Wsbcpa 1B310 Aa
Wsbcpa 1B310 Aa
Wsbcpa 1B310 Aa
Prepared/Checked By
Doug Howe/Johnathan Line
Detailed By:
Concurrence/Approval
Signatures:
Design Engineering
Supervisor:
Other Approvals
/Concurrences (as
required):
STA:
Travis Cruzan
Purchasing:
STANDARD NOTES:
FOR CURRENT RELEASE STATUS, SEE THE WERS ENGINEERING NOTICE.
The terms weld, welding, braze, etc. pertain to GMAW, hybrid laser-GMAW and Brazed (GMAB and Hybrid Laser-
GMAB) joints as the terms are pertinent. This Weld Specification (WS) is a supplement to the released drawing of a given
part, and all requirements herein must be met in addition to all other requirements of the part drawing unless specifically
approved in writing by the responsible Ford Product Development Design and Release (D&R) Engineer & Manager,
Product Development (PD) department welding Subject-Matter Expert (SME)/Design Leader (as appropriate), and
Supplier Technical Assistance (STA) and/or Ford Welding Manufacturing Engineer & Manager. No commercial or other
agreements (e.g., Statement of Works (SOW)) will supersede or exclude the requirements of this specification if
specification is applied to any Ford Motor Company GMAW, hybrid laser-GMAW, GMAB and/or Hybrid Laser-GMAB
joined product. Any approved and signed “Exceptions” to this document should be detailed on the Ford or Supplier Final
Release Detail(s) under the Welding WS callout:
• “Weld/Brazing must conform to WSBCPA-1B310-AA. Except as noted below…”, or
• “Weld/Brazing must conform to WSBCPA-1B310-AA. Exceptions are listed on a Separate Signed Exceptions
Page. See DCP and/or Control Plan."
This Weld Specification is intended to evaluate specific characteristics as a supplement to normal material inspections,
dimensional checking, and in process controls and should in no way adversely influence other inspection operations.
Preparation and submission of an acceptable PFMEA and Control Plan are the responsibility of the manufacturing source.
The manufacturing source will retain the original Control Plan and any later revisions according to Section 7.3 in FAP02-
001. The PFMEA must be reviewed with, and a copy should be provided to, the design responsible Product Engineering
activity and STA/Weld Manufacturing activity.
Definitions of welding terms, procedures, and discrepancies are generally based on those in the American Welding
Society’s (AWS) publication AWS A3.0:2001 “Welding Terms and Definitions”
It is recommended that the supplier have copies of the applicable publications and references noted in Section V available
in his plant’s Quality Control, Manufacturing, Engineering, and/or Product Testing Offices. Applicable information from
these documents is incorporated into this document to the maximum extent possible. Having copies of these documents is
not required.
NOTE: If local Ford Product Development Commodity Activity has an approved specification for use in specific
welding applications, the local requirements supersede the above list.
In case of any conflict between these publications, the following is a list of prioritization from highest to lowest governing
documents:
1) Ford Released Engineering Assembly Detail, then
2) Signed Addendum to this Engineering Specification, then
3) Exception(s) on the Ford Released Engineering Part (Component / Assembly) Detail or Supplier Part Drawing
NOTE: Supplier component details will not take precedence over Ford requirements, then
4) This Engineering Specification: WSBCPA-1B310-AA, then
5) Reference documents.
It is the supplier’s responsibility that sub-assemblies must conform to Sections I.1 Scope of Weld Specification, General
Statement, II.3 Summary of ES Tests and Acceptable Parameters, and III. Test Procedures and Requirements. All PIA
welds either produced at the supplier’s facility, or their supplier's are subject to this document and the specifications noted
in section I. 1 Scope of Weld Specification, General Statement.
Gas Metal Arc-Welding (GMAW) is a process where heat generated by an electric arc generated in a protective gas melts
a consumable electrode (filler metal wire) and work pieces together as shown in Figure 1. This also encompasses Metal
Inert Gas welding (MIG).
Hybrid laser-GMAW welding is a process of forming a metallurgical bond where a laser head is used to heat the joint
and/or wire and/or weld the metal pieces together used in conjunction with GMAW weld head. This includes tandem laser
– welding operations.
Brazing (GMAB and Hybrid Laser-GMAB) is a process of forming a diffusion bond where heat generated melts a
consumable electrode (wire) which binds the work pieces together. Laser can be used to supply the heat.
: Sheet Metal
: Fillet
: Filler Metal Wire Feed
: Filler Metal Wire Coil
: Gas Nozzle
: Electrode Contact
: Active/Inert Gas
: Electric Arc
• The modes of operation shall be limited to Automatic, Semi-Automatic, or Manual welding / brazing (Ref:
Section II.1.2.1 Welding Types this document). The use of Laser seam tracking devices is permissible when
supported by Metallographic evidence (proof of sustainability through cut and etch). The processes used shall
be limited to the following:
- Gas Metal Arc Welding (GMAW i.e. MIG [Metal Inert Gas])
- Flux Cored Arc Welding (FCAW)
- Submerged Arc Welding (SAW)
- Arc spot welding in conjunction with any of the above processes.
- If used as a burn-through spot weld, a clamping pressure system must be incorporated in the welding gun.
- Hybrid Laser and GMAW
- GMAB and Hybrid Laser-GMAB
• The following are additionally approved for repair only:
- Gas Tungsten Arc Welding (GTAW i.e. HeliArc)
- Shielded Metal Arc Welding (SMAW i.e. STICK Welding) with prior approval by Ford Engineering and
STA.
• Semi-Automatic welding processes shall be subject to these guidelines.
- All welds whose start or terminations are to be held to less than ±3.0 or -0 / +6.0 mm are to be made in a
positive locating fixture to ensure their location.
- Wire feed adjustments and voltages are to be secured and/or controlled so that they cannot be changed,
except by designated personnel.
- The welding control is to be of a design that provides a digital readout of both arc voltage and wire feed
speed.
All GMAW and Brazed (GMAB and Hybrid Laser-GMAB) joint designs must be assessed by the responsible Ford
Product Development Engineering Departments (and Manufacturing, where applicable by commodity group) in
I.5.3 Weld Depiction and Callout (Not measured weld, but for CAD depiction only, including reasonable overlap of
weld start/stops, etc.):
I.5.3.1 All welds are to be depicted including tack and temporary on all Ford CAD models and details (e. g. -5005-
sheet 2) [includes CAD data provided by suppliers]. Welds are to be depicted at minimum length. Weld stops
and starts must be depicted.
I.5.3.2 Weld fill will be depicted as shown (ref: Figures 4 through 9). Depictions reflect actual weld plus a clearance
allowance. See the boxes below Figures 8 and 9.
I.5.3.3 Weld starts and stops are to be depicted using an equilateral triangle ( ).
Figure 2 Figure 3
T1
Figure 4 Figure 5 T1
T1
"A" + T1
Figure 6
Figure 7
R = "A"
R = "A"
T1
"A" + T1
Figure 8 Figure 9
"A"
MIG, MAG, and GMAB: "A" is the greater of 5.0 mm or T1.
Hybrid Laser GMAW and Hybrid Laser-GMAB – "A" is the greater
of 3.0 mm or T1.
Joint symbols shall be in accordance with Ford Engineering CAD and Drafting Standard D-3 (Welding Symbols and
Specifications):
MS Mild Steels, Hot and Cold Rolled, Low Carbon WSS-M1A365-A11 – A15, A20-A23
Check commodity material First Pick List(s) for appropriate material usages
Notes:
1) DP, Trip and Boron steels are included in this Engineering Specification within a limited applicability. The use of
these materials needs to be verified with the relevant Engineering Departments on a case-by-case basis.
NOTE: Particular care must be taken for Dual Phase steels grade 780 DP and above as well as TRIP,
Martensitic, and Boron steels due to significant HAZ softening effects relative to base materials and weld
wire strengths.
2) WSS-M99P39-A1/A2/A3/A4 performance specification must be called out with these Boron steels.
3) Seats: Global Seat Engineering materials selections are performed in conjunction with tier 1 and 2 seat
supplier steel strategies due to commercial considerations. However, all steels must meet all static, dynamic,
and durability requirements for life of product (10 years/150k miles)
Any base sheet metal needs the approval from the relevant Materials Engineering, and PD (Core PD is default) Engineering
Departments and as applicable, Manufacturing.
The text of the referenced Ford Material Specifications is available at the following web link:
http://www.mats.ford.com/mats/scripts/spec_by_mtlCat.html, Metals 1A-99A.
GMAB and Hybrid Laser-GMAB wire to comply with WSB-M4A177-A* or ISO 24373:2009 Welding Consumables –
Solid Wires and Rods for Fusion Welding of Copper and Copper Alloys-Classification.
- Wire usage is limited to CuSi3 type wire (AWS) or CU 6560 (ISO). Maximum Si content is 3.0% for corrosion reasons.
NOTE:-
- Use of alternate weld/brazing wire may be acceptable based on analysis and/or test results. Alternate weld/brazing wire
use is to be noted on the part detail. The use of an alternate wire needs the concurrence of the relevant Product
Development Engineer, PD Technical Expert and STA Engineer, and/or Body and Manufacturing Engineering
Department as applicable. (Core PD is default).
Weld Wire
Minimum Minimum Minimum
Minimum Wire 2/
Tensile Tensile Yield Welding Wire GMAW
Tensile GMAW 2/
Strength Strength Strength Gas 1/ ISO 1/
Strength AWS and
(MPa) (ref) KSI (ref)(MPa)
(KSI) 5042
310 45 230
See
430 62 350
Table I-6 G 2Si,
490 70 400 ER70S-3, G 3Si1 /
70 or 80 ER70S-6 or G 4Si1
550 80 450 ER80S-G or
G 4Mo
620 90 520
1/
Si content is to be limited to 0.75 % (ER70S-3 / G 2Si) by weight where e-coat is
used. This results in less silicate formation, although it is worse for weld flow
2/
NOTE: Weld wire chemistries must be verified to produce Minimum Tensile Strength.
Other suffixes (e.g. AWS D2) are permissible.
Figure 15
NOTE: In general, Groove Welds (Flare Bevel / Flare-V) are not considered structural (Evaluate in CAE as if not
present). However, they can be considered structural in Seating applications.
Figure 16 Figure 17
Weld Root
L2 T2
Theoretical Theoretical
Root Throat
FIGURE 18
Effective Throat
L1
Actual
Z1 Throat
T1
Gap
T2
Face
Z2 Penetration
L2
FIGURE 19
I.8.3 Weld Length Defects (Reference Figures 20 to 25)
Definitions are from American Welding Society publication AWS 3.0-2001, unless otherwise stated. Types of
defects are:
I.8.3.1 Arc Strike:
A discontinuity resulting from an arc, consisting of any localized re-melted metal, heat-affected metal, or
change in the surface profile of any metal object.
I.8.3.2 Burn Thru:
Holes burned completely through the weld joint and/or base metal. (Engineering Specification definition).
I.8.3.3 Cracks: Surface Cracks, End Crater Cracks
Cracks are fracture type discontinuities characterized by a sharp tip and high ratio of length to width. They
Global Manufacturing Quality
GIS1 Item Number: 25.06
GIS2 Classification: Proprietary
FAF03-150-3 (previously form: 3947-A2) Frame 15 of 61 Version Date: 20090323
Weld Specification: WSBCPA-1B310-AA
Global Gas Metal Arc Weld, Hybrid Laser-GMAW, and Brazing:
GMAB and Hybrid Laser-GMAB
typically result from an non-homogeneous heat distribution in the joint and a subsequent uncontrolled
solidification of molten filler metal.
I.8.3.4 Crater:
A depression at the termination of a weld bead(s) or in the molten weld pool. (Ref: AWS D8.8-2007).
I.8.3.5 Inclusions:
Shall be considered and judged as being porosity (Ref: AWS D8.8-2007).
I.8.3.6 Meltback:
This occurs where the base metal melts back from the edge but does not become part of the weld. This
condition leaves a void between the weld deposit and the base metal. (Ref: AWS D8.8-2007).
I.8.3.7 Melt Thru:
The protrusion of metal through the base metal surface opposite the weld joint location. (Engineering
Specification definition).
I.8.3.8 Notching:
Gouging of the parent metal at the ends or edge of the welded joint (Ref: AWS D8.8-2007).
I.8.3.9 Porosity:
Cavity type discontinuities formed by gas entrapment during solidification or in a thermal spray deposit. (Ref:
AWS D8.8-2007).
I.8.3.10 Spatter
Spatter is defined as filler metal particles that are expelled during the welding operation and do not form a part
of the seam. Spatter - to a certain degree - is considered process typical and cannot be avoided entirely.
However, the occurrence of spatter shall be reduced to an absolute minimum by adjusting the welding process
parameters during the definition of the job characteristic curve in PV-testing. Shielding must be used when
depicted on the part detail.
I.8.3.11 Undercut:
A groove melted into the base metal adjacent to the weld toe or weld root and left unfilled by weld metal.
WELD -
TRAVEL
ANGLE
WELD -
WORKING
MELT-THROUGH ANGLE
FIGURE 20 FIGURE 21
Figure 22
Good weld; notching is less than T1 Bad weld – notching is greater than T1 (1.6 mm in example)
FIGURE 23 FIGURE 24
UNDERCUT
INSUFFICIENT ROOT
PENETRATION
FIGURE 25
I.9.2 Semi-Automatic welding processes shall be subject to the guidelines noted in Section I.3. Process Description.
Personnel involved in weld inspection shall be certified by the supplier as receiving adequate formal training on the
recognition of weld defects, their cause, and effect on the product. Training shall consist of a minimum aggregate of 40
hours. Appropriate visual aids of actual welds should be available for this program and in the inspection area.
I.13.1 For all identified part welds (“CC/ ”,”S”, “K”, “KB”), the supplier will perform weld section and etch analysis
(or root bend or crush for "KB" class welds) to demonstrate compliance with Section II.3.2 Weld Quality
Global Manufacturing Quality
GIS1 Item Number: 25.06
GIS2 Classification: Proprietary
FAF03-150-3 (previously form: 3947-A2) Frame 18 of 61 Version Date: 20090323
Weld Specification: WSBCPA-1B310-AA
Global Gas Metal Arc Weld, Hybrid Laser-GMAW, and Brazing:
GMAB and Hybrid Laser-GMAB
Evaluations – Visual and Cross-Sectional. The section locations are identified and numbered on the part assembly
drawing as follows:
N-CC/ -L/R where:
N Identifies individual number of weld section. "CC/ " welds should be identified and numbered first,
followed by "S", “K”, and "KB" class welds in order of ‘priority’.
CC/ , S, K, KB Designates Classification as "CC/ ", "S", "K", "KB" or "U" (if designated) per I.14.1 through
I.14.6 Weld Classifications / Analysis. Must be present for "CC/ ", "S", "K", or "KB" class welds. Not
required for "U" class welds
L/R/B May be used to designate if only left side [L] and/or right side [R] of part weld section and/or both [B] weld
sections are required. If not called out, assumed to be both sides of the part where geometry is symmetrical.
Where multiple sides are called out, each weld will have a unique weld number.
—-- or Bar or section line (with arrows pointing to side of weld section to be reviewed) drawn thru weld
where section cut is to be performed.
I.14.1 "CC/ " – CC / Inverted Delta welds are those where the DFMEA severity ranking is 9 or 10 (YC). Each weld is
evaluated independently. If multiple weld failures are required for failure, the welds may be classified other than
"CC/ "."CC/ " welds must be evaluated using cut and etch procedures.
I.14.2 "S" Welds – Sensitive welds must be evaluated using cut and etch procedures.
I.14.2.1 "S" welds will be selected based on information from, but is not limited to (if multiple welds are used to
maintain a connection, each weld may be analyzed independently):
I.14.2.1.1 Welds as determined through CAE assessment as needing special considerations including:
I.14.2.1.1.1 During a strength event, the parent metal stress cannot exceed 95% of the ultimate strength of the base and/or
weld materials which would be an indicator of potential weld nugget separation, or
I.14.2.1.1.2 Weld fatigue as determined using the FESafe Verity Weld Fatigue Tool with CAE performance less than
100%, or other Ford approved software with CAE fatigue performance less than 200% of the weld seam
target, or
I.14.2.1.1.3 High stress areas, exceeding 75% of material yield, as defined by CAE Analysis and/or test, proving
grounds, or field failures. Perform a sensitivity analysis using the FESafe Verity Weld Fatigue Tool, where
each end of the effective weld length is shortened and lengthened by the lesser of 9 to 12 mm (as determined
by CAE grid size) or 5% of the total weld length, but not to be shortened and lengthened by more than a total
of 12 mm. If test validation proves shortened and lengthened welds are capable of passing appropriate tests
in adequate sample sizes (absolute minimum of three), the weld may be classified "K" or "KB"
I.14.4 For symmetrical or mirror image welds, if one weld is to be classified “CC/ ", ”S”, "K" or "KB" by above
analysis, the opposite weld will also be classified “CC/ ", ”S”, "K" or "KB". e.g. if a weld to the point three
bracket on the left side is classified "S" per above analysis, then the symmetrical or mirror weld on the point three
bracket on the right side is to be classified "S" also, or
I.14.5 Welds which cannot be viewed or repaired after assembly (closed out welds) are to be considered for “CC/ " or
"S” classification. There must be a method to insure weld presence.
I.14.6 "U" welds: Unclassified – welds that are not classified "CC/ ", "S" or "K / KB".
I.15.1 Inspection frequencies and quantities detailed below in Section II.3 Summary of ES Tests and Acceptable
Parameters are based on a high volume assembly line (about 60 units per hour, 16 to 20 hours per day (2, 8 to 10
hour shifts), and 5 days per week). Frequencies may be increased or decreased when agreed to at by least two of
STA, Product Engineering, and/or Manufacturing based on the quantity of parts produced, and the frequency of
part inspections and analysis (batch / batch size). For “CC/ ” or “S” welds, it is highly desired that inspection
and analysis are completed prior to the supplier shipping the batch that the sample is verifying. Only with STA
and Product Engineering approval, completion of inspection of the batch may be revised such that inspection is
completed prior to assembly of a vehicle or a sub-assembly (module) at the assembly / manufacturing facility
{when applicable}, or at the latest assembled at a Ford facility. Inspection and analysis for “CC/ ” or “S” welds
is not to be reduced such that completed units can be moved beyond the final Ford assembly plant's control prior
to completion of inspection and analysis of the batch.
I.15.2 For Seats reference Section II.3.1.3 Seat Structures Commodities (SS) Frequency and Sample Requirements
below for inspection frequencies and quantities. Note the specific commodity instructions below in Section II.3.
I.15.4 Completion of weld section analysis: Weld section analysis must be completed prior to the end of the next same
scheduled shift; root bend or crush before end of current shift. Sections may be obtained from completed or partial
(front, mid or rear stub) part assemblies as appropriate. Weld sections may be taken from full or partial assemblies
that have been scrapped from the current day’s production for various reasons other than section(s) being
checked.
I.15.5 Inspection frequencies may be adjusted. Appropriate data must be presented reflecting maintenance of an
Occurrence of Cause rank of 2 or less based on 120 calendar / 85 production days of data (or 90 calendar / 60
production days for "S" and "K / KB" welds). The occurrence rating shall be determined by dividing the number
of defects produced by the number of parts manufactured over the 120 calendar / 85 (or 90 / 60) production day
period of time as described in the AIAG FMEA manual, 4th Edition (ref Figure 26, below). The result of this
calculation is occurrence per thousand. The result shall then be cross referenced to the table below.
Global Manufacturing Quality
GIS1 Item Number: 25.06
GIS2 Classification: Proprietary
FAF03-150-3 (previously form: 3947-A2) Frame 20 of 61 Version Date: 20090323
Weld Specification: WSBCPA-1B310-AA
Global Gas Metal Arc Weld, Hybrid Laser-GMAW, and Brazing:
GMAB and Hybrid Laser-GMAB
I.15.5.1 The frequency of inspection of "CC/ ", "S", and "K / KB" welds can be reduced with proof of sustainability
after phase III PSW, for individual lines, if IP-1 level of quality has been established and:
• If supported through a review of the DFMEA, PFMEA, and Control Plan, and
• After more than 120 calendar / 85 production days for "CC/ "; 90 calendar / 60 production days for "S"
and/or "K / KB" welds experience at production rate, and. appropriate data is provided to obtain both Ford
STA and Product Engineering concurrence. This is to be documented through a SREA or other acceptable
written method.
I.15.5.2 "CC/ " weld inspection frequency may be reduced to the “S”, or "K / KB" level, but the classification cannot
be changed on the part detail or any other document.
I.15.5.3 "S" and "K / KB" class weld inspection frequency may be changed to a lower level of inspection, and also may
be reclassified to “K / KB" or "U" respectively. Each reduction in the classification must be addressed
separately.
II.2 In-Process (IP) tests are used to further understand the relationship between significant design and process
characteristics, exhibit sustainability, and to establish a basis for continuing improvement. Tests must be completed with
production parts on an ongoing basis. Sampling plans for both IP testing and evaluation of the significant process
characteristics must be included in the Control Plan in line with this specification. Note specific commodity frequency and
sampling requirements for inclusion in Weld Control Plans. When the process is found to be trending or out of control or
the test acceptance criteria are not met, the reaction plan approved in the Control Plan shall be invoked.
Welded joints that do not meet the requirements outlined in Section II. Summary of Production Validation and In-Process
Tests, and Section III. Test Procedures and Requirements, of this Engineering Specification need to be repaired following
the reworking procedure as outlined in Section IV.2 Repair Methods.
The tables that follow summarize the various PV-and IP-tests and the acceptance parameters for each. They form the basis
on which to develop a complete control plan for these and their related significant process characteristics. The control plan
will include frequencies, sample sizes and reaction plans; see Ford Quality System Requirements, ISO/TS 16949:2002.
c
L
Line 1
Part Flow
a L
a a
b b
b
c c c
Perform as many weld inspections as possible on the same part so as to minimize the number of parts to be destroyed. An
additional operation does not mean an additional part needs to be destroyed, as the additional inspection is to be
performed on the same part.
NOTES: Where multiple tables with multiple fixtures make up a line, inspected parts are to be rotated so as to evaluate
each fixture and combination of fixtures at an equal rate.
Where the same tools are used for multiple shifts, part inspections are to be rotated so that each parts from each shift are
inspected at the same frequency e.g. every other day for two shift operations.
Operation 1 Operation 2
.
b a
c
b
a
c
c a
a b
c
b
NOTE: Where multiple tables with multiple fixtures make up a line, inspected parts are to be rotated so as to evaluate
each fixture and combination of fixtures at an equal rate.
Perform as many weld inspections as possible on the same part so as to minimize the number of parts to be destroyed. An
additional operation does not mean an additional part needs to be destroyed, as the additional inspection is to be
performed on the same part.
Weld LengthandQuality
andlength-> II.3.1.2.1.1
Inspection-> II.3.1.2.1.2
100%Visual check for
BendandPeel
per operation
per model*
per model*
per model*
per month
per month
per month
per fixture
per fixture
per week
per week
per week
II.3.1.2.3
II.3.1.2.3
per shift
per shift
per shift
per line
per line
per day
per day
per day
Remarks
Prototype - to PV
1 / 10 or
CC/ , S, K, 1/50
100% 100% - - - X X X - - - - - - - - - - - - - - - -
& KB 2/100
3/150 …
1/) 2/)
PV to IP: From Run at Rate to Production proveout (10 /5 days of consecutive samples)
1) Each weld / weld segment
CC/ 100% 3 - - - X X X - 1
1) - - X - X X X - - - - - - - - for 10 consecutive
to be analyzed individually.
days w/o failure
Only welds that do not
2)
S 100% 3 - - - X X X - 1
2) - - X - X X X - - - - - - - - for 5 consecutive show sustainablity must
days w/o failure continue be analyzed until
2) sustainability is
K & KB 100% 3 - - - X X X - 1
2) - - X - X X X - - - - - - - - for 5 consecutive
demonstrated for the
days w/o failure
appropriate period of time.
2)
Unclassified 100% 3 - - - X X X - 2) - - X - X X X - - - - - - - - for 5 consecutive
1
days w/o failure
In Production
3/
Semi-Automatic and
5/ 3/ Manual: Section and Etch -
CC/ 100% 3 - - - X X X - 1 - - X - X - - - - - - - -
additional inspection per
shift
per two days
S 100% 3 - - - X X X - 1 - - - - X - - - - - - - - -
4/
K 100% 3 - - - X X X - 1 - X - - - X X - - - - - - - - Some portion of K weld
sectioning (e.g.8/10) can
be replaced by Bend or
KB 100% 3 - - - X X X - 4/ - X - - - X X 4/ - X - X X X -
1 1 Peel (K B) weld analysis
greater II.3.1.2.2
of 1 /
Unclassified 100% 3 - - - X X X month 1 - - - - X - - - - - - - - -
or 1 /
30,000
5/
= rotating per shift (all robotically applied)
* Model: Substantial difference, e.g. FWD vs AWD, wheelbase, unique welds
Global Manufacturing Quality Office
GIS1 Item Number: 25.06
GIS2 Classification: Proprietary
FAF03-150-1 (previously form: 3947-A1) Frame 25 of 61 Version Date: 20100323
Weld Specification: WSBCPA-1B310-AA
Global Gas Metal Arc Weld, Hybrid Laser-GMAW, and Brazing:
GMAB and Hybrid Laser-GMAB
II.3.1.2.1 Visual and/or Automated Inspection,
II.3.1.2.1.1 All parts: Dimensional, and Weld Length Inspection, on or offline:
• 100% Visual check for weld presence and appearance
II.3.1.2.1.2 Formal Weld Inspections – offline: 3 per operation / per shift /per fixture:
• Weld length inspection: (III.4.1: III.4.1.1 and III.4.1.2 Inspection of the Visible Portion of Weld)
• Weld check for weld quality, comply with II.3.2. Weld Quality Evaluations – Visual and Cross-Sectional
(visual (v) items)
II.3.1.2.2 Unclassified welds: Inspect the greater of one part per fixture per month or one part per 30,000 from each
table via cut and etch, or bend and peel / crush. 1 / 30,000 inspections are to be rotated so that parts from all
fixtures will be evaluated at the same frequency.
II.3.1.2.3 "CC/ ", "S" , "K / KB", and “U” weld inspections:
II.3.1.2.3.2.1 After M1 is approved, a part with all welds shall be high gloss painted black, e-coated or black anodized.
This part shall have all welds outlined in red for “CC/ ", light green for "S", and white for “K” / "KB"
class welds with their lengths annotated. Additionally, the outlined welds will have the agreed to
sectioning areas marked in yellow, with the weld numbering scheme relating back to the part detail
identifying the areas of weld cross sectioning. Interior welds, including in-accessible and “closed out”
welds, shall also be marked on the exterior or the part (E.G. weld plates, nuts, interior reinforcements,
etc.).
II.3.1.2.3.2.2 Weld analysis via section and etch shall be each weld, per day, per model, per fixture, per shift.
Inspections will be performed until each section passes all criteria for a minimum of 10 production days
Global Manufacturing Quality Office
GIS1 Item Number: 25.06
GIS2 Classification: Proprietary
FAF03-150-1 (previously form: 3947-A1) Frame 26 of 61 Version Date: 20100323
Weld Specification: WSBCPA-1B310-AA
Global Gas Metal Arc Weld, Hybrid Laser-GMAW, and Brazing:
GMAB and Hybrid Laser-GMAB
for “CC/ ” class welds, or 5 production days for "S", "K / KB " and Unclassified welds, and concurrence
from Ford engineering and STA is received to proceed to IP sampling per Section II 3.1.2.3.3. Where
there are multiple fixtures, inspection will be alternated between fixtures so that each is inspected at the
same frequency; a minimum of one part per fixture every other day.
II.3.1.2.3.2.3 Any alteration, change in process – mechanical, assembly, material, etc., weld wire (inclusive of size of
wire, or solid to cored, etc.), changes in weld position or angle, creates a new weld that must be evaluated
per IV.1 Alteration to Production.
An agreed to part (from PV) shall be reviewed. If there are any changes from PV, a part shall be high
gloss black painted, e-coated or black anodized. This part shall have all welds outlined in red for “CC/ ",
light green for "S", and white for “K / KB" welds with their lengths. Additionally, the outlined welds will
have the agreed to sectioning areas marked in yellow, with a weld numbering scheme relating back to the
part detail identifying the areas of weld cross sectioning Interior welds , including in-accessible and
“closed out” welds, must also be marked on the exterior the part (E.G. weld plates, nuts, interior
reinforcements, etc.). If agreed to in advance, only changed welds need to be marked as described.
II.3.1.2.3.3.1 "CC/ " (YC in DFMEA) (ref appropriate inspection chart for your commodity below):
Cross-section and etch, one part per line, per fixture per day (6 parts in operation 1 (Figure 27) above).
Inspections are to be rotated so that parts from all fixtures will be evaluated at the same frequency. For
semi-automatic and manual welds, the inspection frequency will be one part per line, per fixture, per day,
per shift.
II.3.1.2.3.4 Any alteration in part design, change in material (or source), change in manufacturing process, or change in
weld process (e.g. wire inclusive of -size of wire, or solid to cored, etc.) changes in a weld position, or
angle, that could affect part function, performance, durability, or appearance creates a new weld that reverts
back to the PV weld sampling plan or as agreed to with Ford engineering and STA - until capacity
sustainability is re-established. Costs for any Ford engineering change that results in a new weld, or an
existing weld reverting back to PV weld sampling may be included in the quote for the change. Quality
actions will not incur any additional costs to Ford.
NOTE: during any weld quality issue(s) any of the above sampling plans can or may be reverted back to.
Weld sections shall be taken from the area or areas that have demonstrated a failure or questionable weld
(customer issue - plant or dealer). The fall back to a higher weld sampling frequency is the supplier's
quality responsibility. It is between Ford Motor Company Engineering, STA, and the Supplier to
recognize when this is enforced and for STA and Engineering to determine when this higher weld
sampling frequency is returned to the normal sampling plan(s). Depending on the severity of the
concerns, a higher sampling frequency may be required to reach IP status.
Section Inspection
Functional Testing
Destructive, Non-
Visual Inspection
destructive, and
(Cut & Etch)
per shift/lot
per shift/lot
per shift/lot
per month
per month
per month
per fixture
per fixture
per fixture
per week
per week
per week
per table
per table
per table
per day
per day
per day
Additional Requirements Instructions/Comments/Remarks
Pre-DV phase
Weld Types
PV testing
III.3.3.2. Voltage [V] -5% of nominal Nominal as determined in +5% of nominal see 1) 100 % 2/
PV testing
III.3.3.3. Wire Feed Speed [m/min] -10% of nominal Nominal as determined in +10% of nominal see 1) 100 % 2/
PV testing
III.3.3.4. Wire Feed Motor Current -25% of nominal Nominal as determined in +25% of nominal see 1) 100% 2/
(amps) PV testing
III.3.3.5. Welding Speed [m/min] -10% of nominal Nominal as determined in +10% of nominal see 1) 100 % 2/
PV testing
III.3.3.6. Flow of Shielding Gas -15% of nominal As at PPAP +15% of nominal see 1) 100 % 2/
[l/min]
Arc length (if available) As determined in PV As at PPAP As determined in PV see 1) 100 % 2/
testing 3/ testing
Polarity As determined in PV As at PPAP As determined in PV see 1) 100 % 2/
testing 3/ testing
CTWD (Contact to work As determined in PV Nominal as determined in As determined in PV see 1) 100 % 2/
testing 3/ testing
Stick out length 0 As at PPAP 3.2 mm see 1) 100% 2/
Dwell (arc on time [sec]) As determined in PV Nominal as determined in As determined in PV see 1) 100 % 2/
1
/ Reference Commodity-specific frequency and sampling requirements sections and tables
2/
100% verification through process monitoring or startup check sheet verification of running within the parameter window.
3/
See Table IV-1 Weld Changes / Actions
conditions noted below): 100% T1 leg length (fusion 1) T1 (L1) fusion (leg length must consider
along face) max gap conditions noted below): min. 70%
T1 leg length (fusion along face)
2) T2 (L2) fusion: 100% T1 leg length (fusion along
faying surface plane) 2) T2 (L2) fusion: min. 70% T1 leg length
(fusion along face)
Root Penetration (reference specific schematics
for lap-joint, t-joints, flare-bevel/flare-V/flare- Root Penetration (reference specific
groove/V-groove & butt-joints): schematics for lap-joint, t-joints, flare-
Minimum ==> T1 L1 leg < 70˚ angle relative to faying surface bevel/flare-V/flare-groove/V-groove & butt-
Penetration/ (fusion zone) joints): 0.1 x T1 at nominal target of 0.3 x T1 *
I Depth of Fusion & ==> I f >70˚ to 90˚, confirm root fusion and gap - or use '< 1.5mm GMT methodology' to left
Minimum Actual confirm with Ford PD, Mfg, STA Engineering
Throat ==> I f >90˚, not acceptable Actual Throat: a ≥ 0.7 x T1
T-Joints:
Leg penetration: All legs must achieve penetration depth of 0.1 x T1 ≤ penetration depth ≤ T2 at nominal
target of 0.3 x T2
2) T2 (L2 ) fusion:
* minimum of 70% T1 leg length (fusion along face)
Flare-bevel/Flare-V/Flare-groove/V-groove: Flare-bevel/Flare-V/Flare-groove/V-groove:
Leg penetration: All legs must achieve penetration Leg penetration: All legs must achieve
depth of 0.1 x T1 ≤ penetration depth ≤ T2 at nominal penetration depth of 0.1 x T1 ≤ penetration
target of 0.3 x T2 depth ≤ T2 at nominal target of 0.3 x T2
Minimum
Penetration/ Leg length fusion: Leg length fusion:
I Depth of Fusion & 1) T1 (L1) fusion (leg length must consider max gap 1) T1 (L1) fusion (leg length must consider
Minimum Actual conditions noted below): 100% T1 leg length (fusion max gap conditions noted below): min. 70%
Throat along face) T1 leg length (fusion along face)
2) T2 (L2) fusion: 100% T1 leg length (fusion along 2) T2 (L2) fusion: minimum 70% T1 leg length
face) (fusion along face)
Root Penetration: Evidence of root fusion Root Penetration: Evidence of root fusion
Leg Penetration/Depth of fusion: All legs must achieve leg fusion depth of 0.1 x T1 ≤ maximum
fusion depth ≤ T1 at nominal target of 0.3 x T1
Root penetration and joint fusion (Weld size dimension): ≥ 0.85 of joint contact surface
h-excessive or
incomplete fill Butt-Joints ("Groove Weld"):
V/I
(top and bottom Not to exceed 0.2 mm + 0.2 x T1 or 2.0mm, whichever is greater
as depicted)
Linear Butt-Joints ("Groove Weld"):
V/I
Misalignment 0.2mm + 0.2 x T1 or 5 mm, whichever is smaller
Global Manufacturing Quality
GIS1 Item Number: 25.06
GIS2 Classification: Proprietary
FAF03-150-3 (previously form: 3947-A2) Frame 34 of 61 Version Date: 20090323
Weld Specification: WSBCPA-1B310-AA
Global Gas Metal Arc Weld, Hybrid Laser-GMAW, and Brazing:
GMAB and Hybrid Laser-GMAB
V = visual
T1 (min) Gauge Range:
inspection T1 (min) Gauge Range:
Test >1.5 mm
I = section 0.7 to 1.5mm Visual Aids
inspection
Characteristics (based on governing metal thickness, T1
(based on governing metal thickness, T1 (min)
V/I = both (min)
Bead concavity & Top & Lower bead convexity: weld toe ≥ 125˚ relative to T1 top surface plane and T2 lower surface
I
convexity plane
Lower (Root)
convexity "weld toe"
angle
V Discontiuities No burnt off wire, fishhooks, or any similar sharp protrusion that exceed 5.0 mm in height
V/I Fusion - Lack of See penetration above and in addition maintain maximum gap specification control conditions Above
Gap target = 0 mm
Gap target = 0 mm Max. allowable: < 0.7 x T1, or 175% electrode
Max. allowable: G <0.5 x T1 (never exceed 1.0 mm) diameter, whichever is smaller (never to
I Gaps Special Note: Max. allowable for Dual Phase and exceed 1.5 mm for thick stack-ups)
UHSS steels (Tensile strength 780 MPa or more): ≤ Special Note: Max. allowable for Dual Phase
0.4 mm and UHSS steels (Tensile strength 780 MPa or
more): ≤ 0.4 mm
I Weld leg See penetration above and in addition maintain maximum gap specification control conditions Above
Global Manufacturing Quality
GIS1 Item Number: 25.06
GIS2 Classification: Proprietary
FAF03-150-3 (previously form: 3947-A2) Frame 35 of 61 Version Date: 20090323
Weld Specification: WSBCPA-1B310-AA
Global Gas Metal Arc Weld, Hybrid Laser-GMAW, and Brazing:
GMAB and Hybrid Laser-GMAB
V = visual
T1 (min) Gauge Range:
inspection T1 (min) Gauge Range:
Test >1.5 mm
I = section 0.7 to 1.5mm Visual Aids
inspection
Characteristics (based on governing metal thickness, T1
(based on governing metal thickness, T1 (min)
V/I = both (min)
Note: Especially important for Dual Phase and other UHSS applications
(Tensile strength 780 MPa or more)
V Melt Back - Edge Must not exceed stock thickness and to decrease to zero at or before the root of the weld.
Distortion that occurs as a result of the welding process must be controlled to fall within the tolerances as shown on the
engineering drawing.
The visible part of the weld shall be inspected for discrepancies using the following three inspection methods.
FIGURE 30
FIGURE 31
FIGURE 32
Weld Testing Information On-line for Micro-Hardness Testing:
From http://www.angelfire.com/my/welding/test.html :
"13-24. HARDNESS TESTS
a. General. Hardness may be defined as the ability of a substance to resist indentation of localized displacement. The
hardness test usually applied is a nondestructive test, used primarily in the laboratory and not to any great extent in the
field. Hardness tests are used as a means of controlling the properties of materials used for specific purposes after the
desired hardness has been established for the particular application. A hardness test is used to determine the hardness of
weld metal. By careful testing of a welded joint, the hard areas can be isolated and the extent of the effect of the welding
heat on the properties of the base metal determined.
(a) General. There are several types of hardness testing machines. Each of them is singular in that its
functional design best lends itself to the particular field or application for which the machine is intended.
However, more than one type of machine can be used on a given metal, and the hardness values obtained
can be satisfactorily correlated. Two types of machines are used most commonly in laboratory tests for
metal hardness: the Brinell hardness tester and the Rockwell hardness tester.
(b) Brinell hardness tester. In the Brinell tests, the specimen is mounted on the anvil of the machine and a
load of 6620 lb (3003 kg) is applied against a hardened steel ball which is in contact with the surface of the
specimen being tested. The steel ball is 0.4 in. (10.2 mm) in diameter. The load is allowed to remain 1/2
minute and is then released, and the depth of the depression made by the ball on the specimen is measured.
The resultant Brinell hardness number is obtained by the following formula:
It should be noted that, in order to facilitate the determination of Brinell hardness, the diameter of the
depression rather than the depth is actually measured. Charts of Brinell hardness numbers have been
prepared for a range of impression diameters. These charts are commonly used to determine Brinell
numbers.
(c) Rockwell hardness tester. The principle of the Rockwell tester is essentially the same as the Brinell
tester. It differs from the Brinell tester in that a lesser load is impressed on a smaller ball or cone shaped
diamond. The depth of the indentation is measured and indicated on a dial attached to the machine. The
hardness is expressed in arbitrary figures called "Rockwell numbers." These are prefixed with a letter
notation such as "B" or "C" to indicate the size of the ball used, the impressed load, and the scale used in
the test. "
• AET Integration in Wixom, MI (Jack Sang & Cindy Jiang) - utilized by Ford (Seats and Research & Advanced
Engineering team) for welding fatigue, transverse ("micro") hardness testing, etc. http://www.aet-int.com/
The test specimen shall be manufactured using base sheet metal as well as filler metal wire identical to production
conditions in terms of material specification, gauge and base sheet metal coating. The length of the bead shall be as
indicated on the assembly drawing. The test specimen shall be loaded gradually and continuously until separation
occurs. Separation is acceptable in the base sheet metal or in the HAZ, but not in the weld bead.
Force
Force
Figure 33 Figure 34
Mechanical testing such as crush test may be used to supplement root bend and chisel testing. Process/procedure and
method of testing will be documented, and the method, frequency, and location will be documented in the Weld Control
Plan.
Minimal acceptable conditions for Crush Test:
III.4.4.3 Static Tensile and Torque Strength Test (or local procedure depending on loading of component.)
The static tensile or torque strength test shall be performed in accordance with:
• ISO 14273, Specimen Dimensions And Procedure For Shear Testing Resistance Spot, Seam And Embossed
Projection Welds or
• Auto/Steel Partnership Test Procedures for North America
III.4.4.4 Chisel Test (Destructive) [Optional – Not to be used as a primary validation process, but can be used in
conjunction with other verification methods].
Minimum acceptable conditions for the destructive chisel test are:
• the base metal tears out with weld or
• the weld separates through the throat (in metal thickness over 3mm) – root fusion must be evident and visible.
The chisel test can be applied on subassembly or complete bodies. It is performed to validate the evidence of fusion for
the entire weld.
Destructive chisel testing requires separating the base sheet metal adjacent to the weld in the direction parallel to the
weld using a chisel. The chisel according to ISO 10447 is shown as an example in Figure 35 for Europe. Figure 36
shows the chisel used in North America.
40
R 70
All edges to be
15 free of burrs
24 9 Ø 12.5
FIGURE 36: Spot Test Chisel Used in North America (ref.: tool # 5ZF-15063)
The non-destructive chisel test can also be used to verify the integrity of joints that were welded with parameters outside
the job characteristic curve which do not display imperfections in a visual inspection (Section III.3 Weld Parameter
Monitoring).
The test set up and test conditions shall be agreed upon with the relevant PD Technical Expert (and/or STA
Expert/Engineer and/or Body and Manufacturing Engineering Department as applicable) taking into consideration the
location and loading condition of the relevant joint on the vehicle. Testing can be performed on either components or
subassemblies (e.g. sled testing, drop testing) that contain the welded joint.
III.4.6 New Material Weld Analysis (NOTE: This cold test is Ford responsibility):
For materials classified as described in V.2.1 Introduction: below for welding or subjected to welding that is not
customary for the known material, weld tests must be conducted that comply to FLTM (Ford Laboratory Test Method)
BA 113-08 “Spot Weld Test Criteria for Bare and Coated (Zn & Zn/Fe) Low Carbon and Medium Strength Steel Sheet"
or applicable industry standard(s), e.g. AWS D-8.9 M: 2002 (basis for BA-113-08).
The general Ford vehicle minimum temperature test requirement is - 40° C (-40° F), but welding components of
materials not common to the selected welding process may result in weldments that may be subjected potential
environmental temperatures of -54° C (-65° F) or lower. It is strongly recommended that these component weldments be
subjected to metallurgical evaluation and weld analysis (Charpy Impact, cut - mount – polish – etch - microstructure
analysis, chisel, peel, crush, or similar evaluation(s)), after a cold soak to a minimum of - 54 °C (- 65° F) (min of 3
samples). Actual components, or surrogate parts of the same mass, material weld stack up and thicknesses, may be used
for these tests:
Mechanical Test Verification: If the materials fall into the classes of materials mentioned in V.2.1 Introduction:,
verification should consist, at a minimum, of mechanically testing samples at room temperature and samples subjected
to cold soak for any mechanical property change(s) per the following:
Ambient Temperature (20° C (68° F)) – Mechanically test a minimum sample of 3 at room temperature. Evaluate the
joint through the use of known tests: Charpy Impact Test, chisel test, root bend, metallurgical, or crush test, using
coupons or surrogate parts of adequate size and mass. Perform fastener testing, as applicable.
Cold Soak Test: Mechanically test a minimum sample of 3 at -54 C (-65 F) (a known cold soak source is ATNPC
Livonia). Parts should be tested as quickly as possible, not to exceed 10 minutes, after removal from cold soak. Evaluate
the joint through the use of at least the same known tests used for ambient temperature evaluation: Charpy Impact Test,
chisel test, root bend, metallurgical or crush test, using coupons or surrogate parts of adequate size and mass. Perform
fastener testing, as applicable.
Test Results: If Charpy Impact and/or other tests indicate significant material property decrease(s), alternative actions
are required, potentially consisting of post stamping, forming, or weld process changes.
Global Manufacturing Quality
GIS1 Item Number: 25.06
GIS2 Classification: Proprietary
FAF03-150-3 (previously form: 3947-A2) Frame 49 of 61 Version Date: 20090323
Weld Specification: WSBCPA-1B310-AA
Global Gas Metal Arc Weld, Hybrid Laser-GMAW, and Brazing:
GMAB and Hybrid Laser-GMAB
IV.REVALIDATION REQUIREMENTS
If following the PV “CC/ ”-Class sampling frequency and time, the weld fails to achieve the requirements of Weld
Analysis of II.3.1.2.3.2, the Supplier shall continue with sampling plan frequency associated with PV “CC/ ”-Class
welds until the Supplier Weld Inspections requirements are met.
• Process Change - Any change in the process which could alter its capability to meet the design requirements or
durability of the product. This includes:
New, different, relocated, or rehabilitated production machinery or equipment (does not include portable
manual GMA-Welding equipment)
Any change in subcontracted products or services including the use of engineering-approved alternate
materials
Changes to rework methods
Changes in the sequence of operations
Changes in chemical compounds such as lubricants, which are part of the product
Changes to filler metal or gas shielding type
• Engineering Change - Any change in the part(s) initiated by Ford Motor Company.
• Material and Coating Change - Any change in the material properties, or a change in sheet metal coating
when the new/revised coating is not listed in Section I.7.2. A change in steel supplier for steels having minimum
yield strength equal to or exceeding 310 MPa in the "as received condition" is also considered a material change.
• Sub-Supplier Change - Any change in the source of subcontracted components.
• Adopting Optional Design - Any change where the supplier incorporates optional designs specified on the
released engineering drawing or relevant CAD model.
Note: Possible changes listed in Table IV-1 Weld Changes / Actions shall not be made in conjunction with one another.
Only one of the listed changes shall be made before scheduled section and etch occurs. If two or more such changes
are made in conjunction with each other, Travel Angle plus Work angle excepted, the weld shall be treated as a
new weld and immediately revalidated through the steps commencing with the PV “CC/ ”-Class sampling
frequency and time (II.3.1.2.3.2.2 Weld Analysis…). Any major changes affecting weld processes must be
approved and revalidated by the supplier’s weld engineer.
Note: The following are examples of changes that require notification of Ford Engineering and STA:
-EPA Notification of Water-Shed Compliance, and - Changing from Copper Coated Wire to Bare Wire or Heavy Metal
Compliance.
- Ground Water/Storm or Sewerage Floor Drain Run-Off is an immediate, mandatory report to Ford Engineering and
STA.
∆ Gas flow rate – change over +/- No Address gas flow rate
15%
Global Manufacturing Quality
GIS1 Item Number: 25.06
GIS2 Classification: Proprietary
FAF03-150-3 (previously form: 3947-A2) Frame 52 of 61 Version Date: 20090323
Weld Specification: WSBCPA-1B310-AA
Global Gas Metal Arc Weld, Hybrid Laser-GMAW, and Brazing:
GMAB and Hybrid Laser-GMAB
Table IV-1 Weld Changes / Actions (Ref: Table II-6)
Change SREA a/ and Sampling Quantity Comments
Validation (successive samples)
Required?
∆ to chemicals such as die lubricant SREA Validation may be required
at engineering and / or
STA request
∆ Cleanliness
∆ - New, different, rehabilitated or SREA 6 piece last off Validation may be required
relocated equipment. Does not (rehabilitated or relocated), at engineering and STA
include portable , manual welding and 6 piece first on request
equipment verification and
determination
∆ subcontracted materials, source(s), SREA Validation may be required
or services including engineering at engineering and / or
approved alternate materials STA request
∆ rework methods SREA Validation may be required
at engineering and / or
STA request
∆ parts initiated by Ford Motor Validation may be required
Company at engineering and / or
STA request
∆ material properties or change in Validation may be required
coatings not listed in Tables I – 2 or at engineering and / or
I-4 STA request
∆ suppliers of steels of 310 MPa or SREA Validation may be required
greater at engineering and / or
STA request
∆ where the supplier incorporates SREA Validation may be required
optional designs specified on the at engineering and / or
released engineering drawing or STA request
relevant CAD model
∆ Joint fit up (gap) < 80% of No
maximum
∆ Joint fit up (gap) ≥ 80 % of No Take action to address gap
maximum before attains maximum
∆ Joint fit up (gap) > maximum Yes Ford to determine if parts
are acceptable
∆-Joint width for welding
a/
SREA – Supplier Request for Engineering Approval, Ford Form 1638, available at:
https://web.qpr.ford.com/sta/SREA.html
1/
. For power supply's with adaptive controls, a base schedule shall be the point of reference for changes
that are made manually to the weld program. Adaptive changes to the weld schedule made by the Power
Supply during the course of a weld are accepted, as long as the base schedule is always the point of adaptive
reference
IV.2.2 The following procedures are to be followed when weld repairing. Each supplier or body shop must demonstrate
compliance and obtain Product Development, or both Body and Manufacturing Engineering, approval for
specific defect locations and conditions/facilities utilized for repair. A visual aid display of these procedures in
the repair area is required. Weld repairs are allowed anywhere on the part unless otherwise specified on the
assembly detail.
A program / part specific repair procedure must be defined for each GMA-Weld joint within the structure during
the design process. Repair procedures must be inline with process guidelines as defined in Sections I.3. Process
Description and I.9 Welding Processes.
All non-compliance shall be documented. Documents shall be reviewed at least semi-annually to determine
resolution to any repetitive issues. The minimum documentation required is: part(s) identification, root cause,
and repair procedure(s). Commencing at IP, the engineering or line supervisor shall submit these documents to
the Quality lead for the assembly line for review and signature, supported by welding data as appropriate.
In the case of a discrepant weld, when reworking becomes necessary, the following rules apply, unless specified
differently on the assembly drawing or in the CAD-file:
• Any welds that are missing, contain skips, are of inadequate leg or fillet size, below specified length,
contain discontinuities, or insufficient throat thickness may be brought within specification by additional
welding, using the same welding process and filler wire applied to make the original weld.
• Burn through 9.0 mm or less in diameter:
- Grind off any excess metal from the burn through area, using a disk having a maximum courseness of
60 grit.
- Remove the oxide and bevel the edges of the hole
- A chill block may be used if required
- Puddle weld the hole using the same process that was used to make the original weld.
- Using the same grinding tool, remove any metal representing excessive weld penetration if accessible.
- Build up any localized areas which visual examination indicates an under-filled weld condition
- Grind off any excess metal, if required for clearance purposes
• Any burnt off wire, fishhooks, or any similar sharp protrusion that exceed 5 mm in height must be
removed.
• Weld Porosity is repairable after grinding out the porosity
• Undercuts greater than allowed and less than 50% T1 are repairable by added welding to meet specification
requirements.
IV.4.1 Unacceptable “S”. “K”, “KB” and/or Unclassified weld(s) / brazing received by Ford Assembly Plant(s). These
become class “CC/ ” or “S” only if concurred through both Ford Engineering and STA. This may be processed
through a WERs Notice and detail revision.
IV.4.2 Unacceptable “S”. “K”, “KB” and/or Unclassified weld / brazing issues that can't be resolved within 24 hours of
identification are elevated to class “CC/ ” unless Ford Engineering and STA grant exception to the supplier in
specific incidences. This may be processed through a WERs Notice and detail revision.
IV.4.3 Unacceptable welds / brazing that are temporarily re-classified "CC/ " per paragraphs IV.4.1 or IV.4.2 can be
reclassified to the original level of “S”” or sub-sequentially to an original level of “K/KB” or "U" upon proof of
sustainability.
Note: Once a weld / braze has been moved to the "CC/ " list, per items IV.4.1 or IV.4.2, it can be removed
only after an IP-1 level of quality has been re-established (ref: Sections II.3.1.2 and II.3.1.3 {Commodity
Specific} Frequency and Sample Requirements), and increased sampling for each weld sample has been
maintained a minimum of ten (10) working days. Depending on the severity of the production quality
concerns, Ford Motor Company Design and STA representatives can require that a higher sampling
frequency be utilized, and/or longer sample time be required to achieve IP-1 status. The supplier shall submit
a SREA to request engineering and STA to consider accepting this weld(s) reverting to a "S", "K"/"KB", or
Global Manufacturing Quality
GIS1 Item Number: 25.06
GIS2 Classification: Proprietary
FAF03-150-3 (previously form: 3947-A2) Frame 55 of 61 Version Date: 20090323
Weld Specification: WSBCPA-1B310-AA
Global Gas Metal Arc Weld, Hybrid Laser-GMAW, and Brazing:
GMAB and Hybrid Laser-GMAB
"U" class weld/ braze. Welds / brazing may be individually assessed for status change by plant and/or
assembly line.
IV.4.4 At anytime from DV through Production, quality occurrences may be cause for sections to be taken from the
area or areas that have demonstrated a failure instead of or in additon to location(s) as indicated on the part
detail(s). Sectioning location(s) as defined on the part details may be changed to improve the scrutiny of sample
tests. Change of location requires agreement between Ford STA, PD, and Manufacturing. The location of the
section and etch shall not be moved to areas where this technique is not valid (start/stop overlap, radii, etc.).
NOTE: See ISO/TS 16949:2002, Control of Subcontracted Suppliers; Retention of Inspection and Test Samples;
Notification of Completion of Inspection and Testing; Changes in Manufacturing Process; Change Approval
Control Plans address all significant design and process characteristics, which include all ES tests and Control Item
characteristics. They describe the process potential studies that will be performed for product validation (including PV
tests) and the ongoing product and process evaluation for continuing improvement (including IP tests). They include
acceptance criteria, sample size, frequencies, data analysis methods and reaction plans.
For Seat Systems and per Seat SDS ST-0812, all GMAW welding parameter controls will be identified, noted as SC's on
the Control Plans and monitored on-going to assure sustained quality. Process parameter setting ranges are chosen as
part of demonstrating welding capability during pre-DV, DV, PV and IP phases (i.e., Welding Implementation
Readiness). These settings will remain in place unless a Ford-approved (approved by responsible Ford PD and STA
Engineers as well as by Global Seats Engineering Welding Design Leader/Technical Specialist) SREA accompanied by
a robust capability/correlation study demonstrating sustained weld quality is approved.
The control plan is developed, and updated as necessary by the manufacturing source in conjunction with the design
responsible Product Engineering activity and other appropriate functions such as Supplier Technical Assistance (STA).
The control plan defines the management of the upstream production process and part variables (significant process
characteristics) that affect the outcome of the ES tests or other significant design characteristics. The control plan also
identifies the specific ES tests, with their sample sizes and frequencies which will be performed in order to:
• Confirm whether the process is being managed effectively.
• Further identify significant process characteristics.
• Evaluate performance of marginal processes.
• Better anticipate the customer effect of proposed process improvements.
For any part on which ES tests have been specified, the manufacturing source must present the control plan and any
revisions to the design-responsible Product Design activity for review. This Product Engineering activity has flexibility
to honour business relationships with suppliers having proprietary processes.
Examples of formats for control plans are shown in Quality System Requirements, ISO/TS 16949:2002. Internal
reference documents can also be found in procedure VOPQUG-051 (Control Plans – Vehicle Operations Procedure –
Global).
V.1.1 The physical test specimens or photographs of it are to be retained in an orderly and retrievable manner for 1
month. Adequate written records and photographs to adequately describe qualities of all section inspections are
to be kept through the current model year and one (1) year thereafter by the supplier. These specimens and
V.2.1 Considerations for Proper Stamping and Welding of New Materials or Proto-Type Materials, Stampings, and
Mechanical / Draw Pierce Operations
Note: The following requirements shall be evaluated and complied with as appropriate prior to approval for new
components, or any change in Process or materials.
Introduction:
This pertains to Materials that are classified as HSLA, UHSS, AHHS, Micro Alloy, B (Boron), Hot Form, DP (Dual
Phase), SF (Stretch Flange) TRIP, etc. (all steel alloys with tensile strengths at or above 420 MPa or those materials that
use high or low pressure bending (Hydroform, tube bending, or expanding type devices or mandrels)). This addendum
also pertains to rolling mills where special steel formulations could produce (but not limited to); folds, cold laps, banded
microstructures, ferrite counts, magnetism, and other metallurgical issues that may be detrimental to downstream
processing. This requirement is also inclusive for materials using process annealing, during stamping, bending, or
forming operations (inclusive of tube rolling mills).
Common Misconception: 40% thinning is not the same as 40% elongation. 40% thinning takes away 40% of the load
bearing capability (neglecting the effects of work hardening).
Note; The following are engineering tools which are useful in validating forming or welding processes. These tools may
be used singularly or in combination with each other, dependent on component complexity and/or material reduction (as
noted by the procedures that follow).
1) FLD (Forming Limit Diagram); shall be conducted and submitted to Ford engineering for approval, for new processes
or any change in process once approval to tool has been granted by Ford. (Source – frame assembly or final component
supplier)
2) CGA (Circle Grid Analysis); shall be conducted and submitted to Ford engineering for approval for new processes or
any change in process once approval to tool has been granted by Ford. (Source – steel mill or stamping house)
3) TLD (Thinning Limit Diagram); shall be received from / reviewed by the Steel Supplier and submitted to Ford
engineering for approval, for new processes or any change in process once approval to tool has been granted by Ford.
Steel Suppliers should support all of the items listed above at the die development stage at the die site.
V.2.2 Tools for Verification of Thinning and Splits (Ford operating procedures take precedence over the following):
1) Vernier Calipers, Micrometers, Blade Micrometers, etc., - these instruments shall be capable of accessing the specific
area in question and shall be held perpendicular or normal to the surface to be inspected. All instruments and shop tools
shall have last in house calibration date and sticker with traceability to NIST.
2) Ultrasonic Testing (refer to Ford Policy Letter L-4): Probes shall have a calibrated standard with last in house
calibration, including date and traceability, to NIST. The correct surfactant/couplant, as directed by the ultrasonic tester
and probe manufacturer(s), shall be stated and used in all calibration and inspection procedures. All probes and
Global Manufacturing Quality
GIS1 Item Number: 25.06
GIS2 Classification: Proprietary
FAF03-150-3 (previously form: 3947-A2) Frame 57 of 61 Version Date: 20090323
Weld Specification: WSBCPA-1B310-AA
Global Gas Metal Arc Weld, Hybrid Laser-GMAW, and Brazing:
GMAB and Hybrid Laser-GMAB
standards in conjunction with the electronic box shall have last in house calibration date and sticker with traceability to
NIST.
4) Fluorescent Penetrant Inspection (FPI), - surface only, surface fine / hair line.