Technology Standard of Pipe Rehabilitation (2021)
Technology Standard of Pipe Rehabilitation (2021)
Technology Standard of Pipe Rehabilitation (2021)
Chunwen Yan
Junyu Xu
Technology
Standard
of Pipe
Rehabilitation
Technology Standard of Pipe Rehabilitation
Lu Wang Chunwen Yan Junyu Xu
• •
123
Lu Wang Chunwen Yan
School of Engineering and Technology China Geological Equipment
China University of Geosciences (Beijing) Group Co., Ltd.
Beijing, China Beijing, China
Junyu Xu
China Society of Trenchless Technology
Beijing, China
This Springer imprint is published by the registered company Springer Nature Singapore Pte Ltd.
The registered company address is: 152 Beach Road, #21-01/04 Gateway East, Singapore 189721,
Singapore
Preface
Underground pipelines are the critical infrastructure of the city. They include the
water supply and drainage system, gas pipeline, electric power pipeline and com-
munication pipeline, transporting energy and removing waste for residents, facto-
ries and enterprises located in different places of the city. The pipes for the city likes
the blood vessels for the human body. Therefore, they are called as the “lifeline
of the city.” However, with the development of the city, due to years of use,
underground pipelines are tending to be aging and have some defects,such as cracks
and leaks. If they are not repaired or renewed in time, the city operation will be
seriously affected.
Trenchless pipe rehabilitation technology is a new technology that could repair
and renew the original pipeline without excavating the ground. It does not affect the
normal life around the pipeline. What is more, it can save the construction time. As a
result, it lowers the cost compared to the traditional rehabilitation method. Therefore,
it is not only very welcomed by the trenchless construction units, but also supported
by the government. Thus, it has been developed rapidly in the recent ten years.
However, due to the trenchless pipe rehabilitation technology is new and is not
developed maturely, the pipeline renovation construction by this technology is
chaotic and do not have standard to reference. The relevant terminology are not
unified which is not good for communication. In this situation, authors compiled
this technical regulation which is referring to various international advanced stan-
dards and relevant theories, summarizing domestic and foreign experience of
trenchless pipe rehabilitation projects and combining personal construction expe-
rience for many years.
This standard summarizes the technical method and construction process of
underground pipeline testing, cleaning and renovation. It has 20 chapters and two
appendixes in total. Its content includes: Pipeline rehabilitation construction orga-
nization design, pipeline cleaning, preparations before construction, pipeline
detection and quality assessment, pipeline renovation design/method/equipment
selection/steps/technical indicators, universal construction techniques, construction
general rules, the engineering quality acceptance, construction health, safety,
environmental protection and production management, and so on. This book
v
vi Preface
The author(s) disclosed receipt of the following financial support for the research,
authorship and/or publication of this book: This work was supported by the Natural
Science Foundation of China (41902320) and the Fundamental Research Funds for
the Central Universities (2652018089).
Thanks to Prof. Wenjian Zhu of Beijing Institute of Exploration Engineering for
offering professional advice for this book. Thanks to Senior Engineer Fangjun Li
and Mingqi Wang for supporting the translation work of this book. Thanks to
Prof. Yuanbiao Hu of China University of Geoscience (Beijing) for revising and
proofreading the English of this book. Thanks to my students Pingfei Li and
Xuesong Bai for helping me search and organize the materials. In addition, the
authors express their appreciation to China Society for Trenchless Technology for
providing data and materials.
vii
Contents
1 Scope . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1
2 Normative Reference Documents . . . . . . . . . . . . . . . . . . . . . . . . . . 3
3 Basic Rules . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5
3.1 Pipe Diameter Series . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5
3.2 Pipeline Type . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5
3.3 Pipeline Rehabilitation Length Series . . . . . . . . . . . . . . . . . . . . 5
3.4 Classification of Pipeline Rehabilitation Methods . . . . . . . . . . . 6
3.5 Basic Principles of Pipeline Rehabilitation Method
Selection . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .......... 6
3.6 Selection of Pipeline Rehabilitation . . . . . . . . . . . .......... 7
3.7 Main Process of Pipeline Rehabilitation . . . . . . . . .......... 8
4 Pipeline Rehabilitation Construction Organization Design . . . .... 9
4.1 Basic Requirements for Construction Organization Design .... 9
4.2 Design Basis for Construction Organization . . . . . . . . . . . .... 9
4.3 Requirements and Main Contents of Construction
Organization Design . . . . . . . . . . . . . . . . . . . . . . . . . . . . .... 9
4.4 Preparation and Approval of Construction Organization
Design . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .... 12
5 Pipeline Cleaning . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 13
5.1 General Provisions . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 13
5.2 Pipeline Cleaning Quality Level . . . . . . . . . . . . . . . . . . . . . . . 13
5.3 Pipeline Cleaning Methods . . . . . . . . . . . . . . . . . . . . . . . . . . . 15
5.4 Selection of Pipeline Cleaning Methods . . . . . . . . . . . . . . . . . . 20
6 Pipeline Inspection and Quality Assessment . . . . . . . . . . . . . . . . . . 21
6.1 Pipeline Inspection . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 21
6.2 Pipeline Quality Evaluation . . . . . . . . . . . . . . . . . . . . . . . . . . . 26
ix
x Contents
Appendix A . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 119
Bibliography . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 165
Chapter 1
Scope
This standard specifies the technical requirements and relevant management stan-
dards for all procedures in the construction of trenchless pipeline rehabilitation
(replacement and renovation).
This standard is suitable for the construction project which utilizing the trenchless
pipeline rehabilitation technology to renovate and upgrade the underground pipelines.
The following documents are necessary when you are using this standard. For any
dated references, only the dated version applies to this standard. For any undated
references, its latest version (including all the modified documents) applies to this
standard.
《Structural design code for pipelines of water supply and waste water engineering》
GB50332;
《Code for construction and acceptance of water and sewerage pipeline works》
GB50268;
《Code for design of gas transmission pipeline engineering》GB50251;
《Code for construction and acceptance of city and town gas distribution works》CJJ
33;
《Technical specification for detection and evaluation technique of urban sewer
pipeline》CJJ 181;
《Technical specification for trenchless rehabilitation and renewal of urban sewer
pipeline》CJJ/T 210;
《Technical specification for trenchless rehabilitation and replacement engineering
of city gas pipe》CJJ/T 147;
《Technical specification for trenchless rehabilitation and renewal of urban water
supply pipelines》CJJ/T 244;
《Technical specification for safety of operation, maintenance and rush-repair of city
gas facilities》CJJ 51;
《Technical specification for safety of urban sewer maintenance》CJJ 6;
《Technical specification for operation, maintenance and safety of urban water supply
pipe-networks》CJJ 207.
3.1.1 Small diameter: a pipe with inner diameter less than 200 mm.
3.1.2 Medium diameter: a pipe with an inner diameter greater than or equal to 200 mm
and less than 800 mm.
3.1.3 Large diameter: a pipe with an inner diameter greater than or equal to 800 mm.
3.2.1 According to the type of pipeline, the pipeline can be divided into: drainage
pipeline, water supply pipeline, gas pipeline, oil and gas pipeline, industrial pipeline,
heat supply pipeline, etc.
3.2.2 The types of pipelines can be divided into: gravity pipelines and pressure
pipelines according to the pipeline operating pressure status.
3.4.1 Pipeline rehabilitation is divided into two categories: pipeline replacement and
pipeline renovation.
3.4.2 According to the degree of pipeline structure rehabilitation, renovation
is divided into: structural renovation, semi-structural renovation, and functional
renovation.
3.4.3 Pipe replacement mainly includes: pipe cracking, pipe eating and pipe pulling.
3.4.4 Pipeline renovation are divided into two categories according to their integrity:
localized renovation (spot renovation) and overall renovation.
3.4.5 According to the combination of the inner wall of the original pipeline and
the outer wall of the liner, the pipeline renovation is divided into three categories:
interval renovation, closed renovation, and pasted renovation.
3.4.6 According to whether the pipeline function or requirements (pressure, flow)
are improved after the renovation, the pipeline renovation is divided into two types:
upgrade renovation and non-upgrade renovation.
3.4.7 The overall renovation of the pipeline mainly includes: Sliplining (including
Discrete Sliplining), pipe Segmental Lining, Improved Sliplining (including
Swagelining, Folded Lining), Cured-in-Place-Pipe(CIPP) (including Inversion
Lining and Drawing), Spirally Wound Lining, Spraying Lining, etc.
3.4.8 Localized renovation mainly includes: Spot CIPP, Stainless Steel foam sleeve,
Spot grouting, pipe Segmental lining, etc.
3.5.4 With the goal of high efficiency, low consumption, safety and environmental
protection, ensure the quality of pipeline renewal, reduce labor intensity, and strive
for good economic and social benefits.
3.5.5 The renovation should be adapted to the natural geographical and climate
conditions of the construction area.
3.6.1 Select the rehabilitation according to the diameter requirements after the
pipeline rehabilitation. If you need to increase the diameter of the pipeline, you need
to use the pipeline replacement, including the pipe creaking and the pipe eating, etc.
3.6.2 According to the type of pipeline renovation: structural renovation, semi-
structural renovation, functional renovation, etc., select the pipeline renovation.
3.6.3 Select the pipeline rehabilitation according to the pipeline type. The appropriate
pipeline types for different renovation methods are shown in Table 3.1.
3.6.4 Select the renovation method according to the old pipeline material. The suitable
pipeline types for different rehabilitation methods are shown in the Table 3.2.
3.6.5 According to the pipe diameter and rehabilitation length, select the pipe
rehabilitation method.
Table 3.1 Different types of pipelines are suitable for different renovation methods
Method
Type of Sliplining Pipe Modified CIPP Spirally Spraying Pipe Pipe
pipeline segmental sliplining wound lining cracking eating
lining lining
Sewer ++ ++ ++ ++ + ++ ++ ++
pipeline
Water + + + ++ – ++ ++ ++
supply
pipeline
Gas + – + ++ – – ++ ++
pipeline
Oil and + – + ++ – + ++ ++
gas
pipeline
Industrial + – + + – + ++ ++
pipeline
Note ++ very suitable; + suitable; – not suitable
8 3 Basic Rules
3.6.6 According to the cross-sectional shape of the pipeline, select the pipeline
rehabilitation method.
3.6.7 According to the degree of pipeline damage and the requirements after the
rehabilitation, select the pipeline rehabilitation method.
3.6.8 Select the pipeline rehabilitation method based on the pipeline and its
surrounding environment.
3.7.1 The construction process of the pipeline replacement project mainly includes:
Site investigation → Pipeline initial cleaning → Pipeline inspection → Building
construction site → Work pit preparation → Equipment installation and commis-
sioning → Replacement construction preparation → construction → Pipe end
processing and connection → Testing and acceptance → Site environment restora-
tion.
3.7.2 The construction process of the pipeline rehabilitation project mainly
includes:
Site investigation → Pipeline initial cleaning → Pipeline inspection → Building
construction site → Pipeline cleaning → Work pit preparation → Equipment instal-
lation and commissioning → Repair construction preparation → Rehabilitation
construction → Pipe end processing and connection → Test and acceptance →
Site environment restoration.
Chapter 4
Pipeline Rehabilitation Construction
Organization Design
2. Project overview
(1) Explain the project name, work content, project deadline and construction
requirements, etc.;
(2) Explain the project’s geographic location, traffic conditions, topography,
local climate, etc.;
(3) Explain the surrounding environment: surrounding structures and existing
underground pipelines, site conditions, etc.;
(4) If it is necessary to excavate the work pit, the engineering geological
conditions should also be outlined.
3. Construction workloads
(1) According to the pipeline to be repaired, explain the construction sequence;
(2) Calculate the general workload according to the construction sequence.
4. Rehabilitation technical design
(1) Determine the pipeline rehabilitation method according to the pipeline
rehabilitation requirements;
4.3 Requirements and Main Contents of Construction Organization … 11
(2) Determine the inspection and cleaning methods and standards according
to the construction sequence;
(3) Determine the main construction materials for rehabilitation and main
technical parameters;
(4) Design and calculation of the wall thickness of the liner;
(5) Perform the necessary calculation of the pipe ring stiffness strength;
(6) Give the main technical measures for pipeline rehabilitation;
(7) When new technology of rehabilitation is adopted, detailed technical
measures shall be given;
5. Device selection
According to the diameter of the pipeline and the length of the rehabilitated
pipeline, determine the type of related equipment, including cleaning equip-
ment, testing equipment, power machine, pipeline rehabilitation construction
related equipment, etc., the performance parameters of the main equipment
should be noted.
6. Site layouts
(1) According to the site situation of the pipeline, give the layout of the work
pit;
(2) According to the site investigation and the selected equipment, give the
construction site layout.
7. Engineering quality requirements and guarantee measures
(1) Engineering quality index
According to the specific requirements of the pipeline rehabilitation design.
(2) Quality assurance measures
(1) To select the material of the inner liner, including protective measures
and precautions during operation;
(2) According to the method of pipeline rehabilitation, technical measures
to guarantee the construction quality are given;
(3) According to the specific conditions of the project, technical solutions
for difficult point are given.
8. Accident prevention and safety technical measures
(1) According to the site conditions, the technical requirements and measures
of cold prevention, fire prevention, flood prevention and other disasters and
construction safety should be put forward;
(2) According to the pipeline situation, preventive and treatment measures for
the rehabilitation quality accidents should be proposed;
(3) According to the existing pipelines around the work pit and underground,
detailed protective measures for surrounding buildings and underground
pipelines should be put forward;
(4) To propose emergency plans for possible major accidents.
12 4 Pipeline Rehabilitation Construction Organization Design
4.4.1 Under the lead of the chief engineer of the construction unit, relevant technical
personnel jointly prepare the rehabilitation construction organization design.
4.4.2 The construction organization design of pipeline rehabilitation shall be
reviewed by the construction unit and reported to the task issuing unit or owner
for approval.
4.4.3 During the construction of pipe rehabilitation, if the design is found to be incon-
sistent with the actual situation, promptly communication with the project issuing
unit or owner should be done. Then modify the design in accordance with the relevant
standards of project management, and do not alter the design without consent.
4.4.4 For pipeline rehabilitation projects with greater engineering difficulty and
greater risks, industry expert demonstration meetings must be held to review
and demonstrate the organization design of the pipeline rehabilitation project
construction.
Chapter 5
Pipeline Cleaning
4. Use and maintenance of the robotic cleaning equipment: The main equipment
of the robotic cleaning is the pipeline robot and perform regular maintenance on
the robot according to the instructions of the robot manufacturer.
(5) You can use high-pressure water to clean the inner wall of the pipeline, and
use a fan and sponge ball to dry the wall after cleaning;
(6) The cleaned sewage and dirt should be collected and should be treated in a
centralized manner;
(7) The inner wall of the pipe after cleaning should be dry and free from dirt.
If it fails to meet the standard, it should be cleaned again.
4. Use and maintenance of high-pressure water jet cleaning equipment:
(1) The main equipment for high-pressure water jet cleaning is a high-pressure
water jet cleaning vehicle;
(2) Before each use, you should carefully check whether the high-pressure hose
is damaged, the joint connection is tight and sealed, and the damaged high-
pressure hose cannot be used continuously, and should be replaced in time;
(3) High-pressure water jet cleaning operators should be trained before they can
start operations;
(4) The high-pressure water jet cleaning vehicle high-pressure water pump
set, high-pressure hose, nozzle and other accessories should be regularly
checked to ensure that the equipment is complete and in good condition.
(3) The construction personnel should wear neat clothes to prevent chemical
agents from harming the body;
(4) Pay close attention to the spread of toxic and harmful gases generated during
the chemical cleaning process to avoid personal injury;
(5) After cleaning, the waste liquid should be recovered in time and handled in
a proper manner, and no leakage or arbitrary discharge is allowed.
4. Use and maintenance of chemical cleaning equipment:
(1) The main equipment of chemical cleaning includes: pharmaceutical pump,
medicine distribution tank, connecting pipe;
(2) Before cleaning, carefully check whether the type, pressure, and displace-
ment of the pharmaceutical pump are appropriate. After the cleaning system
is connected, use fresh water to debug the system;
(3) After cleaning, use fresh water to rinse the drug pump, dispensing tank,
connecting pipe, etc. Regularly maintain the medicament pump set and the
mixing tank.
5.4.2 Choosing the pipe cleaning method is mainly according to the following factors:
pipe types, pipe dirt types, pipe materials, general condition of pipe interiors.
Chapter 6
Pipeline Inspection and Quality
Assessment
2. Camera inspection
(1) Camera inspection adopts Closed-Circuit-Television (CCTV) to inspect
underground pipelines. The technicians interpret the pipeline status based
on the inspection video.
(2) The basic steps of inspection: collecting data—on-site survey—preparing
testing plan—cleaning and blocking drainage—testing and collecting image
data with CCTV testing system—summarizing data, outputting testing
report—acceptance data accuracy—submission evaluation report.
(3) Camera inspection should meet the following requirements:
(1) Pipeline inspection and evaluation using closed-circuit television
should be conducted in units of the pipeline between two adjacent
inspection wells;
(2) Before the inspection, the equipment should be thoroughly checked
and debugged on the ground to ensure that the equipment can work
normally;
(3) Before the instrument enters the well for inspection, the display board
should be photographed. The display board should display the infor-
mation, such as the pipe location, pipe serial number, pipe diameter,
inspection time and the name of the person in charge. The information
displayed on the board should be written clearly in regular font.
(4) When CCTV is used for inspection, the height of the water level in the
pipeline should not exceed 20% of the vertical height of the pipeline;
(5) When encountering defects or abnormalities in the pipeline, the inspec-
tion equipment should temporarily stop moving forward, change the
camera to carefully photograph the abnormal parts of the defect, and
then continue to move forward;
(6) When inspecting obstacles that cannot be passed, the CCTV should be
exited, and the obstacles should be cleared to continue the detection;
(7) When scaling, siltation or severe corrosion and flaking on the inner
wall of the old pipe affect the TV image effect, the inside of the pipe
should be cleaned and continue to be tested;
(8) The pipeline camera system should use color CCTV testing equipment
with explosion-proof function and lens with rotation and zoom func-
tions. The CCTV testing equipment should be equipped with a CCD
camera with a horizontal resolution of not less than 460 lines;
(9) CCTV inspection video data should be physically archived in a
common format MPEG or AVI in a timely manner and be handed
over to special personnel for collection and sorting.
3. Periscope inspection
(1) Periscope inspection is also called Quick View inspection (QV). Quick View
inspection (QV) is mainly used for rapid inspection and diagnosis of the
6.1 Pipeline Inspection 23
Start of Evaluation
YES NO
Continue to run Whether to accept or not Repair or Replace
7.1.1 The pipeline rehabilitation design should adopt the principle of design for
different pipe section-by-section. For the pipe of different diameters and different
defect levels, the pipeline rehabilitation should be designed section-by-section.
7.1.2 If it is confirmed by the external pressure failure load test that the rehabilitated
pipeline has the same damage strength as the new pipeline, the pipeline renovation
structure calculation can be omitted.
7.1.3 The design of the pipeline rehabilitation should meet the following basic
requirements:
1. The rehabilitated pipeline should meet the requirements of the force;
2. The rehabilitated pipeline should meet the stability requirements;
3. The rehabilitated pipeline shall meet the requirements of over-current capability;
4. The rehabilitated pipeline shall meet the requirements of the dredging.
7.1.4 The basic principles of pipeline rehabilitation method selection are as follows:
1. Specify the type of pipeline rehabilitation: pipeline replacement, upgrade reno-
vation, structural renovation, semi-structural renovation, functional renovation;
2. The main considerations include: pipeline type, pipeline quality, pipeline stress,
flow area/diameter, pipeline shape, pipeline path (bending), surrounding envi-
ronment (temperature, working pit, etc.), sanitation and resistance to the pipe
For corrosion and other performance requirements, see Table 7.1.
7.1.5 In addition to the relevant requirements of this standard, the liner design
in pipeline renovation should also meet the relevant standards or requirements of
pipeline strength and stability in different industries.
7.2.1 When the old pipe is replaced by the pipe cracking method, the wall thickness
of the pipe shall be designed in accordance with the requirements of the newly
established pipes in different industries.
7.2.2 The maximum standard size ratio of the new PE pipeline replaced by the pipe
cracking method should meet the requirements of Table 7.2.
7.3.1 See Table 7.3 for the check and calculation requirements of strength and radial
stability of gravity pipeline renovation.
7.3.2 Refer to Table 7.4 for the check and calculation requirements of the strength
and radial stability of the pressure pipeline renovation design.
7.3.3 For high-pressure and ultra-high-pressure pipelines, transport dangerous goods,
and other dangerous pipelines, semi-structure renovation should not be adopted.
7.3 Pipeline Renovation Design 31
7.3.4 The methods, calculation formulas and parameter values for the design calcula-
tion and stability check of pipeline renovation strength shall be carried out with refer-
ence to the relevant provisions of engineering design codes of pipelines in different
industries.
7.3.5 when the upgrading renovation is implemented, the upgraded pipeline technical
requirements should be adopted, and the comprehensive strength of the new pipe
or the composite with the old pipe and its grouting body or adhesive body of the
annular gap should be carried out according to the requirements of the relevant
pipeline standards in different industries check or radial stability check calculation
to determine the liner thickness or grouting technical requirements.
Table 7.3 Basic requirements for check and calculation of gravity pipeline renovation strength and
radial stability
Renovation type Requirements and Renovation method Checking method
considerations of
renovation
Functional Renovation Pasted renovation No need for strength or
renovation requirements: stability check or
anti-corrosion, verification calculation,
improving the determine the thickness
performance of the inner of the liner according to
surface of the pipeline, requirements such as
etc.; main corrosion protection or
considerations: the surface treatment
internal surface Closed renovation and Under the condition of
conditions of the interval renovation vacuum negative
original pipeline, the pressure, check the
surface quality strength or radial
requirements after stability of the lined
repair, the over-current pipe to determine the
capacity ratio thickness of the lined
before/after repair pipe
Semi-structural Renovation Pasted renovation Under common or
renovation requirements: plugging partial external loads
and sealing, partial such as vacuum
reinforcement of the negative pressure and
structure, etc.; main external groundwater
considerations: ratio of static pressure, the
over-current capacity strength check or radial
before/after repair of the stability check of the
pipeline; external composite pipe of the
groundwater hydrostatic new pipe and the old
pressure or some pipeline is performed to
external load required determine the thickness
by the lining layer of the new pipe
(continued)
32 7 Pipeline Rehabilitation Design
7.3.6 The value of vacuum negative pressure of gravity pipeline should be 0.03 MPa;
the value of vacuum negative pressure of pressure pipeline should be 0.05 MPa.
7.3.7 The outer diameter of the inner liner used by sliplining should not be less than
10% of the original pipe inner diameter, and the reduction should not be greater than
50 mm.
7.3.8 The outer diameter of the inner liner of modified sliplining and CIPP should
be consistent with the original pipe inner diameter.
7.3.9 When the liner pipe is located above the groundwater level, the standard size
ratio (SDR) of the liner pipe in CIPP shall not be greater than 100; the standard size
ratio (SDR) of the PE liner pipe shall not be greater than 42.
Table 7.4 Basic requirements for check and calculation of gravity pipeline renovation strength and
radial stability
Renovation type Requirements and Renovation method Checking method
considerations of
renovation
Functional Renovation requirements: Pasted renovation No need for strength or
renovation anti-corrosion, improving stability check or
the performance of the verification calculation,
inner surface of the determine the thickness
pipeline, etc.; main of the liner according to
considerations: the requirements such as
internal surface corrosion protection or
conditions of the original surface treatment
pipeline, the surface Closed renovation Under the condition of
quality requirements and interval vacuum negative
after renovation, the renovation pressure, check the
over-current capacity strength or radial
ratio before/after stability of the lined
renovation pipe to determine the
thickness of the lined
pipe
Semi-structural Renovation requirements: Pasted renovation Under the combined
renovation plugging and sealing, conditions of internal
partial reinforcement of pressure or vacuum
the structure, etc.; main negative pressure and
considerations: ratio of external groundwater
over-current capacity static pressure or part of
before/after renovation of external load, the
the pipeline; internal strength check or radial
pressure required by the stability check of the
lining, external composite pipe of the
hydrostatic pressure of new pipe and the old
the groundwater, or some pipeline is performed to
external loads, etc determine the thickness
of the new pipe
(continued)
34 7 Pipeline Rehabilitation Design
7.3.10 When the interval renovation is used for semi-structural and structural reno-
vation, the annular gap between the liner pipe and the old pipe should be grouted.
The liner pipe, grouting body and the composite pipe body formed with the old pipe
should be checked and tested whether can bear the total load acting on the pipe.
7.4.1 When the modified sliplining is used to renovate the pipeline, the maximum
allowable pulling force of the liner should be calculated according to (7.1):
1 1
Fmax = · π σ (D02 − Di2 ) (7.1)
K 4
7.4.2 When the pulling process is used for sliplining, the maximum allowable pulling
force of the liner should be calculated according to (7.1), K is 2.
Chapter 8
Preparations Before Construction
8.1.1 Before we design the engineering of the trenchless pipeline rehablitation, rele-
vant information on the construction site should be collected and site surveys should
be conducted.
8.1.2 For the pipeline rehabilitation project under special conditions, the feasibility
of the process method can be verified using the test section engineering.
8.1.3 The validity period of the pipeline rehabilitation design of trenchless shall not
exceed one year, and projects over one year shall be reviewed or redesigned.
8.1.4 Subject to the conditions of construction, the construction site shall occupy no
or less cultivated land, forest land, green land and site as much as possible.
8.1.5 The distribution of underground cables, pipelines and high-voltage wires on
the construction site should be understood.
8.1.6 Formulate reasonable platooning schemes, protection schemes for underground
facilities and traffic dredging schemes, etc.
8.2.1 The depth and diameter of all inspection wells on the old pipeline, as well as
the branch pipes in the well, the flow direction, the elevation of the bottom of the
pipe, the diameter of the inlet and outlet, etc. should be investigated.
8.2.2 Detailed investigation shall be conducted on the conditions of other under-
ground pipelines in the construction area, soil conditions in the construction area,
underground wells in the construction area, civil air defense facilities, obstacles,
8.4.1 The construction site should ensure road access and the site is level.
8.4.2 The construction site should meet the requirements of different construction
equipment layouts on the site area.
8.4.3 Traffic guidance investigation should be conducted for road construction, and
special plan for road construction should be approved.
8.4.4 Site survey should includes the investigation of the construction equipment and
vehicle parking location.
8.4.5 The location of the work pit shall be determined according to the design
scheme and the actual situation on the site. The location of the work pit shall avoid
underground structures, underground pipelines and other obstacles.
8.4.6 The slope of the working pit or working well shall be supported before construc-
tion. When the construction in the rainy season, the pipeline is buried deep, and the
excavation location is on the municipal road, in order to ensure the construction
safety, the support method of bolt shotcrete should be adopted.
8.4.7 When there is dynamic load around the work pit, corresponding protective
measures should be taken according to the environmental conditions. During the
rehabilitation construction process, if it is necessary to pile earthwork, materials,
construction and placement of construction machinery and equipment near the work
pit, the safety of the work pit support should be checked and confirmed to be safe.
8.4.8 Prior to the construction of the gas pipeline renovation, a plan should
be formulated for the gas suspension, evacuation, and purge of the pipeline in
service, and it should comply with the provisions of the urban gas-related safety
technical standard s.
8.4.9 Pipeline pretreatment includes: local reinforcement, repair, plugging, etc.
Pipeline cracks, interface dislocations, grooves, sharp protrusions, etc. are repaired
in accordance with the design and construction process requirements. If necessary,
40 8 Preparations Before Construction
point-shaped excavation can be used to remove obstacles that affect the construction
of the new pipe.
8.4.10 Welding of plastic pipes: welding procedure evaluation shall be carried out
before welding, and the welding quality shall comply with the relevant regulations
of relevant industries.
Chapter 9
Pipe Cracking
The pipe cracking is suitable for the replacement of concrete pipes, steel pipes, and
cast iron pipes whose original diameter is DN100 ~ 600 mm, and suitable for the
replacement of diameter expansion construction from first grade to second grade.
9.2.1 When the pipe cracking is adopted, the top soil of the old pipe to be rehabilitated
shall not be less than 0.7 m. The safety distance between the outer wall of the new
pipeline to be laid and the outer wall of other underground pipelines shall meet the
following requirements:
1. The safety distance of the pipes with the same diameter should not be less than
0.5 m;
2. The safety distance of the expansion pipes and the other pipes shall not be less
than 0.7 m.
9.2.2. For new pipes, HDPE new pipes of PE80 grade or above should be generally
selected, and they should comply with the relevant material standards.
9.2.3 According to different use function, pressure level, pipeline buried depth,
medium, etc., HDPE pipes with different standard size ratio SDR values should
be determined.
9.2.4 In the same rehabilitated pipe section, the same HDPE pipe shall be used, and
pipes of different models or different manufacturers shall not be used.
9.2.5 New pipes should be carefully inspected, and there should be no visible cracks,
holes, scratches, inclusions, bubbles, deformation or other defects.
9.3.1 The specifications of the pipe cracking equipment and its applicable pipe
diameter should be selected according to Table 9.1.
9.3.2. The recommended split pipe head (knife) for different pipes should be selected
according to Table 9.2.
9.4.1 The pit position and size of the work pit shall meet the following requirements:
1. The size of the work pit should be selected according to the size of the equipment
to facilitate the construction operation. The bottom of the pit should be 350 mm
lower than the bottom end of the outer wall of the old pipeline to be rehabilitated;
2. The initial working pit width of the inlet pipe should be greater than the diam-
eter of the new pipe 300 mm and not less than 650 mm; the length should be
determined according to the allowable bending radius of the PE pipe, see Fig. 9.1.
9.4.2 The construction of the work pit shall meet the following requirements:
1. The wall surface of the equipment pit should be perpendicular to the plane of the
bottom of the pit and the center line of the old pipe;
2. Gravel not less than 80 mm thick should be laid under the equipment pit;
3. The interface between the inlet pit wall and the old pipeline should be properly
excavated;
4. The work pit should be kept dry, and precipitation should be carried out if
necessary.
9.4.3 When using hydrostatic method for pipeline rehabilitation construction, the
following requirements shall be met:
1. The alarm device and emergency switch of the equipment should be tested before
construction;
≥h
L
Fig. 9.1 Schematic diagram of the initial working pit of the inlet pipe. h––Working pit height;
L––working pit length
44 9 Pipe Cracking
9.4.4 Before welding, the polyethylene pipe should be evaluated for welding
procedures to ensure the welding quality.
9.5.1 The staff in the starting work pit should be coordinated with the operation
host personnel at the end of the equipment pit. Intercom communication should be
adopted.
9.5.2 When using the pneumatic method for pipeline rehabilitation construction, the
following requirements shall be met:
1. During the process of cracking the pipe, a constant pulling force should be applied
to the cracked pipe head;
9.5 Pipe Cracking Construction 45
2. Before the cracked pipe head reaches the receiving pit, the construction should
not be terminated.
9.5.3 During construction, the new pipe should be placed on the roller bracket on the
ground, and it is strictly prohibited to drag on the ground.
9.5.4 When there is a sudden increase in traction during construction, the construction
must be stopped immediately and the cause must be ascertained before proceeding.
9.5.5 During construction, the number of the pulling rods entering the pipeline shall
be recorded to determine the position of the pipe splitter when it moves forward.
9.5.6 After the new pipe is pulling into the old pipe, the excess pipe section should
be cut off, and 500 mm length pipe sections should be reserved at both ends to adapt
to the later contraction of the pipe.
9.5.7 The polyethylene pipes in the working pit shall relieve the stress for not less
than 24 h before connection.
9.5.8 In the starting pit and receiving pit, the annular gap between the new pipeline
and the soil shall be sealed, and the sealing length shall not be less than 200 mm.
9.5.9 After the polyethylene pipes in the work pit are connected, the leak detec-
tion shall be carried out, and the work pit shall be backfilled after passing the leak
detection.
9.6.1 Equipment operators should strictly abide by the equipment operation rules.
9.6.2 All pipes must comply with the relevant standards of various industries. Before
the material is used, the material performance should be re-inspected according to
relevant regulations.
Chapter 10
Sliplining
10.1.1 It is suitable for the renovation of various specifications of round, square and
other special-shaped pipes.
10.1.2 When partial damage occurs on the pipe, such as falling off and missing
partially, misalignment of pipe end, partially cracked, partially corroded, partially
leaked, etc., localized repair or pretreatment should be performed first.
10.1.3 Each renovated pipe section should be decided whether it needs to be designed
separately according to the actual situation. If the bend of a certain section of the pipe
section exceeds the capacity of the repaired bent pipe or the pipe diameter changes,
section measures should be taken. Those who need to design work pits can set up
work pits at these points as the receiving pit of the previous section of pipeline and
the starting pit of the next section of pipeline.
10.2.1 The outer diameter of the liner used in sliplining should be smaller than the
inner diameter of the original pipe, but the reduction in diameter should not exceed
10% or 50 mm of the inner diameter of the old pipe.
10.2.2 The minimum length of the initial working pit of the pulling process shall be
calculated according to formula (10.1), and the layout of the initial working pit shall
be as shown in Fig. 10.1.
1
L = [H × (4R − H )] 2 (10.1)
In the formula:
1 ground roller frame; 2 wear pad; 3 trumpet-shaped introduction pipe; 4 old pipe
Fig. 10.1 Schematic diagram of the initial working pit layout of the traction process
Fig. 10.2 Schematic diagram of the initial working pit layout of the jacking process.
10.2.3 The initial working pit size and layout of the jacking process are shown in
Fig. 10.2.
10.3.1 The equipment used includes: traction device, hot melt welding machine and
grouting equipment. The traction device is generally composed of a winch, a guide
10.3 Equipment Use and Maintenance 49
pulley, a wire rope, a traction head, etc. The traction system should be equipped with
an automatic display device to record the traction force during construction.
10.3.2 The equipment required on site includes conventional equipment and special
equipment. Conventional equipment is used and maintained in accordance with rele-
vant regulations and instructions. Special equipment must be used and maintained
in accordance with the equipment instruction manual.
10.4.1 It should be selected according to the design plan and the actual situation on
site, develop a try-on plan, and determine the location of the work pit.
10.4.2 The cleaning and testing of pipelines before pipe penetration shall comply
with the provisions of this code.
10.4.3 Before passing through the pipe, a polyethylene section with a length of not
less than 3 m and the same diameter as the liner pipe shall be used to detect the
passing capacity of the pipe section, and the depth of scratches on the surface shall
be tested. The depth of the scratches shall not exceed 10% of the wall thickness.
10.4.4 The connection of the pipeline shall meet the following requirements:
1. Check the damage of the pipeline before connection: the score on the outer
surface of the pipeline should not exceed 10% of the wall thickness, there should
be no buckling caused by excessive or sudden bending, the flattening rate for
short pipes should not exceed 5%, and the inner surface should not have any
wear and cutting;
2. For the use of open flame connection equipment to connect pipes in work pits or
inspection wells, the content of combustible gas should be evaluated in advance;
3. The connection of pipelines should adopt the method of electro fusion welding
butt joint. The electro fusion welding butt joint shall meet the requirements in
GB19809 of “Code of Practice for the Preparation of Plastic Pipes and Fittings
Polyethylene (PE) Pipes / Tubes or Pipes / Pipes electro fusion welding Butt
Components”
10.5.1 The new pipe can be installed into the original pipe by pulling, pushing or
combining pulling and pushing. In the installation of ultra-normal wall thickness or
ultra-long polyethylene pipes, the combination of pulling and pulling should be used.
10.5.2 The pulling process should meet the following requirements:
50 10 Sliplining
1. When pulling the pipeline, necessary measures should be taken to prevent the
liner from being crushed and scratched when entering the old pipeline;
2. In the case of pulling obstruction, the size of the drawing force should be
controlled to prevent the pipeline from exceeding the rated allowable value;
3. The pulling rate of the pipeline shall not exceed 1.5%, the pulling speed shall not
exceed 0.3 m/s, and the construction shall be slowed down in the pipeline where
the bend or the pipeline deformation is large;
4. The pulling operation process should not be interrupted;
5. When inserting the new pipe into the old pipe, the length of the end of each
section of the new pipe protruding from the port of the old pipe should meet
the requirements of the pipeline’s tensile deformation recovery and connection
operation. The recommended value is: 1% L + 20 mm; The recovery time should
be maintained for 24 h.
10.5.3 The short pipe pushing process should meet the following requirements:
1. Electro fusion welding welded polyethylene linning pipe can also be installed by
pushing;
2. When the space of the working pit is restricted or a mechanical socket type joint is
used, the pushing process can be used to allow water flow in the original pipeline,
but its water level should be below the pipeline arch line;
3. This process can also be used for the curve jacking of short tubes;
4. Water pumps and temporary drainage facilities should be prepared at the
construction site.
10.5.4 Reinforcement measures such as fixing and grouting can only be carried out
after the new pipe is stable and the stress is completely relaxed.
10.5.5 The annular gap between the liner pipe and the original pipeline should be
grouted. The grouting should meet the following requirements:
1. For a pipe with a diameter of more than 800 mm, the annular gap between the
new pipe and the old pipe must be grouted;
2. Grouting should be carried out in sections, and the annular gap should be evenly
filled, and the grouting pressure should not be greater than the allowable grouting
pressure of the new pipe;
3. During the grouting process, the grouting pressure should be adjusted by
installing vertical pipes or other methods;
4. When the diameter of the new pipe is greater than 900 mm, it shall be supported
in the pipe to prevent the new pipe from deforming under the effect of grouting
pressure.
5. After the grouting is completed, the grouting hole should be sealed.
10.6 Quality Assurance Measures 51
10.6.1 The materials used should conform to the relevant national codes and standards
and be re-inspected according to the codes.
10.6.2 Sliplining construction shall be functionally tested in accordance with relevant
technical regulations and acceptance specifications.
Chapter 11
Pipe Segmental Lining
11.1.1 The pipe segmental lining is divided into modular lining and stainless-steel
lining; the modular lining is only applicable to the renovation lining gravity flow
pipes. The material for the module lining is PVC sheet profile, and the material for
the stainless-steel lining is stainless-steel plate.
11.1.2 The pipe segmental lining is only applicable to the repair of pipelines that can
be accessed by people and have a caliber greater than 800 mm.
11.1.3 The pipe segmental lining can be applied to the repair of the following
situations, see Table 11.1.
11.2.1 The material used in the pipe segmental lining is a factory-prepared stainless
steel, PVC and other sheet profiles with durability, corrosion resistance and smooth
surface.
11.2.2 Module lining.
1. Commonly used modular lining PVC sheet profile structure is shown in Fig. 11.1;
2. Refer to Table 11.2 for the recommended pipe segment size;
3. Refer to Table 11.3 for the recommended size of rectangular pipe segments;
4. The sheet profiles used in the same repaired section should be the same material,
and there should be no defects such as visible cracks, holes, entrained debris or
other damage.
5. Samples of different profiles of different production batches should be sampled
and tested separately. The detection and requirements of the physical properties
of PVC sheet profiles shall meet the requirements of Table 11.4.
6. The pipe segment profile for modular lining shall be clearly marked, and the
mark shall include the manufacturer’s name or trademark, product number, place
of origin, production equipment, production date, model, material grade, and
the name of the specification on which the product is produced. Each piece of
segments profile should be marked.
7. The adhesive or sealant used should be compatible with the PVC composite
material and pipe assembly process.
8. The strength and fluidity of the grout used in the module lining must meet the
requirements of Table 11.5 of this regulation. At the same time, the grout must
also have anti-segregation, micro-expansion, anti-cracking and other properties.
9. The filler is not easy to separate in water and has excellent fluidity and strength.
The formulation and composition of the filler are shown in Table 11.6.
11.2.3 Stainless Steel Lining.
1. The stainless steel plate should comply with the relevant provisions of the current
national standard “Stainless Steel Cold Rolled Steel Plates and Strips” GB /
11.2 Construction Design and Materials 55
T3280 and the national standard “Stainless Steel Hot Rolled Steel Plates and
Strips” GBT4237, and the performance of the welding consumables should
comply with the current national standards “Stainless Steel Electrodes” GB /
T983 relevant regulations.
2. The mechanical performance of stainless-steel plates liner with different brands
should be in accordance with Table 11.7.
Table 11.8 Applicable conditions and uses of different brand stainless steel plates
Brand Applicable conditions Uses
06Cr19Ni10 (type 304) Chloride content ≤200 mg/L Drinking water, drinking cold
water, hot water and other
pipes
022Cr19Ni10 (type 304L) Pipes with corrosion resistance
requirements higher than type
304
06Cr17Ni12Mo2 (type 316) Chloride content ≤ 100 mg/L Pipes with corrosion resistance
requirements higher than type
304
022Cr17Ni12Mo2 (type 316L) Seawater or high chlorine
media
3. The applicable conditions and uses of different grades liner with stainless steel
plates can be selected according to Table 11.8.
4. The thickness and perimeter of the stainless-steel plates should be determined
according to the design requirements. The raw material size of the stainless-steel
plates should be selected based on the convenience of construction. The blanking
size of the stainless-steel plates used for the preformed pipe blank should be cut
according to the design size.
5. The stainless-steel welding consumables used for welding should match the
stainless steel plates used.
6. During the transportation, storage and construction of the pipe joints, semi-
finished products and structural parts (parts) used, measures shall be taken to
prevent their damage and corrosion. Stainless steel materials should be stored in
a warehouse away from the pollution of oil, acid, alkali, salt and other chemi-
cals. Prefabricated stainless steel tube blanks should not be stacked to prevent
deformation and wrinkling after compression.
7. The negative pressure should be considered in the design of the stainless-steel
lining. Special design should be made for places that are prone to negative pres-
sure, such as local high points and downstream of main line valves, to avoid
negative pressure causing the plates to collapse.
8. The segment plates should consider the length, nodes, equipment materials and
other issues to determine the appropriate length of the segmented plates and the
location of the breaking point.
11.3.1 The equipment used includes plate rolling machine, argon arc welding
machine, pipe support, in-pipe transport vehicle, generator, blower, winch, lighting
transformer, etc.
58 11 Pipe Segmental Lining
11.3.2 12V AC or DC electrical appliances should be used for the lighting equipment
in the tube.
11.3.3 The safe power consumption of the in-pipe welding machine shall comply
with the relevant regulations.
11.3.4 Gas cutting tools are strictly prohibited in the pipe.
11.3.5 The equipment needed on site includes conventional equipment and special
equipment. The conventional equipment should be used and maintained according
to relevant regulations and instructions. The special equipment should be used and
maintained according to the equipment instruction manual.
11.4.1 Pipe cleaning and testing shall comply with the relevant provisions of Chaps. 5
and 6 Regulation.
11.4.2 When the pipeline needs to be interrupted, the flow direction of the media in
the pipe should be investigated. Corresponding rehabilitation method for interrupting
pipe should be adopted according to the original pipe material. The interrupting pipe,
the treatment of residual liquid in the pipe and the laying of temporary pipelines
should ensure safety and convenient restoration.
11.4.3 The original pipe should be repaired for cracks, staggers, deletions, collapses,
etc., and leaks should be blocked. For the misalignment greater than 8% of the pipe
diameter, it should be corrected first.
11.4.4 Before the installation of the stainless-steel plates, the inside of the orig-
inal pipe should be kept tight, leak-free, dry and continuous forced ventilation. The
construction personnel in the pipe should wear complete labor protection equipment,
and the power cord in the pipe should be well insulated.
11.4.5 The size of the pipe segmental plate should ensure that it can pass through the
wellbore.
11.4.6 When the work pit is to be excavated at both ends of the pipe to be repaired,
the size of the work pit should be adapted to the length and width of the pipe segment,
and the depth of the pit is equal to the bottom of the pipe. The slope excavation, step
excavation or support of the work pit wall should meet the requirements of GB50268
and JGJ120.
11.4.7 The inner diameter of the original pipe shall be accurately measured, and the
cut size of the stainless-steel plate shall be determined according to the measurement
results. For the stainless steel plate of special parts such as elbows, reducing diame-
ters, branch pipes, etc., the size of the lining parts should be accurately measured in
advance, and the material should be cut according to the design drawing.
11.5 Pipe Segmental Lining Construction 59
(a) Stainless steel welding operations shall comply with the relevant provisions
of the current national standard “Code for Construction and Acceptance of
Field Equipment Industrial Pipe Welding Engineering” GB50236;
(b) When the high temperature of the welding operation is prone to adversely
affect the original pipeline, heat insulation measures should be taken
60 11 Pipe Segmental Lining
(c) When the butt welds are aligned, the inner wall should be flush, and the
amount of misalignment of the inner wall should not be too large;
(d) When welding stainless steel, the distance between longitudinal welds
should be greater than 200 mm to avoid cross welds;
(e) At the end of the original pipeline, a full weld sealing treatment should be
carried out between the stainless-steel liner and the original pipeline inner
wall.
11.6.5 In the installation of PVC segments, the operator should pay special attention
to the connection of the buckle, and the locking screws should be provided on the
sides of the segments.
11.6.6 The design or installation of PVC segments shall resolve the influence of
temperature changes and vibration on its stability through wedge-shaped structures
and grouting.
11.6.7 The grouting should be carried out in batches according to the designed ratio
to ensure that the highest position is grouting.
Chapter 12
Modified Sliplining
12.1.1 The modified sliplining includes: deformed lining and swagelining. The mate-
rial used to modified sliplining is a high density polyethylene pipe. The deformed
lining is suitable for the renovation of DN50 ~1600 mm pipeline; Swagelining is
suitable for the renovation of DN50 ~800 mm pipeline.
12.1.2 When using the modified sliplining to renovate the gas pipeline, the maximum
allowable working pressure of the pipeline after renovation should not exceed
0.4 MPa.
12.1.3 Before using the modified sliplining to renovate the pipe, the feasibility assess-
ment of the construction process should be carried out according to the actual situa-
tion of the project; if necessary, a pipe section with the same diameter, material and
cross-sectional shape as the inner lining pipe and the length not less than 3 m can be
used for trial sliplining, and detect the surface damage of the pipe section after trial
sliplining, the scratch depth on the outer surface of the pipe should not be greater
than 10% of the wall thickness of the liner.
12.2.1 The maximum single section length of modified sliplining should not exceed
300 m. When it exceeds 300 m, the pulling force required for construction and the
tensile strength of the pipe shall be checked and calculated, and the construction shall
be carried out only when the requirements are met.
12.2.2 The working pit shall be excavated at both ends of each pipeline to be reno-
vated, and the length of the initial working pit shall be determined by the following
formula:
© China Architecture & Building Press 2021 63
L. Wang et al., Technology Standard of Pipe Rehabilitation,
https://doi.org/10.1007/978-981-33-4984-1_12
64 12 Modified Sliplining
In the formula:
L Length of starting work pit, m;
H Distance between pipeline center to be renovated and road surface, m;
R Polyethylene pipe is allowed to bend radius, m, and R ≥ 25dn ;
dn Outer diameter of pipeline to be renovated.
12.2.3 For renovation of the same pipe section, the inner lining pipe of the same
material shall be used. The inner lining pipe shall not have visible cracks, holes,
scratches, inclusions and other damage defects.
12.2.4 The electro fusion welding connection should be made before the lining pipe is
reduced in diameter. The electro fusion welding connection of the lining pipe should
be in accordance with the “Code of Practice for the Preparation of Plastic Pipes
and Pipes Polyethylene (PE) Pipes/Pipes or Pipes/Pipes Hot Melt Butt Assemblies”
GB19809.
12.2.5 Polyethylene pipes and fittings produced with special blends should be used
for lining pipe.
12.2.6 After the lining pipe arrives at the construction site, the mechanical properties
of the pipe should be tested according to the production batch, and the qualified pipe
can be used for construction.
12.3.2 The equipment required on site includes conventional equipment and special
equipment. The conventional equipment is used and maintained according to relevant
regulations and instructions. The special equipment needs to be used and maintained
according to the equipment instruction manual.
12.4 Construction Preparation 65
12.4.1 The cleaning and inspection of the pipeline to be renovated shall meet the
requirements of Chaps. 5 and 6 of this regulation.
12.4.2 After the cleaning work is completed, a HDPE pipe with the same diameter
as the reduced or folded liner pipe and a length of not less than 3 m should be used
for trial wear. Wire rope pulling should be used before and after the trial wear pipe.
If there are obstructions or scratches that exceed 10% of the liner wall thickness
during the try-on process, the pipeline should be reprocessed and cleaned until the
requirements are met.
8. Pulling the lining pipe into the pipeline to be renovated shall meet the following
requirements:
(a) Before pulling in, the introduction device and protection device should be
installed at the pipeline starting end;
(b) The pull-in speed should be controlled at 5–8 m/min;
(c) The folded lining pipe should have a construction margin that is not less
than 1.5 m in the work pit.
9. The restoration of the folded lining pipe should meet the following requirements:
(a) When the folded lining pipe reach the right place in the pipeline to be
renovated, the blind plate should be welded to the end of the folded lining
pipe;
(b) The speed of boosting should be strictly controlled during recovery, and the
recovery pressure should be strictly performed according to the parameters
of the construction process assessment;
(c) After the folded lining pipe returns to a round shape and the pressure is
stable, the stable time of this pressure should not less than 24 h
10. The recovery process of the factory prefabricated folded lining pipe should meet
the following requirements:
(a) During the recovery process, the changes of the temperature and pressure
should be recorded to ensure that the temperature and pressure of each stage
of the recovery have reached the relevant requirements. A temperature
measuring instrument should be installed between the old pipe and the
lining pipe to detect the outside temperature of the lining pipe;
(b) Inject steam with a temperature of 112–126 °C and a pressure of 100 kPa
into the folded lining pipe. When the temperature around the lining pipe
reaches 85 ± 5 °C, pressurize the steam pressure to 180 kPa;
(c) Maintain the steam pressure for a certain time to fully expand the folded
pipe and form a concave shape at the branch tube;
(d) The temperature of the folded lining pipe should be cooled to below 38 °C,
and then slowly pressurized to about 228 kPa, and then continue to cool
with air or water until the surrounding temperature;
(e) After the lining pipe is restored and cooled, cut both ends of the pipe neatly.
Both ends of the lining pipe should be at least 100 mm longer than the pipe
to be renovated.
11. After the factory prefabricated folding pipe returns to round, the water in the
pipe should be drained and the pipe should be dried.
12. The electric fusion and hot fusion connection between the folding pipes in the
working pit shall meet the following requirements:
(a) Before connection, stress relaxation of not less than 24 h should be
performed, and a fixed point should be set on the polyethylene pipe;
12.5 Modified Sliplining Construction 67
(b) When the standard size ratio (SDR) of the lined pipe is 26, the folding
pipes in the work pit should be connected with reducing pipe fittings;
(c) Before the inner liner is connected, a rigid inner support bush should be
installed at the port of the folded pipe;
(d) The annular space between the folded inner liner and the steel pipe should
be filled with flexible breathable material in the work pit.
13. The lining pipe and the old pipe shall be connected by a steel-plastic conversion
joint or a flange-type steel-plastic conversion, and the connection shall comply
with the relevant industry regulations.
12.6.1 The materials used should conform to the relevant national codes and standards
and be re-inspected according to the specifications. Materials that do not meet the
specifications are prohibited.
12.6.2 Perform functional tests should be in accordance with relevant technical
regulations and acceptance specifications.
Chapter 13
Cured in Place Pipe (CIPP)
13.1.1 Pipes suitable for CIPP is that whose materials are steel, reinforced concrete,
cast iron, plastic, etc.
13.1.2 The cross-sectional shape of the pipeline whoes cross-sectional shape is round,
rectangular, oval, etc are applicable for the CIPP.
13.1.3 Generally, the drainage pipe applicable to the CIPP is the pipes whose diam-
eter is 200~2700 mm; the water supply pipe applicable to the CIPP is the pipes
whose diameter is 200~1500 mm; the gas pipe applicable to the CIPP is the pipe
whose diameter is 200~600 mm; The applicable diameter of UV CIPP is generally
ϕ200~1600 mm.
13.1.4 The maximum length of a single section of pipeline for hot water or steam
CIPP should not exceed 300 m; the maximum length of a single section of pipeline
for UV CIPP should not exceed 150 m.
13.1.5 The maximum angle of the pipe elbow applicable to the CIPP is 45°; the angle
of the pipe elbow applicable to the UV CIPP is 11.25°.
13.1.6 For the renovation of drinking water pipelines, the materials must meet the
requirements of the health department.
1. The hose should consist of a single layer or multiple layers of needle felt or non-
woven or woven material combination, which should be able to impregnate the
resin and not react with the resin, and can withstand the tensile force, pressure
and curing temperature of the construction;
2. The outer surface of the hose should be covered with a non-permeable plastic
film compatible with the resin used;
3. The joints between the layers of the hose must be staggered and must not be
overlapped; the tensile strength of the hose is in accordance with “Tensile prop-
erties of textile fabrics Part 1 Determination of breaking strength and breaking
elongation” GB/T3923.1 The result of test shall not be less than 5 MPa.
4. The hose should be able to stretch and have a certain toughness, and its length
should be greater than the length of the pipeline to be renovated; the diameter of
the hose should ensure that it can be closely attached to the inner wall of the old
pipeline after curing;
5. The supplier shall provide a test report of the initial structural performance of
the hose after curing.
13.2.3 The resin used in CIPP method should meet the following requirements.
1. The resin can be thermosetting resin, and a certain number of additives should
be added to meet the design requirements such as controlling the curing time;
2. The resin should be able to cure under the action of hot water, hot steam or
ultraviolet rays, and the initial curing temperature should be less than 80 °C.
13.2.4 For the resin cured by UV light, the UV light generating device should be
able to meet the requirements of the corresponding tube diameter and resin curing.
13.3.1 The equipment used includes generators, steam or hot water or UV light
generators. If pipes are produced on site, equipment for making impregnated hoses
should also be provided.
13.3.2 The equipment required on site includes conventional equipment and special
equipment. The conventional equipment is used and maintained according to relevant
regulations and instructions. The special equipment needs to be used and maintained
according to the equipment instruction manual.
13.4 Construction Preparation 71
13.4.1 Pipeline cleaning and testing shall comply with the provisions of Chaps. 5
and 6 of this standard.
13.4.2 Pipeline pretreatment should meet the requirements of CIPP process and
engineering design.
13.4.3 The amount of resin should be carefully calculated before immersing the hose.
The various components of the resin should be fully mixed. The actual amount of
preparation should be 5–10% more than the theoretically calculated amount.
13.4.4 After the resin is mixed, it should be impregnated in time, and the residence
time should meet the requirements of the manufacturer; if it cannot be impregnated in
time, the resin should be refrigerated, and the temperature of the refrigerated should
be below 15 °C.
13.4.5 The hose should be impregnated with resin under vacuum, the hose material
should be fully saturated with resin, and the number of dry spots or bubbles should
be controlled within a reasonable range.
13.4.6 The temperature of the hose should be controlled during storage and trans-
portation of the resin-impregnated hose, and the temperature and time during storage
and transportation should be recorded; when the hose is immersed at the construction
site, the temperature of the immersion work environment should be lower than 20 °C.
13.5.1 The impregnated hose can be inverted into the pipeline to be renovated by
water pressure or air pressure. The inversion pressure should be large enough to
allow the impregnated hose to invert to the other end of the pipe and make the hose
tightly adhere to the wall of the old pipe; the inversion pressure must not exceed the
maximum allowable tension of the hose.
13.5.2 During inversion, the proper inverting speed should be maintained to make
the hose stretch smoothly.
13.5.3 During inverting, lubricants can be used to reduce the inversion resistance. The
lubricants used must be non-toxic oil-based products. They must not adversely affect
resin-impregnated hoses, boilers, and pump systems, and will not breed bacteria and
affect the flow of liquid.
13.5.4 After inversion, the resin impregnated hose should be longer than 200 mm at
both ends of the original pipe.
72 13 Cured in Place Pipe (CIPP)
13.5.5 Hot water or hot steam can be used to cure the inverted impregnated resin
hose.
13.5.6 Curing with hot water should meet the following requirements:
1. The heating rate of the hot water should be controlled according to the pipe
diameter, material wall thickness, resin material, type of curing agent and ambient
temperature, etc., so that it slowly reaches the temperature required for resin
curing;
2. A temperature measuring instrument should be installed to monitor the temper-
ature when water flows in and out;
3. A temperature sensor should be installed between the impregnated resin hose and
the old pipe both at the beginning and end of the renovated section to monitor the
temperature change of the pipe wall. The temperature sensor should be installed
at least 300 mm away from the inside of the old pipe port;
4. It is advisable to determine the curing state of the resin through the resin exotherm
curve monitored by the temperature sensor.
13.5.7 The use of hot steam curing should meet the following requirements:
1. The hot steam should be slowly heated up to the temperature required to cure
the resin. The temperature and time required for curing should consult the resin
material manufacturer;
2. The steam generating device should have a suitable monitor to accurately measure
the temperature of the steam, and the temperature during the curing process of
the liner pipe should be measured and monitored;
3. We can know about the curing state of the resin through the heat release curve
of the resin monitored by the temperature sensor
13.5.8 During the curing process, consideration should be given to the material of
the renovated pipe section, the thermal conductivity of the surrounding soil, the
ambient temperature, the groundwater level, etc., in order to properly adjust the
curing temperature and time. During the curing process, changes in temperature and
pressure should be recorded in detail.
13.5.9 After the hose is cured, it should be cooled first, and then the pressure should
be reduced. When water cooling is used, the inner liner should be cooled to below
38 °C, and then depressurized; when using air cooling, it should be cooled to below
45 °C before depressurizing. When draining or exhausting pressure, the pressure
should be reduced slowly. Vacuum in the pipeline must be prevented from damaging
the liner.
13.5.10 The lining pipe end should be cut neatly at the exit of the renovated pipe
section. If the lining pipe is not tightly bonded to the old pipe, a resin mixture should
be filled between the lining pipe and the old pipe to seal.
13.6 Construction of Pulling Method 73
13.6.1 Before pulling in the soft liner, a cushion film with a width greater than 1/3
of the circumference of the pipe should be laid on the bottom of the old pipe, and
the cushion film should be fixed on both ends of the old pipe.
13.6.2 The pull-in operation of the soft liner shall comply with the following
regulations:
1. Before pulling the soft liner into the old pipe, it should be folded in half;
2. The soft liner impregnated with resin should be smoothly and slowly pulled into
the old pipeline along the smooth cushion film at the bottom of the pipe, and the
pulling speed should not exceed 5 m/min;
3. When pulling in the soft liner, avoid wearing or scratching of the soft liner;
4. The stretch rate of the soft liner shall not exceed 2%;
5. Both ends of the soft liner should be 300–600 mm longer than the old pipe.
13.6.3 The inflation device should be installed at the inlet end of the hose. The gas
generating device used should be able to control and display the pressure.
13.6.4 The expansion of the soft liner shall meet the following requirements:
1. Before inflating, you should carefully check whether each connection is well
sealed. A pressure regulating valve should be installed at the end of the hose to
prevent the air pressure in the pipe from being too high;
2. The air pressure should enable the soft liner to fully expand and close to the inner
wall of the old pipe.
13.6.5 Two methods of hot steam or ultraviolet light should be used to cure the
resin-impregnated soft liner.
13.6.6 When using hot steam curing, the temperature sensor should be installed on
the outer surface of the soft liner at the beginning and end of the old pipe, and the
installation position should be at least 300 mm away from the inside of the old pipe
port.
13.6.7 Steam curing shall comply with the relevant provisions in 13.5.7 of this stan-
dard, and the pressure and temperature of the curing process shall be recorded in real
time in detail.
13.6.8 After the curing of the soft liner is completed, cooling and depressurization
shall be carried out. The cooling and pressure reduction shall comply with the relevant
provisions in 13.5.9 of this standard.
13.6.9 The following requirements should be met when curing with UV light:
1. When the UV lamp is installed, the inner membrane of the soft liner should not
be cut;
74 13 Cured in Place Pipe (CIPP)
2. Consult the material supplier to obtain the best resin curing time and pressure;
3. The advance speed of the UV lamp and the air pressure in the pipe should be
reasonably controlled to ensure that the resin is completely cured;
4. After the resin is cured, the pressure in the pipe should be slowly reduced;
5. When the inner diameter of the pipeline to be renovated is less than 600 mm, the
ring stiffness value of the liner using UV CIPP repair process should not be less
than 5000 N/m2 .
13.7.1 Check the quality certificate, specifications, production date and use period,
temporary storage temperature of the hoses before construction to ensure that the
quality of the materials and the specifications of the materials used are consistent
with the design.
13.7.2 In the process of the material entering the original pipeline, a special person
should check whether the hose is damaged; if there are more serious conditions, the
on-site professional and technical personnel should be notified in time to take corre-
sponding measures; if the situation is particularly serious, the construction should
be stopped. The inversion method should control the inverting speed by controlling
the flow of injected water or gas; the UV CIPP method should control the material
moving speed by controlling the speed of the hoist.
13.7.3 During the curing process of the inversion method, the operator should pay
special attention to the uniformity of hot water or steam, the speed of rising and
cooling, and the pressure in the pipe; during the UV CIPP curing process, the opera-
tion should be strictly in accordance with the inflation pressure and inflation speed,
the walking speed of the UV lamp, and the temperature control required by the
supplier.
13.7.4 In case of pipeline plugging and diversion, double-insurance plugging walls
shall be provided for pipelines above DN600.
13.7.5 The bundling of the ends of the pipe curing by inversion method should be
reliable, and two bandings should be set at each end; the inlet and outlet pipes for
hot water curing should be distributed at both ends of the pipe; the steam delivery
pipe for steam curing should be located in the center of the pipeline to be repaired.
13.7.6 During the process of putting the UV lamp into the hose, if the hose sags, stop
putting the lamp immediately; The connector should be provided with anti-shedding
straps; if an abnormal situation occurs during the UV curing process, the emergency
stop button of the curing machine and the intake valve should be pressed first, and
then other arrangements should be made.
Chapter 14
Spray Lining
weather, different periods of vehicles and pedestrian flow on the entry road and
construction site.
14.1.8 For the water source survey on the renovation site, it is advisable to survey the
location of the existing water source on the site, the distance from the construction
site, the amount of water, and the laying environment of the transmission line. For
the power supply survey at the renovation site, it is advisable to survey the power,
voltage, location of the power supply and the distance between the construction site
and the environment of the transmission line, etc.
14.2.1 The construction design shall accurately describe the materials, caliber,
pipeline structural conditions of the pipeline to be scaled and corroded, the length of
the single section of the renovation section and the angle of the pipeline within the
section.
14.2.2 The spraying method and the performance of the spraying material should
ensure that the flow pressure and deformation of the renovated pipeline and the
water quality and sanitation meet the requirements of the design or relevant industry
specifications.
14.2.3 Cement mortar spraying and epoxy resin spraying are only used for functional
renovation of pipelines. The selection of spray coating wall thickness should be
determined by referring to Tables 14.1, 14.2, 14.3 and 14.4 unless the design company
has requirements.
14.2.4 The deviation of spray thickness should meet the design requirements.
14.2.5 The amount of spraying material should be determined by formula (14.1)
except the design company has specific requirements.
Q = (π × D × t) × L × 103 + c (14.1)
Table 14.2 Selection table of coating thickness for cement mortar spray cast iron pipe
Pipe nominal diameter (mm) Coating thickness (mm)
Nominal value Minimum vale
40–300 3 2.0
350–600 5 3.0
700–1200 6 3.5
1400–2000 9 6.0
2200–2600 12 7.0
In the formula:
Q The amount of spraying material, L;
D Inner Diameter of Pipe, m;
t Spraying thickness, m;
L spray pipe length, m;
78 14 Spray Lining
c Considering the amount of solidification and loss (L), the polyurethane material
should be taken (4–12) × 103 (L) per spraying; The amount of other materials
should be specifically determined in combination with the instructions for use of
the paint and the spraying equipment, storage status, and environment
14.2.6 The temporary storage time on site of the spraying material should meet the
requirement of the operating instruction.
14.3.1 The equipment used includes: generator, blower, air compressor, air sprayer
or centrifugal sprayer, etc.
14.3.2 The conventional equipment attached to the spraying shall be used and
maintained in accordance with the relevant regulations and instructions.
14.3.3 The anti-loosening device shall be installed on the high-pressure air pipe
specialized for spraying.
14.3.4 Cleaning of special centrifugal nozzle components for spraying shall meet the
following requirements:
1. After spraying, the nozzle assembly should be disassembled before cleaning: the
cup, the paint mixing tube after the rotating cup, the mixing head, and the paint
delivery short pipe;
2. No need to clean the mixing tube after rotating the cup;
3. The mixing head and the paint delivery pipe should be cleaned multiple times with
a separate cleaning pump, after cleaning the mixing head, spray the de-rusting
lubricant to the air inlet;
4. The rotating cup should be placed in the diluent and soaked for 24 h, and then
cleaned. It is forbidden to wipe the rotating cup with abrasive materials.
14.4.1 When the work pit needs to be excavated at both ends of the original pipeline,
the size of the work pit along the axis of the pipeline should not be less than 2.5 m,
the width of the pit should not be less than 1.5 m, and the depth of the pit is 0.5 m
lower than the bottom of the pipe. Slope excavation, bench excavation or support
of the work pit wall should meet the requirements of “Code for Construction and
Acceptance of Water Supply and Drainage Pipeline Engineering” GB50268 and
“Technical Specifications for Support of Building Foundation Pit” JGJ120.
14.4 Construction Preparation 79
14.4.2 Survey and treatment of medium flow before pipe breakage, pipe breakage,
treatment of residual liquid in the pipe, and laying of temporary pipelines shall ensure
safety and ease of recovery.
14.4.3 Before cleaning, it is advisable to check the status of the pipeline inner wall,
such as corrosion, damage, blockages, and the condition of branching pipe, and save
CCTV image data.
14.4.4 Before spraying, pipeline pretreatment should be carried out. The pretreatment
includes: derusting, descaling, cleaning and drying of the pipeline. The pretreatment
should meet the following requirements:
1. It is advisable to use a combination of tools and appliances such as winches, grab
harrows, steel wire harrows, etc. to carry out pipeline derusting and descaling
operations many times;
2. The derusting and descaling of the pipeline should be selected according to the
material of the pipeline, the inner diameter of the pipeline, and the degree of
scaling.
3. The pipeline cleaning after derusting and descaling should be carried out by high
pressure water jet machine or combination cleaning method;
4. Drying the inner wall of the pipe, removing sediments and accumulated water
should use a sponge drying ball or absorbent cotton, and the inner wall should
be smooth, free of corrosion, no particles and no accumulated water after the
pipeline is dried.
5. For large cracks and holes in the pipe wall, pretreatment should be carried out
until the pipe can meet requirements of the spray renovation.
2. The preheating time of the paint in the spraying machine’s storage irrigation shall
be determined according to the ambient temperature of the spraying machine’s
temperature sensor. The preheating operation of the paint should open the heating
switch of the storage tank, the mixer of the storage tank and the umbilical pipe.
3. When the air compressor pressurizes the storage tank of the sprayer, the pressure
in the tank should be controlled not to exceed 250 Mbar, and operate according to
the following procedure: first confirm that all umbilical valves and return valves
are open, then slowly open the storage tank vent valve, next adjust the pressure
in the tank to 170 Mbar.
14.5.6 Spraying
1. The spraying start operation should be carried out according to the following
steps:
14.5 Polyurethane Spraying Construction 81
(a) Before spraying, the air supply switch of the rotating cup should be activated
to rotate the rotating cup, and then the air supply pressure should be increased
to the rated value;
(b) When the two valves at the end of the umbilical pipe are opened and the
paint supply countdown ends, the umbilical pipe reel rotation control switch
is activated. Control the pressure of the umbilical reel rotary pump during
the spraying process.
2. In automatic spraying, the control parameters should be entered according to the
equipment prompts.
3. When spraying ends and the spray head moves out of the pipe, stop spraying
immediately.
14.6.1 When mechanical spraying is used, manual spraying may be used for special
pipe fittings such as elbows, tees and adjacent gate valves. The combination of
mechanical spraying and manual spraying shall adopt a gradual approach.
14.6.2 When the sprayed cement mortar reaches the final setting, it should be imme-
diately watered and cured, and the mortar layer should be kept moist for no less than
7 days.
14.6.3 During the curing period, the holes in the renovated pipe section with open
pretreatment should be tightly closed.
14.7.1 Epoxy resin spraying should first choose centrifugal spraying or gas spraying
according to parameters such as pipe diameter.
14.7.2 Spray paint should be fully stirred and cured for 15 min before spraying.
14.7.3 For equipment spraying, the flow rate of the nozzle and the traveling speed of
the spraying vehicle should be controlled.
14.7.4 For multiple spraying, the latter spraying should be carried out after the surface
of the previous spraying is dry.
14.7.5 For air spraying operation, the paint should be put into the sprayer first, and
then the sprayer should be connected to the air compressor and the air outlet pipe.
14.7.6 Air spraying should be sprayed more than 2 times.
14.7.7 Excess material for gas spraying should be blown out by high-pressure gas.
82 14 Spray Lining
14.7.8 The first primer spraying of centrifugal spraying should be completed within
1 h after sandblasting and derusting.
14.7.9 The thickness of centrifugal spraying can be achieved by multi-layer spraying.
14.7.10 For curing after the epoxy resin is sprayed, the breeze should be sent into
the tube until the coating film is initially hardened; then it can be cured naturally, or
warm air can be sent for heating and curing. When the temperature of heating and
curing is 25 °C, the curing time should be more than 4 h; when the temperature of
heating and curing is 60 °C, the curing time should be more than 3 h.
14.8.1 In the process of derusting and spraying of pipes, the concentration of harmful
substances in the air shall not exceed the provisions of GB6514; the dust content in
the air shall not exceed the provisions of TJ36.
14.8.2 For polyurethane spraying, build a sun-proof shed at the pit to ensure that the
temperature in the pipeline is not greater than 40 °C in summer construction; build
a thermal insulation shed at the pit to ensure that the temperature in the pipe is not
less than 3 °C during winter construction.
14.8.3 When spraying cement mortar, the slump of the mortar should be controlled
at 60–80 mm; when the pipe diameter is less than 1000 mm, it can be increased but
not more than 120 mm.
14.8.4 When the ambient temperature is lower than 5 °C or the humidity is higher
than 85%, epoxy resin spraying is not suitable.
14.8.5 During the rainy period, windproof and rainproof sheds should be added
to all exposed electrical equipment, the number of electrical equipment detections
should be increased, the protection of spraying equipment should be strengthened,
and anti-skid facilities on site should be added.
14.8.6 The content of spraying records shall meet the requirements of national and
local municipal engineering construction technical data.
Chapter 15
Spirally Wound Lining
15.1.1 The spirally wound lining should choose the manual winding and the mechan-
ical winding according to the specific situation; the mechanical spirally wound lining
has two kinds: expansion lining and fixed diameter lining.
15.1.2 The applicable scope of spirally wound lining should meet the following
requirements:
1. It is suitable for the renovation of rain and sewage drainage pipes made of ductile
iron pipes, reinforced concrete pipes and other synthetic materials;
2. It is suitable for the renovation of large rectangular box culverts and various
irregular drainage pipes;
3. The manual winding is suitable for the overall renovation or localized renova-
tion of the drainage pipe with a diameter of 800–000 mm; the expansion lining
is suitable for the overall renovation of the drainage pipe with a diameter of
150–800 mm; the fixed diameter lining is suitable for the localized and overall
renovation of the drainage pipe of 450–3000 mm;
4. It is suitable for structural defects of pipelines showing deformation, misalign-
ment less than 3 cm, disconnection, leakage, corrosion, and stable pipeline
foundation structure, and no obvious change in pipeline line type;
5. It is suitable for the renovation of local trachoma, dewstone, flaking and other
diseases on the inner wall of the pipeline;
6. It is suitable for preventive repairs when the pipeline interface is in the sign of
leakage or critical state;
7. It is not suitable for the renovation of structural defects such as pipeline foun-
dation breakage, severe pipeline breakage, severe disconnection of inverted
pipelines, severe misalignment of pipeline interfaces, and severe deformation
of pipeline linearity.
15.2.1 Spiral pipe can choose independent structure pipe and composite pipe
according to specific application situation. The independent structure pipe means
that the new pipe does not rely on the original pipe at all and bears all the burden
alone; the composite pipe means that the spiral pipe bears part of the load, and the
other part of the load is borne by the structural grouting between the new and old
pipes.
15.2.2 Strip profile
1. The belt-shaped profile is a belt-shaped product of different widths extruded with
PE or PVC. The inner layer is smooth and has a certain thickness. It can be fasten
tightly with each other by the lock catches.
2. The performance of materials used to manufacture occlusal strips should meet
the design requirements. High-strength should choose the type of PVC profile
with stainless steel.
3. The strip profile is rolled into a roll on the drum for easy transportation and
storage. The production date and length should be printed on the profile to ensure
that the material is used within the period of use.
15.3.1 The equipment used includes generator, blower, air compressor, sealant pump,
special winding machine, etc.
15.3.2 The equipment required on site includes conventional equipment and special
equipment. Conventional equipment is used and maintained in accordance with rele-
vant regulations and instructions. Special equipment must be used and maintained
in accordance with the equipment instruction manual.
15.3.3 Winding machines and other major underground equipment should be mainly
composed of stainless steel parts because they work in water or humid environment
all year round. After each construction, it should be cleaned in time and applied with
anti-rust agent to ensure the normal use of the machine in the future.
15.4.1 Use high-pressure water to remove all garbage, tree roots and other obstacles
that may affect the installation of new pipes.
15.4.2 Sewage pipes that need to be rehabilitated should be detected and recorded
with closed-circuit television.
15.4.3 All obstacles should be recorded, and if necessary, they should be washed
repeatedly.
15.4.4 The position of the branch pipe must be recorded. When the renovation is
completed, reopen the branch pipe.
1. Initial winding of the pipe: under the drive of the machine, the PVC profile is
continuously entangled in the winding machine, and the primary and secondary
locks on both sides of the profile are interlocked by spiral rotation, thereby
forming a continuous seamless newer than the original pipe liner. After the
winding of a section of spiral pipe is completed, the secondary lock is pulled
off by pulling the embedded steel wire, so that the new liner begins to expand
radially until the new liner is tightly attached to the inner wall of the original
pipe.
86 15 Spirally Wound Lining
2. During the winding process, the winding machine continuously repeats the
following actions:
(1) Inject the lubricating sealant into the female lock of the main lock (the
lubricating sealant plays the role of lubricating in the process of winding
and expanding, and the sealing of the formed liner at the end of expansion);
(2) Entrapped high-tensile pre-embedded steel wire: When this wire is pulled
out, the secondary lock will be cut to allow the new tube to expand, but the
steel wire is not pulled out during the winding process of the new pipe;
(3) The strip profile is rolled into a circular liner;
(4) The expansion of the pipeline is finally formed. After the initial winding is
completed, the winding machine stops working; then drill two holes in the
new pipe at the end and insert steel bars to prevent the new tube from rotating
in the next expansion; after completion, Start the wire drawing equipment
and winding machine. As the embedded steel wire is slowly pulled out, the
interlocking secondary buckle is cut during the winding forming process,
so that the profile slides along the track of the main lock under the drive of
the winding machine and continue to expand in the radial direction until the
liner at the non-fixed end (winding machine end) is also tightly attached to
the original pipe wall.
3. After the expansion of the new pipe is completed, the ends of the new pipe are
sealed with polyethylene foam or polyurethane.
is that the manual winding method is used to improve the overall strength of the
renovated pipe before the winding construction. A steel frame is installed in
the annulus space of the old pipe and the winding pipe, and the steel-concrete
structure is formed after the cement slurry is poured.
15.6.1 Before each winding construction, check the certificate, profile specifications,
production date and use period of the profiles used to ensure that the quality of the
materials and the specifications of the materials used are consistent with the design.
15.6.2 During the winding process, a dedicated person should check whether the
profile is damaged or bent, and repair small defects in a timely manner; if there are
more serious conditions, the professional technicians on site should be notified in time
to take corresponding measures; In some particularly serious situations, construction
should be stopped to ensure the quality of each winding.
15.6.3 During winding, the operator should pay special attention to the reduced-
diameter connection of the male and female locks and the glue injection in the
locks.
15.6.4 The grouting shall be carried out in batches according to the designed ratio.
15.6.5 The spirally wound lining should provide various test and evaluation reports of
the technology before construction and use. The report includes but is not limited to
the chemical resistance report of the profile, the wear resistance report of the profile,
and the tightness report of the pipe, compression resistance report of the pipe and
strength report of the grouting material, etc.
Chapter 16
Localized Renovation
16.1.1 Localized renovation includes spot CIPP, stainless steel foam sleeve, pipe
segmental lining, grouting, etc.
16.1.2 There are many localized renovation methods for pipelines, which are diffi-
cult to generalize. You can refer to related similar processes. For engineering accep-
tance of localized renovation, you can refer to related similar processes. For difficult
reference methods, you can determine the test method and acceptance procedure.
5. It is not suitable for the renovation of structural defects such as pipeline foun-
dation fracture, pipeline rupture, pipeline disconnection in an inverted shape,
serious misalignment of pipeline interface, and serious deformation of pipeline
line shape.
prevent the loss of soil around the pipeline, to improve the bearing capacity of
the foundation soil of the pipeline.
5. The airbag selection for localized renovation should consider the consistency
with the inner diameter of the pipeline.
17.1.1 The handling of ports shall comply with this regulation or relevant regulations
of related industries.
17.1.2 The renovated pipelines should be in line with the relevant regulations of
related industries.
17.2.1 After the leak test is qualified, the backfill operation should be carried out in
time and the construction site should be cleaned up.
17.2.2 The backfill of the work pit shall comply with the provisions of the current
national standard “Code for Construction and Acceptance of Water Supply and
Drainage Pipeline Engineering” GB50268.
17.2.3 The restoration of the construction site should not be worse than the condition
before construction.
18.1.1 In addition to meeting the requirements of this regulation, the content, proce-
dures and records of acceptance shall also meet the requirements of the current
industry pipeline standards.
18.1.2 The structural or functional test of the pipeline after renovation shall be
carried out in accordance with the relevant provisions of the current relevant pipeline
standards.
18.1.3 After the replacement and renovation project is completed, the construc-
tion company shall first conduct a visual inspection of the rehabilitated pipeline, as
well as the pre-inspection of the strength and tightness test, and notify the relevant
departments to accept after acceptance.
18.1.4 If the current standards for pipelines in related industries do not mention the
structural or functional acceptance of the renovated pipeline, the test conditions, main
parameters and acceptance values should be set according to the design requirements
of the design book and the purpose of the test; pipelines with similar test conditions,
the structural or functional acceptance after renovation should be based on the test
results.
18.1.5 The current standard has clear requirements for the main materials for restora-
tion, and its specifications, dimensions, and performance should meet the require-
ments of the current standard, and the number of on-site samples for the acceptance
of the same batch of products should not be less than 1 group.
18.1.6 For the quality acceptance of the renovation that main material is not clearly
stipulated in the current industry pipeline standards, the acceptance shall be carried
out according to the design requirements or compared the test value of the main
parameters of the material with the standard prescribed value in accordance with the
current standards; For curing, it is advisable to compare the test value of the main
parameters after curing with the standard specified value for acceptance.
18.1.7 The acceptance of the polyethylene (PE) pipe for water supply related to the
drainage pipe by by spliting and inserting shall be carried out in accordance with
GB/T 13663 of the polyethylene (PE) pipe for water supply.
18.1.8 For the acceptance of the quality of the inner surface of the pipeline renova-
tion after renovation that is not mentioned in the current standards of the relevant
industry pipelines, the quality of the inner surface of the pipeline after renovation
should be checked and accepted in accordance with the requirements of the design
or construction plan.
18.1.9 Pipeline pretreatment, renovation and cleaning, and quality of rehabilitated
pipeline, should use CCTV equipment for pipeline inspection according to this regu-
lation and the relevant provisions of the current national relevant industry standards,
when the pipe diameter is not less than 800 mm, you can also send a person into the
pipeline for inspection and take the image.
18.1.10 The acceptance of the pretreatment and cleaning procedures involving the
pipeline to be renovated shall be carried out in accordance with the requirements of
the design or construction plan for pretreatment and cleaning.
18.2.1 Main control project: The quality of pipeline pretreatment and renovation
cleaning should meet the requirements of Table 5.2. The pretreatment parts should
have no influence on the defects of the next repair and renovate process.
Inspection method: Check the CCTV records (or visual records in the tube). For
the pre-treatment related to the pipeline functional or structural performance, if it
cannot be judged that the pre-treatment can completely eradicate the functional or
structural defects, it should be determined through field test verification.
18.2.2 General items: linear and smooth filling, staggered and broken parts of the
pipeline, smooth interface, smooth transition of special parts. Before closed renova-
tion (CPP, swagelining, deformed lining, etc.) and interval renovation (sliplining, pipe
segmental lining, spirally wound lining, etc., including expansion cracking method),
the original pipeline leakage and residual liquid should not affect the construction of
subsequent processes.
Inspection method: Check the pipeline pretreatment construction records, mate-
rials and physical construction inspection records or reports.
18.3 Acceptance for Pipe Rehabilitation 99
of the inner surface of the liner pipe is not greater than 20 mm or not larger
than the inner diameter of the pipeline to be repaired (The special-shaped
pipe takes a smaller inner diameter value) 3%, and the fold is not more than
10 for every 50 m of continuous extension;
(g) When using the pipe segmental lining, the stainless-steel sleeve and the spot
CIPP, the lining pipe should be closely attached to the original pipeline, the
lining should be complete, and the lap should be smooth and firm;
(h) When the mechanical spirally wound lining is adopted, the joints of the
seams are tightly fitted and the connection is firm, without obvious protru-
sions, depressions, staggers and other phenomena. It is strictly forbidden to
have longitudinal bulges, flattened loops, and seam detachment;
(i) The verticality deviation of the lining pipe ports. If the outer diameter of
the lining pipe is less than or equal to DN600, it should not be greater than
4 mm; if the outer diameter of the lining pipe is greater than DN600, it
should not be greater than 6 mm.
5. The pipeline after renovation should be free of obvious wet stains and water
seepage, and dripping and line leakage are strictly prohibited.
6. If the lining pipe and the pipeline to be renovated are tightly fitted, there should be
no leakage between the two layers of pipes; when the sealing device is installed,
it should meet the design requirements and the sealing is good; The gap filling
should be free of looseness, voids and other phenomena.
18.3.2 The acceptance of the main control items of each rehabilitation method shall
meet the requirements of Table 18.1.
18.3.3 General items: The acceptance of the general items of each repairing and
rehabilitate method should meet the requirements of Table 18.2.
18.4.1 The temperature of the lining pipe should not be higher than the temperature
of the surrounding soil before the structural or functional test of the pipe.
18.4.2 After the pipeline renovation is completed, the gravity flow pipeline shall
be tested for pipeline tightness, and the test shall be conducted in accordance with
the relevant provisions of relevant industry standards. Under conditional conditions,
selectively conduct well-to-well tightness tests.
18.4.3 After the pipeline renovation is completed, the pressure pipeline shall be
subjected to a pressure test. The pipeline shall be tested in stages and boosted in stages
according to the actual working pressure requirements. The test shall be carried out
in accordance with the relevant regulations of relevant industry standards.
Table 18.1 Acceptance chapter 9 of the main control project of each rehabilitation method
Rehabilitation method Items and methods of each construction method inspection
Inspection items and requirements Inspection method
Pipe cracking The entry inspection of new pipes, meets the requirements in On-site measurement or sampling test, inspection of factory
Sects. 9.2 and 18.3.1 of this Regulation certificate, performance test report, sanitary approval documents
and supplier’s product instructions, etc.
New pipe connection meets the requirements of Article Test welding, check the quality of the weld, check the connection
18.3.3 of this regulation record
Sliplining (Discrete The entry inspection of liner meets the requirements in On-site measurement or sampling test, inspection of factory
sliplining included) Sects. 10.2 and 18.3.1 of this regulation certificate, performance test report, sanitary approval documents
18.4 Test After Pipe Rehabilitation
The installation position of the lining layer is accurate, CCTV inspection, review CCTV inspection report
completely covering the part defects to be repaired and
closely fitting the original pipeline. The performance of the
lining layer meets the requirements of 18.3.1 of this
regulation
103
104 18 Engineering Acceptance
18.4.4 For pipes that are localized renovated, no air-sealing or water-sealing tests
are necessary, and the leakage should be judged by CCTV testing. There should be
no leakage on the inner wall of the lining pipe. The defect to be renovated should
be completely covered. The lining pipe should be in close contact with the old pipe
wall and there should be no leakage.
18.4 Test After Pipe Rehabilitation 105
18.4.5 Sampling inspection should verify the data of its process inspection and accep-
tance according to different renovation processes, and the repair pipeline that meets
the design and construction requirements can be tested for strength.
18.4.6 Pipe restoration test, sample tube strength test, peel strength test, hydraulic
burst test, etc., can be determined according to different renovation process
requirements, relevant industry standard requirements, and based on existing test
conditions.
18.4.7 Before construction, if the test conclusion is used as the basis for structural or
functional acceptance, the test purpose, main parameters, qualified values, and test
methods specified in the design document or construction plan shall be used.
18.5.1 The conclusion of project quality acceptance is only qualified and unqualified.
Unqualified items should be renovated and reworked to pass.
18.5.2 Project quality acceptance shall be carried out according to sub-items and
sub-projects, and shall meet the following requirements:
1. The divisional project can be divided into several divisions according to the
length of the pipeline or the re-segment, when the project is small, it may not be
divided;
2. The sub-projects are divided by pipeline pretreatment, cleaning and pipeline
rehabilitation.
18.5.3 The acceptance judgment for completion acceptance shall meet the following
requirements:
1. The sub-project meets the following requirements to be qualified:
(a) The pass rate of the main control project is 100%;
(b) The pass rate of general projects reaches 80%, and the maximum deviation
is less than 1.5 times of the allowable deviation.
2. All the sub-items of the divisional project shall be qualified, then the divisional
project shall be qualified.
Chapter 19
Health, Safety, Environmental Protection
(HSE)
off, and warning signs should be hung or a special person should be set up for
supervision.
5. Electricity for construction strictly abides by the regulations of “Safety Code for
Electricity Supply and Power on Construction Site”.
6. Hand-held power tools shall comply with the provisions of “Safety Technical
Regulations for Management, Use, Inspection and Maintenance of Hand-held
Power Tools” GB/T3787.
products, such as: white canvas overalls, masks, face masks, protective gloves,
foot covers, etc. when operating.
7. When argon arc welding personnel leave the workplace or the welding machine
is not in use, they must cut off the power supply. If the welding machine fails,
it should be repaired by professionals, and safety measures such as protection
against electric shock should be taken during the repair.
8. In the welding and cutting workplaces, there must be fire prevention equipment,
such as fire hydrants, fire extinguishers, sand boxes and buckets filled with water.
9. When welding in the pipeline, the container must have inlets and outlets, and be
equipped with ventilation equipment; the lighting voltage in the container must
not exceed 12 V, and welding or cutting in containers that have been sprayed
with paint, rubber, fuel, etc. is strictly prohibited.
10. When conducting electric welding operations in a fire-prohibited place, a
fire permit must be obtained, and guardians and fire prevention measures are
required before operation.
11. Construction workers should beware of electric shock during construction.
Workers should wear insulated rubber shoes and be careful not to be injured by
arcs and metal splashes.
12. After the welding or cutting work is completed, carefully check the surroundings
of the welding site and confirm that there is no fire hazard before leaving the
site.
1. Before construction, the design and/or construction company shall prepare the
“Pipeline Renewal Construction Organization Design”.
2. Strictly organize the implementation and management in accordance with the
design requirements of Chap. 4 Engineering Construction Organization of this
Code.
1. The post setting can be set by the construction unit according to the project scale,
the process and equipment used, etc.
2. Construction personnel engaged in pipeline rehabilitation shall pass the necessary
safety training.
A.1.1 Pipes
(1) Conduit, pipeline, duct: Any closed channel of any length used for conveying
medium such as liquid, gas (steam), fine particles solids or for installation of
pipes, cables or other facilities.
(2) Pipeline (conduit) structure: A general term for the hollow body structure
formed by the closed channels and their ancillary facilities (pipeline accessories
and ancillary structures). The channels are used for conveying various media
or installation of pipelines, cables and other facilities.
(3) Buried conduit, underground pipeline: An underground pipe is a pipe laid
underground for conveying liquid, gas, or fine particles solids.
(4) Above-ground conduit (pipeline): A pipe laid directly above the ground or
on a ground pier.
(5) Submerged pipeline, subaqueous pipeline: A pipe laid under water or in the
underwater soil.
(6) Submarine pipeline: A pipe laid in seawater below the sea surface or on the
seabed.
(7) Overhead pipeline: A pipeline erected above the ground, consisting of a
spanning structure and a supporting structure (bracket, bracket, etc.).
(8) Pipe bridge: The dedicated structures which is used to build the pipeline in
the form of Bridges to across the obstacles such as rivers, lakes, sea areas,
railways, highways, valleys.
(9) Industrial pipeline: A general term for all tubular facilities which is within
or between the industrial (petroleum, chemical, light industry, pharmaceutical,
mining, etc.) enterprises used for the production or transmission of media.
(10) Water supply conduit (pipeline): A general term for pipes conveying raw
water or finished water.
(11) Water transmission conduit (pipeline): Generally, it refers to the pipeline
which is conveying raw water and has a certain length.
© China Architecture & Building Press 2021 119
L. Wang et al., Technology Standard of Pipe Rehabilitation,
https://doi.org/10.1007/978-981-33-4984-1
120 Appendix A
(12) Water distribution pipeline: The pipeline which is conveying finished water.
(13) Drainage pipeline, sewer pipeline: A system consisting of pipes, drains and
associated facilities for the collection and discharge of sewage, waste water
and rainwater.
(14) Storm sewer conduit (pipeline): The pipeline which used to transport urban
intercepted rainwater.
(15) Combined drainage conduit (pipeline): The pipes that carry rainwater inter-
ception, domestic sewage, industrial wastewater and other combined discharge
in cities and towns.
(16) Sewage conduit (pipeline): The pipeline conveying treated or untreated
domestic sewage or industrial wastewater from towns or industrial and mining
enterprises.
(17) Culvert: A general term for a drainage pipe structure that crosses an embank-
ment or river bank for the purpose of discharging surface water. It is generally
composed of tunnel body pipe structure and inlet and outlet water entrance
structure, including culvert, arch culvert, box culvert, cover culvert and other
culvert structure types.
(18) Pipeline for water supply in building: A general term for water supply
pipelines explicitly or implicitly installed inside industrial and civil buildings.
(19) Pipeline for wastewater (sewerage) in building: A general term for domestic
sewage and industrial waste water pipes explicitly or implicitly installed inside
industrial and civil buildings.
(20) Down pipe, down spout: An indoor or outdoor vertical drainage pipe that
directs rainwater from the roof or platform of a building to an underground
drainage pipe or other treatment means. There are circular, rectangular and
other cross-section forms.
(21) Cooling water pipeline: A general term for pipes and associated installations
that convey uncooled and cooled water between cooling substances and cooling
devices.
(22) Petroleum transmission pipeline: A general term for pipelines and their ancil-
lary facilities transporting crude oil or refined oil products from production,
storage and other oil supply facilities to users.
(23) Gas transmission pipeline: A general term for pipelines and their ancillary
facilities transporting natural gas, gas, etc. from production, storage and other
gas supply facilities to users.
(24) Heat-supply pipeline: A general term for the pipes and their auxiliary facilities
conveying heat supply medium from thermal power plants, boiler houses and
other thermal sources to users, including above-ground laying, underground
laying, trench laying, direct buried laying and other laying methods.
(25) Heating pipeline: A general term for pipes and accessories used for building
heating, conveying heating medium from heat source or heating device to heat
dissipation equipment.
(26) Pipe duct: Underground pipes for the laying and replacement of water-gas
(steam) and other piping facilities. It is also the common name of the envel-
opment structure for laying and transporting heat supply medium pipelines
Appendix A 121
(Heating groove), including rectangular, circular, arch and other pipe structure
forms.
(27) Cable duct: Underground piping for the laying and replacement of electrical
or telecommunications cable facilities. It is also the enveloping structure of
cable laying facilities, including rectangular, circular, arched and other pipe
structures.
(28) Accessible duct: A general term for underground pipelines such as conduits
and cable trenches in which a person may pass and carry out inspection and
maintenance. An underground duct that allows a person to pass upright is called
a walkway-duct. An underground duct where a person has to bend down to
pass is called a semi-open trench.
(29) Unpassable duct: The cross section of the underground pipe trench can only
meet the minimum clearance size requirements for laying pipelines or cables,
and people can not enter.
(30) Combined duct: It is also called common ditch, which is used to lay water,
gas (steam) pipes and cables in the section and transport more than two kinds
of facilities with different purposes.
(31) Combined duct: See Combined piping.
(32) Electrical conduits: For the protection and protection of buildings (structures)
internal and external buried, overhead electrical line systems through the pene-
tration and replacement of telecommunications or power cables, including
smooth sleeve, wave twisted sleeve, insulating sleeve, flame retardant and
non-flame retardant and other different materials and performance types.
(33) Non-pressure pipeline: The liquid transported in the pipeline operates under
the action of its own weight and gravity, and the highest operating liquid level
of the liquid in the pipeline does not exceed the inner top of the pipeline section.
(34) Pressure conduit/pressure pipeline: A general term for pipes which
conveying medium such as liquid and gas is operated under pressure. Generally
expressed by atmospheric pressure, according to the requirements of different
media and their corresponding working pressure, can be divided into low pres-
sure, medium pressure, high pressure and other different pressure classes of
pipelines.
(35) Gravity-flow conduit (pipeline): The liquid transported in the pipeline oper-
ates under the action of its own weight and gravity. If the highest running water
head does not exceed the inner top of the pipe section, it is a non-pressure pipe,
and if the highest running water head exceeds the inner top of the pipe section,
it is a pressurized gravity flow pipe, also known as artesian pipe.
(36) Free-flow conduit (pipeline): See Gravity-flow conduit (pipeline).
(37) Pipeline undercrossing: A way in which a pipe passes under a natural or
artificial obstacle, such as a river, railroad, highway, or building.
(38) Pipeline aerial (over) crossing: A means of piping over a natural or artificial
obstacle such as a river, valley, railroad, highway, etc.
(39) Pipeline trestle: A truss or frame structure used to support an overhead
pipeline, which is generally composed of supporting columns, hat beams and
beams.
122 Appendix A
(40) Pipeline pier: A solid load-bearing structure used to support an overhead pipe,
usually made of brick, stone or concrete.
(41) Rigid pipe: A circular pipe supported by external forces mainly depending on
the strength of the pipe body material. The deformation under external load is
very small and the failure of the pipe is due to the control of wall strength.
(42) Flexible pipe: Circular pipe with significant deformation under external load.
The vertical load is mostly balanced by the elastic resistance generated by the
soil on both sides of the pipe, and the failure of the pipe is usually caused by
deformation rather than damage to the pipe wall.
(43) Semi-flexible pipe: A circular pipe whose deformation is sufficient to make
the soil on both sides produce elastic resistance under the action of vertical
heals. The elastic resistance of the soil supports the corresponding vertical
load. The numerical value is determined by the ratio of the annular stiffness
of the pipe to the elastic modulus of the soil. The structural calculation of pipe
belongs to the category of flexible pipe, and semi-flexible pipe is equivalent to
semi-rigid pipe.
(44) Semi-rigid pipe: See Semi-flexible pipe.
(45) Liner: Daub on the inner wall of the pipe or at the same time as the tube wall
structure inside the tube surface layer, such as reinforced concrete pipe inner
wall daub or inlaid plastic layer, steel tube and cast iron pipe inner wall daub
cement mortar layer, glass fiber pipe inner wall hot round resin layer, is a part
of the pipe structure.
(46) Coating, surface layer: Daub the outer surface layer formed on the outer wall
of the pipe or at the same time with the structure of the pipe wall during pipe
making. For example, the cement mortar layer sprayed on the outer wall of
prestressed concrete pipe, the asphalt resin coil layer coated on the outer wall
of steel pipe or cast iron pipe, and the thermogenic resin layer on the outer
wall of glass fiber pipe. It’s part of the pipeline structure.
(47) Pipeline joint: A general term for the connection form between adjacent
orifices on a pipe or between a pipe and a pipe fitting. According to the require-
ments of its connection function, it can be divided into rigid connection, flexible
connection, etc. According to the pipe structure, there are insert type, tongue
and groove type, sleeve type, etc. According to the pipe material can be divided
into welding, welding, bonding and so on.
(48) Pipe fitting: A general designation for all types of connections between circular
pipe ends, such as tapered pipe, elbow, tee, four-way, reducer and pipe seal
head. Generally, it is made according to standard specifications.
(49) Pipe accessory: A general term for special pipe unit such as pipe fitting,
compensator, valve and its assembly.
(50) Pipeline appurtenance: A general term for installation of various facilities
for controlling the conveying medium and construction for inspection and
maintenance, such as various types of inspection Wells, valve Wells, inlet and
outlet, etc. It is an integral part of pipeline engineering.
(51) Thrust blocks: A device for preventing horizontal and vertical pipe movement
caused by axial forces, such as internal pressure or temperature action, on a
Appendix A 123
(1) Pipe rehabilitation: The work to deal with defects in pipes and auxiliary
structures. According to the size of the project, pipeline rehabilitation is
divided into small rehabilitation, major rehabilitation and rush rehabilitation;
According to the treatment method, pipeline rehabilitation is divided into
pipeline maintenance and pipeline rehabilitation.
(2) Pipe maintenance: The operation maintenance work such as checking and
cleaning the underground pipeline and its auxiliary structure.
124 Appendix A
(3) Emergency rehabilitation: While the pipelines have a burst and serious
leakage, maintenance operation was done under the condition of the pipeline
still in use. It also known as emergency maintenance.
(4) Structural rehabilitation: A kind of rehabilitation technology which is done
in the case of inner liner pipeline bearing the internal and external pressure.
(5) Semi-structural rehabilitation: A kind of rehabilitation technology which is
done while the original pipeline bears external earth pressure, dynamic load and
internal water pressure, the inner liner pipeline bears external water pressure
and vacuum pressure.
(6) Non-structural rehabilitation: A kind of rehabilitation technology which is
done while the internal and external pressure of pipeline is completely borne
by the original pipeline body.
(7) Structural rehabilitation: A kind of rehabilitation method that the new
liner pipe is independent of the original pipe structure and can bear external
hydrostatic pressure, earth pressure and dynamic load.
(8) Outside pipe rehabilitation: The pipeline structure reinforcement work,
leakage sealing work and other repair work which are done outside the pipeline.
(9) Grouting: A rehabilitation method in which the slurry (chemical slurry or
cement slurry) or resin is injected into the crack area of the pipeline under the
action of pressure to achieve the purpose of leakage prevention and closure.
The grouting method has two kinds: grouting inside the pipeline and grouting
outside the pipeline from the formation.
(10) Grouting pressure: Maximum pump pressure when injecting mud.
(11) Whole renovation: Renovation for the whole construction section of the
pipeline. Reinforcement and renovate the existing piping integrally which are
between two (or more) inspection Wells. This technology regulation includes
ultraviolet curing, hot water curing, short pipe lining.
(12) Localized renovation: A renovation method for the localized leakage, damage,
corrosion and collapse of the original pipe with a certain length.
(13) Spot renovation: Renovation for the local damage, interface dislocation, local
corrosion and other defects in the old pipes, such as stainless-steel sleeve, spot
CIPP, rubber stainless steel extension method, etc.
(14) Live renovation: Renovation for the pipe under the condition of not inter-
rupting the operation function, also known as renovation without stopping
production, online renovation.
(15) Robot: Remote control equipment with closed circuit television monitors
which is mainly used for localized renovation work, such as cutting obstruc-
tions inside the pipe, opening the connecting holes of the branch pipe, polishing
and refilling defective areas, and injecting resin into cracks and holes.
(16) Bypass pumping: A pumping method is used temporarily to control or change
the flow of a pipe for the purpose of cooperating with the construction.
(17) Bypass: A temporary fluid transfer setup to share the overflow of a sewage
system.
(18) Diverting: A method of diverting a normal sewage flow through a special
sewage system usually involves bypass pumping.
Appendix A 125
(19) Upsizing: Method of pipe replacement for increasing the cross-section size of
old pipes
(20) Lining: A renovation method for pipe defects, improving its performance and
prolonging its service life by laying a new pipe in the old pipe or installing
lining layer in the inner wall of the old pipe.
(21) Annular space: A circular space between the inner wall of the original pipe
and the outer wall of the lined pipe.
(22) Chemical stabilization: A method of pipeline rehabilitation in which one or
more solutions are poured into a section of pipeline during construction so that
the chemical reaction can seal the crack and improve the fluidity of pipeline.
(23) Coating , surface layer: Which is painted on the outer surface layer of
pipelines or formed at the same time with the pipeline wall structure when
the pipe is being made. Apply the outer surface layer formed on the outer wall
of the pipe or at the same time with the pipe wall structure during pipe making,
such as the cement mortar layer sprayed on the outer wall of the prestressed
concrete pipe; Asphalt or asphalt resin coated on the outer wall of steel pipe
and cast iron pipe; Thermosetting resin layer of glass fiber tube outer wall.
(24) Liner: The lining formed in the old pipeline through a variety of trenchless
rehabilitation methods without damaging the old pipeline.
(25) Slip lining rehabilitation: A rehabilitation method that the new pipe is directly
installed into the old pipe as the lining, and the ring gap between the old pipe
and the new pipe should be filled with grouting.
(26) Embedding rehabilitation: A rehabilitation method that the new pipe is
directly placed into the old pipe as the lining, and no ring gap fit between
new and old pipes.
(27) Lining rehabilitation: A rehabilitation method that the liner pipe and the old
pipe can form an integrated composite pipe.
(28) Upgrading rehabilitation: Pipeline rehabilitation to improve pipeline oper-
ating pressure, safety, etc.
(29) Winch: A device used to pull a CCTV camera or cleaning tool inside a sewer
pipe.
(30) Close fit: A lining system for a tight fit between old and new pipes after
renovation.
(31) Joint sealing: A method of inserting an expandable packer into a pipe to seal
leaking joints and injecting resin or slurry to seal the joints. The packer should
be recovered when the plugging is complete.
(32) Pipe bursting/splitting: A pipe rehabilitation method that the original pipe is
broken or cut from the inside by the crushing (cracking) pipe equipment, and
the original pipe fragments are pushed into the surrounding soil to form the
pipe hole, and the new pipe is pulled into the pipe hole simultaneously. This
method mainly used for replacing brittle pipes such as concrete pipes and clay
126 Appendix A
pipes. There are pneumatic tube crushing method and hydraulic expansion
method.
(33) Pipe bursting, cracking: It is a kind of pipe rehabilitation method. So as to
replace the old pipe or expand the capacity, a splitter is guided by the old pipe
and cut and expand the old pipe, while the new pipe is pulled in.
(34) Burst strength: The internal pressure required to cause pipe or casing failure.
(35) Fracture, splitter: A pipe breaker that breaks old pipes and squeezes pipe
fragments into the surrounding soil.
(36) Pneumatic head: A power tool driven by compressed air that provides pulse
power to drive the crusher tool forward and to break up the old pipes.
(37) Hydraulic head: A power tool driven by hydraulic power that provides impulse
power to drive the crusher tool forward and break up the old pipe.
(38) Static head: A expansion head which is slightly larger than the inner diameter
of the old pipe, is connected behind the drill pipe during operation, and expands
the old pipe during the process of static pressure pull-back and then drags the
new pipe into the old pipe.
(39) Guide nose: A circular wheel which is connected in front of the first pulling
rod supports and protects the pulling to entry pipe.
(40) Soil displacement: In the process of pipe replacement, the soil around the pipe
is squeezed and occurs displacements.
A.1.2.3 Sliplining
(50) Dragging head: In order to protect the head of the new pipe and prevent soil,
water and foreign matter from entering the new pipe when pulling the new
pipe into the old pipe, the conical protection joint connected in front of the
new pipe has a pulling ring at the front end of the protection head, which can
be connected to the winch of the working pit in front through steel cables.
(51) Maximum allowing pulling force: When thrust through the pipe by pulling,
the maximum safe pulling force that can be used taking into account the cross-
section area of the new pipeline and the tensile yield strength of the pipeline
when thrust through the pipe.
(52) Maximum allowing pulling length: When a new tube is inserted by pulling,
the new pipe drawing length is determined after taking into account the
maximum allowing pulling force, mass per unit length of pipe and friction
coefficient between the old and new pipes, the new pipe drawing length is
determined.
(53) Maximum allowing pushing force: When thrust through the pipe by incre-
mental launching method, the maximum safe jacking force that can be used
taking into account the cross-section area of the new pipeline and the maximum
allowable compressive stress of the pipeline.
(54) Maximum allowing pushing length: When a new tube is inserted by incre-
mental launching method, the new pipe jacking length is determined after
considering the maximum allowing pushing force, mass per unit length of
pipe and friction coefficient between old and new pipes.
(55) Minimum allowable radius of curvature of liner: In the process of hoisting,
winding and installation of new pipe interspersed construction, the minimum
allowable turning radius is set to avoid excessive bending to damage new pipe.
(56) Protecting connector: An automatic disconnection device installed between
the winch and the tub head during pulling intubation to prevent the winch’s
pull from exceeding the ultimate tensile resistance of the pipe. It is used to
ensure that the tow rope and the tub head will automatically detach when the
pulling force exceeds the maximum allowable traction.
(57) Protecting ring: In order to prevent friction damage to the outer layer of the
new pipe and reduce drag resistance, short pipes are arranged at certain distance
outside the new pipe.
(58) Positioner: When the new pipe is inserted into the old pipe, due to the dead
weight of the pipe or the buoyancy of mud, the new pipe will often sink at
the bottom of the old pipe or float at the top of the old pipe. In order to make
the new pipe in the middle of the old pipe, the short pipe applied at intervals
outside the new pipe is used to fix the new pipe in the axis position of the old
pipe.
128 Appendix A
(59) Segment: It is the pipe prefabricated plate which can be assembled into a
certain diameter of pipe. It includes stainless steel pipe pieces, plastic pipe
pieces.
(60) Stainless steel lining: The renovation method of pipeline with stainless steel
material as lining; For large diameter pipes that can be entered by people, the
pipe billet is made of stainless-steel plate and welded manually in the pipe to
form the lining layer.
(61) PVC module assembling: A renovation method of pipeline in which plastic
modules are connected and assembled into new pipes by using bolts, and
special grouting is filled between the existing pipes and the assembled plastic
pipes.
(62) Supporting segment: In the process of assembling the pieces of pipe, the
construction work which is to positioning and fixing the pieces of pipe.
(63) Segment assembly: Construction personnel enter into the pipe to assemble
prefabricated pipe pieces into lining structure.
(64) Splice segment lining: A renovation method of pipeline that splice sections
are spliced into a new pipe in the original pipe, and the gap between the new
pipeline and the original pipeline is filled.
(65) PVC lining concrete and reinforced concrete sewer pipe: A pipe with PVC
(modified Polyvinyl chloride) sheet lining inserted into the inner wall of the
pipe during the molding process based on concrete and reinforced concrete
drain pipes.
(66) Relaining key pull strength: A special tensile testing machine is used to
measure the strength of the fixed key of PVC sheet lined with pipes, which is
expressed by the tensile force on the key bar of unit length, to check whether
the fixed key of PVC sheet is firmly embedded in concrete.
(67) Sweating soldering: After the PVC sheet overlaps with each other, the contact
parts of the two connection surfaces are heated and melted together by the
special hot melt tool.
(68) Electric spark insulation performance: High voltage electrostatic output
detection equipment is used to detect the surface of PVC sheet lined with pipe
line by line to test the integrity and integrity of PVC sheet inside the pipe.
(69) Lining with close fit pipes: The new liner whose outer diameter is the same as
the inner diameter of the old pipe shall be temporarily reduced in section size
and inserted into the old pipe, and then the new lining pipe shall be restored
to fit closely with the inner wall of the old pipe. This pipeline rehabilitation
method does not need grouting to fill the gap between the old and new pipes.
Lining with close fit pipes includes swagelining and deformed lining.
(70) Deformed and reformed lining, swagelining: Utilized the memory function
of materials, the diameter of the circular new pipe is reduced by extrusion
Appendix A 129
or drawing. After being putted into the old pipe, the new pipe’s diameter is
restored to the original size by heating or pressurizing. In this way, the new l
new pipe will fit with the old pipe closely. The method includes two technology:
swage lining technology and rolldown technology.
(71) Die shrinking-diameter method: It relates to an interpolation lining construc-
tion method. After the polyethylene liner pipe is passed through the die
compression diameter equipment forging die sleeve, the outer diameter of
the line pipe is reduced and then put it into the old pipe. Using the memory
function of PE material, after the external pressure is removed, the PE liner
pipe is restored to its original diameter naturally or by pressure.
(72) Roller shrinking-diameter method: It relates to an interpolation lining
construction method. After the polythene liner pipe is multi-stage rolled by
the roller reducing equipment, the outer diameter of the line pipe is reduced
and then put it into the old pipe. Using the memory function of PE material,
after the external pressure is removed, the PE liner pipe is restored to its original
diameter naturally or by pressure.
(73) Die draw: The new pipe is pulled out by a tapered steel die, which makes
the long molecular chains of the plastic pipe reassemble, and then the pipe
diameter will be reduced by 7–20%. Thus, it can be inserted into the old pipe
smoothly. If the pipe diameter is small, it can be drawn at room temperature. If
the pipe diameter is large, the die is usually heated to more than 100 °C ahead
of the being drawn. After the liner is in place, the diameter is gradually restored
to the original structure relying on the memory function of plastic molecular
chain. In this way, the new line pipe can form a close match with the old pipe.
(74) Fold and formlining , fold-and-formlining: The method is suitable for
deformable PE or PVC pipe. Using the memory function of material, the
circular new pipe is folded into “U” shape or “C” shape in factory or construc-
tion site. Then the “U” shape or “C” shape pipe is pulled into the old pipe.
With pressurized or heated, the “U” shape or “C” shape pipe will restore to its
original shape and size. In this way, the new pipe will match with the old pipe
closely.
(75) Folded pipe: It relates to a pipe with a U-shaped or C-shaped section which
is formed by pressing and folding a circular plastic tube.
(76) Deformed-and-reformed lining (DRP): A term used to describe some
systems in which the liner is deformed to reduce its size during insertion,
and then reverted to its original shape by the application of pressure and/or
heat.
(77) Slot: When the thermoplastic deformed polyethylene liner is restored to its
original circular shape, because of losing its supporting point at the side joint
or deformation of the pipe, the liner pipe has a local deformation by expansion.
(78) Dragging pit: A work pit used for placing equipment such as a traction frame.
(79) Interposing pit: A work pit used for inserting PE pipe and installing deformed
lining equipment.
130 Appendix A
(80) Rebound: The process relates to that the deformed tube restore to a circular
shape by means of pressurization and heating after being inserted into the
repaired pipe.
(81) Inversion method: The hose impregnated with thermal-cured resin material
is transported to the construction site. Under the action of water pressure and
air pressure, the hose is inverted and putted into the pipe and close to the inner
wall of the pipe. Then the resin material is cured by hot water, steam, spray
or ultraviolet heating, thus forming a high-strength resin pipe inside the old
pipe.
(82) Dragging method: The hose impregnated with thermal-cured resin material
is transported to the construction site. The hose is pulled into the old pipe by
traction, and then pressurized to make it expand and cling to the inside of the
pipe. It’s a way of curing by heating is similar with inversion method.
(83) Inversion: When using the CIPP to renovate the pipe, the hose is inverted and
putted into the pipe with the water pressure and air pressure, making the resin
impregnated side cling to the inner wall of the old pipe seamlessly, airlessly
and tightly.
(84) Resin: Generally, it refers to the unsaturated, styrene-based thermal curing
resin and catalyst system, or an epoxy resin and curing agent. The selection
of resin should match the flip process adopted.
(85) Thermosetting resin: A kind of resin that has chemical changes after heating
and gradually hardens and forms. After being hardened into shape, it does not
become soft or dissolve when heated again. Thermosetting resins commonly
used for new pipes include unsaturated polyester resin and epoxy resin.
(86) Thermoplastic resin: Resin with properties of softening by heating and hard-
ening by cooling without having chemical reactions. No matter how many
times it is heated and cooled, it can keep the properties. Thermoplastic resin
commonly used for new pipes include PE and PVC and so on.
(87) Adhesive: A gelatinous substance used to bond a tubular composite lining
material to the inner wall of a metal pipe when use inversion method to repair
the pipe.
(88) Soaking: The process of distributing the adhesive over the hose and
distributing it evenly before use inversion method to renovate the pipe.
(89) UV protective film: A plastic film on the outermost layer of a hose that
protects the resin inside the hose’s fiberglass braid from ultraviolet radiation
and damage.
(90) Inner membrane: A plastic film in the innermost layer of the hose that
protects the resin inside the hose’s fiberglass braid from volatile during storage
and transportation.
(91) Soft liner, hose: A tube consisting of one or more layers of flexible nonwoven,
woven, or non-woven and woven mixed materials.
Appendix A 131
(92) Ultraviolet light curing: A kind of curing method relates to that the inner
liner pipe is impregnated with photosensitive resin. After being placed in the
old pipeline, the inner liner is cured by ultraviolet light to form the glass fiber
reinforced plastic lining layer.
(93) Hot water curing method: An integral pipe rehabilitation method in which
the inner liner impregnated with thermosetting resin is inverted or pulled into
the old pipe and cured by heating water.
(94) Steam curing method: After the inner liner pipe is placed into the old pipe, the
steam equipment distributes the steam through the pipe. The steam will make
the temperature of the gas in the new pipe rise above the curing temperature
of the resin. In this way, the resin of the inner liner pipe is cured.
(95) Ambient curing method: A kind of curing method that the resin of the inner
pipe is cured under the room temperature.
(96) CIPP of UV curing: Without changing the location of the old pipeline,
the hose soaked in resin is placed into the old pipeline by pulling or by
air compress and close to the inner wall of the pipeline. Then utilizing the
properties of the resin that can be cured when exposed to ultraviolet light, put
the ultraviolet lamp into the inflatable hose and control the ultraviolet lamp
to walk in the hose at a certain speed, it can make the hose solidify gradually
from one end to the other and close to the inner wall of the pipeline to be
repaired.
(97) Roller: The device is installed at the surface wellhead or downhole pipe
mouth to change the direction of the hose being pulled, avoid the friction
between the hose and the wellhead or the pipe mouth, protect the ultraviolet
film of the hose, and guide the direction of the hose pulling.
(98) Curing entry shaft: When the CIPP of UV curing method is used to renovate
the drainage pipe, a well in which a hose installed in a section of the pipeline
to be repaired begins to solidify. No curing equipment is placed near the
ground of curing entry shaft and the UV lamp is normally placed into the
pipe from this well.
(99) Curing reception shaft: When the CIPP of UV curing method is used to
renovate the drainage pipe, a well in which a hose installed in a section of
the pipeline to be renovated is finally solidified. Compared with the curing
entry shaft, the site near the ground of the curing reception shaft is larger. The
curing equipment is placed at the curing reception shaft and the ultraviolet
lamp is taken out from here.
(100) Clinging: The condition in which the outer surface of the lined pipe is in
close contact with the inner surface of the old pipe after the restoration of
roundness and relaxation.
(101) Clinging liner: A kind of lined pipe construction that the outer surface of the
newly formed liner pipe is in close contact with the inner surface of the old
pipe after the pipe is repaired.
(102) Swell: The area in which the liner pipe body is separated from the original
pipe wall and formed a bulge.
132 Appendix A
(103) Curing pressure: The minimum air, water or steam pressure required to
solidify new pipe.
(104) Curing time: The minimum time required to maintain curing pressure and
temperature when new pipe is solidified.
(105) Wrinkling: Due to the inner diameter difference between the new liner pipe
and the old one, or the insufficient air pressure, etc., the new pipe could not be
fully expanded, resulting in the local surface undulation after solidification.
(106) Pinhole: Because the lining hose and impermeable film have suffered cone
piercing during transportation or construction, there are holes in the solidified
new pipe wall.
(107) Notch: The lining hose and impermeable film have been damaged in the
process of transportation and construction, resulting in that the new pipe has
overall discontinuity and gap defect after solidification.
(108) Bubbling: During the curing process of the new pipe, because the curing
temperature is too high, or the adhesion between the impermeable film and
the woven cloth is not strong, it is leading to the local protruding on the
surface of the cured pipe.
(109) Weak zone: During the curing process of the new pipe, because the curing
temperature is too low, or the heating time is too short or the cooling of the
groundwater outside the pipe, some areas of the cured pipe where the strength
and stiffness do not meet the structural strength requirements.
(110) Spiral winding: A device that could make the plastic tape with a rebar become
a lining layer on the inside of an old pipe. The ring gap between the liner and
the old pipe usually needs to be fixed by grouting.
(111) Mechanical spiral winding: A kind of pipe renovation method that the strip
profile is winded into a new pipe in the old pipe by the spiral winding machine
and the gap between the new pipeline and the old pipeline is treated by
grouting.
(112) Pushing machine winding: The winding machine is placed in the working
pit. The main and secondary locks on both sides of the profile are interlocked
respectively. By spiral rotation, the profile forms a new continuous seamless
waterproof pipe with fixed diameter and is pushed into the old pipe by the
winding machine.
(113) Self running winding: The winding machine moves along the old pipe,
spinning and winding the pipe while the new pipe stays still.
(114) Manual spiral winding: For large diameter pipelines that allow people to
enter, a new pipeline could be wound manually in the old pipeline and the
annular space between the old and new pipelines should be grouting.
(115) PVC lining belt: The PVC lining belt is prefabricated profile, which is wound
on site, and its shape completely conforms to the shape of the old pipe or
conveying pipe.
Appendix A 133
(116) PVC sealing connecting strip: It is the matching product of the lining belt,
and its construction principle is equivalent to producing a locking mechanism
at the edge of the contour forming lining belt.
(117) Lining strip reel: The PVC lining tape is provided by coil, which should be
placed above the working well. The end of the section should be found from
the coil and pulled out, and the lining tape should be installed inside the pipe
through the working well.
(118) Section height: The section height of the profile belt.
(119) Section width: The section width of the profile belt.
(120) Anti-corrosion repair: On the premise that the original structure of the old
pipeline can still bear internal pressure, external earth pressure and dynamic
load, a spray repair method is used to solve the problem of corrosion and
improve the roughness of pipe inner wall.
(121) Reinforced repair: Due to cracks, local mild damage, local corrosion and
other defects on the pipe to be repaired, the original structure of the pipeline
cannot fully bear internal pressure, external earth pressure and dynamic load.
A spray repair method is used to make the pipe can bear internal pressure,
external earth pressure and dynamic load independently.
(122) Working pit for spray: A work pit that is used to store the waste removed
from the inner wall of the pipeline, where the nozzle begins (away from
the spraying machine) or ends (close to the spraying machine) the spraying
process.
(123) Gunite: A method of pipe rehabilitation in which steel bars are placed on the
walls of an old sewage pipe and is sprayed with concrete to form a covering.
(124) Substrate: The inner surface of the pipe to be repaired.
(125) Coating: The film layer formed by curing the coating on the substrate. When
the pipe is repaired by reinforced spray method, the coating is an integral new
pipe.
(126) Cement mortar coating: In order to prevent the pipe inner wall from corro-
sion and scaling which will reduce the roughness of the pipe wall, the cement
paste lining layer is applied on the inner wall of the pipe. There are some
methods, such as mechanical spraying, hand daub and centrifugal daub.
(127) Resin coating: The inner wall of steel pipe and cast-iron pipe is sprayed with
resin by rotary jet.
(128) Coating thickness: The distance between the coating surface and the
substrate surface.
(129) Wet-film thickness: The wet coating thickness measured immediately after
coating is applied.
(130) Dry-film thickness: The thickness of the remain coating on a surface after
hardening.
(131) Injection machine: Machine used for pipe spraying repair operation.
134 Appendix A
(132) Umbilical tube: A composite pipe consist of multiple pipes which is serving
for the spraying operations. Inside the composite pipe, there are two paint
pipes, one compressed air pipe, three accompanying heating pipes, one
accompanying wire rope. Outside the composite pipe, it is a rubber pipe.
The umbilical tube can be reeled to the coil of the spraying machine.
(133) Rotating sprayer: A high-speed rotating nozzle used to spray the lining
material (cement slurry, resin, etc.) during spraying and repairing operation.
(134) Rotating speed: Turns number of spray nozzle per unit time during spraying
and repair.
(135) Walking speed: The travel distance of the jet along the pipe axis in unit time
during spraying repair operation.
(136) Jet velocity: The speed at which the lining material is ejected by the rotating
nozzle during the spray repair operation.
(137) Resin injection: A localized renovation method for pipe which is often used in
sewage pipes. By injecting resin into cracks and holes, it can prevent leakage
and further deterioration after curing, and can also increase the structural
strength.
(138) Stainless-steel lining: A stainless steel sleeve with adsorbed styrofoam
sponge is installed at the partial damage of the pipe. After the styro-
foam expands, a sealable contact is formed between the old pipe and the
stainless-steel sleeve.
(139) Localized repair: Methods to repair the local damage, interface dislocation,
local corrosion and other defects in the original pipeline. In this regulation,
it means spot cured-in-place pipe method and stainless-steel sleeve method.
(140) Spot CIPP, spot cured-in-place pipe: A localized renovation method of
applying resin-impregnated fabric to the damaged part of the pipe by balloon
dilation and then curing the pipe by heating.
(141) Joint sealing: A localized renovation method of inserting an expandable
packer into a pipe and injecting resin or slurry to seal the joints.
(142) Plugging lining with hoop: A localized renovation method for pipe leakage
by putting a pipe hoop outside of the pipe wall.
(143) Fracture embedment method: In the renovated position of original rein-
forced concrete pipe, water-soluble polyurethane slurry is grouting into the
pipe with a certain grouting technology to fill and close the defective parts,
which make the pipe impermeability and reinforcement.
(144) Stainless steel double expansion ring method: With the annular rubber
sealing belt and stainless steel sleeve ring as the main repair materials, double
expansion ring of rubber ring is installed at the pipe interface or local damaged
part. After the double expansion ring of rubber ring is in place, it is fixed with
2–3 stainless steel expansion rings to achieve the purpose of no leakage.
Appendix A 135
(14) Pigging system: Pigging system is a complete set of equipment use to remove
the condensates and sediments in the pipe, isolate, replace or inspect the pipe
online. The commonly used pipe cleaning methods is mechanical cleaning,
hydraulic cleaning and chemical cleaning.
(15) Mechanical cleaning: The inner wall of the pipe is cleaned by friction
descaling using tools such as bar, barrel and capstan brush.
(16) Hydraulic cleaning: The inner wall of the pipe is cleaned by high-pressure
water or water flow with head pressure. Hydraulic washing equipment includes
high-velocity jet head, cleaning ball and hinge disc cleaner.
(17) Chemical cleaning: It is a pipe cleaning method with injecting the chemical
agent into the pipeline, making the chemical cleaning solution flow in the
pipeline, and then the chemical agent and the scale formation on the inner
wall of the pipe will have chemical reaction. It can accelerate the stripping and
cleaning the pipe.
(18) PIG: A bullet-shaped cleaning tool made from a special polyurethane foaming
system. The commonly used pigging tools are spherical pigging (PIG ball),
cup-type pigging and soft pigging, which can be equipped with instruments
for measuring tube wall thickness, internal corrosion, pipe deformation and
position settlement.
(19) Pigging: Using the pressure of the fluid in the cleaned pipe or the water pressure
or air pressure provided by other equipment as the power to push the pig
forward in the pipe, scrape the dirt on the pipe wall, and discharge the dirt and
clean out debris accumulated in the pipe.
(20) Sandblasting cleaning: A method of cleaning and derusting by using
compressed air as power to form a high-speed jet to spray the materials (copper
ore, quartz sand, emery sand, iron ore) to the inner surface of the pipeline at
high speed.
(21) Preparatory cleaning: Before inspecting the pipeline, water jet is usually used
to remove debris inside the pipeline.
(22) Obstacle removing with robot: The robot is guided by the internal video
camera system to locate and remove garbage and foreign matter in the pipe.
(23) Pushrod cleaning: A method of using manpower to push bamboo, steel bars,
ditch sticks and other tools into pipes to clear blockages.
(24) Winch bucket cleaning: The method of dredging pipe by drawing dredging
device inside pipe with winch.
(25) Cleaning bucket: Bucket, shovel and other tools used in dredging winch.
(26) Purging: The removal of residual gas and dirt from a gas facility prior to
commissioning or maintenance.
(27) Relief: The process of using the dispersion equipment to empty the air, gas or
mixed gas in the gas facilities.
(28) Hot-tapping: Use special machines and tools to process holes in pressurized
gas pipelines and operate without gas leakage.
Appendix A 137
(29) Plugging: The plugging head is pulled into the pipe from the opening and
sealed the pipe to prevent the flow of medium in the pipe.
(58) Sewers canner and evaluation technologies set: Like closed circuit television
(CCTV), it can provide the front screen, can also provide 360 DHS scanning
the visual image of the pipe inner surface, can analyze data in the office later,
promise not to ignore some important pipeline defect assessment technology.
This system can also record pipe slope, so the available pipes prolapse and
Appendix A 139
sediment of potential location, 360 DHS scanning plane view to detect the
entire surface of the pipe, but also can measure the joint gap.
(59) Renovation index: A value is calculated according to the structural defect’s
degree and number of pipelines by a certain formula. The higher the value is,
the greater the intensity of repair.
(60) Maintenance index: A value is calculated according to the type, score, number
and influencing factors of pipeline functional defects. The higher the value is,
the greater the urgency of pipeline maintenance.
(61) Structural defect: Defects affecting the strength, stiffness and tightness of
the pipeline, such as deformation, fracture, wrong opening, leakage and other
structural defects which can only be eliminated by semi-structural repair or
structural repair means.
(62) Functional defect: The pipe structure is not damaged and its defects only
affects the overcurrent capacity or water quality defects.
(63) Roughness coefficient: It is used to show the effect coefficient of the head loss
caused by the rough pipe.
(64) Partially deteriorated pipe: The pipe has slight structural damage, but the
pipe can still bear external earth pressure and dynamic load within its design
life, or its section deformation is not greater than 2.5% of the pipe nominal
inner diameter.
(65) Fully deteriorated pipe: The pipe has serious structural damage. The pipe
cannot still bear external earth pressure and dynamic load although it is still
within its design life, or its section deformation is greater than 2.5% of the
pipe nominal inner diameter.
(66) Corrosion: Physical and chemical interactions between metals and environ-
mental media, which result in changes in the properties of metals and often
result in damage to the metals, the environment or the functions of the technical
systems.
(67) Biological corrosion: A corrosion of piping material caused by the action of
organisms (e.g. bacteria, algae, fungi).
(68) Corrosion rate: The amount of mass lost per unit time due to corrosion.
(69) Crack, cracking: An axial or radial crack in a pipe characterized by a sharp
tip and a large aspect ratio of cracking displacements.
(70) Deformation: Permanent changes in shape, such as bending, buckling, depres-
sion, ellipticity, ripple, fold, or other changes that affect roundness or flatness
of pipe section.
(71) Dent: Local plastic deformation in which the surface curvature of a pipe
changes significantly due to impact or extrusion by external forces.
(72) Spring back: After the removal of external constraints, the sag depth of the
pipeline decreases due to elastic unloading.
(73) Rebounding: The decrease of sag depth under internal pressure.
(74) Dent depth: The maximum reduction in pipe diameter relative to the original
diameter at the concave position.
(75) Collapse: Failure of a pipeline due to structural fracture.
140 Appendix A
(76) Encrustation: Saline groundwater seeps into the tube, after its evaporation, it
left behind deposits in the pipe.
(77) Erosion: Pipe surface deterioration caused by wear and tear of fluids.
(78) Pitting: Some local deep punctured erosion caused by high corrosion in the
pipe.
(79) Infiltration: The phenomenon that clean water, rainwater or ground water
enter the pipe through cracks, defective joints, man-hole or maintenance well,
or the phenomenon that the medium inside the pipe flows to the outside.
(80) Spalling: The phenomenon that part of the pipeline structure is separated from
the pipeline parent.
(81) Scaling , tuberculation: A tuberculous mass resulting from localized
corrosion at different sites.
(82) Sediment: The deposition of small particles in the pipe can result in a reduction
in cross-sectional area.
(83) Segment: A section of pipe that serves as an evaluation unit.
(84) Section: Each part of a pipeline divided for the purpose of risk assessment of
the pipeline. It is the smallest unit of risk assessment of the pipeline.
(85) Failure consequence: The degree of adverse effects caused by the leakage
accident in the pipe section, such as casualties and environmental losses.
(86) Attribute: Description of relevant characteristics of pipelines, including
characteristics of pipeline ontology, pipeline operation, and surrounding
environment.
(87) Semi-quantitative risk assessment method: It is a kind of pipeline risk assess-
ment method. It establishes an index system according to pipeline attributes
and their contribution to risk, scores the failure possibility and failure conse-
quence of each pipeline segment, and uses the score value to represent the
pipeline risk.
(88) Semi-quantity risk assessment: The process of scoring various factors that
affect the possibility and consequence of failure according to the scoring system
and synthesizing the risk value represented by the score.
(89) Failure probability: The probability of a pipeline accident which is expressed
in fraction.
(90) Basic model for failure probability assessment: The unified failure proba-
bility scoring model is adopted in the evaluation of pipeline failure probability.
This model includes the basic factors affecting pipeline failure, namely, scoring
items, and gives the default weight of these scoring items.
(91) Third-party damage: Unintentional damage to the pipeline caused by a person
other than the owner, the user, management and maintenance party of the
pipeline.
(92) Pipeline essential safety quality: The safety level of pipeline determined
by factors such as pipeline design, manufacturing, construction, geological
conditions, natural disasters, defects, etc.
(93) Risk value: The product of the probability of failure and the consequences of
failure which is expressed in fractions.
Appendix A 141
(94) Leakage test: Take gas as medium, the test is done to detect the leakage point
in the pipeline system by using blowing agent, color developing agent, gas
molecular sensor or other means under the design pressure.
(95) Water pressure test: Take water as the medium, make the water full of the laid
pressure pipeline, test whether the pipeline structure is damaged and whether
its water percolating capacity conforms to the stipulated standard of allowable
seepage water (or allowable pressure drop) at the specified pressure value. This
test method is mainly used for the pressure pipeline conveying liquid.
(96) Closed water test: Test to check whether the laid pipe segment conforms to
the specified allowable leakage standard by water injection method according
to the specified head, generally used for gravity flow pipeline (non-pressure
pipeline).
(97) Leak test: It is also called functional test to inspect the leakage of pipelines
with liquid or gas in laid pipelines. There are two kinds of tests: closed water
test and closed gas test.
(98) Closed water test: Tests to check whether the laid pipe segment conforms to
the specified allowable leakage standard by water injection method according
to the specified head, generally used for gravity flow pipeline (non-pressure
pipeline).
(99) Closed air test: Tests on laid pipe sections to check whether they conform
to the specified leakage amount at the specified pressure value by means of
inflation, mainly used in pipelines conveying gases and inflammable, explosive
or toxic media.
(100) Construction planning: A work plan prepared by the construction unit and
approved by the competent department for the completion of the trenchless
project work objectives.
(101) Management of construction production: In order to ensure the coordina-
tion and continuity during the trenchless construction production process, a
set of management work is done including planning, organizing, directing,
controlling and regulating.
(102) Pipeline design: The design and planning department puts forward the prin-
ciple of the general outline of pipeline laying track, and the competent unit
or construction unit designs the pipeline track according to the trenchless
construction process characteristics, pipeline conditions, and the conditions
around the construction site. The optimized pipeline parameters and construc-
tion methods shall be submitted to the design and planning department for
approval.
(103) Construction design: With the requirements of pipeline design, the construc-
tion unit shall design the trenchless construction scheme according to the
pipeline track, engineering geological conditions and pipeline parameters.
142 Appendix A
(119) Limited space work: Operators enter the limited space to carry out activities.
(120) Acceptance: On the basis of the construction unit’s own quality inspection
and assessment, a kind of construction test activity which is organized by the
project quality acceptance of responsibility (supervision or the construction
unit) and with attendance of all the relevant units to confirm division (a
branch), unit (units) engineering quality whether achieve qualified or not by
sampling the reinspection, audit of construction materials, and according to
the contract documents, design documents and relevant standards in written
form.
(121) Check (inspection): The activity of measuring, checking and testing the
quality parameters or quality characteristics of a project or project material
inspection project and comparing the results with the requirements speci-
fied in the standard to determine whether the project or project material is
qualified.
(122) Site acceptance: Inspect the materials, components and equipment entering
the construction site according to the contract, design requirements and rele-
vant technical standards, and confirm whether the products are qualified or
not.
(123) Check (inspection) lot: An inspection body consisting of a certain number
of samples, aggregated for inspection under the same production conditions
or in a prescribed manner.
(124) Evidential testing: In the construction unit or the construction supervising
units under the witness of the construction unit of the field test of personnel
involved in the engineering structure safety test blocks, test samples and
materials on site, and through the provinces (municipalities directly under
the central government) to the construction administrative department at or
above the level of their recognition of qualifications and the metrological
certification of quality and technical supervision department quality testing
unit for testing.
(125) Handing over check (inspection): Activities to be inspected by both the
undertaking party and the completion party and to confirm whether the work
can continue.
(126) Dominant item: Tests in engineering that are decisive for safety, health, the
environment and the public interest.
(127) General item: Inspection items other than dominant items.
(128) Sampling check (inspection): According to the specified sampling scheme
(frequency), randomly select a certain number of samples from incoming
materials, components, equipment or engineering inspection items according
to the inspection batch.
(129) Sampling frequency: The sampling range and the number of points to be
drawn according to the characteristics of the items to be tested.
144 Appendix A
(130) Qualified rate: The percentage of the number of points qualified in the
same inspection item and the number of points to be inspected in the same
inspection item.
(131) Quality of appearance: A qualitative assessment of the external quality of a
project made by the project quality inspector through visual observation and
necessary measurement means (measured and measured).
(132) Rework: The replacement, remaking and construction of the unqualified parts
shall be taken.
(133) Peels strength: A unit of force N/mm required to strip a unit width adhesive
tape from a particular adhesive surface at a given Angle and rate.
(134) Test assembly: A component formed by gluing the test tape to a steel plate.
(135) Roughness average: The arithmetic mean deviation of the roughness contour
is the arithmetic mean of the absolute deviation of the roughness contour
within the sampling length.
(continued)
Defect name: Fracture Defect code: PL
Definition: The external pressure of the pipe exceeds its own capacity and causes the pipe to
break. There are longitudinal, annulus and compound three kinds of fractures
Grade Definition Value Sample figure
A.2.1.2 Deformation
146 Appendix A
2 The deformation is 2
5–15% of pipe diameter
3 The deformation is 5
15–25% of pipe
diameter
4 The deformation is 10
greater than 25% of pipe
diameter
A.2.1.3 Corrosion
Appendix A 147
2 Moderate 2
corrosion: The
inner surface of the
pipe appears peel
off and the coarse
aggregate or rebar
is partly exposed
3 Severe corrosion: 5
The coarse
aggregate or rebar
is fully exposed
148 Appendix A
A.2.1.4 Misalignment
2 Moderate 2
misalignment: The
deviation of the two
connected pipe is
between ½ and 1 of
the pipe wall
thickness
3 Severe misalignment: 5
The deviation of the
two connected pipe is
between 1 and 2 times
of pipe wall thickness
4 Most severe 10
misalignment: The
deviation of the two
connected pipe is
greater than 2 times of
pipe wall thickness
A.2.1.5 Fluctuation
Defect name: Fluctuation Defect code: QF
Definition: The interface position is shifted and the vertical position of the pipe has changed. Thus, the water is accumulated in the lower place
Grade Definition Value Sample figure
Appendix A
(continued)
149
(continued)
150
(continued)
Appendix A
(continued)
Defect name: Fluctuation Defect code: QF
Definition: The interface position is shifted and the vertical position of the pipe has changed. Thus, the water is accumulated in the lower place
Appendix A
Defect description
D
H
H is the height of the fluctuation, that is, the value of the pipe deviating from the design height
151
152 Appendix A
A.2.1.6 Disconnection
1 Mild disconnection: A 1
small amount of soil has
been forced into the pipe at
the end of the pipe
2 Moderate disconnection: 3
The disconnection distance
is less than 2 cm
Defect description
A.2.1.10 Leakage
3 Floating leakage: A 5
large amount of water
gush or spray from the
defect point of the pipe
and the gushing
leakage surface area is
less than 1/3 of the
pipeline section
2 The sediment 2
thickness is between
30 and 40% of the
pipe diameter
3 The sediment 5
thickness is between
40 and 50% of the
pipe diameter
4 The sediment 10
thickness is greater
than 50% of the pipe
diameter
A.2.2.2 Scaling
(continued)
Defect name: Scaling Defect code: JG
Definition: An attachment on the inner wall of a pipe
Grade Definition Value Sample figure
A.2.2.3 Obstacle
2 Section loss is 2
15–25%
3 Section loss is 5
25–50%
Defect description The type of obstacle and the section loss rate should be recorded
Appendix A 161
2 Section loss is 3
15–25%
3 Section loss is 5
25–50%
2 Section loss is 2
15–25%
3 Section loss is 5
25–50%
A.2.2.6 Floatage