)
40 cm 2.93 3.30
60 cm 2.13 2.15
80 cm 1.60 1.72
SPACING VERTICAL 80 cm
SPACING HORIZONTAL 60 cm
QUANTITY OF REBAR PER 6.0 lm
AREA VERTICAL
FRONT 10.69 17.10
LEFT 22.19 35.50
BACK (T&B Area) 8.38 13.41
BACK (Firewall) 7.18 11.48
RIGHT (Firewall) 25.65 41.03
TOTAL 74.08 118.52
19.75
930.98475433825
155.164125723042
2060
2060
1920
1920
35.9775
16800
2800
127
138
2060
1920
8.21
7940 5980
-1940
W1 W2
h v h v
920 1520 720 720
920 1520 720 720
920 1520
920 1520
920 1520
920 1520
920 1520
920 1520
920 1520
920 1520
AREA
(sq.m.)
FRONT 19.11
LEFT 45.43
BACK (T&B Area) 15.58
BACK (Firewall) 5.84
RIGHT (Firewall) 23.24
TOTAL 109.21
For 6 sq.m. per liter application (1 coat) 18.20 liters CONCRET PUTTY
For 6.25 sq.m. per liter application (2 coats) 34.95 liters FLAT LATEX
For 6.25 sq.m. per liter application (2 coats) 34.95 liters SEMI-GLOSS
THINNER, PAINT
average actual consumption 2.10 liter
NEUTRALIZER, CONCRETE
coverage at 20 sq.m. per gallon 49.83 liter
GROUT, TILE - WHITE
average actual consumption 3.0 kg
PUTTY, CONCRETE
coverage at 6 sq.m. per liter (1 coat) 36.40 liter
RIVET, BLIND 1/8in X 5/8in
actual consumption 320 pc
SCREW, FICEM 3/4IN
actual consumption 228 pc
ELBOW PVC, PLAIN - BLUE 12.50mm X 90DEG
actual installation 10 pc
RIVET, BLIND 1/8in X 5/8in
Capping
18 Side Spaced @ 0.40m
13 Front Spaced @ 0.40m
5 Side T&B Spaced @ 0.40m
12 Breaker/Fire wall
18 Gutter
86 Ceiling Eaves
159.6 Total per unit (with 5% wastage)
THICKNESS OF PLASTER
MIXTURE CLASS PROPORTION
8mm 12mm 16mm 20mm 25mm
A 1:2 0.144 0.216 0.288 0.360 0.450
B 1:3 0.096 0.144 0.192 0.240 0.300
C 1:4 0.072 0.108 0.144 0.180 0.255
D 1:5 0.060 0.090 0.120 0.150 0.188
SAND (m3) 0.008 0.012 0.016 0.020 0.025
MIXTURE CLASS D
THICKNESS OF PLASTER 16mm
MIXTURE CLASS D
Size of CHB 4"
PART OF AREA CEMENT CHB (pc)
STRUCTURE (bags) SAND (m3)
FRONT 10.69 3.505 0.465 133.57
LEFT 22.19 7.277 0.965 277.32
BACK (T&B Area) 8.38 2.750 0.365 104.79
BACK (Firewall) 7.18 2.354 0.312 89.71
RIGHT (Firewall) 25.65 4.206 1.116 160.29
Septic Tank 7.26 2.381 0.316 90.75
Kitchen Sink 0.63 0.207 0.027 7.88
Catch Basin 0.86 0.283 0.038 10.80
TOTAL 82.83 22.96 3.60 875.11
PROJECT : GREEN MEADOWS RESIDENCES
LOCATION : SAN JOSE, BATANGAS
HOUSE MODEL : VERDES DUPLEX V2
SUBJECT : ESTIMATE FOR MASONRY, CONCRETING AND PLASTERING PER UNIT
DATE : OCTOBER 1, 2020
10 400
12 500
16 600
CONCRETING WORKS
VERDES V2
BAR
BAR DIAMETER
PART OF STRUCTURE INSTALLATION QUANTITY LOCATION LENGTH (mm)
(mm)
TYPE
WALL FOOTING MAIN BAR 2 10 GRIDLINE A-1-2 5500
STIRRUPS 20 8 GRIDLINE A-1-2 492
MAIN BAR 2 10 GRIDLINE 1-A-B 4000
STIRRUPS 15 8 GRIDLINE 1-A-B 492
MAIN BAR 2 10 GRIDLINE 2-A-B 4000
STIRRUPS 15 8 GRIDLINE 2-A-B 492
MAIN BAR 2 10 GRIDLINE A'-2-3 2000
STIRRUPS 8 8 GRIDLINE A'-2-3 492
MAIN BAR 2 10 GRIDLINE 3-A'-B 2150
STIRRUPS 9 8 GRIDLINE 3-A'-B 492
MAIN BAR 2 10 GRIDLINE B-2-3 2000
STIRRUPS 8 8 GRIDLINE B-2-3 492
MAIN BAR 2 10 GRIDLINE B-1-3 6300
STIRRUPS 22 8 GRIDLINE B-1-3 492
COLUMN FOOTING MAIN BAR B.W. 8 12 GRIDLINE A1 644
MAIN BAR B.W. 8 12 GRIDLINE A2 644
MAIN BAR B.W. 8 12 GRIDLINE B1 644
MAIN BAR B.W. 8 12 GRIDLINE B2 644
FLOORING -L&D MAIN BAR B.W. 8 10 LONG SPAN 4240
MAIN BAR B.W. 6 10 SHORT SPAN 5740
FLOORING -T&B MAIN BAR B.W. 4 10 LONG SPAN 1540
MAIN BAR B.W. 3 10 SHORT SPAN 2240
COLUMN MAIN BAR 4 12 GRIDLINE A1 4271
STIRRUPS 23 10 GRIDLINE A1 820
MAIN BAR 4 12 GRIDLINE B1 4271
STIRRUPS 23 10 GRIDLINE B1 820
MAIN BAR 4 12 GRIDLINE A2 3950
STIRRUPS 21 10 GRIDLINE A2 820
MAIN BAR 4 12 GRIDLINE B2 3950
STIRRUPS 21 10 GRIDLINE B2 820
STIFFINER BEAM MAIN BAR 2 12 SB-1 6300
STIRRUPS 33 10 SB-1 490
COLUMN AT PITCH WALL MAIN BAR 2 12 1187
STIRRUPS 7 10 490
SINGLE ATTACHED DUPLEX
CONCRETING WORKS
VERDES V2 SINGLE ATTACHED DUPLEX
BAR BAR DIAMETER ACTUAL CUT TOTAL LENGTH TOTAL LENGTH
PART OF STRUCTURE INSTALLATION QUANTITY LOCATION LENGTH (mm)
TYPE (mm) LENGTH (mm) (mm) (mm)
WALL FOOTING MAIN BAR 2 10 GRIDLINE A-1-2 5500 6000 12000 24000
STIRRUPS 20 8 GRIDLINE A-1-2 492 500 10000 20000
MAIN BAR 2 10 GRIDLINE 1-A-B 4000 4500 9000 18000
STIRRUPS 15 8 GRIDLINE 1-A-B 492 500 7500 15000
MAIN BAR 2 10 GRIDLINE 2-A-B 4000 4500 9000 18000
STIRRUPS 15 8 GRIDLINE 2-A-B 492 500 7500 15000
MAIN BAR 2 10 GRIDLINE A'-2-3 2000 2300 4600 9200
STIRRUPS 8 8 GRIDLINE A'-2-3 492 500 4000 8000
MAIN BAR 2 10 GRIDLINE 3-A'-B 2150 2500 5000 10000
STIRRUPS 9 8 GRIDLINE 3-A'-B 492 500 4500 9000
MAIN BAR 2 10 GRIDLINE B-2-3 2000 2300 4600 9200
STIRRUPS 8 8 GRIDLINE B-2-3 492 500 4000 8000
MAIN BAR 2 10 GRIDLINE B-1-3 6300 7000 14000 14000
STIRRUPS 22 8 GRIDLINE B-1-3 492 500 11000 11000
COLUMN FOOTING MAIN BAR B.W. 8 12 GRIDLINE A1 644 750 6000 12000
MAIN BAR B.W. 8 12 GRIDLINE A2 644 750 6000 12000
MAIN BAR B.W. 8 12 GRIDLINE B1 644 750 6000 6000
MAIN BAR B.W. 8 12 GRIDLINE B2 644 750 6000 6000
FLOORING -L&D MAIN BAR B.W. 8 10 LONG SPAN 4240 4300 34400 68800
MAIN BAR B.W. 6 10 SHORT SPAN 5740 6000 36000 72000
FLOORING -T&B MAIN BAR B.W. 4 10 LONG SPAN 1540 1600 6400 12800
MAIN BAR B.W. 3 10 SHORT SPAN 2240 2300 6900 13800
COLUMN MAIN BAR 4 12 GRIDLINE A1 4271 4500 18000 36000
STIRRUPS 23 10 GRIDLINE A1 820 900 20700 41400
MAIN BAR 4 12 GRIDLINE B1 4271 4500 18000 18000
STIRRUPS 23 10 GRIDLINE B1 820 900 20700 20700
MAIN BAR 4 12 GRIDLINE A2 3950 4000 16000 32000
STIRRUPS 21 10 GRIDLINE A2 820 900 18900 37800
MAIN BAR 4 12 GRIDLINE B2 3950 4000 16000 16000
STIRRUPS 21 10 GRIDLINE B2 820 900 18900 18900
STIFFINER BEAM MAIN BAR 2 12 SB-1 6300 7000 14000 14000
STIRRUPS 33 10 SB-1 490 500 16500 16500
COLUMN AT PITCH WALL MAIN BAR 2 12 1187 2000 4000 4000
STIRRUPS 7 10 490 500 3500 3500
SEPTIC TANK
VERDES V2 SINGLE ATTACHED DUPLEX
BAR BAR DIAMETER ACTUAL CUT TOTAL LENGTH TOTAL LENGTH
PART OF STRUCTURE INSTALLATION QUANTITY LOCATION LENGTH (mm)
TYPE (mm) LENGTH (mm) (mm) (mm)
SLAB ON GRADE MAIN BAR B.W. 5 10 LONG SPAN 1240 1300 6500 13000
MAIN BAR B.W. 3 10 SHORT SPAN 2340 2400 7200 14400
VERTICAL BAR 4 10 LONG SPAN 1440 1500 6000 12000
VERTICAL BAR 3 10 SHORT SPAN 1440 1500 4500 9000
HORIZONTAL 2 10 6000 6000 12000 24000