Testing & Commissioning Checklist - HVAC Pumps

The document provides testing and commissioning procedures for chilled and condenser pumps. It lists documents required prior to testing, including calibration certificates and testing forms. It then provides a start-up checklist to check the availability of power, water supply, and pertinent pump data. The testing procedure involves measuring megger readings, configuring motor data to variable frequency drives, obtaining pressure and flow readings, and checking voltage and current against motor specifications.

Uploaded by

JM Arcilla
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
475 views2 pages

Testing & Commissioning Checklist - HVAC Pumps

The document provides testing and commissioning procedures for chilled and condenser pumps. It lists documents required prior to testing, including calibration certificates and testing forms. It then provides a start-up checklist to check the availability of power, water supply, and pertinent pump data. The testing procedure involves measuring megger readings, configuring motor data to variable frequency drives, obtaining pressure and flow readings, and checking voltage and current against motor specifications.

Uploaded by

JM Arcilla
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 2

TESTING & COMMISSIONING PROCEDURE

PROJECT: WORLD WIDE PLAZA

DOCUMENTS REQUIRED PRIOR TO TESTING AND COMMISSIONING OF CHILLED AND CONDENSER PUMPS
1 Calibration certificate of clampmeter, tachometer and insulation tester
2 Testing and commissioning form.

START-UP CHECKLIST FOR PACO PUMPS


Before starting the equipment, check the following:
1 Check availability of permanent power prior to starting the pump.
2 Check availability of sufficient water supply prior to running of pump.
3 Check all pertinent data prior to testing ( capacity in terms of gpm or lps, head in terms of feet
or meters, motor rating, electric data as per name plate: power input, kw or HP, voltage, V;
frequency, Hz; phase; FLA)
4 Suction and Discharge valves condition
5 Suction and Discharge gauges
6 Check the alignment of the pump and motor
7 Check the motor rotation

TESTING PROCEDURE OF PACO PUMPS

1 Conduct megger reading for each pump motor. (Isolate if the controller is VFD)
2 Configure the motor data to the VFD, once completed, start-the pump based on
the desired speed.
3 Obtain pressure reading by means of suction and discharge gauges (psi), first at
fully-closed valve then at fully open valve
4 Obtain a reading on line voltage: Line 1-2, Line 2-3, Line 3-1 by the aid of a clamp meter
to verify the voltage rating.
5 Obtain ampere reading: Line 1-2, Line 2-3, Line 3-1 by the aid of a clamp meter to check if it is
within the range of the FLA of the motor.
6 Obtain capacity in terms of gpm by plotting the acquired TDH in the pressure gauges
to the performace curve of each pump.
NG & COMMISSIONING PROCEDURE

STING AND COMMISSIONING OF CHILLED AND CONDENSER PUMPS

RT-UP CHECKLIST FOR PACO PUMPS

ng ( capacity in terms of gpm or lps, head in terms of feet

TING PROCEDURE OF PACO PUMPS

e 2-3, Line 3-1 by the aid of a clamp meter to check if it is