Modeling Mineral Size Reduction in The Closed-Circuit Ball Mill at The Pine Point Mines Concentrator (1981)
Modeling Mineral Size Reduction in The Closed-Circuit Ball Mill at The Pine Point Mines Concentrator (1981)
Modeling Mineral Size Reduction in The Closed-Circuit Ball Mill at The Pine Point Mines Concentrator (1981)
ABSTRACT
Finch, J.A. and Ramirez-Castro, J., 1981. Modelling mineral size reduction in the closed-
circuit ball mill at the Pine Point Mines concentrator. Int. J. Miner. Process., 8:
61--78.
INTRODUCTION
M o d e l l i n g of c l a s s i f i c a t i o n a n d c o m m i n u t i o n u n i t s f o r c i r c u i t e v a l u a t i o n ,
c o n t r o l a n d s c a l e - u p s t u d i e s has s e e n a m a j o r e f f o r t in t h e l a s t t w e n t y years.
U s u a l l y t h e average, o r overall, p e r f o r m a n c e is m o n i t o r e d . F o r h o m o g e n e o u s
feeds (i.e. n o p a r t i c l e t o p a r t i c l e v a r i a t i o n i n p r o p e r t i e s s u c h as d e n s i t y or
h a r d n e s s ) this is a p p r o p r i a t e . H o w e v e r , f o r h e t e r o g e n e o u s feeds, s u c h as
P b / Z n ores, i n d i v i d u a l m i n e r a l b e h a v i o u r is m o r e a p p r o p r i a t e .
M o d e l l i n g i n d i v i d u a l m i n e r a l b e h a v i o u r in c l o s e d g r i n d i n g c i r c u i t s has
b e e n d e s c r i b e d b y C a m e r o n e t al. ( 1 9 7 1 ) , L y n c h ( 1 9 7 7 a ) a n d F i n c h a n d
COF
RMD CF
B A L L MILL
3.5x4.9 m
Fig. 1. The No. 3 grinding circuit at the Pine Point Mines concentrator. (Three out of
five cyclones were in operation at time of sampling; all streams identified were sampled.)
R ( x , r ) = R ( x , O ) exp ( - K r ) (1)
where R (x, T), R (x,0) is the cumulative percent retained above size x at
time r and 0, respectively, where r is the mean residence time given by:
VBH volumetric ball mill hold-up of slurry
v= - (2)
VFR volumetric feed rate of slurry to ball mill
By analogy with the relationship between the discrete size rate-of-breakage
parameter and particle size, it is assumed that:
K = Cx n (3)
As written, the equations apply to the overall size reduction. The sub-
script m will be used to denote an individual mineral, so equations
analogous to eqs. I and 3 can be written:
and
Km = Cmxnm (5)
Hence r and the ball mill feed and discharge size distribution must be
measured. Failing a direct measure of r, it can be estimated from VBH (as-
sumed constant) and VFR determined from a mass balance.
EXPERIMENTAL PART
Plant tests
A mass balance around the cyclone was conducted which gave a better
than 0.95 correlation coefficient for the circulating load estimate (Finch
and Matwijenko, 1977). The circuit was then balanced and data adjusted
using the scheme described by L y n c h (1977b) extended to adjust mineral as-
says. Two additional constraint equations are required to balance mineral
flows, namely: (1) mass of mineral entering circuit equals that leaving; and
(2) mass of mineral entering ball mill equals that leaving, i.e. Rm(0,T ) must
equal Rm (0,0). The mineral mass flows must be balanced across the ball
mill, for, if R m (0,r) 4= Rm(0,0), the calculated rate-of-breakage parameter,
Kin, becomes distorted especially as x + 0. Table I gives some data on the
balanced circuit.
TABLE I
mtph Fresh feed (%} Ball mill feed (%) Circulating % w/w solids in r s.g. ball
load ratio ball mill feed mill feed
PbS ZnS FeS2 PbS ZnS FeS~ (rain.)
154.2 1.9 8.7 14.1 6.8 12.6 32.9 1.63 70.1 3.11 3.63
190.3 1.8 6.6 6.3 9.3 12.3 27.1 2.00 73.6 2.18 3.50
154.2 34.3 47.5 94.2 39.4 49.9 34.68 36.68 62.90 20.57 37.89
190.3 29.8 39.6 93.9 34.3 40.6 28.77 33.18 52.80 23.39 35.39
The volumetric ball mill hold-up of slurry was calculated from mill ge-
ometry. The mill is 3.5 m by 4.9 m. Assuming ball filling to the lip of the
overflow, bulk ball filling was estimated to be 18.35 m 3 ( - 40% mill
volume). Assuming the balls pack to give 38% voids (Taggart, 1945) and
slurry filling is 120% of void volume, the mill hold-up volume is 8.37 m 3 or
18% of mill volume. From the volumetric flow rate of cyclone underflow
slurry, r can be calculated; r is given in Table I.
cient greater than 0.95 on the circulating load estimate. The size distribu-
tion data was then adjusted (Lynch, 1977b).
A wide range of operating conditions was represented by these data sets.
Table II gives data for the lowest (489 m t ph ) to highest (674 m t p h ) fresh
feed rate. The range in circulating load was 1.75 to 6.45 and in % -28 mesh
in ball mill feed, 68.6 to 78.7. Percent solids of ball mill feed remained ap-
p r o x i m a t e l y co n s t ant at 75% w/w.
Assuming a hold-up volume of 18%, as at Pine Point, the VBH is 14.5 m 3.
The specific gravity of ball mill feed was assumed to be 3 and r was
calculated. The range in r was 0.37 to 1.32 min.
TABLE II
Operating conditions at the low (489 mtph) and high (674 mtph) tonnage Gibraltar data
Laboratory tests
During the sampling at 154.2 m t p h at Pine Point, sufficient ball mill feed
and rod mill discharge was cut (-= 30 kg) for l aborat ory batch grinding tests.
Some of the properties of these t w o materials are given in Table III.
A 16.5 cm × 20.3 cm Abb~ porcelain grinding jar rot at ed at 68% of its
critical speed was used. Grinding conditions were based on a void volume of
12% of mill volume (Le Houillier and Marchand, 1977) and slurry filling of
120% o f void volume (cf.assumption for plant mill). Details are given in
Table IV. The r od mill discharge (RMD) and ball mill feed (CUF) samples
had a specific gravity of 3.08 and 3.53, respectively, giving required sample
masses of 1000 g (RMD) and 1150 g (CUF). These samples were obtained
on a spinning riffler. Grinding times were 1 to 12 rain. with a fresh sample
for each time. The products were w e t / d r y screened from 28 to 400 mesh in
TABLE III
Comparison of ball mill feed (CUF) and rod mill discharge (RMD) samples used in
laboratory tests
% +65 mesh % -200 mesh % PbS % FeS2 % ZnS specific gravity
TABLE IV
Size (cm) No. % mill (of total vol.) % mill cm 3 % voids cm 3 % solids
R ( x , t ) = R ( x , O ) e x p [ - b t p] (7)
RESULTS
Plant tests
I I I I
/
•S .5 o
mtph "g~rain /
d a154.2 3.11 ~/
/° n=1.043 -+.026
3 /
E
.02 i I i i
20 50 100 200 500 1000
2 I I t I I I I I [
E 1
cc ~ G i b r a l t a r Data
.~ .2
~ K(x): Cx
C= .00389 -+.00041
.1 n = .747 -+.020
I F I I I
24 •
c~
20 •
16
16 20 24
Fig. 4. Measured vs simulated % -200 mesh in ball mill discharge for Gibraltar data.
Laboratory data
Figure 7a, b shows the disappearance plots for ball mill feed overall and
galena. Note the deviation from first order at the coarser sizes. E x c e p t for
galena, at sizes less than 65 mesh p was generally in the range 0.9 < p
69
i I r I /
?,
o /
.S o PbS o //A
o CaI-Dol /
°/ / v
~; --- Overall
oJ
//8
o~ .1 I/ v
CC /o / / o ~ ZnS
// ~ FeS 2
t//
r~ Q
¢J
.01 I I I
20 50 100 200 500 1000
11] 2 mtph ~ 18
u. " 1C
i 1 i i i i i ~ i 1 i i L ~ i
270/400 150/200 65/100 35/4B 270/400 1501200 551100 35148
Particle Size ,mesh Particle Size, mesh
Fig. 6.a. Simulated (full line) and measured (symbol) mass frequency size distribution of
PbS and FeS 2 in the ball mill discharge at 154.2 mtph fresh feed rate. Assumption is
K m = K. b. As (a) but for 190.3 mtph fresh feed rate case.
100 ~ I I I I I 100 J I I I I I
50
I ~ ° ~
•
° ~ °
+200 Mesh
p= 1.03
°
50 " ~ O ~ o
o ~......~..
b •
b= . 0 7 - +200
p=0.98
Mesh
+ 6 5 Mesh
\ •
o WRA L L ~:
5
\
+65 Mesh
"
p = 1.09
o,. • b= .27 o,, ~ p= 1 . 2 2
• ~ \
T i m e , t, Min. T i m e , t, Min.
Fig. 7.a. Disappearance plots for +28, +65 and +200 mesh overall using ball mill feed
(CUF) sample, b. Disappearance plot for +28, +65 and +200 mesh galena using ball mill
feed (CUF) sample.
1
i j i I
"7
E .5 o
-,- o Rod Mill Discharge o
.2
E e
¢j
.02 i r ~ i
20 50 100 200 500 1000
Particle S i z e , x, m i c r o n s
1 __
I I l [ l
.1
/
,/ •
.~ .05 ]"'+ •
0 f •
., o
.02 L t £ I ;
10 20 50 100 200 500 1000
Particle S i z e , x, microns
Fig. 9. Mineral cumulative-basis rate-of-breakage parameter, Km, from laboratory tests
on rod mill discharge and ball mill feed samples as a function of particle size, x.
The trends are similar to those observed for the continuous mill, the
mineral rate-of-breakage versus x lying parallel to the overall and pyrite
being the hardest c o m p o n e n t . T he difference between rod mill discharge
and ball mill feed samples appears small. Although galena is difficult to
quantify with a single parameter, comparing the b and p parameters with
the overall (Fig. 7a, b) shows galena is similar to the overall.
From the evidence presented, mineral size reduction through the closed-
circuit ball mill at Pine Point can be a ppr oxi m at ed by a plug flow material
transport model with an overall cumulative rate-of-breakage parameter.
Combining this with the cyclone modelling scheme proposed by L ynch
(1977a) and Finch and Matwijenko (1977) a simulator describing mineral
behaviour can be constructed. The two unit models, derived from data at
the 154.2 m t p h test, are:
Ball Mill:
R m ( X , T ) = R m ( x , 0 ) exp (-0.0009xl'°4T) (10)
Cyclone:
Ym = (1 - 0 . 3 1 ) ( 1 - exp [-0.693(~/Rs0m ) ~ " + ] } + 0.31 (11)
.,,o / : / PbS I , v
m
o. o CYCLONE OVERFLOV~
60 / Measured
FeS2 ,/ o symbols
Simulated
40 /o -- Ym m o d e l
"~ Cal-
(O Dol o
-- - - Ym measured
0 I I I I I
400 200 100 48 28
DISCUSSION
Figures 2 and 3 show that the plug flow approximation with cumulative-
basis first-order kinetics leads to a simple closed-circuit ball mill size reduc-
73
Mineral size r e d u c t i o n
Laboratory-derived kinetics
CONCLUDING REMARKS
CONCLUSIONS
ACKNOWLEDGEMENTS
The authors wish to thank the personnel at the Pine Point Mines con-
centrator for their enthusiastic help in sample gathering and Gibraltar Mines
for making data available. Funding was partly from a Mexican government
grant to Ramirez-Castro, the Natural Sciences and Engineering Research
Council of Canada, the Quebec Department of Education (FCAC programme)
and Dept. of Supply and Services, Canada.
REFERENCES
Austin, L.G., 1973. Understanding ball mill sizing. Ind. Eng. Chem. Process Des. Dev.,
12: 1 2 1 - 1 2 9 .
Austin, L.G., 1971/1972. A review -- introduction to the mathematical description of
grinding as a rate process. Powder Technol., 5: 1--20.
Cameron, A.W., Kelsall, D.F., Restarick, C.J. and Stewart, P.S.B., 1971. A detailed
assessment of concentrator performance at Broken Hill South Limited. Australas. Inst.
Min. Metall., Proc., 240: 53--65.
Finch, J.A. and Matwijenko, O., 1977. Individual mineral behaviour in a closed grinding
circuit. CIM Bull., 70: 164--172.
Furuya, M., Nakajima, Y. and Tanaka, T., 1971. Theoretical analysis of closed-circuit
grinding system based on comminution kinetics. Ind. Eng. Chem. Process Des. Dev.,
10: 449--456.
Gaudin, A.M. and Meloy, T.P., 1962. Model of a comminution distribution equation for
repeated fracture. Trans. AIME, 223: 43--50.
Harris, C.C., 1971. The effect of time on batch grinding. Powder Technoh, 4: 57--60.
Hathaway, R.E. and Gunthals, D.L., 1976. The continuous measurement of particle size
in fine slurry processes. CIM Bull., 69: 64- -71.
Himmelblau, D.M., 1970. Process Analysis by Statistical Methods. Wiley, New York, N.Y.
118 pp.
Hodouin, D., B~rub~, M.E. and Everell, M.D., 1978. Modelling industrial grinding circuits
and application in design. CIM Bull., 71: 138--146.
Horst, H.E. and Bassarear, J.H., 1976. Use of simplified ore grindability technique to
evaluate plant performance. Trans. AIME, 260: 348--354.
78