Spog - Kg-Dwn-98/2 Cluster Ii Fpso Ptkss Block Fabrication Schedule

1. PT. KARIMUN SEMBAWANG SHIPYARD provides a fabrication schedule for blocks in the PTKSS FPSO project through August 2020. 2. The schedule outlines 19 total blocks across 5 sequences, including load-bearing quarters, pipe rack stools, and crane pedestals. 3. Fabrication is scheduled to take place at PTKSS and includes material receiving, lofting, cutting, and block construction, with target completion dates for each sequence.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
91 views1 page

Spog - Kg-Dwn-98/2 Cluster Ii Fpso Ptkss Block Fabrication Schedule

1. PT. KARIMUN SEMBAWANG SHIPYARD provides a fabrication schedule for blocks in the PTKSS FPSO project through August 2020. 2. The schedule outlines 19 total blocks across 5 sequences, including load-bearing quarters, pipe rack stools, and crane pedestals. 3. Fabrication is scheduled to take place at PTKSS and includes material receiving, lofting, cutting, and block construction, with target completion dates for each sequence.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 1

PT.

KARIMUN SPOG - KG-DWN-98/2 CLUSTER II FPSO


SEMBAWANG
SHIPYARD PTKSS BLOCK FABRICATION SCHEDULE
Updated Date 10-Jun-20
SCM PM -
Tan ST
SCM PTKSS
Overall Weight
Block Block Proposed Required Mold Loft Barge ETA Material Receive Material Receive Material Fabrication Fabrication
No Sequence (004) Actual Lofting Material Plate Cutting Material PTKSS Fabrication Fabrication
Type Name Fab.Location Revised Shipment Singapore PTKSS PTKSS Received Gain Gain
(Delivery) IFC Received SUB- Duration
Sequence
(Ton) Finish Date Issue Date Issue Date Start Date Finish Date Cutting (%) ETA Date Plan Date Actual Date Weight (Ton) (%) CONT. Start Date Finish Date Weight (Ton) (%)

1 1ST LQ QCS PTKSS 37.28 30-Jun-20 In Hand In Hand Issued 2020-05-18 2020-05-23 100.0% 1st 2020-05-20 2020-05-25 2020-05-27 30.42 81.6% KJP 2020-05-29 2020-06-28 30 7.90 21.2%

2 1 ST LQ QCP PTKSS 36.49 30-Jun-20 In Hand In Hand Issued 2020-05-15 2020-05-18 100.0% 1 st
2020-05-20 2020-05-25 2020-05-27 30.96 84.8% KTA 2020-05-29 2020-06-28 30 5.66 15.5%
Pipe Rack
3 1 ST
Stool PS1A PTKSS 2.89 30-Jun-20 In Hand In Hand Issued 2020-05-22 2020-05-31 100.0% 2 nd
2020-06-04 2020-06-09 0.0% 2020-05-29 2020-06-28 30
Pipe Rack
4 1 ST
Stool PS1B PTKSS 3.07 30-Jun-20 In Hand In Hand Issued 2020-05-17 2020-05-19 100.0% 1 st
2020-05-20 2020-05-25 2020-05-27 1.95 63.5% CTN 2020-05-29 2020-06-28 30 0.61 21.2%

5 2ND LQ QDP PTKSS 29.29 15-Jul-20 In Hand In Hand Issued 2020-05-27 2020-06-07 82.0% 2nd 2020-06-04 2020-06-09 0.0% 2020-06-15 2020-07-15 30

6 2ND LQ QDS PTKSS 30.93 15-Jul-20 In Hand In Hand Issued 2020-05-13 2020-05-20 100.0% 1st 2020-05-20 2020-05-25 2020-05-27 26.72 86.4% KTA 2020-05-29 2020-06-28 30 4.83 15.6%
Pipe Rack
7 2ND Stool PS1 PTKSS 2.56 15-Jul-20 In Hand In Hand Issued 2020-05-22 2020-05-31 100.0% 2nd 2020-06-08 2020-06-13 0.0% 2020-06-15 2020-07-15 30
Pipe Rack
8 2ND Stool PS2 PTKSS 3.60 15-Jul-20 In Hand In Hand Issued 2020-06-02 2020-06-07 100.0% 2nd 2020-06-08 2020-06-13 0.0% 2020-06-15 2020-07-15 30

9 3 RD LQ QAP PTKSS 64.63 30-Jul-20 In Hand In Hand Issued 2020-06-06 2020-06-06 100.0% 2 nd
2020-06-08 2020-06-13 0.0% 2020-06-15 2020-07-30 45

10 3 RD LQ QAS PTKSS 72.29 30-Jul-20 In Hand In Hand Issued 2020-06-07 85.0% 2 nd


2020-06-08 2020-06-13 0.0% 2020-06-15 2020-07-30 45
Pipe Rack
11 3 RD
Stool PS3 PTKSS 20.00 30-Jul-20 In Hand In Hand Issued next blk to start cutting 3 rd
2020-06-22 2020-06-27 0.0% 2020-06-29 2020-07-29 30
Pipe Rack
12 3 RD
Stool PS4 PTKSS 2.56 30-Jul-20 In Hand In Hand Issued next blk to start cutting 3 rd
2020-06-22 2020-06-27 0.0% 2020-06-29 2020-07-29 30

13 4TH LQ QBP PTKSS 27.07 15-Aug-20 In Hand In Hand Issued 2020-06-01 2020-06-05 100.0% 3rd 2020-06-22 2020-06-27 0.0% 2020-06-29 2020-07-29 30

14 4TH LQ QBS PTKSS 36.18 15-Aug-20 In Hand In Hand Issued 2020-06-01 2020-06-05 100.0% 3rd 2020-06-22 2020-06-27 0.0% 2020-06-29 2020-07-29 30
Pipe Rack
15 4TH Stool PS4A PTKSS 20.00 15-Aug-20 O/S O/S 4th 2020-07-06 2020-07-11 0.0% 2020-07-13 2020-08-12 30

16 5TH LQ QEP PTKSS 16.44 30-Aug-20 In Hand In Hand Issued 4th 2020-07-06 2020-07-11 0.0% 2020-07-13 2020-08-12 30

17 5 TH LQ QES PTKSS 17.07 30-Aug-20 In Hand In Hand Issued 4 th


2020-07-06 2020-07-11 0.0% 2020-07-13 2020-08-12 30

18 5 TH Crane CPP1 PTKSS 50.00 30-Aug-20 2020-05-20 2020-07-06 4 th


2020-07-06 2020-07-11 0.0% 2020-07-13 2020-09-11 60
Pedestal

19 5 TH Crane CPP2 PTKSS 50.00 30-Aug-20 O/S O/S 4 th


2020-07-06 2020-07-11 0.0% 2020-07-13 2020-09-11 60
Pedestal

20 5 TH Crane CPS1 PTKSS 50.00 30-Aug-20 2020-05-20 2020-07-06 4 th


2020-07-06 2020-07-11 0.0% 2020-07-13 2020-09-11 60
Pedestal

21 5TH Hull EGR PTKSS 25.00 30-Aug-20 2020-05-13 2020-07-13 5TH 2020-07-20 2020-07-25 0.0% 2020-07-27 2020-08-26 30

22 5TH Module MS40 PTKSS 60.00 30-Aug-20 2020-05-07 2020-08-02 4th 2020-07-06 2020-07-11 0.0% 2020-07-13 2020-08-27 45
Stool

6TH Module MS90 PTKSS 60.00 5-Sep-20 In Hand In Hand Issued next blk to start cutting 4th 2020-07-06 2020-07-11 0.0% 2020-07-13 2020-08-27 45
Stool

6TH Module MS53 PTKSS 60.00 5-Sep-20 In Hand In Hand Issued next blk to start cutting 4th 2020-07-06 2020-07-11 0.0% 2020-07-13 2020-08-27 45
Stool

6 TH Module MS51 PTKSS 60.00 5-Sep-20 2020-05-07 2020-06-25 4 th


2020-07-06 2020-07-11 0.0% 2020-07-13 2020-08-27 45
Stool

6 TH Module MS54 PTKSS 60.00 5-Sep-20 2020-05-07 2020-07-31 4 th


2020-07-06 2020-07-11 0.0% 2020-07-13 2020-08-27 45
Stool

23 7 Th LQ QFP PTKSS 21.08 15-Sep-20 In Hand In Hand Issued 5 TH


2020-07-20 2020-07-25 0.0% 2020-07-27 2020-08-26 30

24 7 Th LQ QFS PTKSS 19.00 15-Sep-20 In Hand In Hand Issued 5 TH


2020-07-20 2020-07-25 0.0% 2020-07-27 2020-08-26 30

25 7 Th LQ QHU PTKSS 18.00 15-Sep-20 In Hand In Hand Issued 2020-05-30 2020-06-02 100.0% 5 TH
2020-07-20 2020-07-25 0.0% 2020-07-27 2020-08-26 30

30 8TH Pipe Rack MPR1 PTKSS 75.00 30-Sep-20 O/S O/S 5TH 2020-07-20 2020-07-25 0.0% 2020-07-27 2020-09-25 60
Structure

31 9TH Module MS20 PTKSS 60.00 15-Oct-20 2020-05-07 2020-07-05 6TH 2020-08-03 2020-08-08 0.0% 2020-08-10 2020-09-24 45
Stool

32 9TH Module MS30 PTKSS 30.00 15-Oct-20 In Hand In Hand Issued 6TH 2020-08-03 2020-08-08 0.0% 2020-08-10 2020-09-24 45
Stool

33 9TH Pipe Rack MPR2 PTKSS 75.00 15-Oct-20 O/S O/S 6TH 2020-08-03 2020-08-08 0.0% 2020-08-10 2020-10-09 60
Structure

34 10 TH Module MS31 PTKSS 60.00 30-Oct-20 2020-05-09 2020-06-01 7 TH


2020-08-17 2020-08-22 0.0% 2020-08-24 2020-10-08 45
Stool

35 11 TH Heli-Deck HDK PTKSS 100.00 30-Nov-20 2020-05-27 2020-07-20 7 TH


2020-08-17 2020-08-22 0.0% 2020-08-24 2020-11-24 90

36 Module MS52 PTKSS 60.00 O/S O/S Do not have MS50 Module Stools according to Tan ST Information
Stool