Asset Privatization V TJ Enterprises
Asset Privatization V TJ Enterprises
Asset Privatization V TJ Enterprises
DECISION
TINGA, J.:
Petitioner argued that upon the execution of the deed of sale it had
complied with its obligation to deliver the object of the sale since
there was no stipulation to the contrary. It further argued that being
a sale on an as-is-where-is basis, it was the duty of respondent to
take possession of the property. Petitioner claimed that there was
already a constructive delivery of the machinery and equipment.
The RTC ruled that the execution of the deed of absolute sale did
not result in constructive delivery of the machinery and equipment.
It found that at the time of the sale, petitioner did not have control
over the machinery and equipment and, thus, could not have
transferred ownership by constructive delivery. The RTC ruled that
petitioner is liable for breach of contract and should pay for the
actual damages suffered by respondent.
I.
II.
The Court of Appeals erred in not considering that the sale was on
an "as-is-where-is" basis wherein the properties were sold in the
condition and in the place where they were located.
III.
IV.
The reason for the failure to make actual delivery of the properties
was not attributable to the fault and was beyond the control of
petitioner. The claim for damages against petitioner is therefore
bereft of legal basis.8
On the second issue, petitioner posits that the sale being in an as-
is-where-is basis, respondent agreed to take possession of the
things sold in the condition where they are found and from the place
where they are located. The phrase as-is where-is basis pertains
solely to the physical condition of the thing sold, not to its legal
situation.16 It is merely descriptive of the state of the thing sold.
Thus, the as-is where-is basis merely describes the actual state and
location of the machinery and equipment sold by petitioner to
respondent. The depiction does not alter petitioner's responsibility
to deliver the property to respondent.ςηαñrοblεš νιr†υαl lαω lιbrαrÿ
Anent the third issue, petitioner maintains that the presence of the
disclaimer of warranty in the deed of absolute sale absolves it from
all warranties, implied or otherwise. The position is untenable.
As to the last issue, petitioner claims that its failure to make actual
delivery was beyond its control. It posits that the refusal of Creative
Lines to allow the hauling of the machinery and equipment was
unforeseen and constituted a fortuitous event.
Moreover, Art. 1504 of the Civil Code provides that where actual
delivery has been delayed through the fault of either the buyer or
seller the goods are at the risk of the party in fault. The risk of loss
or deterioration of the goods sold does not pass to the buyer until
there is actual or constructive delivery thereof. As previously
discussed, there was no actual or constructive delivery of the
machinery and equipment. Thus, the risk of loss or deterioration of
property is borne by petitioner. Thus, it should be liable for the
damages that may arise from the delay. ςηαñrοblεš νιr†υαl lαω lιbrαrÿ
Article 1170 of the Civil Code states: "Those who in the performance
of their obligations are guilty of fraud, negligence, or delay and
those who in any manner contravene the tenor thereof are liable for
damages." In contracts and quasi-contracts, the damages for which
the obligor who acted in good faith is liable shall be those that are
the natural and probable consequences of the breach of the
obligation, and which the parties have foreseen or could have
reasonably foreseen at the time the obligation was constituted.24The
trial court correctly awarded actual damages as pleaded and proven
during trial.25
WHEREFORE, the Court AFFIRMS in toto the Decision of the Court of
Appeals dated 31 August 2004. Cost against petitioner.
SO ORDERED.