Specification - Plant Site Data Sheet & Project Data Sheet

You are on page 1of 6

Power and Water Utility Company for Jubail and Yanbu (MARAFIQ) Master Specification MQ-SP-C-2000

Project Name Date:15 Feb 2011


Contract Number Page 1 of 6
Revision 1

SPECIFICATION – PLANT SITE DATA SHEET & PROJECT DATA SHEET

This specification has been revised as indicated below and described in the revision record on the following
page. Please destroy all previous revisions.

Revision Date Originator's Reviewed/Checked By Pages


No. Name & Initials Name & Initials
A 9/15/2010 Brooke Shondelmyer 4
0 11/03/2010 Brooke Shondelmyer Greg Luttrull 6
1 2/15/2011 Brooke Shondelmyer Greg Luttrull 6

APPROVALS SIGNATURES DATE

Lead Engineer Greg Luttrull 2/15/2011


Project Engineering
Manager: Ed Haney 2/15/2011
Client Approval:

ISSUED FOR : Construction X Other Approved


Power and Water Utility Company for Jubail and Yanbu (MARAFIQ) Master Specification MQ-SP-C-2000
Project Name Date:15 Feb 2011
Contract Number Page 2 of 6
Revision 1

SPECIFICATION – PLANT SITE DATA SHEET & PROJECT DATA SHEET

Record of Revisions
Revision Date Description
No.

A 9/15/2010 Issued for Approval, Table of Contents Only

0 11/03/2010 Issued for Review/Approval

1 2/15/2011 Issued Approved


Power and Water Utility Company for Jubail and Yanbu (MARAFIQ) Master Specification MQ-SP-C-2000
Project Name Date:15 Feb 2011
Contract Number Page 3 of 6
Revision 1

SPECIFICATION – PLANT SITE DATA SHEET & PROJECT DATA SHEET

Scope

PIP CVC01017, Plant Site Data Sheet, dated February 2005, is adopted for project use with the following
modifications noted in this addendum.

PIP CVC01018, Project Data Sheet, dated March 2005, is adopted for project use with the following
modifications noted in this addendum.

Modifications to the Original Specification

The following requirements are defined as additions, deletions, and revisions to PIP CVC01017.

Section Description

2.1 Process Industry Practices Replace with the following:


(PIP) 2.1 Marafiq Specifications
MQ-SP-P-5001 – Process and Utility Piping Design, Layout and Drawing
2.3 Government Regulations Add the following:
 Royal Commission Environmental Regulations
Attachments Add the following Section:
Attachments
 Rainfall Intensity for Various Durations and Return Periods (Jubail
Industrial City)
 Intensity-Duration-Frequency Curve of Rainfall (Yanbu Industrial
City)

Modifications to the Original Specification

The following requirements are defined as additions, deletions, and revisions to PIP CVC01018.

Section Description

2.1 Process Industry Practices Replace with the following:


(PIP) 2.1 Marafiq Specifications
MQ-SP-C-2009 – Chain Link Fence and Gates Installation
2.3 Government Regulations Add the following:
 Royal Commission Environmental Regulations
Power and Water Utility Company for Jubail and Yanbu (MARAFIQ) Master Specification MQ-SP-C-2000
Project Name Date:15 Feb 2011
Contract Number Page 4 of 6
Revision 1

SPECIFICATION – PLANT SITE DATA SHEET & PROJECT DATA SHEET

PIP CVC01017
Project Data Sheet

TABLE OF CONTENT
1. INTRODUCTION ............................................................................................................................................ 2
1.1 Purpose ....................................................................................................................................................... 2
1.2 Scope ........................................................................................................................................................... 2
2. REFERENCES ................................................................................................................................................. 2
2.1 Process Industry Practices ....................................................................................................................... 2
2.2 Industry Codes and Standards ................................................................................................................ 2
2.3 Government Regulations.......................................................................................................................... 3
DATA FORMS
CVC01017-D - Plant Site Data Sheet - U.S. Customary Units
CVC01017-DM - Plant Site Data Sheet - SI Units

PIP CVC01018
Project Data Sheet
TABLE OF CONTENTS
1. INTRODUCTION....................................................................................................................................................... 2
1.1 Purpose ....................................................................................................................................................... 2
1.2 Scope ........................................................................................................................................................... 2
2. REFERENCES............................................................................................................................................................ 2
2.1 Process Industry Practices ....................................................................................................................... 2
2.2 Industry Codes and Standards ................................................................................................................ 2
2.3 Government Regulations.......................................................................................................................... 2
DATA FORM
CVC01018-D - Project Data Sheet - Plant Site Data Sheet, U.S. Customary Units
CVC01018-DM - Project Data Sheet - Plant Site Data Sheet, SI Units

Attachments
1. Rainfall Intensity for Various Storm Durations and Return Periods (Jubail Industrial City)
2. Intensity-Duration-Frequency Curve of Rainfall (Yanbu Industrial City)
Power and Water Utility Company for Jubail and Yanbu (MARAFIQ) Master Specification MQ-SP-C-2000
Project Name Date:15 Feb 2011
Contract Number Page 5 of 6
Revision 1

SPECIFICATION – PLANT SITE DATA SHEET & PROJECT DATA SHEET


Power and Water Utility Company for Jubail and Yanbu (MARAFIQ) Master Specification MQ-SP-C-2000
Project Name Date:15 Feb 2011
Contract Number Page 6 of 6
Revision 1

SPECIFICATION – PLANT SITE DATA SHEET & PROJECT DATA SHEET

You might also like