Risk MGT Plan - Group 3 Assignment Rev01
Risk MGT Plan - Group 3 Assignment Rev01
AND TECHNOLOGY
Project Brief
The Group 3 project managers has been tasked to be the Project Managers for the
Proposed Old Mutual Pension Fund (OMPF) Shopping Mall Project in Belvedere. This
document is a comprehensive risk management plan that includes all the relevant details
and procedures to be followed in order to manage project risks on the project.The purpose
of this risk management plan is to outline the process of conducting risk management
activities for the project. The risks particular to this project may arise from or in connection
with the following construction project phases;
2.0. METHODOLOGY
The [ CITATION Pro13 \l 7177 ] risk management approach will be taken to manage the
risks on this project. The approach includes the processes of identifying, analysing risks,
planning risk responses and controlling the risks. The most prioritised risks will be added to
the project schedule or programme to ensure that the assigned risk owners or managers
take the necessary steps to implement mitigation responses at the appropriate time during
project implementation.
The risk managers/ owner must provide status updates on their assigned risks in the bi-
weekly project team meetings. Upon the completion of the project, during the closing
process, the project manager will analyse each risk as well as the risk management
processes followed. Based on this analysis, the project manager will identify any
improvements that can be made to the risk management process for future projects. These
improvements will be captured as part of the lessons learned knowledge base.
Risk identification will be conducted in the initial project risk assessment meetings.
The project team will use the following methods to identify the risks on that may affect the
project.
a) The Crawford Slip Method
This is a simple yet effective type of brainstorming that gives the opinions of all team
members’ equal weight, however quiet they are. The project manager will chair the risk
assessment meeting and distribute notepads to each member of the team and allow 10
minutes for all team members to record as many risks as possible.
b) Expert Interviews
Expert Interviews will be held to identify risks, the project plan may be adjusted to avoid very
high impact risks that may cause project failure. The remaining risks will then be included in
the Risk Register.
Risk assessment meetings will be held by key team members and stakeholders. The risks
identified during this meeting are also added to the project plan and Risk Register.
The project team will also review the history of similar projects in order to determine the most
common risks on shopping mall projects in Harare and the strategies that were used to
mitigate those risks.
Risks may arise from or in connection with the following factors on the proposed project;
a) EMA restrictions
b) Town planning provisions and approvals
c) Architectural & Engineering Design Approvals
d) Procurement Strategy
e) Inflation
f) Cost & Schedule Estimates Accuracy
g) Currency risks
h) Cash flow and Liquidity
i) Design Changes (Variation orders)
j) Design Team & Contractor’s Performance
Once the risks have been identified, the project team must prioritize the risks. This process
contains two sub-processes which are qualitative risk analysis and quantitative risk analysis.
Risks which are more likely to occur and have a significant impact on the project all fall
under high priority risks while those which are more unlikely or have a low impact will be of
lower priority
Qualitative risk analysis – Qualitative risk analysis process will prioritise risks identified on
the project for further analysis or action by assessing the combined risk of occurrence and
impact. The assessment will enable the project Manager reduce the level of uncertainty and
focus of high priority risks. PM with the support of the project team shall conduct these
assessments and thereof issue a risk matrix and a risk priority list.
The following tools and techniques will be used by the project team;
Quantitative risk analysis – Risks may further be analysed using quantitative risk analysis.
The Quantity Surveyor, Risk Analysis Experts with the support of the PM will be responsible
for estimating the cost implications or time implications of the identified risks. Expected
Monetary Value (EMV) method will be used in numerically analysing the risks. The EVM of
each risk is calculated as;
If the EMV is negative it depicts the contingent reserves to be set aside to cater for project
threats. Alternatively, if the EMV is positive it means that the project will benefit from risk
related activities. In addition, the project team will also use expert judgement to identify and
quantify risks. The arithmetic summation of the Expected Monetary Values will aggregate to
the project contingency reserve.
The project manager will lead the project team in developing responses to each identified
risk. As more risks are identified, they will be analyzed or qualified and the team will develop
risk response strategies. These risks will also be added to the Risk Register and the project
plan to ensure they are monitored at the appropriate times and are responded to
accordingly.
.
Table 3 – Treatment of Negative Risks
Positive Risks Treatment
Strategy Description
Exploit eliminating the uncertainty associated with
a particular upside risk by ensuring the
opportunity definitely happens, e.g. using
BIM software
Enhance Increasing probability and/or positive
impacts of an opportunity
Share Allocating some or full ownership of the
opportunity to third party who is best able to
capture the opportunity
Accept not take any action until the risk occurs.
Risk monitoring and control will be a continuous process throughout the life of this project.
As risks approach on the project schedule the project manager and team will ensure that the
appropriate risk owner provides the necessary status updates which include the risk status,
identification of trigger conditions, and the documentation of the results of the risk response.
The PM and Project Team will perform the following activities when monitoring and
controlling risks;
The responsibility of managing risk is allocated amongst the key project stakeholders on the
project. The decision authority for selecting whether to proceed with any risk response
strategies and contingency plans with cost and schedule implications will remain with the
Project Manager. The PM will seek approval through the change control board before
implementing the decisions or actions with cost and schedule implication. The risk
management processes are allocated as follows;
Table 4- Risk Responsibility Chart
Risk Responsibility Chart
Project Sponsor Project Consultant Contractor
Manager Team
Plan Risk X X X
Management
Identify Risk X X X X
Perform X X X
Qualitative Risk
Analysis
Perform X X X
Quantitative
Risk Analysis
Plan Risk X X X
Responses
Monitor & X X
Control Risks
The following budget need to be allocated to the project in order to carry out the risk
management processes effectively.
The risks identified on the project will be categorized by project phases. A risk break down
structure will be developed showing risks assumed for each project phase as follows;
OMPF Proposed
Shopping Mall
Risk Factors Risk Factors Risk Factors Risk Factors Risk Factors
The project team will determine the combinations of probability and impact that will result in
the classification of risks into high, medium and low risks as guided by the main
stakeholders’ tolerance levels.
The Group 3 will also use the probability impact ranges to prioritize the identified risk. The
Impact of risks on each project objective are prioritized by the risk impact scale as outlined
below.
Table 7 – Risk Impact Ranges
Risk Impact ranking
Medium 5%-10% cost increase 5%-10% Scope changes within 5%-10% Reworks constitutes to between 5% -10% of
schedule of the scope baseline the project cost
increase
High >10% cost increase >10% schedule Scope changes more than 10% Reworks constitutes to more than10% of the
increase of the scope baseline project cost
6.3. Probability impact Matrix
The probability impact matrix is a combination of the risk probability of occurrence and
impact on the project objectives of cost, schedule, scope and quality. The impact of risks on
project’s schedule, scope and quality is translated into monetary value. The table below
highlights the formulated probability impact matrix for the project.
Stakeholder risk tolerances were determined on the main stakeholders on the project. A
stakeholder analysis process was carried out to cover the tolerances of each stakeholder
during project initiation. The following Stakeholder Tolerance Matrix was developed.
a) Enhance the infrastructure for reporting key information, particularly that used by the
project team and OMPF management to identify, monitor and manage risks.
b) Improve the decision-making process throughout the project team
c) Reduce the probability and severity of losses resulting from risk management
weaknesses;
d) Improve the speed at which information is available and hence decisions can be
made.
These principles must be adopted by the project team and risk owners when reporting risks;
a) Completeness
b) Timeliness
c) Adaptability
d) Accuracy
e) Comprehensiveness
f) Clarity and usefulness
The Risk Register for this project is a log of all identified risks, their probability and impact to
the project, the category they belong to, mitigation strategy, and when the risk will occur.
The register will be created through the initial project risk management meeting led by the
project manager. During this meeting, the project team will identify and categorize each risk.
Additionally, the team will assign each risk a score based on the probability of it occurring
and the impact it could potentially have. The Risk Register also contains the mitigation
strategy for each risk as well as when the risk is likely to occur.
Based on the identified risks and timeframes in the risk register, each risk will be added to
the project plan. At the appropriate time in the plan—prior to when the risk is most likely to
occur—the project manager will assign a risk manager to ensure adherence to the agreed
upon mitigation strategy. The each risk manager will provide the status of their assigned risk
at the bi-weekly project team meeting for their risk’s planned timeframe. The Risk Register
will be maintained as an appendix to this Risk Management Plan.
References
Project Management Institute. (2018). A Guide to the Project Management Body of
Knowledge. Newtown Square, Pennsylvania: Project Management Institute.