LOADING & UNLOADING

PROCEDURE
DOC NO MKS-QHSEM-013
Page 1 of 2
\

PT. SORIK MARAPI GEOTHERMAL POWER

WORK PROCESS
LOADING & UNLOADING
PROCEDURE
DOC NO MKS-QHSEM-013
Page 2 of 2
\

PT. SORIK MARAPI GEOTHERMAL POWER

WORK PROCESS
LOADING & UNLOADING
PROCEDURE
DOC NO MKS-QHSEM-013
Page 3 of 2
\

PT. SORIK MARAPI GEOTHERMAL POWER

WORK PROCESS

LOADING & UNLOADNG WORK PROCEDURE


LOADING & UNLOADING
PROCEDURE
DOC NO MKS-QHSEM-013
Page 4 of 2
\

PT. SORIK MARAPI GEOTHERMAL POWER

WORK PROCESS

Submitted By, Review By, Acknowledge By, Distribution


SGI : SOFT COPY
MKS : SOFT COPY
LOADING & UNLOADING
PROCEDURE
DOC NO MKS-QHSEM-013
Page 5 of 2
\

PT. SORIK MARAPI GEOTHERMAL POWER

WORK PROCESS

Antoni Sinaga Jhonny Lento Sentosa


HSE Dept Site Engineer Director
No Rev Issue Date Brief of Revision
LOADING & UNLOADING
PROCEDURE
DOC NO MKS-QHSEM-013
Page 6 of 2
\

PT. SORIK MARAPI GEOTHERMAL POWER

WORK PROCESS

 SCOPE

This procedure for according to procedure of loading and unloading material , for construct
Civil Work Phase III

 REFERENCE
LOADING & UNLOADING
PROCEDURE
DOC NO MKS-QHSEM-013
Page 7 of 2
\

PT. SORIK MARAPI GEOTHERMAL POWER

WORK PROCESS

o SOP loading & unloading material

 PREPARE EQUIPMENT OF TRUCK

 Prepare PTI ( Pree Tip Inspection ) form

 Ensure all equipment already inspect by Company


LOADING & UNLOADING
PROCEDURE
DOC NO MKS-QHSEM-013
Page 8 of 2
\

PT. SORIK MARAPI GEOTHERMAL POWER

WORK PROCESS

 LOADING MATERIAL

 Positioning the Pick up / DUMP TRUCKin AT lifting area (according to plan)

 Opened the rear door of the pick up / Dump truck completely

 Perform material that over weight filling into a dump truck using an excavator / shovel

 Using hand glove for lifting material


LOADING & UNLOADING
PROCEDURE
DOC NO MKS-QHSEM-013
Page 9 of 2
\

PT. SORIK MARAPI GEOTHERMAL POWER

WORK PROCESS

 Signal man must be e can see by driver


 The load must accordance with the carrying capacity
 Close the back door of the pick up / dump truck correctly

 During travelling the road must accordance with the journey management plan
(out of the loading area)

 UNLOADING MATERIAL
LOADING & UNLOADING
PROCEDURE
DOC NO MKS-QHSEM-013
Page 10 of 2
\

PT. SORIK MARAPI GEOTHERMAL POWER

WORK PROCESS

 Positioning dump trucks / pickups on hard and flat areas (according to plan)
 Open the back door of the dump truck / pick up

 Unload material slowly

 Ensure driver can see flagman

 Close the back door of the pick up properly


LOADING & UNLOADING
PROCEDURE
DOC NO MKS-QHSEM-013
Page 11 of 2
\

PT. SORIK MARAPI GEOTHERMAL POWER

WORK PROCESS