Exercises On Relay Settings - Memo
Exercises On Relay Settings - Memo
Exercises On Relay Settings - Memo
http://www.polytechnic.edu.na
SCHOOL OF ENGINEERING DEPARTMENT OF
ELECTRICAL ENGINEERING
ELECTRICAL PROTECTION
Question 2 (25)
Consider the 13.8 kV system shown in Figure Q2.1. Assume all sequence reactances are the same for each
component. Determine CT ratios, tap settings and time-dial settings (TDS) for the relays R1 and R2 operating
circuit-breakers B1 and B2.
Possible CT ratios are: 50:5, 100:5, 150:5, 200:5, 250:5, 300:5, 400:5, 450:5, 500:5, 600:5, 800:5, 900:5,
1000:5, 1200:5.
Use the characteristic curves of the IFC-53 electromechanical relay shown in Figure Q2.2. The line reactances
are in ohms. The co-ordination time is specified to be equal to 0.3 s. Apply a safety factor of 3 for reliability of
operation. Indicate the actual pick-up currents in the lines. Summarise your settings in tabular form.
NB:
1. Use the principle that a back-up relay must operate for the smallest current in the zone of the relay it is
backing-up.
2. A breaker opens all three lines when tripped by its relay.
Figure Q2.1.
1
Figure Q2.2. Characteristic curves of type IFC-53 time over-current relays.
2
Solution:
(1.0)
1.2.2. Negative-sequence network:
(1.0)
1.2.3. Sequence network connection for a line-to-line fault:
This is the minimum fault current. Call it I fmin. Applying the reliability (safety) factor of 3,
I f min 267.4
I p , desired 89.1 A … (1.0)
3 3
3
[Alternative approach:
It is generally the case that the maximum fault current is for a three-phase or a SLG fault. Assume that it is a
three-phase fault and to get maximum fault current for a fault at Bus 3.
VL L / 3 13.8 103 / 3
I 3 fault j 308.815 A … (4.0)
j ( X G 1 X 12 X 23 ) j (5.0 8.0 12.8)
3 3
I fault min I 3 fault j 308.815 j 267.442 A … (2.0)]
2 2
2.1. R1 must serve as the back-up for R2. It must operate for the smallest current in R2’s zone (267.4 A),
therefore the selection of CT ratio and Tap must be based on the line-line fault at the far end of line 2 – 3
(the R2 zone).
2.2. The selection of CT ratio and Tap will therefore be the same as for R2, i.e. a CT ratio of 100/5 and a Relay
Tap Setting of 5.0 A … (1.0)
7967
I f ,max I a1 j 613.1 A … (2.0)
j13.0
5
2.3.4. The relay current of both R1 and R2 is then 613.1 30.655 A … (1.0)
100
4
2.3.5. For a Relay tap Setting of 5, the Ratio-of-Relay-Current-to-Tap-Setting for both relays is
30.665
6.131 … (1.0)
5
2.3.6. From Figure Q2.2 the operating time for R2 is 0.135 s since the Time-dial Setting for R2 is ½ (this is
given by the intersection point where the ½ TDS meets a vertical line drawn at 6.131) … (2.0)
2.3.7. So in the event of failure of R2, relay R1 must operate in 0.135 + 0.3 = 0.435 s … (1.0).
2.3.8. From Figure Q2.2, the required Time-dial Setting for R1 is 2.0 (this TDS is determined by the
intersection point of the vertical line from 6.131 and the horizontal line from 0.435 s) … (2.0)
Question 3 (14)
For the diagrams shown in Table Q3.1 draw the current flows, in both the power and relay circuits, for both
healthy and faulty conditions for an earth-fault anywhere within the system. Write the resultant equations at
the relaying points.
5
Table Q3.1.
Current flows without fault Current flows with earth-fault
1.