Item Process Description Activity Verify Hold Point Inspection Test Eqpt Responsible Applicable Specs/ Document
No. Inspection Test Method Frequency Required Person Code Records
Siteworks and
2.0
Earthworks
Survey Results Contractor
2.1 Layout and Stacking Orientation/location of lot Survey N/A N/A Transit N/A IFC/As-built dwgs
Verification Surveyor
Visual/Dimensional / Underground Surveyor/
2.2 Excavation Column and footings dimensions/locations Survey Daily Transit/Level N/A IFC/As-built dwgs
Levelness obstruction Supervisor
Visual/Sieve Surveyor/ Inspection/Acceptance
2.3 Backfilling Filling materials Thickness per layer FDT Results Upon application Engineer's Level As specified
Analysis Supervisor Report
Base compaction mixture
of hard durable stones, Checked thickness per layer, grading, placing &
2.4 FDT per Layer Visual/FDT Results FDT Results Per layer FDT Apparatus QC Engineer 95% Dry Density FDT Results
crushed slag/gravel, spreading of earth materials (filling materials)
crushed sand, soil, etc.
Inspection/Acceptance
2.5 Soil Poisoning Surface preparation and chemical used Lab Test Visual Result of Lab Test Upon application N/A Supervisor As specified
Report
Check material class, sizes, type, grade and mill Visual/ Tensile Result of Lab Tensile Stress Test Reports/Mill
3.0 Reinforcing Steel Visual/Mill Certificate Upon delivery QC Engineer ASTM A615 Gr 40
cert. Strength Test Test/Mill Certificate Apparatus Certificate
Req'd sizes, dimension,
Check supports, ties, stirrups, splices, spacing Visual/Measure Supervisor/QC Inspection/Acceptance
3.1 Placement splicing/lapping, Measurement Daily Steel tape As specified
dowels & cover ment Engr Report
orientation
Check dimension, elevation, plumbness, levelness, Visual/Measure Inspection/Acceptance
Survey results Measurement Daily Transit/Level QC Engineer As specified
cleanliness ment Report/As-built dwgs
5.0 Concreting
Visually check tools, eqpt.,
Check area cleanliness & provision for equipment batch plant, concrete matls, Unobstructed and
5.1 Site preparation Visual Prior to pour N/A Supervisor N/A N/A
access safety paraphernalia, clean area
barricades
Pour card permit shall be accomplished prior to Pour card permit Concrete Placement
5.2 Before Pouring N/A Pour card permit approvals N/A N/A QC Engineer N/A
pouring approvals Inspection Report
More than 1 hour
Receipt/Time interval
5.3 During Pouring Interval of delivery schedule Timing after volume is N/A N/A QC Engineer N/A N/A
between pours
batched
INSPECTION TEST PLAN - CIVIL
Item Process Description Activity Verify Hold Point Inspection Test Eqpt Responsible Applicable Specs/ Document
No. Inspection Test Method Frequency Required Person Code Records
Result of Slump Test Slump cone/
All concrete delivery shall be tested Slump Test Temperature Before pour QC Engineer ASTM C-143 Slump Test Reports
& Temperature Thermometer
Maintained samples, with 5 cylinders for every
Compressive Compressive test Compressive Strength
50m³ volume of concrete, i.e., 7, 14, 28 day curing Samples taken and cured Failed test result 7, 14, 28 days QC Engineer ASTM C39
Strength test apparatus Test Results
time
Tools & equipment to be Improper method of
Supervisor/QC Inspection/Acceptance
Using transit mixers Check consolidation & finishing Visual used, concrete placement depositing, vibrating, During pour N/A As specified
Engr Report
procedure finishing
Cracks and Other Visually check surface condition, take core Concrete Placement Supervisor/QC Quality Incident
6.1 Visual N/A 2 days after pour N/A As specified
Deformities samples when necessary Procedure/Curing Method Engr Investigation report
Check and monitor that rectification shall be made Deviation in Supervisor/QC Approved Repair
Visual Repair Procedure During repair N/A As specified
as per approved repair procedure procedure Engr Procedure