2 X 7.6 Skew 31
2 X 7.6 Skew 31
2 X 7.6 Skew 31
000
0.075
0.395 ___ 0.300
0.500 ___ 0.400
0.15
BOD 99.425
0.25
BOB 99.175
MFL 98.375
1.475
Skew 31
Abutment 10.63
Rear side 10.44
9.97 10.05
9.97
0.650
BOB 99.175
1.475
Wing
Rear side
0.400
1.780 0.300 LF4
0.400
2.080 0.300 LF3
0.400
0.150 2.380 0.250 LF2
0.300
0.100 2.780 0.100 95.900 BOF LF1
2.980 0.100 Length @PCC
3.150
2.920 2.96
2.22
1.475
1.200
0.15
0.15 1.600 0.15
0.15
0.15 1.900 0.15
0.15
0.1 2.200 0.1
2.400 0.1
Pier straight length 12.1
LF4 13.4
LF3 13.7
LF2 14
LF1 14.3
95.900 Length @PCC 14.5
TAMIL NADU GOVERNMENT
HIGHWAYS DEPARTMENT
Sub Estimates
Name of Work:
Estimate Amount :
Name of work
ABSTRACT ESTIMATE
Total 109.22cum
2. Earthwork excavation in all classes of soils depositing on bank with all
leads and lifts as per SS20B, including cost of all labour, equipments and all
incidental charges such as baling our water, providing and maintaining
necessary cofferdams, sheeting, shoring bracing and their subsequent
removal, removal of all logs, stumps, grubs and other deleterious matter and
obstructions, trimming bottom of excavation backfilling, and clearing the site
and disposal of all surplus materials etc., complete as per relevant standard
specification for FOUNDATION OF ABUTMENTS, PIERS AND WINGS.
Abutments 1x2
Wings 2x2
Piers 1x1
Total 47.06cum
3 Earthwork excavation in soft desintegrated rock depositing on bank with
all leads and lifts as per SS20B, including cost of all labour, equipments and
all incidental charges such as baling our water, providing and maintaining
necessary cofferdams, sheeting, shoring bracing and their subsequent
removal, removal of all logs, stumps, grubs and other deleterious matter and
obstructions, trimming bottom of excavation backfilling, and clearing the site
and disposal of all surplus materials etc., complete as per relevant standard
specification for FOUNDATION OF ABUTMENTS, PIERS AND WINGS.
Abutments 1x2
Wings 2x2
Piers 1x1
Total 251.01cum
4 Plain Cement Concrete of grade M10 Nominal Mix (1:3:6) using 40mm
ISS size HBG graded metal including cost and conveyance of all materials
to site including cost of cement at site including cost of formwork, soft water,
labour charges for mixing, transporting, laying and curing concrete , working
at depths , tools and plants and maintaining of protective bunds, cofferdams,
shoring, strutting etc., complete as per relevant standard specifications, for
LEVELLING COURSE BELOW FOOTINGS OF ABUTMENTS AND PIERS.
Abutments 1x2
Wings 2x2
Piers 1x1
Total 15.69cum
5 Vibrated Cement Concrete of grade M20 Nominal Mix (1:1.5:3) using
40mm ISS size HBG graded metal including cost and conveyance of all
materials to site including cost of cement at site including cost of formwork,
soft water, labour charges for mixing, transporting, laying and curing
concrete , working at depths , tools and plants and maintaining of protective
bunds, cofferdams, shoring, strutting etc., complete as per relevant standard
specifications, for FOOTINGS OF ABUTMENT, PIERS AND WINGS
BELOW SILL LEVEL.
Abutments 1x2
Abutments 1x2
Abutments 1x2
Abutments 1x2
Wings 2x2
Wings 2x2
Wings 2x2
Wings 2x2
Piers 1x1
Piers 1x1
Piers 1x1
1x2
2x2
Total 170.41cum
6 Vibrated Cement Concrete of grade M20 Nominal Mix using 40mm ISS
size HBG graded metal including cost and conveyance of all materials to
site including cost of cement at site including cost of formwork, soft water,
labour charges for mixing, transporting, laying and curing concrete , working
at depths , tools and plants and including all other incidental charges etc;
complete as per relevant standard specifications, for SUBSTRUCTURE OF
ABUTMENTS, WINGS, AND PIERS ABOVE SILL LEVEL.
1x2
2x2
Total 62.76cum
7 Vibrated Reinforced Cement Concrete of grade M30 design mix using
ISS size HBG graded metal including cost and conveyance of all materials
to site including cost of cement at site including cost of formwork, soft water,
labour charges for mixing, transporting, laying and curing concrete , working
at depths , tools and plants including all other incidental charges etc;
complete as per relevant standard specifications, for DIRT WALL CUM BED
BLOCK OVER ABUTMENTS AND BED BLOCK OVER PIERS.
Abutment 1x2
2 x 10 x 1 x - 20.00Nos.
Wings 2x2
4 x 2 x 2 x - 16.00Nos.
Total 36.00Nos.
9 Providing and fixing KRAFT PAPER for full width of seating of deck slab
and including cost and conveyance to worksite, labour for fixing the same in
correct position and all other incidental charges etc., complete.
Total 87.76cum
11 Providing filter media behind the abutments and wings with clean III
graded material 53mm to 5.6mm to 600mm thick and well compacted in
layers with smaller sized towards the soil and bigger size towards the wall
including cost and conveyance to work site including all labours and other
incidental charges including hire charges for tools and plants employed etc.,
for filter media as per MOST's (Roads Wing) specifications for Roads and
Bridges " Fourth Revision Cl. 309-3-2-13 and 305 -4-4 etc., complete.
1x2
Over abutments dirt wall
2 x 0.600 x 10.440 x 0.205 2.57cum
2x2 (2.45+2.22)/2
Over wings rear batter
4 x 0.600 x 2.335 x 1.786 10.01cum
2x2
Over wings back wall
4 x 0.600 x 2.450 x 0.205 1.21cum
Total 35.67cum
12 Filling behind Abutments and Wings with clean gritty gravel including
cost and conveyance of gravel to worksite, laying, handling charges and filling
in layers, tamping under optimum moisture content to get the maximum
density including watering, with all leads for water and all other incidental
charges etc, complete for FILLING BEHIND THE ABUTMENTS AND
WINGS.
Abutments 1x2
1x3
PVC EXPANSION
JOINT
3 11.610 34.83rm
Total 34.83rm
14 Supply and fabrication of Fe-500 steel required for all RCC items of
works involved in the schedule cost of steel at site fabrication,labour charges
for cleaning the rods straightening, cutting, bending, tying grills, including
overlapping to the required length whenever necessary and placing the
reinforcement in position as specified in the drawings, including cost of
binding wire, provision of spacer bars, cover blocks and all other incidental
charges etc,complete, Fe-500 grade
1x2
For Deck Slab
2 4.470 8.94MT
1x2
For Crash Barrier
2 0.760 1.52MT
1x2
For Bed Block cum dirt
wall over abutment
2 0.350 0.70MT
1x1
For Bed Block cum dirt
wall over piers
1 0.295 0.30MT
1x2
For Approach Slab
2 0.670 1.34MT
1x2
For wearing coat over
deck slab
2 0.435 0.87MT
1x2
For wearing coat over
approach slab
2 0.190 0.38MT
Total 14.05MT
15 Vibrated Cement Concrete M15 grade, Nominal Mix 1:2:4, using 40mm
ISS hard granite broken metal including cost and conveyance of all
materials to site and cement at site including cost of formwork, lead for soft
water, labour charges for mixing , transporting, laying, and curing concrete
working in heights and hire charges for tools and plants, and all other
incidental charges etc complete as per relevant specification for BASE
COURSE BELOW APPROACH SLAB.
Total 9.87cum
16 Vibrated reinforced cement concrete M30 design mix using ISS graded
hard granite broken metal including cost and conveyance of all materials to
site including cement at site including labour charges for mixing, laying, curing
concrete, working at heights, hire charges for tools and plants, including all
other incidental changes etc., complete for APPROACH SLAB.
Total 21.77cum
17 Vibrated Reinforced Cement Concrete M-40, Grade, Design Mix, using
ISS size hard granite broken graded metal including cost and
conveyance of all materials to site including cement at site but excluding cost
and fabrication of steel, including labour charges for mixing, transporting,
laying, and curing concrete, working at heights, hire charges for tools and
plants, including all other incidental charges etc.,, complete for RCC CRASH
BARRIERS OVER DECK SLAB. -1RM(For Estimate Purpose, mix 1:1.5:3)
Total 14.03cum
18 Vibrated Cement Concrete M20 grade, Nominal Mix using 40mm ISS size
hard granite broken graded metal including cost and conveyance of all
materials to site and cement at site including labour charges for mixing,
transporting, laying, and curing concrete, working at heights, hire charges for
tools and plants, including all other incidental charges,etc.,complete as per
standard specification for PCC PARAPETS OVER WINGS.
Parapet 2x2
Bootom Portion 4 3.500 0.500 0.300 2.10cum
2x2 ((0.450+0.300)/2)
Tapper Portion 4 3.500 0.375 0.600 3.15cum
2x2
Straight portion 4 3.500 0.300 0.300 1.26cum
Total 6.51cum
19 Providing and fixing of cast iron drainage spouts 100mm dia as per
MOST drawing SD/205 with grating arrangements at top as shown in the
drawing using 12mm x 25mm flats for grating arrangements, and 100mm dia
drainage spout projecting beyond the bottom of deck slab as shown in the
drawing including cost and conveyance of cast iron pipes and flats and fixing
them in position etc,complete.
Drainage spouts 2 x 2
4 4Nos.
Total 4Nos.
20 VCC M30 (design mix) using 20mm ISS HBG graded metal as the max. size
of coarse aggreagates including cost & conveyance of all materials to site
and cost of cement at site, but excluding cost & fabrication of steel, but
including cost of form work, soft water, labour charges for mixing,
transporting, laying, curing concrete working at heights, hire charges for T&P
including all other incidental charges etc., complete as per relevant std
specification for Wearing coat.
1x2 (0.45+0.90)/2
Body wall 2 6.600 0.675 1.600 14.26cum
2x4 (22/7) X 1.10^2 (0.60+0.90)/2
D/s for Pipes - 8 0.950 1.000 0.750 -5.70cum
Total 8.56cum
Scaffolding and centering charges for the structural components of
abutment piers, bed block and deck slab including cost and conveyance of
all material to the site including all labour charges and incidental charges
etc., complete.
Abutment
Wings
Abutment sqrt(0.030^2+0.300^2)
Front Batter 1 x 2 x 10.63 x 0.30 = 6.41sq.m
(9.97+10.05)/2 sqrt(0.034^2+0.300^2)
¶/4 (0.600+0.570)
Wings
(2.960+2.920)/2
(0.880+0.816)/2
Pier
1 x 2 x 14 x 0.15 = 4.20sq.m
Pier sqrt(0.040^2+1.200^2)
¶/2 (0.460+0.500)
199.56sqm
= 1.171
Abutment sqrt(0.150^2+1.475^2)
(10.44+10.05)/2 sqrt(0.166^2+1.475^2)
¶/4 (0.570+0.420)
Wings
(3.15+2.96)/2
(0.500+0.816)/2
Pier sqrt(0.050^2+1.475^2)
¶/2 (0.460+0.500)
168.08sqm
62.76cum
= 2.678
Centering for Dirt wall cum Bed Block
Abutment
Pier
(22 x 0.435)/7
24.78sqm
7.58cum
= 3.269
(0.500+0.400)/2
213.05sqm
= 2.428
3.13sqm
9.87cum
= 0.317
(0.395+0.300)/2
12.44sqm
21.77cum
= 0.571
sqrt(1.175^2+0.050^2)
sqrt(0.750^2+0.050^2)
sqrt(0.250^2+0.175^2)
95.82sqm
Area per one cum of concrete = 95.82sqm
14.03cum
= 6.828
sqrt(0.150^2+0.600^2)
(0.30+0.45)/2
30.83sqm
6.51cum
= 4.736
Construction of Minor Bridge at Km 3/4 of Kayathar - Therkkumayilodai Road to
N.W:-
Vadakkumayilodai Road
Stacking /
Name of Lead in Cost of Conveyance
Reach Kind of metal Storage Total
Quarry KM material Charges
charges
Cement 12 - - - 6078.37
Km 128/4 of Madurai - Kanniyakumari Road CT 0.20
Steel 12 - - - 47238.37
4.75 mm IRC
12 578.00 121.80 - 699.80
&Below
SOURCE OF SUPPLY
1 Cum Rate for Vib. CC M10 nominal mix (1:3:6) 4358.90 Cum Rs. 4358.90
Providing and maintaining protective bunds and L.S. 30.00
coffer dams
Bailing out water L.S. 30.00
Curing Concrete " 6.00
Soft water " 20.00
Hire charges for T&P " 84.00
TOTAL Rs. 4528.90
Rate per cum Rs. 4528.90
5 Vibrated Cement Concrete of grade M20 Nominal Mix, using
40mm ISS size HBG graded metal including cost and
2conveyance of all materials to site including cost of cement
at site including cost of formwork, soft water, labour charges
for mixing, transporting, laying and curing concrete , working
at depths , tools and plants and maintaining of protective
bunds, cofferdams, shoring, strutting etc., complete as per
relevant standard specifications, for FOOTINGS OF
ABUTMENT, PIERS AND WINGS BELOW SILL LEVEL-
1 Cu.m Rate for Vib. PCC M20 Nominal Mix Rs. 5177.17 Rs. 5177.17
1 Cum Rate for Vib. PCC M20 Nominal Mix 5177.17 Cum. Rs. 5177.17
1 Cum Rate for Vib. PCC M20 Nominal Mix 5177.17 Cum. Rs. 5177.17
4.736 sq.m Formwork and Centering 694.57 sq.m Rs. 3289.48
Curing Concrete L.S. Rs. 20.00
Soft water Rs. 6.00
Hire charges for T&P L.S. Rs. 84.00
TOTAL Rs. 8576.65
Rate per cum Rs. 8576.65
19 Providing and fixing of cast iron drainage spouts 100mm dia.
as per MOST drawing SD/205 with grating arrangements at
top as shown in the drawing using 12mm x 25mm flats for
grating arrangements, and 100mm dia. drainage spout
projecting beyond the bottom of deck slab as shown in the
drawing including cost and conveyance of cast iron pipes and
flats and fixing them in position etc., complete.
8.40
9.80
11.61