Chapter 2 Working With Project Teams
Chapter 2 Working With Project Teams
2
WORKING WITH PROJECT TEAMS
PROJECT TEAM
Project teams must be organized to carry out the work necessary to complete
engineering and construction projects. Team members are crucial to the success of the
project. The project manager depends on the team because he or she does not usually
have the expertise to do all the work needed to complete the project. For any group, there
must be a leader to guide the overall effort. The project manager also acts as a facilitator
Project teams are made up of all project participants, including house staff and
achieve the shared goal of completing the scope, budget, and time constraints. The
management.
The project manager must build and lead an effective project team for a successful
project. Team building is a process of influencing a group of diverse individuals, each with
its own goals, needs, and perspectives, to work together effectively for the benefit of the
project. Team efforts should be more than just the sum of individual endeavor. Every team
influence their team members to do what they need to do to get the job done.
TEAMWORK
Teamwork is not a new concept; it is only being re-examined after two decades of
and downsizing of businesses have also given renewed emphasis to teamwork, as the
work to the completion of projects. Everyone agrees that it is significant; the real challenge
Teamwork begins with the project sponsor who determines goals, objectives,
goal. When handling several small tasks, the project manager is typically asked to share
team members with other project managers. The length of the project is usually limited,
with little interaction between the project manager and the team members. Often team
members are professionals who are recruited from outside sources to perform a particular
role or function.
Since the project manager is usually responsible for overseeing several projects,
it is often difficult for him or her to give the required attention to each project, which
complicates scheduling and management of resources. Only limited workers can be
provided on small projects. In this form of the work environment, the willingness of the
project manager to work with the different divisions within his or her company to get
people to work on the project is critical in completing the tasks on schedule and within the
budget.
to each project. As a result, time's lost when team members are waiting for details. Since
small projects have limited durations, there is often a lack of time for thorough preparation
and in-process problem correction. The learning curve for the workers begins to climb
While managing several small projects does not have the formality of managing a
meetings.
Once the project moves from design into the building, the owners, designers, and
contractors' teams' work must be combined into a collaborative effort. Each of these
teams has its own goals, the diverse skills that each group possesses must converge into
an overlapping setting, as illustrated in Figure 2-1. Each triangle in Figure 2-1 is a team.
While each team performs a different role, each team must cultivate an attitude of mutual
ownership of the project. The construction of the team and the collaboration that began
Regardless of the size and number of teams, there must be a single project
manager to make final decisions and maintain a focus on the project. The project manager
of the owner has ultimate responsibility and final authority for the overall project. Project
managers are responsible for overseeing the lower level of the teams responsible for the
technical design and development of the project serve on the owner's project
management team. As shown in Figure 2-1, there is a project manager for in-house
design, a project manager for each design contractor, and a project manager for each
construction contractor. Below these managers are the lower levels of the teams headed
DESIGN TEAMS
The members of the design team are chosen based on their expertise required for
a specific project. The group consists of individuals with diverse backgrounds, including
aided design and design (CADD), project management individuals (cost control,
Each design team shall have a representative of the sponsor, who may be the
project manager of the owner or appointed by the project manager of the owner. This
person must convey the organizational policies and funding limitations of the sponsoring
company to the project team. He or she must have the duty and the power to operate on
behalf of the sponsoring organization. The sponsor's representative plays a crucial role
in discussing concerns related to project conditions and expenses that will affect the
sponsor's company after the project is finished when the sponsor uses it. It reviews and
scope, budget, and schedule before the commitments are made. Unfortunately, the
in trouble. The early involvement of the sponsor's representative can avoid future
problems. The project manager must make this person feel like he or she is part of the
project team.
project manager and his or her supervisor will evaluate the project's need to determine
the discipline skills required and the staff required. The meeting would then be scheduled
with the manager of the relevant discipline managers to request the members of the team.
The project manager always wants the best and most qualified workers assigned
to his or her project. However, the assignment of team members is often based on who
is available at the time assignments are made. If the project manager feels a person
assigned to the team lacks the required skills, the project manager must act as a coach
to assist the team member and make arrangements for additional training to ensure the
CONSTRUCTION TEAMS
different organizations are recruited and assigned to the construction project. Organizing
their efforts is complicated, even though they all work for the same organization. The
project manager of the construction team must remind the team that establishing long-
With all the diversity involved in the building project, people need to be handled so
that they can work together successfully to achieve the goal. These require professional
accomplishing a significant objective. Common sense and versatility are essential for
working with construction teams. The secret to a good construction project is well-trained
construction managers.
TEAM MANAGEMENT
A team must have a well-defined goal with shared goals, objectives, and
strategies. The project manager must learn about the needs of the team members and
promote team involvement. Most employees want to do what must be required of them
and do their job if there are clear instructions. Open and truthful relations are significant
to promote honesty and support for one another. The project manager must ensure that
individuals must have primary responsibility for discreet work. The team needs to have a
shared objective of building a team with a clear idea of what they're going to do and when
When collaborating with team members, the project manager must cross a wide
variety of organizational frameworks to grow the project team into a coherent community.
These must be achieved quickly, considering the limitations imposed by others. People's
skills are vital to the successful management of team members. The project manager
must create a friendly atmosphere that encourages the team to work together and; must
motivate the team to perform well. In addition to planning, scheduling, and overseeing the
project, the project manager is responsible for resolving team members' disputes.
The project manager must set up a management system to complete the project
with the planned specifications. The project manager is required to oversee the activities
of the project within a given framework, budget, and schedule. A variety of decisions must
be taken during team meetings and the process used will have a direct effect on team
results. The project manager must cultivate a style of leadership that is valued and
embraced by the decision-making team of the project. The decision may resolve the best
way to build or generate sketches, while the other may involve producing ideas and
Developing a culture where every team member feels that they are part of the team
and wanted by the members is necessary to a successful team. The conduct and
leadership style of the project manager has a direct effect on the team. The project
manager must have a high degree of integrity and a sense of justice and honesty in
working with team members and those who are not part of the team. The project manager
is a role model for the team in many respects. It is difficult for people to be highly motivated
and efficient when they have a minimal appreciation for their leader.
dedicated workers want, and need, to be informed. Daily meetings of the group are
necessary. There can be different meetings between key team members to exchange
comprehensive information, but a daily weekly team meeting must have to share status,
make decisions, and record data. Since team members are often located in various
team unity. A well-defined scope for the team directs the progress of work; and sets out
TEAM BUILDING
be initiated early in the process and must be constant throughout the life of the project.
Experienced engineers and project managers all agree that teamwork is required, but the
real question is, "How does one organize a successful team?" Effective communication
is essential for team building. The project team cannot work when there are
project. Team building begins with the sponsoring company, with the project charter and
mission statement. The project sponsor must be aware of the goals that have been set,
and he or she must be explicit about their commitments. The project sponsor must have
other third-party participants. Everyone on the project must know that the project sponsor
pays for all and is thus the shared client to all parties.
development, but sometimes that's not the case. Often the project manager must enable
the project sponsor to recognize the value of sequencing work and the effect of decisions
that need to be taken in the design and construction of the project. There must be
cohesion in the project team from the first day of the project. The high turnover of team
members causes a lack of time in training new people and a loss of awareness of previous
costs and construction techniques that are extremely beneficial during the design
process.
Many private-sector ventures are funded by credit institutions. Too often, for these
beginning of the project. For example, the purchasing agent is a significant participant in
a project that must purchase large quantities of material or main equipment. Early
involvement of the person who will be involved in issuing purchase orders, tracking the
shipping dates and delivery dates of the vendors, and receipt of the purchased material
and equipment has a significant impact on meeting the project installation deadlines.
The keywords for team building are pressure, responsibility, honesty, kindness,
respect, and communication. Engineering and construction projects usually require a tight
schedule that puts pressure on the project team to complete their work as soon as
possible. These require cooperation between the team member who must assume
responsibility and carry out their work in the most expeditious manner. The ground rule
should be, "Everyone is a contributor and winner on a successful team." The team must
stop worrying about the 1% that is wrong and focus on the 99% that is right. The project
team must have open communications and avoid hiding errors and pointing the blame. A
successful team can do a successful project and have fun doing it.
weekend retreat for team members, including their family members. The retreat is usually
held in a resort environment to encourage team members to engage with their interests.
These make it possible for all to understand that team members have similar goals and
shared interests. For example, recognizing that others on the team have children with
exceptional talents or need to take care of elderly parents will provide a sense of bonding
and mutual respect, which is the first step towards successful team building.
MOTIVATING TEAMS
hierarchy of needs. It is the quest to satisfy people's needs that drives or motivates
people. The needs include basic physical and psychological needs, which are perceived
in the human mind and complacent by material things. The theory has been used by
managers, as well as educators, to try to understand why people behave the way they
do, how to motivate them, and how to enlist their commitment. Figure 2-2 is a graphical
The project manager must use his or her skills to determine the specific needs of
the team member. It is not easy to identify people's needs in the day-to-day work
team member may be concerned about having adequate time to attend school for a child
example, personal finances or family problems can quickly change a person's needs.
Each project manager must devise a way to identify the needs of the members of his
identified, an appropriate
CONFLICT MANAGEMENT
team members are unavoidable. Conflicts can occur concerning the allocation of
decreased results, and team dissension. Conflicts may occur, therefore, different
agendas among team members, since some team members may work for a variety of
companies. For example, members of one or more design firms, as well as one or more
construction companies, maybe part of the owner's project management team. Similarly,
the project manager of the design team may have team members who are in-house, as
well as design contractors who are hired to conduct special parts of the design. The
construction contractor's project manager typically has a wide variety of staff from both
They must understand that disagreements are often the result of changes, such
of meetings that are not communicated to other team members. The project manager and
team should review each dispute resolution process to capture lessons learned, both
positive and negative, for the benefit of potential project work. To manage the conflict, the
project manager must use techniques to deal with the disagreements, both technical and
personal, that inevitably arise between the team member. Project managers and team
members may feel that arguments are pessimistic, that they should not occur, that they
are caused by troublemakers, or that they should be prevented. However, all project
participants should understand that disputes are inevitable and may actually be helpful if
they are resolved in an acceptable manner. Conflict resolution will lead to creativity and
to fix a disagreement, and it doesn't solve the problem. Withdrawal is a passive solution
to solving a problem, which only momentarily delays the imminent recurrence of the
management technique. However, adopting this method for a moment prevents the
dispute by easing one or more of the parties involved in the conflict. The smoothing
resolution. This strategy includes discussions between the parties to achieve an effective
agreement. The parties to the conflict make trade-offs that sometimes fall short of ideal
solutions. Too often, compromise does not result in an outcome and gives rise to the
involvement of all parties involved. In certain cases, it might be appropriate for the project
of the team.
DEVELOPING A CONSENSUS
There are often several solutions to the problem, each of which can produce the
same result. The members of the team could not agree on any specific solution. Some
participants may be indifferent to a certain solution, while others may have deep feelings
regarding a solution. The project manager must collaborate with the team to build a
consensus on the option of the best solution. In these cases, the project manager must
and indecisions, the project manager must lead the team. Conflict must be acknowledged
attacks, hostile remarks, or defensive acts. Team members should circumvent personal
project.
TEAM CONDUCT
The team is most clearly described as two or more people who, through working
together, do more than work separately. Projects usually consist of several design and
development packages, each with unique roles and responsibilities. Specific rules are
The goals of a particular team accurately set out the project criteria of each specific
group. For example, the safety team should be aware of the need to keep health and
work.
In addition to understanding the targets, the team must also know how it is
supposed to function. The design and development teams should be aware from the
outset of the scope of their powers and the ability to act. For example, some groups may
only be able to solve problems, while others are only needed for regular evaluations, and
others exist to make decisions. Each project requires a set of rules to be followed.
Disorder and agitation are likely to occur without guidelines. Laws should not be
considered restrictive. Instead, a good set of rules allows the team members the ability to
carry out their work because they know what is required of them. Generally, when the
each team should know where it fits into the overall scheme of the other operating teams.
The leader of each project team must answer questions about the relationship of the
internal team. Team members must demonstrate confidence and respect for other team
members, but close personal friendship is not always required. Teams also work based
between members are the responsibility of the senior management. The personal values
of individual team members also have a vital role to play in the project team. Each team
member brings his or her collection of beliefs and morals to the team. Team members
should not expect to compromise their principles and ideals. The team leader must
LEARNING ASSESSMENT
1. The project manager must ensure that the primary responsibility for discreet work
work items in the project, describe the methods to ensure that there will be no
2. You are the project manager of a newly formed team. Suppose you feel that one
of the team members lacks the skills needed to perform the work. Discuss the
methods you would use to help the team member ensure that their work meets
your expectations.
3. The conflict between team members is often the result of changes. List changes
during a project that could potentially lead to disagreement. How would you try to
Reference Material:
Project Management for Engineering and Construction 2nd Ed., Garold D. Oberlender