Construction of Flood Control Structure Along Bislak River, Sitio, Magabobo, Brgy. Salsalamagui, Vintar, Ilocos Norte
Construction of Flood Control Structure Along Bislak River, Sitio, Magabobo, Brgy. Salsalamagui, Vintar, Ilocos Norte
Construction of Flood Control Structure Along Bislak River, Sitio, Magabobo, Brgy. Salsalamagui, Vintar, Ilocos Norte
Date
NAME OF PROJECT : Construction of Flood Control Structure along Bislak River, Sitio, Magabobo, Brgy.
LOCATION : Salsalamagui, Vintar, Ilocos Norte
SOURCE OF FUND : GAA 2020
APPRO./CONTRACT COST : PHP 20,427,120.50
DATE STARTED : September 29, 2020
DATE COMPLETED :
PROJECT INSPECTOR : RODRIGO F. AGUSTIN
PROJECT ENGINEER : MARK LOUIE B. GALIZA
CONTRACTOR : DJCM Construction Corporation
We the undersigned members of the Inspectorate Team, conducted a joint inspection of the above-stated
project and found the same to be satisfactorily completed/ongoing in accordance with the Plans and Specifications
of the Contract.
-
REMARKS 11,866,302.97