Paper - 8: Cost Accounting Bit Questions
Paper - 8: Cost Accounting Bit Questions
Paper - 8: Cost Accounting Bit Questions
in
PAPER - 8
COST ACCOUNTING
BIT QUESTIONS
DIRECTORATE OF STUDIES
THE INSTITUTE OF
COST ACCOUNTANTS OF INDIA
Statutory Body under an Act of Parliament
VISION STATEMENT
“The Institute of Cost Accountants of India
would be the preferred source of
resources and professionals for the
financial leadership of enterprises
globally.”
Courtesy
Vijayawada Chapter of
The Institute of Cost Accountants of India
PAPER - 8
COST ACCOUNTING
BIT QUESTIONS
DIRECTORATE OF STUDIES
THE INSTITUTE OF
COST ACCOUNTANTS OF INDIA
Statutory Body under an Act of Parliament
PAPER - 8
Cost Accounting
Bit Questions
3) When a direct worker is paid on a monthly fixed salary basis, the following is true:
(a) There is no idle time lost.
(b) There is no idle time cost.
(c) Idle time cost is separated and treated as overhead.
(d) The salary is fully treated as factory overhead cost.
6) When you attempt a reconciliation of profits as per Financial Accounts and Cost
Accounts, the following is done:
(a) Add the under absorption of overheads in Cost Accounts if you start from the profits as
per Financial Accounts.
(b) Add the under absorption of overheads in Cost Accounts if you start from the profits as
per Cost Accounts.
(c) Add the over absorption of overheads in Cost Accounts if you start from the profits as
per Financial Accounts.
(d) Add the over absorption of overheads in Cost Accounts if you start from the profits as
per Cost Accounts.
8) In the context of Contract a/c, work completed and not yet certified will beshown
(a) at cost plus + 2/3rd of the notional profit under 'Completed Work'.
(b) at cost plus notional profit less retention money under 'Completed Work'.
(c) at cost under 'Completed Work'.
(d) at cost under WIP a/c.
9) A certain process needed standard labour of 24 skilled labour hours and 30 unskilled
labour hours at Rs. 60 and Rs. 40 respectively as the standard labour rates. Actually, 20
and 25 labour hours were used at Rs. 50 and Rs. 50 respectively. Then, the labour mix
variance will be
(a) Adverse
(b) Favourable
(c) Zero
(d) Favourable for skilled and unfavourable for unskilled
10) If an organization has all the resources it needs for production, then the principal budget
factor is most likely to be
(a) non-existing
(b) sales demand
(c) raw materials
(d) labour supply
15) Which of the following items is not included in preparation of cost sheet?
(a) Carriage inward
(b) Purchase returns
(c) Sales Commission
(d) Interest paid
17) If sales are Rs. 90,000 and variable cost to sales is 75%. Contribution is
(a) Rs. 21,500
(b) Rs. 22,500
(c) Rs. 23,500
(d) Rs. 67,500
28) In a process 8000 units are introduced during a period. 5% of input is normal loss. Closing
work in progress 60% complete is 1000 units. 6600 completed units are transferred to next
process. Equivalent production for the period is:
(a) 9000 units
(b) 7440 units
(c) 5400 units
(d) 7200 units
29) If sales are Rs. 150,000 and variable cost are Rs. 50,000. Compute P/V ratio.
(a) 66.66%
(b) 100%
(c) 133.33%
(d) 65.66%
30) Standard cost of material for a given quantity of output is Rs. 15,000 while the actual cost
of material used is Rs. 16,200. The material cost variance is:
(a) Rs. 1,200 (A)
(b) Rs. 16,200 (A)
(c) Rs. 15,000 (F)
(d) Rs. 31,200 (A)
32) What entry will be passed under integrated system for purchase of stores on credit?
(a) Dr. Stores
Cr. Creditors
(b) Dr. Purchases
Cr. Creditors
(c) Dr. Stores Ledger Control A/c
Cr. Creditors
(d) Dr. Stores Ledger Control A/c
Cr. General Ledger Adjustment A/c
33) In a process 800 units are introduced during 2016-17. 5% of input is normal loss. Closing
work-in-progress 60% complete is 100 units. 660 completed units are transferred to next
process. Equivalent production for the period is
(a) 760 units
(b) 744 units
(c) 540 units
(d) 720 units
34) _____ deals with the principles and methods of determining the production or operation
overheads.
(a) CAS-3
(b) CAS-5
(c) CAS-9
(d) CAS-16
35) There is a loss as per financial accounts Rs. 10,600, donations not shown in cost accounts
Rs. 6,000. What would be the profit or loss as per cost accounts?
(a) Loss Rs. 16,600
(b) Profit Rs. 16,600
(c) Loss Rs. 4,600
(d) Profit Rs. 4,600
36) A hotel having 100 rooms of which 80% are normally occupied in summer and 25% in
winter. Period of summer and winter be taken as 6 months each and normal days in a
month be assumed to be 30. The total occupied room days will be
(a) 1525 Room days
(b) 18900 Room days
(c) 36000 Room days
(d) None of the above
37) A firm has fixed expenses Rs. 90,000, sales Rs. 3,00,000 and profit Rs. 60,000. The P/V
ratio of the firm is
(a) 10%
(b) 20%
(c) 30%
(d) 50%
44) Royalty paid on sales Rs. 89,000 and Software development charges related to product is Rs.
22,000. Calculate Direct Expenses.
(a) 1,11,100
(b) 1,11,000
(c) 1,11,110
(d) 1,10,000
45) Direct Expenses that does not meet the test of materiality can be ———— part of overhead.
(a) Treated
(b) Not treated
(c) All of the these
(d) None of these
47) Charging to a cost center those overheads that result solely for the existence of that cost
Center is known as
(a) Allocation
(b) Apportionment
(c) Absorption
(d) Allotment
50) Standards deals with the principles and methods of determining depreciation and
amortization cost-
(a) CAS 9
(b) CAS 12
(c) CAS 15
(d) CAS 16
52) Equivalent production of 1,000 units, 60% complete in all respects, is:
(a) 1000 units
(b) 1600 units
(c) 600 units
(d) 1060 units
53) Standard price of material per kg is Rs. 20, standard usage per unit of production is 5 kg.
Actual usage of production 100 units is 520 kgs, all of which was purchased at the rate of Rs.
22 per kg. Material cost variance is
(a) 2,440 (A)
(b) 1,440 (A)
(c) 1,440 (F)
(d) 2,300 (F)
54) Standard cost of material for a given quantity of output is Rs. 15,000 while the actual cost of
material used is Rs. 16,200. The material cost variance is:
(a) Rs. 1,200 (A)
(b) Rs. 16,200 (A)
(c) Rs. 15,000 (F)
(d) Rs. 31,200 (A)
55) The basic difference between a fixed budget and flexible budget is that a fixed budget -
(a) is concerned with a single level of activity, while flexible budget is prepared for different
levels of activity
(b) Is concerned with fixed costs, while flexible budget is concerned with variable costs.
(c) is fixed while flexible budget changes
(d) None of these.
64) In which of the following incentive plan of payment, wages on time basis are not
Guaranteed?
(a) Halsey plan
(b) Rowan plan
(c) Taylor’s differential piece rate system
(d) Gantt’s task and bonus system
66) When overtime is required for meeting urgent orders, overtime premium should be
(a) Charged to costing profit and loss A/c
(b) Charged to overhead costs
(c) Charged to respective jobs
(d) Ignored
72) A manufacturing Industry produces product P, Royalty paid on sales is Rs. 23,500 and
design charges paid for the product is Rs. 1,500. Compute the Direct Expenses.
(a) 25,000
(b) 22,000
(c) 26,500
(d) None of these
75) Charging to a cost center those overheads that result solely for the existence of that cost
Center is known as
(a) Allocation
(b) Apportionment
(c) Absorption
(d) Allotment
77) Which method of absorption of factory overheads do you suggest in a concern which
produces only one uniform type of product :
(a) Percentage of direct wages basis
(b) Direct labour rate
(c) Machine hour rate
(d) A rate per units of output
79) When the amount of overhead absorbed is less than the amount of overhead incurred, It is
called
(a) Under- absorption of overhead
(b) Over-absorption of overhead
(c) Proper absorption of overhead
84) Standard deals with the principles and methods of determining the manufacturing Cost of
excisable goods-
(a) CAS 12
(b) CAS 15
(c) CAS 22
(d) CAS 2
87)Which of the following items is not excluded while preparing a cost sheet?
(a) Goodwill written off
(b) Provision for taxation
(c) Property tax on Factory building
(d) Transfer to reserves
(e) Interest paid
97)What entry will be passed under integrated system for payment to creditors for supplies
made?
(a) Dr. Creditors
Cr. Cash
(b) Dr. Creditors
98)The accounting entry in integrated accounts for recording sales will be:
(a) Dr. Cost ledger control account
Cr. Profit and loss account
(b) Dr. Sales account
Cr. Profit and Loss A/c
(c) Dr. Cash A/c
Cr. Sales A/c
102)The most suitable cost system where the products differ in type of material and work
performed is
(a) Operating Costing
(b) Job costing
(c) Process costing
(d) All of these.
108)If sales are Rs. 90,000 and variable cost to sales is 75%, contribution is
(a) Rs. 21,500
(b) Rs. 22,500
(c) Rs. 23,500
(d) Rs. 67,500
109)Variable cost
(a) Remains fixed in total
(b) Remains fixed per unit
(c) Varies per unit
(d) Nor increase or decrease
110)If sales are Rs. 150,000 and variable cost are Rs. 50,000. Compute P/V ratio.
(a) 66.66%
(b) 100%
(c) 133.33%
(d) 65.66%
115)Contribution is Rs. 300,000 and sales is Rs. 1,500,000. Compute P/V ratio.
(a) 15%
(b) 20%
(c) 22%
(d) 17.5%
117)Fixed cost is 30,000 and P/V ratio is 20%. Compute breakeven point.
(a) Rs. 160,000
(b) Rs. 150,000
(c) Rs. 155,000
(d) Rs. 145,000
121)Standard price of material per kg Rs. 20, standards consumption per unit of production is
5 kg. Standard material cost for producing 100 units is
(a) Rs. 20,000
(b) Rs. 12,000
(c) Rs. 8,000
(d) Rs. 10,000
122)Standard cost of material for a given quantity of output is Rs. 15,000 while the actual cost
of material used is Rs. 16,200. The material cost variance is:
(a) Rs. 1,200 (A)
(b) Rs. 16,200 (A)
(c) Rs. 15,000 (F)
(d) Rs. 31,200 (A)
125)Standard price of material per kg is Rs. 20, standard usage per unit of production is 5 kg.
Actual usage of production 100 units is 520 kgs, all of which was purchase at the rate of
Rs. 22 per kg. Material usage variance is
(a) Rs. 400 (F)
(b) Rs. 400 (A)
(c) Rs. 1,040 (F)
(d) Rs. 1,040 (A)
126)Standard price of material per kg is Rs. 20, standard usage per unit of production is 5 kg.
Actual usage of production 100 units is 520 kgs, all of which was purchase at the rate of
Rs. 22 per kg. Material cost variance is
(a) 2,440 (A)
(b) 1,440 (A)
(c) 1,440 (F)
(d) 2,300 (F)
127)Standard quantity of material for one unit of output is 10 kgs. @ Rs. 8 per kg. Actual output
during a given period is 800 units. The standardquantity of raw material
(a) 8,000 kgs
(b) 6,400 Kgs
(c) 64,000 Kgs
(d) None of these.
133)The difference between fixed cost and variable cost assumes significance in the
preparation of the following budget.
(a) Master Budget
(b) Flexible Budget
(c) Cash Budget
(d) Capital Budget
135)Sales budget is a …
(a) expenditure budget
(b) functional budget
(c) Master budget
(d) None of these
137)In a process 6,000 units are introduced during a period. 5% of input is normal loss. Closing
work-in-process 60% complete is 800 units. 4,900 completed units are transferred to next
process. Equivalent production for the period is
(a) 6,800 units
(b) 5,700 units
(c) 5,680 units
(d) 5,380 units
139)Z Ltd. is planning to sell 1,00,000 units of product A for Rs. 12.00 per unit. The fixed costs
are Rs. 2,80,000. In order to realize a profit of Rs. 2,00,000, what would the variable costs
be?
(a) Rs. 4,80,000
(b) Rs. 7,20,000
(c) Rs. 9,00,000
(d) Rs. 9,20,000
141)The most suitable cost system where the products differ in type of material and work
performed is
(a) Process Costing
(b) Batch Costing
(c) Job Costing
(d) Operating Costing
142)In a process 10000 units are introduced during a period. 10% of input is normal loss.
Closing work-in-process 70% complete is 1500 units. 7500 completed units are transferred
to next process. Equivalent production for the period is
(a) 9550 units
(b) 9000 units
(c) 8550 units
(d) 8500 units
143)The sales and profit of a firm for the year 2016 are Rs.1,50,000 and Rs.20,000 and for the
year 2017 are Rs.1,70,000 and Rs.25,000 respectively. The P/V Ratio of the firm is
(a) 15%
(b) 20%
(c) 25%
(d) 30%
144)Standard quantity of material for one unit output is 10 kg @ Rs.8 per kg. Actual output
during a given period is 600 units. The standard quantity of material for actual output is
(a) 1200 kg
(b) 6000 kg
(c) 4800 kg
(d) 48000 kg
150)In job costing to record the issue of direct materials to a job which of the following
document is used?
(a) Purchase order
(b) Goods receipt note
(c) Material requisition
(d) Purchase requisition
151)In a process 4000 units are introduced during a period. 5% of input is normal loss.
Closing work-in-progress 60% complete is 500 units. 3300 completed units are
transferred to next process. Equivalent production for the period is
(a) 3550 units
(b) 3600 units
(c) 3800 units
(d) 3950 units
152)Product A generates a contribution to sales ratio of 40%. Fixed cost directly attributable
to A amount Rs. 60,000. The sales revenue required to achieve a profit of Rs.15,000 is
(a) Rs 2,00,000
(b) Rs 1,85,000
(c) Rs 1,87,500
(d) Rs 2,10,000
153)During a period 13600 labour hours were worked at a standard rate of Rs. 8 per hour. The
direct labour efficiency variance was Rs. 8,800 (Adv). How many standard hours were
produced?
(a) 12000 hours
(b) 12500 hours
(c) 13000 hours
(d) 13500 hours
154)Cash Budget of ABC Ltd. forewarns of a short-term surplus. Which of the following would
be appropriate action to be taken in such a situation?
(a) Purchase new fixed assets
(b) Repay long-term loans
(c) Write off preliminary expenses
(d) Pay creditors early to obtain a cash discount
155)Costs which are ascertained after they have been incurred are known as
(a) Sunk Costs
(b) Imputed Costs
(c) Historical Costs
(d) Opportunity Costs
157)In which of thefollowing methods, issue of materials are priced atpre-determined rate?
(a) Specific price method
(b) Standard price method
(c) Inflated price method
(d) Replacement price method
158)For reducing the labour cost per unit, which of the following factors is the most important?
(a) Low wage rates
(b) Longer hours of work
(c) Higher input-output ratio
(d) Strict control and supervision
159)Maximum possible productive capacity of a plant when no operating time is lost is its
(a) Normal capacity
(b) Practical capacity
(c) Theoretical capacity
(d) Capacity based on sales expectancy
160)In job costing, which of the following documents is used to record the issue of direct
materials to a job?
(a) Goods Receipt Note
(b) Purchase Order
(c) Purchase Requisition Note
(d) Material Requisition Note
162)During a period 2560 labour hours were worked at a standard rate of Rs. 7.50 per hour.
The direct labour efficiency variance was Rs. 825 (A). How many standard hours were
produced?
(a) 2400
(b) 2450
(c) 2500
(d) 2550
163)PQR Ltd. manufactures a single product which it sells forRs.40per unit. Fixed cost is Rs.
60,000 per year. The contribution to sales ratio is 40%. PQR Ltd.’s Break Even Point in units
is
(a) 3500
(b) 3700
(c) 3750
(d) 4000
Answer Key:
1) (b) Direct labour, direct expenses, indirect material, indirect labour, indirect expenses
2) (c) The ordering cost is equal to the carrying cost
3) (b) There is no idle time cost.
4) (b) Travelling expenses to site
5) (d) Night shift allowance paid to a factory worker due to general work pressure
6) (a) Add the under absorption of overheads in Cost Accounts if you start from the
profits as per Financial Accounts
7) (b) drug manufacturing
8) (d) at cost under WIP a/c
9) (c) Zero
10) (b) sales demand
11) (d) Patient Day
12) (d) None of these
13) (c) Time spent by workers off their work
14) (c) Distribution overhead
15) (d) Interest paid
16) (d) All of the above
17) (b)Rs. 22,500
18) (d) There is a decrease in variable cost per unit
19) (c) Variance
20) (b) Functional budget
21) (a) Fixed Cost
22) (c) Perpetual Inventory
23) (a) Charged to costing profit and loss A/c
24) (a) Actual hours being more than normal time
25) (a) Cost allocation
26) (a) Added to financial profit
27) (d) All of the above
28) (d) 7200 units
29) (a) 66.66%
30) (a) Rs. 1,200 (A)
31) (d) Any of the above
32) (c) Dr. Stores Ledger Control A/c
Cr. Creditors
33) (d) 720 units
34) (a) CAS-3
35) (c) Loss Rs. 4,600
36) (b) 18900 Room days
37) (d) 50%
38) (c) Behavior-wise
39) (d) More accurate external financial statements
40) (c) Oil Industry
41) (c) Store Ledger
42) (d) Engineering department
43) (b) Time spent by workers in factory
44) (b) 1,11,000
45) (a) Treated
46) (b) The use of supplementary rates
Column I Column II
i. High Inventory Turnover Ratio A Works overhead
ii. Job evaluation B Opportunity Cost
iii. Salary of Product designers C Co-Product
iv. By product value D Sales and Production Budget
v. Master Budget E Administrative Overhead
F P & L Budget
G Rationality in wage structure
H Efficient use of stock
I Purchase cost / Average inventory
J Evaluationof employee performance
Column I Column II
i. Job Ticket A A technique of Inventory Control
ii. Escalation Clause B BEP Chart
iii. VED Analysis C Contract Costing
iv. Angle of Incidence D Labour Cost Plus Factory overhead
v. Conversion Cost E A method of time booking
Column I Column II
i. Prime Cost A CAS 19
ii. Angle of Incidence B Passenger / Kilometer
iii. Operating Cost C Direct Cost
iv. Joint Cost D Constant
v. Variable Cost per unit E Profitability Rate
Column I Column II
i. Sunk Cost A Costs affected by Decision Making
ii. VED Analysis B Inventory Classification and Control
iii. Relevant Cost C Not Relevant for Decision Making
iv. FSN Analysis D Labour Incentive Method
v. F.W. Taylor E Inventory Control Technique
Column I Column II
i. Rowan A Single Rate of Overhead
ii. JIT System B Labour Turnover
iii. Blanker Overhead C Capital Structure
iv. Traditional Approach D Bonus Plan
v. Separation Method E Inventory Control
Column I Column II
i. Point Rating System A Absorbed in cost of production
ii. JIT System B Job Evaluation
iii. Normal Waste C EBIT
iv. Operating Income D Profitability Index
v. Benefit Cost Ratio E Inventory Control
Column I Column II
i. Salaries of Directors A CAS – 11
ii. Halsey Plan B Dividend Discount Model
iii. John Burr Williams C Waste Reduction Incentive
iv. Group Bonus Plan D Based on 33 1/3 % of time saved
v. Rowan Plan E Indirect labour cost
vi. Cost of new spare net cost of F Based on time saved
reconditioning old spare.
G Based on proportion of time saved
to time allowed.
H CAS – 12
Column I Column II
i. EOQ A Direct labour
ii. Sunk Cost B Inventory Management
iii. Direct worker’s contribution to PF C Profitability rate
iv. Time and Motion Study D Direct Material Cost
v. Primary Packing Material E Excluded from Cost
vi. Telephones F Labour Incentive Scheme
vii. Angle of Incidence G No. of extensions in a department
Column I Column II
i. Component of cost sheet A High initial costs
ii. Objective of Cost Accounting B Classification of cost
iii. CAS 1 C In terms of completed units
iv. Equivalent Production D Reference to the job
v. De-merit of a centralized purchase E To determine the value of closing
organization inventory
Column I Column II
i. Pollution control cost A CAS 18
ii. Joint Cost B CAS 2
Column I Column II
i. Pollution Control Cost A CAS 18
ii. Joint Cost B CAS 2
iii. Capacity Determination C CAS 10
iv. Direct Expenses D CAS 14
v. Research and Development cost E CAS 19
vi. Donations F Decision Package
vii. Notional Rent charged to G Difference in fixed cost/Difference in
contribution per unit.
viii. The method which is followed for H Average price method
evaluation of equivalent production
when prices are fluctuating.
ix. Indifference Point (in unit) I Expenses debited only in cost
accounts
x. Zero based budgeting J Appropriations only in financial
accounts
Column I Column II
i. Advertisement A Value of goods in transit
ii. Credit and Collection B Floor area occupied
iii. Ware house Rent C A percentage of cash collection
iv. Royalties D No. of orders
v. Bad Debts E Sales value
vi. Transit Insurance F Direct allocation
Column I Column II
i. Primary packing materials A Not shown in cost sheet but debited
consumed to P & L a/c.
ii. Captive power plant expense B Forms part of Office and
Administrative expenses
iii. Cash discount allowed C Forms part of selling expenses
iv. Scrap value of abnormal loss of D Treated as part of factory expenses
finished output
v. Cost of free samples of products E Treated as direct expenses
distributed
vi. Depreciation on computer F Not shown in cost sheet but credited
purchased for office to P & L a/c.
vii. Donations G Expenses debited only in the
financial accounts.
viii. Interest paid on loan H Appropriations only in financial
accounts
ix. Notional Rent charged to I Expenses debited only in cost
accounts
x. Notional Interest on Owner’s Capital J Income credited only in cost
accounts
Column I Column II
i. The contract which provide for A Average price method
payment of actual cost plus an
agreed percentage of profit
ii. In contract costing, the cost unit is B Kilowatt
iii. Abnormal loss is transferred to C Job Costing
iv. Job costing is used in D Normal Output
v. Under Job order cost system, each E Cost Plus
job is assigned one identifying job.
vi. Cost of normal loss is borne by F Per bed
vii. Inherent features of process industry G Per contract
viii. The method which is followed for H Automobile garages
evaluation of equivalent production
when prices are fluctuating.
ix. In hospital the cost unit is I Costing Profit and Loss Account
x. In electricity companies, the cost J Work in Progress
unit is
Column I Column II
i. Indifference points (in units) A Difference in Fixed Cost / Difference
in PV ratio
ii. Breakeven point (in value) B Fixed Cost / Contribution per unit
iii. Variable cost per unit C Total Sales Less BEP Sales
iv. P/V Ratio D Marginal Cost
v. Prime Cost + Variable Overhead E Fixed Cost / PV Ratio
vi. Breakeven Point (in quantity) F Difference in Fixed Cost / Difference
in Contribution per unit
vii. Indifference point (in value) G Total Contribution / Total Sales x 100
viii. Shut down point (in Quantity) H Avoidable Fixed Cost / PV Ratio
ix. Shut down point (in value) I Fixed
x. Margin of Safety J Avoidable Fixed Cost / Contribution
per unit
Column I Column II
i. Direct material yield variance A (Standard hour for actual production
minus Actual hours) x Standard Rate
ii. Direct labour rate variance B (Actual Hours at standard rate of
standard gang) minus (Actual Hours at
standards Rate of Actual Gang)
iii. Material price variance C Management by Exception
iv. Variance Analysis D (Standard Rate minus Actual Rate) x
Actual hour
v. Direct Labour yield variance E (Standard rate x Actual hours paid for)
minus (Standard rate x Actual hours
worked)
vi. Direct labour efficiency F (Standard price minus Actual Price) X
variance Actual Quantity
vii. Direct material mix variance G (Standard Quantity for actual output X
Standard Price) minus (Standard price X
Actual Quantity)
viii. Gang variance H Standard cost per unit x (Standard
output for actual mix – Actual output)
ix. Ideal time variance I (Standard yield for actual Mix minus
Actual Yield) x Standard yields Price.
x. Direct material usage variance J (Revised Standard Quantity minus
Actual Quantity) X Standard Price
Column I Column II
i. Master budget denotes the A Financial means
summary of
ii. A flexible budget takes into the B A specified period
account
iii. A budget is expressed in terms of C Flexible budget
iv. Which budget is prepared for a D Master budget
longer period
v. Budget is generally prepared for E Fixed, variable and semi variable
how long costs
vi. Which budget is prepared for more F Functional budget
than one level of activity
vii. The summary of all functional G Principle key factor
budgets
viii. Which budget is prepared at first H Capital expenditure budget
ix. Which budget shows utilization of I Decision package
liquid cash
x. Zero based budgeting J Cash Budget
Column I Column II
i. Imputed costs A Cost control technique
ii. FSN analysis B Treated as part of factory expenses
iii. Captive power plant expenses C Costing Profit and Loss A/c
iv. Abnormal loss is transferred to D Process of classifying material
v. Variance analysis E Direct allocation
F Not involving cash outlay
G Management by exception
H Decision package
Column I Column II
i. Cash discount allowed A Joint Cost
ii. Escalation Clause B Imputed Cost
iii. CAS – 19 C Direct Expenses
iv. Notional Cost D Not shown in cost sheet but debited
to profit and loss account.
v. Zero base budgeting E Sunk cost
F Contract Costing
G Decision package
H Variable Cost
Column I Column II
i. Pharma Industry A Opportunity Cost
ii. Management by exception B Direct Allocation
iii. Assessment of employee with respect to a C Joint Cost
job
iv. Royalties D Batch costing
v. CAS – 19 E Merit Rating
F Variance Analysis
G Job Evaluation
H Notional Cost
Column I Column II
i. Notional cost A Replacement method
ii. Labour turnover B Cost of utilities
iii. CAS – 10 C Production Strategy
iv. Contract Costing D Direct expenses
v. CAS – 19 E Costing department
F Imputed cost
G Escalation clause
H Decision Package
Answer Key:
Ans:1
i. H
ii. G
iii. A
iv. B
v. F
Ans:2
i. E
ii. C
iii. A
iv. B
v. D
Ans:3
i. C
ii. E
iii. B
iv. A
v. D
Ans:4
i. C
ii. E
iii. A
iv. B
v. D
Ans:5
i. D
ii. E
iii. A
iv. C
v. B
Ans:6
i. B
ii. E
iii. A
iv. C
v. D
Ans:7
i. A
ii. F
iii. B
iv. C
v. G
vi. H
Ans:8
i. B
ii. E
iii. A
iv. F
v. D
vi. G
vii. C
Ans:9
i. B
ii. C
iii. A
Ans:10
i. D
ii. E
iii. B
iv. C
v. A
Ans:11
i. D
ii. E
iii. B
iv. C
v. A
Ans:12
i. D
ii. E
iii. B
iv. C
v. A
vi. J
vii. I
viii. H
ix. G
x. F
Ans:13
i. E
ii. D
iii. B
iv. F
v. C
vi. A
Ans:14
i. E
ii. D
iii. A
iv. F
v. C
vi. B
vii. H
viii. G
ix. J
x. I
Ans:15
i. E
ii. G
iii. I
iv. H
v. C
vi. D
vii. J
viii. A
ix. F
x. B
Ans:16
i. F
ii. E
iii. I
iv. G
v. D
vi. B
vii. A
viii. J
ix. H
x. C
Ans:17
i. I
ii. D
iii. F
iv. C
v. H
vi. A
vii. J
viii. B
ix. E
x. G
Ans:18
i. F
ii. E
iii. A
iv. H
v. B
vi. C
vii. D
viii. G
ix. J
x. I
Ans:19
i. F
ii. D
iii. B
iv. C
v. G
Ans:20
i. D
ii. F
iii. A
iv. B
v. G
Ans:21
i. D
ii. F
iii. E
iv. B
v. G
Ans:22
i. F
ii. A
iii. D
iv. G
v. C
119. The balancing in costing profit and loss account represents under or over absorption
of overheads.
120. Operating costing is applied to ascertain the cost of products.
121. Cost of operating the service is ascertained by preparing job account.
122. The problem of equivalent production arises in case of operating costing.
123. FIFO methods are followed for evaluation of equivalent production when prices are
fluctuating.
124. Work in progress is the inherent feature of processing industries.
125. Costs incurred prior to the split off point are known as “Joint Costs”
126. No distinction is made between Co products and Joint Products.
127. Contact costing is variant of job costing.
128. In contact costing, the unit of cost is a job.
129. Contribution= Sales * P/V ratio.
130. Margin of Safety = Profit / P/V ratio
131. P/ V ratio remains constant at all levels of activity.
132. Marginal Costing follows the behaviour wise classification of costs.
133. At breakeven point, contribution available is equal to total fixed cost.
134. Breakeven point = Profit / P/V ratio.
135. Marginal cost is aggregate of Prime Cost and Variable cost.
136. Variable cost remains fixed per unit.
137. Contribution margin is equal to Sales – Fixed cost.
138. Variable cost per unit is variable.
139. Excess of Actual cost over Standards Cost is treated as unfavourable variance.
140. Variances are calculated for both material and labour.
141. While fixing standards, normal losses and wastages are taken into account.
142. Under the system of standard costing, there is no need for variance analysis.
143. Standard costing is an ideal name given to the estimate making.
144. Standards cost, once fixed cannot be altered.
145. Predetermined standards provide a yardstick for the measurement of efficiency.
146. Material cost variance and labour cost variance are always equal.
147. Fixing standards is the work of industrial engineer or the production people and not
of cost accountant.
148. Budget is a means and budgetary control is the end result.
149. To achieve the anticipated targets, Planning, Co-ordination and Control are the
important main tasks of management, achieved through budgeting and budgetary
control.
150. A key factor or principal factor does not influence the preparation of all other
budgets.
151. Budgetary control does not facilitate introduction of ‘Management by Exception’.
152. Generally, budgets are prepared to coincide with the financial year so that
comparison of the actual performance with budgeted estimates would facilitate
better interpretation and understanding.
153. A flexible budget is one, which changes from year to year.
154. Sales budget, normally, is the most important budget among all budgets.
155. The principal factor is the starting point for the preparation of various budgets.
156. A budget manual is the summary of all functional budgets.
157. Factory overhead cost applied to a job is usually based on a pre-determined rate.
158. CAS-19 deals with the principles and methods of determining the manufacturing cost
of excisable goods.
159. Cost ledger control account makes the cost ledger self-balancing.
160. FIFO method is followed for evaluation of equivalent production when prices are
fluctuating.
161. Standard costs and budgeted costs are inter-related and inter-dependent.
162. Multiple costing is suitable for banking industry.
163. There is inverse relationship between batch size and carrying costs.
164. Marginal costing follows the identifiability wise classification of costs.
Answer Key:
1. False
2. False
3. False
4. False
5. False
6. False
7. True
8. False
9. True
10. False
11. True
12. False
13. False
14. False
15. False
16. False
17. True
18. True
19. False
20. True
21. False
22. False
23. False
24. True
25. False
26. True
27. True
28. True
29. False
30. False
31. True
32. False
33. False
34. True
35. True
36. False
37. True
38. True
39. True
40. True
41. False
42. False
43. True
44. False
45. False
46. True
47. False
48. False
49. False
50. True
51. False
52. False
53. True
54. False
55. False
56. False
57. True
58. False
59. True
60. True
61. True
62. False
63. False
64. True
65. False
66. True
67. False
68. False
69. True
70. False
71. True
72. True
73. False
74. True
75. True
76. False
77. False
78. True
79. True
80. False
81. True
82. True
83. True
84. True
85. False
86. False
87. True
88. False
89. False
90. True
91. True
92. True
93. False
94. False
95. True
96.True
97.False
98.False
99.True
100.False
101.False
102.False
103.False
104.True
105.True
106.False
107.False
108.False
109.False
110.False
111.False
112.False
113.False
114.False
115.True
116.True
117.False
118.True
119.False
120.False
121.False
122.False
123.False
124.True
125.True
126.False
127.True
128.False
129.True
130.True
131.True
132.True
133.True
134.False
135.False
136.True
137.False
138.False
139.True
140.True
141.True
142.False
143.False
144.True
145.True
146.False
147.False
148.True
149.True
150.False
151.False
152.True
153.False
154.True
155.True
156.False
157.True
158.False
159.True
160.False
161.False
162.False
163.False
164.False
165.False
166.False
167.False
168.True
169.True
170.True
171.True
34. In the ______ method of pricing material issues, where the prices are falling, profits will
rise.
35. In India, commercial papers can be issued in multiples of Rs. ________
36. When raw material is accounted at standard cost, variances due to normal reasons
will be treated as __________________cost (give the element of cost).
37. Cost of idle time (idle hours x hourly rate) incurred by a worker directly working on a
product is treated as _________________________________ (give the element of cost).
38. Royalty payable based on the right to sell is treated as ___________________________
(give the element of cost).
39. When time saved is equal to time taken then earnings of a worker under Halsey Plan
and Rowan Plan are the ________
40. The difference between actual and absorbed factory overhead is called
_____________________________.
41. Under-absorption of _____________ results in higher amount of profit.
42. Direct Expenses incurred for brought out resources shall be determined at
___________________.
43. Total cost +Profit = ____________.
44. In _____________ Systems, basis of wages payment is the quantity of work.
45. Current Ratio is the ratio of Current Assets to ____________________.
46. In standard costs, ____________________ norm is applied as a scale of reference for
assessing actual cost to serve as a basis of cost control.
47. Material Transfer Note is a ________________ for transferring the materials from one job
to other job.
48. One of the disadvantages of overtime working is incurring
____________________________labour cost.
49. CAS-2 deals with Cost Accounting Standard on ____________ determination.
50. Where the cost and financial accounts are maintained independently of each other, it
is indispensable to ___________ them, as there are differences in the profits of two sets
of books.
51. Maximum Level = (_____________ +Re-order Quantity) - (Minimum Consumption Rate ×
Minimum Re-order Period).
52. CAS-8 deals with the principles and methods of determining the _________________.
53. Store Ledger is kept and maintained in ____________.
54. In a company there were 1200 employee on the rolls at the beginning of a year and
1180 at the end. During the year 120 persons left services and 96 replacements were
made. The labour turnover to flux method is _____.
55. Ideal time arises only when workers are paid on ______ basis.
56. Normal idle time costs should be charged to ___________________ while that due to
abnormal reasons should be charged to ___________________.
57. Direct Expenses incurred for brought out resources shall be determined at
____________________.
58. Direct Expenses incurred lump-sum shall be ____________.
59. Overhead incurred Rs. 16,000 and overhead absorbed Rs. 15,300. There is under
absorption of _____
60. Under integrated accounting system, the accounting entry for payment of wages is to
debit _________________________ and to credit cash.
61. Two principle method of evaluation of equivalent production are ______ and
__________________.
62. When sales are Rs. 300,000 and variable cost is Rs. 180,000, P/V ratio will be _____
63. Goods Received Note is prepared by the ______________________.
64. Transfer of surplus material from one job or work order is recorded in
______________________.
65. _____________________ is discount allowed to the bulk purchaser.
66. ______________________ is a document which records the return of unused materials.
67. In _________________________ systems, twopiece rates are set for each job.
68. The formula for computing wages under time rate is _________________________.
69. In Halsey plan, a worker gets bonus equal to ____ of the time saved.
70. Under Gantt Task and Bonus Plan, no bonus is payable to a worker, if his efficiency is
less than______.
71. Wages sheet is prepared by ________ department.
72. Direct Expenses relate to ________________ or __________________.
73. Penalties/ damages paid to statutory authorities’ _________ be form part of Direct
Expenses.
74. A Direct Expenses related to a _________ form part of the Prime Cost.
75. Overheads are an aggregate of ________________ and
______________and________________
76. Example of after sales services are ____________________ and ___________________
77. Administration overheads are usually absorbed as a percentage of ____________.
78. The difference between actual and absorbed factory overhead is called
_________________________.
79. The term used for charging of overheads to cost units is known as ________________
80. The difference between practical capacity and the capacity based on sales
expectancy is known as ________________.
81. The ____________________ rate is computed by dividing the overheads by the
aggregate of the productive hours of direct workers.
82. Under or over absorption of overheads arises only when overheads are absorbed by
____________________________________.
83. Overhead incurred Rs. 16,000 and overhead absorbed Rs. 15,300. There is under
absorption of ______
84. In Absorption Costing ______ cost is added to inventory.
85. Prime cost + Overheads = _________
86. ______________ +Profit = Sales.
87. Direct Material + _____________ +Direct Expenses=Prime Cost.
88. Salary paid to factory manager is an item of ___________________.
89. In Reconciliations Statements, Incomes shown only in Financial accounts are
________________________.
90. In Reconciliations Statements, Expenses shown only in cost accounts are
____________________.
91. In Reconciliations Statements, overheads Over-Recovered in cost accounts are
______________________.
92. In Reconciliations Statements, overheads Under Recovered in cost accounts are
__________________.
93. Notional remuneration to owner is expense debited only in________________.
94. All the transactions relating to materials are recorded through_______________.
95. The net balance of _____________________ represents net profit or net loss.
96. WIP ledger contains the accounts of all the _____which are under ___________.
97. The two traditional systems of accounting for integration of cost and financial
accounts are the _________________ and the ____________________.
98. Under integrated accounting system, the accounting entry for payment of wages is to
debit ___________________ and to credit cash.
99. Cost of _______________ loss is not borne by good units.
100. If the actual loss in a process is less than the normal loss, the difference is known as
_____________________.
101. ______________Costs are incurred after split off point.
102. The______ product generally has a greater sale value than by product.
103. Statement of cost per unit of equivalent production shows the per unit cost
__________________.
104. In hospital the cost unit is __________.
105. In electricity companies, the cost unit is ___________.
106. The method of costing used in undertaking like gas companies, cinema houses,
hospitals etc is known as ___________________.
107. In motor transport costing two example of fixed cost are________________ and
__________________.
108. Variable cost per unit is _________
109. Marginal cost is the _______ of sales over contribution.
110. P/V ratio is the ratio of _______________to sales.
111. If variable cost to sales ratio is 60%, P/V ratio is ____.
112. ________________ + Variable overhead = Marginal Cost.
113. When sales are Rs. 300,000 and variable cost is Rs. 180,000, P/V ratio will be ____.
114. Variable cost remains _______________.
115. Margin of safety is_____________________________.
116. Breakeven point is ____________________.
117. Contribution margin equals to _____________________
118. Standard cost is a _______________ cost.
119. Standard cost when fixed is recorded on _________________ card.
120. Historical costing uses post period costs while standards costing uses
_________________ costs.
121. Three types of standards are ____________________________.
122. The _____________________ is usually the co-ordinator of the standards committee.
123. Standards cost when fixed are recorded on _________________ card.
124. Basicallythere are two types of standards viz, a) Basic standards, and
____________________.
125. When actual cost is less than the standards cost, it is known as _______________
variance.
126. Standard Costing is one of the _____________ techniques.
127. Standard means a criterion or a yardstick against which actual activity can be
compared to determine the ____________ between two.
128. Budgets are _______ plans.
129. The key factor in a budget does not remain the _______ every year.
130. Cash budget is a part of __________ budget.
131. _____________ budgets are subsidiary to master budget.
132. ________________ leads to budgeting and budgeting leads to budgetary control.
133. ______________ Control involves checking and evaluation of actual performance.
134. A budget is a _____ to management.
135. The principle budget factor for consumer goods manufacture is normally
_____________.
136. A budget is a projected plan of action in _________________________________.
137. ______________ is the process of regulating the action so as to keep the element of
cost within the set parameters.
138. CAS ___ stands for cost of service cost Centre.
139. At _______________ contribution available is equal to total fixed cost.
140. The document which describes the budgeting organisation, budgeting procedure
etc. is known as ___________________.
141. ___________________ is discount allowed to the bulk purchaser.
142. CAS ___ stands for cost of utilities.
143. If the actual loss in a process is less than the normal loss, the difference is known as
_____________________________.
144. The principal budget factor for consumer goods manufacturer is normally
_____________________.
145. Differential cost is the change in the cost due to change in ________from one level to
another.
146. In contract costing, the cost unit is ________________.
147. _______ costs are historical costs which are incurred in the past.
148. CAS-2 deals with Cost Accounting Standard on __________ determination.
149. _______________ is the summary of all functional budgets.
150. Standard costing is one of the ______________ techniques.
Answer Key:
1. is constant
2. Fixed Cost Value
3. Abnormal
4. WIP Control
5. Components or Spare Parts
6. Work Cost
7. Fixed
8. Quantitative
9. material cost
10. Fixed Cost
11. Margin of Safety
12. Financial
13. Inversely
14. Rs. 22,000
15. Uniform Costing
16. direct expenses
17. costing
18. Apportionment/Allocation
19. Direct
20. Conversion
21. Direct Cost
22. Productivity
23. Store Keeper or Stores Personnel
24. Overheads
25. Costing Profit and Loss
26. Costing
27. Opportunity/Notional/Imputed
28. Actual
29. direct material
30. Idle
31. Forfeiting
32. Actual
33. Material
34. LIFO
35. 5 lacs
36. Direct Material
37. Factory overheads or works overhead
38. Selling Overheads or Selling and Distribution Overheads
39. Same
40. Overheads
41. Overhead
42. invoice price
43. Selling Price
44. Piece Rate
45. Current Liabilities
46. Predetermined
47. Document
48. excess (or additional or more or high)
49. capacity
50. reconcile
51. Reorder Level
52. Cost of utilities
53. cost office
54. 9.08
55. Time
56. Production overhead, Costing P & L A/c
57. Invoice Price
58. Amortized
59. Rs. 700
60. Wages Control Account
61. FIFO, Average Method
62. 40%
63. Receiving Department
64. Material Transfer Note
65. Quantity Discount
66. Material Return Note
67. Taylors Differential Piece Rate
68. Hour worked x Rate per hour
69. 50%
70. 100%
71. Pay Roll
72. manufacturing of a product or rendering of service
73. shall not
74. product
75. Indirect Material, Indirect Labour , Indirect Expenses
76. Repair and Maintenance , Replacement of components
77. Works Cost
78. Overheads
79. Absorptions
80. Idle Capacity
81. Direct Labour Hour
82. overheads rates
83. Rs. 700
84. Fixed
85. Total Cost
86. Cost of Sales
87. Direct Wages
88. Factory Overhead
89. Added to Costing Profit.
90. Added to Costing Profit
91. Deducted from Costing Profit.
92. Added to financial profit.
93. Cost Accounts
94. Stores Ledger Control Accounts
95. Costing Profit and Loss Account
96. Jobs, Execution
97. Double Entry Method, Third Entry Method
98. Control Accounts
99. Abnormal
100. Abnormal Gain
101. Subsequent
102. Main
103. Element wise
104. Per Bed
105. Kilowatt
106. Operating Cost
107. Insurance and Depreciation
108. Fixed
109. Excess
110. Contribution
111. 40
112. Prime Cost
113. 40%
114. fixed per unit
115. Actual sales – Sales at Break Even Point
116. Total Fixed Cost / PV Ratio
117. Sales – Variable Cost
118. Predetermined
119. Standard Cost
120. Predetermined
121. Current, Basic and Normal Standard
122. Cost Accountants
123. Standard Cost
124. Current Standard
125. Favourable
126. Cost Control
127. Difference
128. Action
129. Same
130. Financial
131. Functional
132. Forecasting
133. Budgetary
134. Aid
135. Sales, Demand
136. Physical units and monetary terms
137. Cost Control
138. 13
139. Break Even point
140. Budget Manual
141. Quantity Discount / Trade Discount / Cash discount
142. 8
143. Abnormal gain / Abnormal profit
144. Sales Demand / Market Demand / Lack of Demand
145. Activity
146. per contract
147. Sunk
148. Capacity
149. Master Budget
150. Cost Control
Notes
………………………………………………………………………………………………………………………
………………………………………………………………………………………………………………………
………………………………………………………………………………………………………………………
………………………………………………………………………………………………………………………
………………………………………………………………………………………………………………………
………………………………………………………………………………………………………………………
………………………………………………………………………………………………………………………
………………………………………………………………………………………………………………………
………………………………………………………………………………………………………………………
………………………………………………………………………………………………………………………
………………………………………………………………………………………………………………………
………………………………………………………………………………………………………………………
………………………………………………………………………………………………………………………
………………………………………………………………………………………………………………………
………………………………………………………………………………………………………………………
………………………………………………………………………………………………………………………
………………………………………………………………………………………………………………………
Å +91-33-2252 1031/34/35/1602/1492
Delhi Office
CMA Bhawan, 3 Institutional Area, Lodhi Road, New Delhi - 110003
Å +91-11-24666100