NHPC2
NHPC2
NHPC2
Modern times. Increasing automation of Indian industries has created huge demand of power
in India. This huge demand has resulted into demand supply gap in India in recent times.
India is one of the main manufacturers and users of energy. Globally, India is presently
positioned as the 11th largest manufacturers of energy. It is also the worlds’ 6th largest
energy users. In spite of its extensive yearly energy output, Indian power sector is a regular
importer of energy because of huge disparity. Global and Indian economy have decelerated,
but power is one of the few commodities in short supply in India. So, despite the sluggishness
in production and demand for manufactured products, India remains power hungry, both in
terms of normal and peak power demand. Power is derived from various sources in India.
These include thermal power, hydropower or hydroelectricity, solar power, biogas energy,
wind power etc. The distribution of the power generated is undertaken by Rural
Electrification Corporation for electricity power supply. Energy is a basic requirement for
transport, commercial and domestic – needs inputs of energy. The renewable energy based
power generation capacity presently constitutes 5% of the total installed capacity in the
country for power generation from all sources. The country is aiming to achieve up to 10% of
additional installed capacity to be set up till 2012 to come from renewable energy sources.
Hydro power is a renewable economic non polluting and environmentally benign source of
energy. Hydro Power stations have inherent ability for instantaneous starting, stopping, load
variations etc. & help in improving reliability of power system. Hydro stations are the best
1 | Page
choice for meeting the peak demand. The generation cost is not only inflation free but
reduces with time Hydroelectric projects have long useful life extending over 50 years and
help in conserving scarce fossil fuels. They also help in opening of avenues for development
As the world is facing the crisis of “Global Warming” and the shortage of fuel is causing a
problem for energy generation, so to avoid these problems the trend is to develop the cleaner
The project comprised of study of Hydro Power regulations of CERC. The project has been
undertaken with the objective of understanding and critically analyzing the power
generation tariff structure followed by National hydro power Corporation of India Ltd.
This tariff structure is governed by the administered pricing based on norms notified by
Central Electricity Regulation commission in line with the tariff policy notified by GOI.
Along with the inclination of fully achieving this objective the report also covers the
following areas:
Comparison of the current tariff structure with the one being followed earlier.
To determine the areas of tariff where GENERATION could have benefited if the
new tariff norms had been followed from the very beginning.
2 | Page
In the end some suggestions and recommendations are given as per the findings of the
project. Tariff for a sample hydro power plant was also determined.This project is an attempt
to review out the various issues with the tariff structure and their determination.
and discuss with the concerned dealing officers, and correlate the procedures with different
books and journals and to come out with some heartfelt suggestions which I hope will be of
good use to its users and any suggestion to improve it would be a welcome.
3 | Page
OBJECTIVES OF THE STUDY
To study the methodology adopted by NHPC for pricing of GENERATION services and
critically analyse the power GENERATION tariff structure followed by the National hydro
power Corporation of India Ltd. Along with the inclination of fully achieving this objective
To study and calculate various parameters required for calculation of tariff for
To see if there is still scope for improvement in new tariff norms and how tariff
To Study the Various problems faced by the NHPC.Ltd , while determining the
4 | Page
.
RESEARCH METHODOLOGY
This chapter presents the basic methodology and requirements in research. It includes the
nature and scope of the study, method of study, source of data, literature survey and methods
The study is descriptive and analytical in nature, as it lends to elaborate on the process of
determination of tariff structure. The study takes into account the theoretical as well as the
This study is about the analysis of tariff development of hydropower plant in India. The study
is descriptive in nature. The researcher has utilized the descriptive method in acquiring
Since the report required studying the theoretical as well as the practical aspects of financing
1. Primary data.
2. Secondary data.
5 | Page
1. Primary data - mainly I have a discussion with commercial department on the related
topics, understanding the various aspects in tariff determination, the effect of new regulation
2. Secondary data – going through with the company manual, books, journals, internet to
collect the related and latest information which is useful for the project.
LITERATURE SURVEY:
Extensive reading have been done from annual reports of NHPC Ltd., various guidelines
issued by GOI with respect to the tariff , Electricity Act, 2003; Tariff guidelines issued by
The report thus contains the mix of all the above-mentioned sources. The summary and
6 | Page
This project has various boundaries which are require to be overcome:
Each hydro power plant is unique in itself and may be exposed to different geological
constraints. So same set of parameters can’t be applied to all hydro power plants.
major constraint.
The project lacked the practical touch as interaction with the officials of the
Companies which made the detailed project reports (DPRs) was minimal.
Confidential information:- In depth knowledge about each factor is not possible due to
confidential in nature.
Power is an essential requirement for all facets of our life and has been recognized as a basic
human need. It is the critical infrastructure on which the socio-economic development of the
7 | Page
country depends. The growth of the economy and its global competitiveness hinges on the
availability of reliable and quality power at competitive rates. The demand of power in India
is enormous and is growing steadily. The vast Indian power market, today offers one of the
India is endowed with a wealth of rich natural resources and sources of energy. Resources for
power generation are unevenly dispersed across the country. This can be appropriately and
optimally utilized to make available reliable supply of electricity to each and every
household. Electricity is considered key driver for targeted 8 to 10% economic growth of
India. Electricity supply at globally competitive rates would also make economic activity in
As per the Indian Constitution, the power sector is a concurrent subject and is the joint
responsibility of the State and Central Governments. The power sector in India is dominated
by the government. The State and Central Government sectors account for 58% and 32% of
the generation capacity respectively while the private sector accounts for about 10%. The
bulk of the transmission and distribution functions are with State utilities. The private sector
has a small but growing presence in distribution and is making an entry into transmission.
Power Sector which had been funded mainly through budgetary support and external
Some facts
8 | Page
More than 64% of India’s total installed capacity is contributed by thermal power.
Significant jump in unit size and steam parameters will result in higher efficiencies
Western region accounts for largest share (30.09%) of the installed power in India
Unbalanced growth remains the cause of concern for the Indian power sector. Only
about 56% of households have access to electricity, with the rural access being 44%
Southern region remains the dominant region in renewable energy source accounting
for more than 57% of the total renewable energy installed capacity.
making India the third largest producer of electricity in Asia. Generating capacity has grown
manifold from 1,362 MW in 1947 to 141GW (as on 30.09.2004). The overall generation in
India has increased from 301 Billion Units (BUs) during 1992- 93 to 558.1 BUs in 2003.
India’s Total installed capacity of power sector has been 141 GW. This India’s 141GW of
total power is generated by its three different sectors, i.e., state sector, central sector and
private sector. Stare sector contribution has been 53% to total installed capacity. Likewise,
contribution of central sector and private sector has been 34% and 13.5% respectively.
9 | Page
India's total installed capacity
14%
state sector(53.5%)
central sector(34%)
private sector(13.5%)
53%
34%
30.00%
20.00%
10.00%
0.00%
total thermal Hydro Nuclear Res
India has fifth largest generation capacity in the world and low per capita consumption at
631 units which is less than half of china. India’s transmission and distribution network is of
6.6 million circuit km. This is considered to be third largest in the world. As per above chart,
thermal fuels like Coal, gas, oil constitute 64.6% of India’s total installed capacity, followed
by 24.7% from hydro power, 2.9% nuclear energy and 7.7% from other energy sources.
10 | P a g e
INDUSTRY STRUCTURE
Power sector structure in India has been very simple yet well defined. Majority of
Generation, Transmission and Distribution capacities are with either public sector companies
or with State Electricity Boards (SEBs). National thermal power corporation, Nuclear Power
Corporation, National Hydro Electric Power Corporation are the public sector companies in
India which are into power generation. TATA power, Reliance Energy is domestic private
players and CLP, Marubeni Corporation is international private players in power sector.
public sector is only power generation. Private sector participation is increasing especially in
Generation, transmission and Distribution. Distribution licences for several cities are already
with the private sector. Three large ultra-mega power projects of 4000MW each have been
POLICY
11 | P a g e
Indian Power Policy framework is designed and developed under Electricity Act 2003 and
National Electricity Policy 2005. Under current policy the Government is keen to draw
private investment into the sector.100% FDI permitted in Generation, Transmission &
Distribution of power and no discrimination is made in terms of foreign private and domestic
private players. All the companies (domestic and private) in this particular sector are treated
at par. Incentives like, Income tax holiday for a block of 10 years in the first 15 years of
operation; waiver of capital goods' import duties on mega power projects (above 1,000 MW
generation capacity) is being provided. Independent Regulators that exist in Indian power
sector are a) Central Electricity Regulatory Commission for central PSUs B)centreal
NHEPC 2755(MW)
NPC 1412(MW)
DOMESTIC PRIVATE
SECTOR
TATA power 2323(MW)
INRERNATIONAL
PRIVATE SECTOR
CLP 655(MW)
MC 347(MW)
12 | P a g e
Above table depicts that NTPC has got highest installed capacity (29144MW) in the public
sector. Secondly, all three players in the public sector have restricted their business only to
power generation. In domestic private sector, TATA Power is the biggest player with
installed capacity of 2323 MW. All the major domestic private players are in to generation
transmission and distribution of power except RPG group which is not in to power
transmission.
,NPC-Nuclear NTPC-National Thermal Power Corporation, NHEPC-National Hydro Electric Power Corporation Power Corporation,
CLP- China Light and Power, MC-Marubeni Corporation
13 | P a g e
The Electricity Act enacted in year 2003 has created a new paradigm for the development of
power sector in India. It has abolished monopoly of the State Electricity Board created under
the Electricity (Supply) Act 1948 and has created a new competitive framework for the
development of the power sector in India with focus on the consumers and safeguarding their
barriers in the entire chain of the electricity supply business. It marks the culmination of the
process beginning in the mid nineties of States enacting their own Reform Acts and the
enactment of the Electricity Regulatory Commission Act of 1998 which brought into place
the Central Electricity Regulatory Commission and authorized the state to create Regulatory
The Act has made structural change in the market with single-buyer model to multi-
Open Access in Transmission is allowed right from the date of promulgation of the act.
Central Electricity Regulatory Commission (CERC) has already notified regulations on non-
discriminatory open access in transmission. Open access in distribution for the consumer
The Electricity Act 2003 addresses concerns of all the players in the power sector and sets up
14 | P a g e
No restriction on captive generation
Open access
Encourage competition
The National Electricity Policy has been notified by the Central Government on January 2005
under the Electricity Act 2003 to set direction of development of the Power Sector. Apart
from the salient features mentioned above, the policy sets momentum in following areas:
15 | P a g e
• Choice of fuel for thermal generation to be based on economics of generation and
supply of electricity
• All India transmission tariff sensitive to distance and direction to be introduced by the
Central Commission
Tariff Policy
Tariff Policy has been notified by the Central Government under the Electricity Act 2003
to set clear methodology and principles for determining tariff by the Regulatory
Commissions and to remove the Regulatory Risks for the various players in the Sector.
The policy has addressed critical issues of uncertainty like computation of cross subsidy
surcharge
16 | P a g e
Transmission tariff sensitive to direction and distance
deals with the tariff computation for the years 2009-10 to 2013-14
NORMS RATIONALISED
schedule.
17 | P a g e
• Formulate national policy on Rural Electrification
• Make Rules & Procedure for implementing provisions of Electricity Act 2003
State Government
etc
• Make Rules & Procedure for implementing provisions of Electricity Act 2003
• Form SLDCs for optimal scheduling & dispatch for the power systems
• Make Rules & Procedure for implementing provisions of Electricity Act 2003
systems
Electricity policy
18 | P a g e
• Fix tariff for generation supply, transmission and wheeling within the state.
According to a report by KPMG and CII, India's energy sector will require an investment of
around US$ 120 billion-US$ 150 billion over the next five years. The government has revised
its target of power capacity addition to 90,000 MW in the 11th Five-Year-Plan (2007-12), up
by 11,423 MW from the earlier estimate of 78,000 MW to sustain the growth momentum of
the economy. Further, according to the Planning Commission estimates, renewable energy
(RE) projects worth US$ 16.50 billion, for the generation of 15,000 MW power, would come
up in the 11th Plan. Moreover, the government has earmarked a total capital subsidy of US$
6.88 billion for providing electricity connections and for the distribution of infrastructure to
rural households.
Subsequent to the Indo-US nuclear deal and India getting clearance from the Nuclear
Suppliers Group (NSG), nuclear power generation is likely to provide an opportunity of US$
19 | P a g e
10 billion in the next five years, according to a JP Morgan estimate. India will now also be
of nuclear reactors with capacities between 1,000 MW to 1,650 MW at 5-6 sites along
India will also be exploring export opportunities and is planning to set up nuclear
power reactors abroad. Three Indian public sector companies—the NPCIL, BHEL and
GE Hitachi Nuclear Energy has tied up with NPCIL and BHEL for building multiple
Sweden sees a market of around US$2 billion in India for back-end operations like
NTPC Ltd and NPCIL would jointly invest around US$ 3.09 billion in the next eight
Investments
totalling to US$ 40.84 billion were made in the power sector. Reliance Power Transmission
will invest nearly US$ 348.66 million in setting up a 1,500-km transmission line.
20 | P a g e
Hyderabad-based Greenko Group plans to invest about US$ 300 million in three years for
Government initiatives
The government has taken several proactive steps to open the sector for the private players
and realise the full potential of the country in the power sector.
Introduction of the Electricity Act 2003 and the notification of the National Electricity
Allowing the private sector to set up coal, gas or liquid-based thermal projects, hydel
Allowing foreign equity participation up to 100 per cent in the power sector under the
automatic route.
Providing income tax holiday for a block of 10 years in the first 15 years of operation
and waiver of capital goods' import duties on mega power projects (above 1,000 MW
generation capacities).
The government has also taken up some ambitious programmes like the Ultra Mega
Accelerated Rural Electrification Programme and the goal of Power for All by 2012
21 | P a g e
4. POWER SECTOR SWOT ANALYSIS
Strengths
India has the fifth largest electricity generation capacity in the world
Transmission & Distribution network of 6.6 million circuit km - the third largest in
the world
No barriers to entry
Weaknesses
Public sector players are only into generation of power
Large demand-supply gap: All India average energy shortfall of 9% and peak demand
shortfall of 14%
22 | P a g e
Lack of exposure of entrepreneurs to handle international contracts
contracts
Lack of necessary infrastructure to transport and store fuel, high cost risk involved in
transporting fuel
Opportunities
huge population base
Opportunities in Generation
India.
Renovation, modernisation, up-rating and life extension of old thermal and hydro
power plants.
Threats
Competition to domestic players from foreign Pvt. players as 100% FDI permitted by
23 | P a g e
Not a lucrative option for investors(ROE )
HYDROPOWER SCENARIO
India is blessed with immense amount of hydro-electric potential and ranks 5th in
under :-
24 | P a g e
Eastern Flowing Rivers of
14,511
southern India
Total 1,48,701
In addition, 56 number of pumped storage projects have also been identified with
small, mini & micro schemes has been estimated as 6 782 MW from 1 512 sites. Thus,
exploitation of hydro-potential has not been up to the desired level due to various
constraint
under which impetus is given to development of hydropower in the country. This was a
welcome step towards effective utilization of our water resources in the direction of
came out with a ranking study which prioritized and ranked the future executable
projects. As per the study, 399 hydro schemes with an aggregate installed capacity of 1
06 910 MW were ranked in A,B & C categories depending upon their inter-se
attractiveness. During May 2003, Govt. of India launched 50 000 MW hydro initiative
was taken up by CEA through various agencies. The PFRs for all these projects have
already been prepared and projects with low tariff (first year tariff less than
25 | P a g e
Rs.2.50/kWh) have been identified for preparation of DPR.
INDIA is endowed with economically exploitable and viable hydro potential assessed to
6780 MW in terms of installed capacity from Small, Mini, and Micro Hydel schemes
have been assessed. Also, 56 sites for pumped storage schemes with an aggregate
installed capacity of 94,000 MW have been identified. However, only 19.9% of the
Long life - The first hydro project completed in 1897 is still in operation at
Cost of generation, operation and maintenance is lower than the other sources of
energy.
makes it suitable to meet peak demand and for enhancing system reliability and
stability.
26 | P a g e
Has higher efficiency (over 90%) compared to thermal (35%) and gas (around
50%).
Cost of generation is free from inflationary effects after the initial installation.
Storage based hydro schemes often provide attendant benefits of irrigation, flood
27 | P a g e
RATIONALE OF REGULATION
A “public utility’ is a company supplying merit goods, such as electricity or water, to a large
section of the population at the quality and quantity that is affordable to all consumer classes.
The industry supplying power or water that emerged in the earlier twentieth century, due to the
stations supplying the power needs of the immediate locality gave place to centralized power
Public utilities in most countries in the past were government owned, as the massive
investments required precluded the private sector. Moreover, there were fears of monopoly
abuse. Technology also favored an industrial structure that was vertically integrated and a
With rapid strides in power generation plants as well as informational technology, the
structure of the power sector changed to that of smaller generation plants as well as functional
unbundling. With the changing structure, competition could be introduced into some
segments of the electricity supply industry while the other segments such as transmission
continue to be regulated. New players entered the market taking over the roles that were
earlier bundled into the vertically integrated monopoly that the electricity utility was.
28 | P a g e
In case of power sector, the need for the regulation of price to the ultimate consumer was
recognized very well due to the intrinsic structural features of the power industry. The main
a) Sellers of power are usually very large corporate and better informed about all factors
compared to buyers who are relatively smaller, scattered and unorganized. This
imperfect.
b) Power can be supplied only through a distribution network of wires and whoever
establishes them first has the incumbent advantage over later entrants thus establishing
The above features are common to many network industries, but the power industry, unlike
other industries such as telecom and natural gas, the flows of electricity across the network of
interconnected lines cannot be directed. Therefore, the price of electricity has been regulated
ever since the industry emerged, not only in India but all over the world. However, the design
of regulation has evolved in response to the structure of the power industry, which in turn has
been significantly dependent on the technology and the state market relations prevalent in each
country.
29 | P a g e
GENERATION OF ELECTRICITY
Any generating company may establish, operate and maintain a generating Station without
obtaining a license under this Electricity Act if it complies with the technical Standards
relating to connectivity with the grid referred to in clause (b) of Section 73.
Authority for its concurrence, a scheme estimated to involve a capital expenditure exceeding
such sum, as may be fixed by the Central Government, from time to time, by notification.
2. The Authority shall, before concurring in any scheme submitted to it under sub-section (1)
(a) the proposed river-works will prejudice the prospects for the best ultimate development of
the river or its tributaries for power generation, consistent with the requirements of drinking
water, irrigation, navigation, flood-control, or other public purposes, and for this purpose the
Authority shall satisfy itself, after consultation with the State Government, the Central
Government, or such other agencies as it may deem appropriate, that an adequate study has
(b) the proposed scheme meets, the norms regarding dam design and safety.
30 | P a g e
3. Where a multi-purpose scheme for the development of any river in any region is in
operation, the State Government and the generating company shall co-ordinate their activities
with the activities of the person responsible for such scheme in so far as they are inter-related.
. (1) Subject to the provisions of this Act, the duties of a generating company shall be to
establish, operate and maintain generating stations, tie-lines, sub-stations and dedicated
transmission lines connected therewith in accordance with the provisions of this Act or the
(2) A generating company may supply electricity to any licensee in accordance with this Act
and the rules and regulations made there under and may, subject to the regulations made
(a) Submit technical details regarding its generating stations to the Appropriate Commission
and the Authority;(b) Co-ordinate with the Central Transmission Utility or the State
Transmission Utility, as the case may be, for transmission of the electricity generated by it.
31 | P a g e
THREE STAGES PROCESS FOR DEVELOPMENT OF
HYDRO ELECTRIC PROJECTS
The upcoming projects of nhpc are categorized broadly into three groups depending upon
the clearance obtained from the government. This broad classification of new projects
indicates the stage/ present status of the projects. This was done with the objective of
reducing the time and cost overrun of various projects. Government of India has introduced
a three stage process for development of hydro electric projects. The three stages are:
Essential geological exploration for establishing type of dam and its foundation and
Topographic survey of the project area and detailed survey or the purpose of
32 | P a g e
Essentially temporary infrastructure/access required for carrying out the above works.
projects.
Hydro-meteorological observations.
logging etc.
33 | P a g e
a) Preparation of detailed project report.
c) Submission of EIA and EMP to MOEF and obtaining forest and Environment
e) Roads and permanent bridges as may be required for approaching work sites and
f) Acquisition of land required for the execution of the project including land.
Initiating the process for acquisition of land of the reservoir sub mergence area.
economic Affairs for execution. The approval of the PIB/CCEA would be sought after
Environment and Forest clearance have been obtained from MOEF and Techno-Economic
34 | P a g e
INTRODUCTION OF
NATIONAL HYDRO
POWER
35 | P a g e
CORPORATION
(NHPC)
A Govt. of India Enterprise, was incorporated in the year 1975 with an authorized capital of
Rs. 2000 million and with an objective to plan, promote and organize an integrated and
efficient development of hydroelectric power in all aspects. Later on NHPC expanded its
objects to include other sources of energy like Geothermal, Tidal and Wind etc.
36 | P a g e
At present, NHPC is a schedule 'A' Enterprise of the Govt. of India with an authorized
share capital of Rs. 1,50,000 Million . With an investment base of over Rs. 3, 17,000 Million
Approx. NHPC is among the TOP TEN companies in the country in terms of
investment.
Initially, on incorporation, NHPC Limited took over the execution of Salal Stage-I, Bairasiul
and Loktak Hydro-electric Projects from Central Hydroelectric Project Construction and
Control Board. Since then, it has executed 13 projects with an installed capacity of 5175 MW
on ownership basis including projects taken up in joint venture. NHPC Limited has also
executed 5 projects with an installed capacity of 89.35 MW on turnkey basis. Two of these
projects have been commissioned in neighboring countries i.e. Nepal and Bhutan.
During the financial year 2007-2008, NHPC Limited Power Stations achieved the
During the period 2007-2008, NHPC Limited had a sales turnover of 23110 Million
National Hydroelectric Power Corporation is one of the largest organization for hydro power
development in India having constructed 13 hydro-power projects in India and abroad. With
an asset value of Rs. 2,54,000 million NHPC has planned to add 2480 MW of power during
Xth plan and 6297 MW of power during XIth plan. NHPC's capabilities include the complete
37 | P a g e
Hydroelectric Projects are recognized as the most economic and preferred source of
electricity, share of hydropower in the total installed capacity in India has been declining
steadily since 1963. The hydro share has declined from 44 percent in 1970 to 24 % in
1999. The ideal hydrothermal mix should be in the ratio of 40:60 and present imbalance is
largely responsible for system instability. In order to reverse the trend and given the
COMPANY VISION
A world class, diversified & transnational organization for sustainable Development of
38 | P a g e
COMPANY MISSION
diversified business.
CORPORATE OBJECTIVES
Management of resources.
Development of vast hydro potential at faster pace and optimum cost eliminating
39 | P a g e
Completion of all on-going projects within stipulated time frame.
stability.
projects.
40 | P a g e
Projects on Turnkey Basis 5 Nos. (89.35 MW)
In 2007-2008
In 2006-2007
41 | P a g e
Performance Rating "Excellent"
In 2005-2006
In 2004-2005
42 | P a g e
FINANCIAL PERFORMANCE DURING 2008-09
Registered a net profit (after tax) of Rs. 1,050 crore (provisional) against the net
profit (after tax) of Rs. 1,004 crore registered during the previous financial year.
Achieved an all time high sales turnover of Rs. 2,562 crore (provisional) as against
Poised to declare an all time high dividend for the year 2008-09. An interim dividend
of Rs. 125 crore for the year 2008-09 has already been paid to Government of
India.
Received ‘NIL’ comments on annual accounts of the company for the year 2007-08
from Comptroller & Auditor General of India. This is the second consecutive year
43 | P a g e
the company has received ‘NIL’ comments.
Better business management coupled with prudent financial policies like efficient
sales realization, better grid management, efficient treasury management systems etc.
have resulted in sound financial position which made the Company self reliant for
the resources generation for ambitious capacity addition program in XI and XII Five
year plans.
Enjoys highest credit rating i.e. AAA for domestic borrowings from M/s Fitch and
BBB- for external borrowings both from M/s Fitch and M/s S&P which is equivalent
to Sovereign rating.
Updated Draft Red Herring Prospectus filed with SEBI during August 2008. The
Power Generation
During the period under review, the operating Power Stations of NHPC generated 16690
Million Units exceeding the annual MoU target of 16200 million units for ‘very good’
rating, as compared to 14813 Million Units generated during the previous year, showing an
increase of 12.69 %. The machine availability of the operating power stations measured as
44 | P a g e
Capacity Index has been 93.61% (provisional) exceeding the annual MoU targets of 92.50%
for ‘Good’ rating. Uri Power Station achieved 100% Capacity Index.
The sale rate of NHPC power during 2008-09 varied from 66 paise per unit (Salal Power
Station) to 300 paise per unit (Dul Hasti Power Station). The average sale rate has been 154
paise per unit. Revenue realization from the beneficiaries of NHPC operating power stations
during 2008-09 has been Rs. 2,420.36 crore (99.69%) against the target of 97%. The actual
NHPC has planned to add 5322 MW during XI plan (2007-12) through 12 projects. Out of these,
two projects with aggregate installed capacity of 1030 MW (520 MW Omkareshwar Project in JV
NHPC abroad
The expertise available with NHPC is being utilized by countries like Bhutan, Myanmar and
45 | P a g e
Preparation of DPRs for 670 MW Chamkharchhu-I and 1800 MW Kuri Gongri
NHPC has signed MoU with the Union of Myanmar on 16 th September, 2008 to
study the master plan for hydro power development of Chindwin River Basin and for
reviewing the DPRs of the 1200 MW Tamanthi Hydroelectric Project and the 642
A tripartite agreement has been signed amongst MEA, NHPC and BHEL on 12.8.
2008 for renovation, modernization and uprating of Varzob Hydro Power Plant-I
(2x3.67 MW) in Tajikistan. NHPC shall execute the civil and hydro-mechanical
Excavation, erection of liner & concreting for Vertical Pressure shaft, Upper &
Erection of switchyard is in progress. Erection of all Radial Gates and Tail Race
46 | P a g e
Channel (TRC) Gates completed. Erection of Intake Gate, Surge Shaft Gate, SFT &
Head Race Tunnel (HRT) excavation completed and 6667m (66%) out of 10084 m
The completion has been delayed due to poor geology in HRT, contractual problem
In Barrage Bays 1 to 7, Intake and Power House, excavation is over and concreting is
in progress.
About 91.10% excavation of Tail Race Channel (TRC) has also been completed.
Supply and erection of Electrical & Mechanical (E&M) and Hydro Mechanical
During flash floods in July’07, entire work area got flooded causing a severe setback
Construction activities are suffering due to off and on agitation by "Gorkha JanMukti
47 | P a g e
Morcha (GJMM) since Feb. 2008.
In Head Race Tunnel (HRT), excavation of 81.90% has been completed out of
31.50 Km length.
During Nov.’06 in HRT face-4, the Tunnel Boring Machine (TBM) was partly
buried due to heavy ingress of silt and water, causing total stoppage of work.
13.85% concreting in Power House completed, but the back hill slope failure
48 | P a g e
36.42% Head Race Tunnel excavation completed.
Concreting upto River Bed Level (RBL) in Dam is completed and above RBL is in
progress.
Head Race Tunnel heading and benching excavation completed except 53m which
will be taken up after completion of Surge Shaft widening and concrete lining are in
progress.
Heading of Tail Race Tunnel (TRT) completed except 49m TRT outlet portion and
benching is in progress.
Erection of 2 nos. draft tubes completed and in other 2 units in progress. Earth mat
Design & Engineering and fabrication of Electrical & Mechanical and Hydro
progress.
49 | P a g e
In Head Race Tunnel, 71.60% excavation completed..
In Tail Race Tunnel (TRT), 89.20% excavation has been completed.
94% Dam excavation and 26% Dam Concreting has been completed.
Head Race Tunnel excavation completed and 2181 m(14%) out of 15995m overt
EOT Crane at Service bay commissioned and erection of Electrical & Mechanical
Excavation for Dam Spillway has been completed and concreting is in progress.
50 | P a g e
During flash floods in July’07, entire work area got flooded causing a severe setback
Construction activities are suffering due to off and on agitation by "Gorkha JanMukti
Power House excavation and concreting upto crane beam level completed
About 86.54% Head Race Tunnel (HRT) excavation completed and lining is in
51 | P a g e
progress.
28.07.08.
Project was cleared by CCEA in July 2007. CCEA clearance for revised Cost
(i.e. by January 2016) has been received vide letter dated 14.1.2009.
Letter of acceptance for award of the project has been issued on 22.1.2009 in
I. INTRODUCTION TO TARIFF
52 | P a g e
“Tariff means maximum of any price, rate or charge payable or demanded
and conditions for the determination of tariff, and in doing so, shall be guided by the
following, namely:-
licensees;
commercial principles;
c. the factors which would encourage competition, efficiency, economical use of the
d. safeguarding of consumers' interest and at the same time, recovery of the cost of
53 | P a g e
f. multiyear tariff principles;
g. that the tariff progressively reflects the cost of supply of electricity and also, reduces
Commission;
of energy;
Provided that the terms and conditions for determination of tariff under the Electricity
(Supply) Act, 1948, the Electricity Regulatory Commission Act, 1998 and the enactments
specified in the Schedule as they stood immediately before the appointed date, shall continue
to apply for a period of one year or until the terms and conditions for tariff are specified
Determination of tariff
1. The Appropriate Commission shall determine the tariff in accordance with provisions
of electricity, fix the minimum and maximum ceiling of tariff for sale or
54 | P a g e
generating company and a licensee or between licensees, for a period not
b. transmission of electricity ;
c. wheeling of electricity;
3. The Appropriate Commission shall not, while determining the tariff under this Act,
show undue preference to any consumer of electricity but may differentiate according
to the consumer's load factor, power factor, voltage, total consumption of electricity
during any specified period or the time at which the supply is required or the
geographical position of any area, the nature of supply and the purpose for which the
supply is required.
4. No tariff or part of any tariff may ordinarily be amended more frequently than once in
any financial year, except in respect of any changes expressly permitted under the
55 | P a g e
5. The Commission may require a licensee or a generating company to comply with
such procedures as may be specified for calculating the expected revenues from the
6. If any licensee or a generating company recovers a price or charge exceeding the tariff
determined under this section, the excess amount shall be recoverable by the person
who has paid such price or charge along with interest equivalent to the bank rate
generating company or licensee in such manner and accompanied by such fee, as may
be determined by regulations.
2. Every applicant shall publish the application, in such abridged form and manner, as
3. The Appropriate Commission shall, within one hundred and twenty days from receipt
of an application under sub-section (1) and after considering all suggestions and
a. issue a tariff order accepting the application with such modifications or such
is not in accordance with the provisions of this Act and the rules and
56 | P a g e
regulations made there under or the provisions of any other law for the time
4. The Appropriate Commission shall, within seven days of making the order, send a
copy of the order to the Appropriate Government, the Authority, and the concerned
5. Notwithstanding anything contained in Part X, the tariff for any inter-State supply,
transmission or wheeling of electricity, as the case may be, involving the territories of
two States may, upon application made to it by the parties intending to undertake such
6. A tariff order shall, unless amended or revoked, shall continue to be in force for such
which is an important unit of corporate centre and has been assigned responsibility of
fixation of tariff of all the operational power stations of the corporation from time to time as
functions of commercial division include Billing for the energy supplied and realization of
agreements in respect of operating power stations as well as Power Purchase Agreement for
the upcoming power stations of NHPC with various Bulk Power Consumers and
coordination with Ministry of Power, various Regional Electricity Boards (REB's), Regional
Load Dispatch Centres (RELD’s), SEB's/Union Territories, CERC, CEA and other power
sector utilities.
RESPONSIBILITIES
58 | P a g e
FUNCTIONS
1. Submission of requisite data to CEA/MOP for tariff fixation, follow up action till
fixation of tariff.
2. Preparation of bills for energy supplied to beneficiaries; billing and follow up action.
4. Participation in meetings and tariff policies entitlement allocation and actual supply
of electricity.
5. Co-ordination and liaison with Regional Electricity Boards, beneficiaries, CEA, MOP
etc.
7. Data bank regarding tariff of NHPC Projects and other Projects in India and Abroad.
COMMERCIAL TARIFF
Each operating power station of the corporation has a station wise tariff. At present the tariff
59 | P a g e
(CERC). The CERC has approved the tariff of Baira siul, Loktak, Salal, Tanakpur, Chamera-
I, Chamera-II, Rangit & Uri Power stations for the period 1.4.2001 to 31.3.2004 on the basis
of CERC (Terms and conditions of Tariff) Regulation 2001. The Commission has approved
the Annual Fixed Charges (AFC) for each of these power stations except for the Chamera II
AFC is to be recovered in the form of capacity and energy charges on monthly basis as per
the directions laid in the tariff orders. The components of tariff (AFC) are Interest on loan,
Interest on working capital, Depreciation, Advance against depreciation, O&M expenses and
Return on equity.
Availability Based Tariff as ordered by CERC has been implemented w.e.f. 01.07.2002 in
In ABT regime the generator has to generate as per schedule given by Regional Load
Dispatch Centre (RLDC), presently being operated by Central Transmission utility (CTU)
and the beneficiary (SEB) has to draw power from grid as per the schedule. Unscheduled
Interchange (UI) charges are imposed on the constituents of the grid who deviate from
schedule.
The CERC has issued the revised CERC (Terms & Conditions of Tariff) Regulations, 2009
on 19.01.2009 which are applicable for the period 01.04.2009 to 31.03.2013. Fresh tariff
petitions of all the operating projects for the period 01.04.2009 to 31.03.2013 have since been
filed by NHPC in CERC based on these regulations. The determination of tariff by the
60 | P a g e
Commission based on the revised terms and conditions will take some time, till that
Commission directed that billing of charges, shall be billed as per AFC as applicable on
31.03.2009 on provisional basis and shall be further subject to adjustment after final
determination of tariff by the Commission in accordance with the revised terms and
conditions.
T
R
A
R
U
T
E
R
P
E
D
E
N
I
R
T
S
D
E
X
NF
IN
I
C
N
O
F L
I
T
M
&
O
R
A
V
K
N
R
O
W
I
G
E
T
S
B
N
O
G
R
A
P
X
H
L
O
E
N
C
O
I
T
A E
S
C
A
N
N
F
A
T
C
I
P
L
T
I
U
Q
EY
61 | P a g e
2. Variable charges
The variable charges in case of Hydro Generating Station are Nil. So tariff in respect of
Hydro Generating Station consists of fixed charges only. These fixed charges were further
divided into:-
1. Capacity charges
2. Energy charges
Interest on loan
Return on equity
O&M expenses
62 | P a g e
Tariff of generating station may be determined for the whole of the generating station or a
stage or a unit of the generating station. For the purpose of determination of tariff, the capital
expenditure incurred duly certified by the auditors or projected to be incurred during the tariff
period of the generating station in accordance with CERC Regulations, in respect of the units
of generating station, completed or projected to complete within 6 months from the date of
the application.
In case of the existing projects, the generating company shall continue to provisionally bill
the beneficiaries or the long-term customers with the tariff approved by the Commission and
applicable as on 31.3.2009.
Provided that where the tariff provisionally billed exceeds or falls short of the final tariff
approved by the Commission under these regulations, the company shall refund to or recover
from the beneficiaries or the within six months along with simple interest at the
rate equal to short-term Prime Lending Rate of State Bank of India on the 1st April of the
concerned/respective year.
63 | P a g e
The Commission shall carry out truing up exercise along with the tariff petition filed for the
next tariff period, with respect to the details capital expenditure including additional capital
expenditure incurred for the period from 1.4.2009 to 31.3.2014, duly audited and certified by
the auditors; as admitted by the Commission after prudence check at the time of truing up.
Construction and financing charges, any gain or loss on account of foreign exchange risk
(i) being equal to 70% of the funds deployed, in the event of the actual equity in excess of
30% of the funds deployed, by treating the excess equity as normative loan, or
(ii) being equal to the actual amount of loan in the event of the actual equity less than 30% of
the funds deployed, - up to the date of commercial operation of the project, as admitted by the
Provided that the assets forming part of the project, but not in use shall be taken out of the
capital cost.
64 | P a g e
Provided also that in case the site of a hydro generating station is awarded to a developer (not
being a State controlled or owned company), by a State Government by following a two stage
project developer for getting the project site allotted shall not be included in the capital cost.
Provided also that the capital cost in case of such hydro generating station shall include:
(a) cost of approved rehabilitation and resettlement (R&R) plan of the project in conformity
(b) Cost of the developer’s 10% contribution towards Rajiv Gandhi Grameen Vidyutikaran
INITIAL SPARES
Initial spares shall be capitalised as a percentage of the original project cost, subject to
65 | P a g e
(c) Series Compensation devices and HVDC Station - 3.5%
The generating company or the transmission for meeting the expenditure on renovation and
modernization(R&M) for the purpose of extension of life beyond the useful life of the
generating station shall make an application before the Commission for approval of the
proposal with a Detailed Project Report giving complete scope justification, cost-benefit
analysis, estimated life extension from a reference date, financial package, phasing of
including foreign exchange component, if any, record of consultation with beneficiaries and
Any expenditure incurred or projected to be incurred and admitted by the Commission after
prudence check based on the estimates of renovation and modernization expenditure and life
extension, and after deducting the accumulated depreciation already recovered from the
original project cost, shall form the basis for determination of tariff.
66 | P a g e
IV. COMPUTATION OF TARIFF
The following are components of tariff:-
2. Incentive
4. Unscheduled Interchange(UI)
a) Return On Equity
b) Interest on Loan
c) Depreciation
e) O&M Expenses
a) Return on Equity
Return on equity is a measure of a company's ability to use its assets to generate additional
67 | P a g e
Return on equity is applicable only to generating stations that come under regulatory
authority. It shall be computed in rupee terms. ROE shall be computed on pre tax basis at
Rate of return on equity shall be computed as per following formula:- Rate of pre-tax return
Illustration:-
I) In case of generating company paying Minimum Alternate Tax @ 11.33% including cess&
surcharge:
=17.481%
II) In case of generating company paying Normal Corporate Tax @ 33.99% including cess &
surcharge:
=23.481%
With normal tax rate ROE will be 21.48%. For timely completion of project, an additional
68 | P a g e
b) Interest on Loan Capital
Interest on loan will be allowed on normative basis. The normative loan outstanding at the
beginning of the tariff period shall be worked out by deducting cumulative repayment from
gross normative loan. The repayment of loan shall be considered from the 1 st year of
commercial operation of the project and shall be equal to the annual depreciation allowed.
The rate of interest shall be the weighted average rate of interest calculated on the basis of
actual loan portfolio at the beginning of each year applicable to the project.
size, type of equipment and its estimated life. Advance against depreciation is applicable only
to generating stations, which comes under regulatory authority. In other cases, this is set to
zero. Depreciation shall be allowed at the rates prescribed by the commission and based on
Straight line method. Considering 10% salvage value depreciation has been allowed upto
90% of the capital cost. Land other than the land held under lease and land for reservoir shall
operation. In case of commercial operation of the asset for part of the year depreciation shall
69 | P a g e
Working capital usually used for the purchase of raw materials, components and spares,
payment of wages and salaries, the day-to-day expenses and overhead costs such as power
and office expenses etc. The interest on working capital is determined on normative basis.
and maintenance of the generating station, expenditure on spares and repairs, administration
and general expenses and other miscellaneous expenses. Operation and maintenance expense
ILLUSTRATION:-
Now we will calculate AFC and Commercial tariff for NHPC’s SEWA-II Project which has
following detail:-
Design Energy………………………………………………………..533.52MU
70 | P a g e
Repayment in 15yrs with 3year moratorium
ROE……………………….……………………………………………………………17.48%
Interest on Loan………………………………………………………………11%
12yrs
= 785.56*5.20%
71 | P a g e
= 40.85
=785.56*1.2%
=9.43
= 58.24
c) ROE = 235.67*17.48%
=41.19
- 15.71
= 1.31
72 | P a g e
ii) 15% of O&M = 15%*15.71
= 2.36
=159.78/6
-=26.63
= (1.31+2.36+26.36)*12.5%
= 30.3*12.5%
= 3.79
AFC = a+b+c+d+e
= 40.85+58.24+41.19+15.71+3.79
= 159.78
73 | P a g e
2) INCENTIVES
The generating company can achieve incentives for maintaining reliable and quality power.
Incentive is based on the declared capacity in MW corresponding to the generation and the
operational cost can also include with variable charges. A penalty clause also can be added
service charges, like reactive power control, voltage and frequency control + cess/service tax
generating company shall recover the cost of hedging & foreign exchange rate variation on
station shall be treated as unscheduled interchanges, charges for which will be governed by
74 | P a g e
V. COMPUTATION AND PAYMENT OF CAPACITY
CHARGE AND ENERGY CHARGE FOR HYDRO
GENERATING STATIONS.
The fixed cost of a hydro generating station shall be computed on annual basis and will be
recovered on monthly basis under Capacity charge(inclusive of incentive) and Energy charge
saleable capacity of the generating station excluding free power to home state.
ILLUSTRATION:-
Now we will calculate total billing charges for the month of April’2009 for Baira suil
Plant.
And will also calculate how it is charged from its Beneficiary say for Punjab.
CHARGES VALUE
PSCH 85.153027
PFP 10.22009
PAFM 100.070
AFC 52.8735
ADE 779.28
AUX 0.7%
NAPAF 85
75 | P a g e
1) ECR= AFC 0.5/ {DE (100-AUX) (100-FEHS)}
= 0.5×159.78×107
779.28 (1-0.7%)(1-12%)
= 85.153027- 10.22009
=74.932937 MU
= 97.85(1-0.7%)(1-12%)
= 85.505244 MU
{In case the energy charge rate (ECR) for a hydro generating station, as computed in step 1
above, exceeds eighty paisa per kWh, and the actual saleable energy in a year exceeds
76 | P a g e
saleable DE as computed in step 3 above then, the Energy charge for the energy in excess of
= 29223845
= 25581230
7) Project total Charge upto the Month= Project Energy charge + Project Capacity Charge
= 29223845+ 25581230
= 54805107
SCHEDULING.
77 | P a g e
The methodology for scheduling and dispatch for the generating station shall be as specified
in the Indian Electricity Grid Code, as amended from time to time.
The provisions of the Indian Electricity Grid Code, as amended from time to time shall be
applicable.
1. Corporate office
2. Regional Office
3. Project Office
Beneficiaries A/c-------------Dr.
To Regional offices
78 | P a g e
To power station
TO sales
NHPC has adopted a monthly billing cycle. Based on the Regional Energy Accounts issued
by the respective Regional Electricity Boards and Regional Load Dispatch Centre’s , billing
is done centrally at the Corporate Office on monthly basis in accordance with the rates, terms
and conditions of the tariff notification issued by Government of India/CERC for that
particular power station. Payments are received through confirmed, revolving, irrevocable
Letters of Credit opened by the beneficiaries in favour of NHPC and also directly through
Demand Draft/Cheques. Due to opening of letters of credit by the beneficiaries and also as a
result of special incentives offered by NHPC to the beneficiaries for making prompt
79 | P a g e
Bills shall be raised for capacity charge and energy charge on monthly basis by the company
in accordance with CERC regulations, and payments shall be made by the beneficiaries
Now we will calculate how we Bill it for a particular Beneficiary lets say for Punjab
= 39.590934-0
= 39.590934
6
= 39.590934 0.39 10
= 15440464
80 | P a g e
4) Capacity Charge = Project Capacity Charge Capacity share
88
= 25581230× 46.5
88
= 13517354
= 15440464 + 13517354
= 28957818
Note 1
Shares / allocations of each beneficiary in the total capacity of Central sector generating
stations shall be as determined by the Central Government, inclusive of any allocation made
out of the unallocated capacity. The shares shall be applied in percentages of installed
capacity and shall normally remain constant during a month. Based on the decision of the
81 | P a g e
Member-Secretary, Regional Power Committee in advance, at least three days prior to
The total capacity share of a beneficiary would be sum of its capacity share plus allocation
out of the unallocated portion. In the absence of any specific allocation of unallocated power
by the Central Government, the unallocated power shall be added to the allocated shares in
Note 2
The beneficiaries may propose surrendering part of their allocated firm share to other
States within/outside the region. In such cases, depending upon the technical feasibility
of power transfer and specific agreements reached by the company with other
States, the shares of the beneficiaries may be prospectively re-allocated by the Central
Government for a specific period from the beginning of a calendar month. When such re-
allocations are made, the beneficiaries who surrender the share shall not be liable to pay
capacity charges for the surrendered share. The capacity charges for the capacity surrendered
and reallocated shall be paid by the State(s) to whom the surrendered capacity is allocated.
Note 3
FEHS = Free energy for home State, in percent and shall be taken as 12%
82 | P a g e
Three types of bills are prepared by the NHPC
1. Provisional bills: This is the starting bill generated by the NHPC against beneficiaries.
Income tax
Additional capitalisation
3. Final bills
REBATE
ACCORDING TO CERC
For payment through LC on presentation of bill, 2% rebate is allowed on the bill amount. In
case payment is made within one month other than LC, 1% rebate is allowed.
For payment through LC on presentation of bill, 2% Rebate is allowed on the bill amount.For
83 | P a g e
In case the payment of any bill is delayed by a beneficiary beyond a period of 60 days from
the date of billing a late payment surcharge of 1.25% per month shall be levied by generating
company.
84 | P a g e
SUMMARY OF NEW CERC PROVISION
a. The Capacity Index has been replaced with Normative Annual Plant Availability
Factor (NAPAF).
b. Earlier system of self-adjusting formula for recovery of Annual Fixed Charges has
been changed. Now, AFC shall be recovered as Energy and Capacity Charges on 50-
50 basis.
d. ROE has been increased from 14 to 15.5% on post-tax basis. 0.5% additional return
e. O&M expenses have been enhanced upwardly from 1.5% to 2% p.a. for new Power
Stations which are commissioned within a period of 5 years. Annual escalation rate
g. The rate of depreciation has been revised upwards from weighted average 2.5-3% to
4.5-5%.
h. Maintenance spares has been allowed at the rate of 15% of O&M expenses instead of
85 | P a g e
i. In case of under and over recovery of tariff the rate of interest has been changed to
j. Earlier system of incentive on achieving higher capacity index over normative level
has been dispensed with. Instead incentive has been made in-built in Capacity
k. Hedging has been allowed in case of interest and repayment of foreign loan. To the
extent, hedging has not been done FERV has been allowed.
l. Rebate to be provided to beneficiaries has been allowed on entire bill amount instead
m. The rate of secondary energy is varying and has been capped to 80 paise per unit.
86 | P a g e
COMPARISON BETWEEN NEW NORMS AND OLD NORMS
The commission in its draft regulations had proposed a ROE of 14% which it argued was
sufficient in view of the huge response of the investors to the IPOs of companies like
NTPC,PGCIL and Reliance Power. However most of the generators contested this fact and
c) Return on Equity
respectively.
0.5 % additional return has been allowed for the projects which are completed
within the prescribed time limit as per Appendix II of the CERC regulation 2009.
87 | P a g e
ROE shall be computed by grossing up the base rate with normal tax rate as
applicable for the year 2008-09 which shall be trued up for each tariff year as per
applicable rate of relevant Finance Act and shall be filed along with the tariff
The above incremental ROE of 1.5% translates into incremental 101.52 Cr. on the
INTERSET ON LOAN
OLD PROVISION NEW PROVISION
The loan outstanding as on 1.4.2004 shall be The normative loan outstanding as on
worked out as the gross loan minus 1.4.2009 shall be worked out by deducting the
normative loan.
The repayment for the period 2004-09 shall The repayment for the respective year of the
applying actual repayment ratio to opening equal to the depreciation allowed for that
the year.
88 | P a g e
DEPRECIATION
OLD PROVISION NEW PROVISION
Depreciation @ 2.57% to 2.8% was allowed Depreciation at the prescribed rates is
till the year of loan repayment with balance allowed for 12 years with balance
depreciable value spread over the balance depreciable value spread over the balance
years after the year of repayments till the years till the 35th year.
35th year.
allowed to the extent of difference between depreciation has been done away with.
amount.
89 | P a g e
B) Maintenance spares @1% of Capital b) Maintenance spares @15% of O&M
Charges and Capacity Charges energy & capacity charges in the ratio
such generation was not an issue for dependent on the actual generation.
Incentive was allowed on the basis of machine Incentive would be available based on
90 | P a g e
The basis of Incentive calculation was excess The basis of incentive would be higher APAF
AFC. AFC.
Rate of Secondary Energy was primary energy Maximum Rate of Secondary Energy has been
Projects in FY08-09
TAX ON INCOME
OLD PROVISION NEW PROVISION
Tax on the income streams of the The Post tax ROE of 15.5% shall be
generating company or the transmission adjusted for the applicable tax rate by the
licensee, as the case may be, from its core formula ROE/(1-t) to arrive at the pre tax
business, shall be computed as an expense ROE and no further tax pass through shall
and shall be recovered from the be allowed whereas tax rate applicable for
91 | P a g e
beneficiaries. the FY 2008-09 would be applied for the
payment and loan repayment on foreign respect of interest on foreign currency loan
currency loan was pass through in Tariff. and repayment of foreign loan has been
allowed.
through in Tariff.
REBATE
OLD PROVISION NEW PROVISION
For payment of bills of Capacity and Energy For payment of bills by the generating
92 | P a g e
rebate of 2% shall be allowed. rebate shall be allowed.
For payment of bills other than LC mode Where payment of bills made other than LC
but within a period of one month of raising mode within one month of presentation of
SURCHARGE
OLD PROVISION NEW PROVISION
Surcharge @ 1.25% per month was levied for Surcharge @ 1.25% per month was levied for
delayed payments beyond 60 days from the delayed payments beyond 60 days from the
93 | P a g e
PROBLEM FACED DURING THE DETERMINATION
OF TARIFF
2. Company has to face problem in maintain the debt – equity ratio.ie,.70:30 as per the
CERC regulation.
3. Final approval is done by CERC, so sometimes AFC determine by the company does
not completely approved by the CERC. Therefore, it’s very difficult to cover full
capital cost.
94 | P a g e
RECOMMENDATIONS
Part A : Issues which were earlier taken up with CERC while furnishing our replies to
draft CERC Regulations and during public hearing and also through separate petition
but the same did not find favour of CERC. Looking into the gravity of its implication on
company performance, NHPC may take up the matter with Ministry of Power and CEA.
95 | P a g e
2. a) NAPAF in respect of ROR stations should not be more than design
PLF.
3. 0.5% additional return provided in the Tariff Notification, 2009 should also be
extended to the new projects being commissioned, where reasons for delay beyond
the original schedule is not attributable to generating company and also approved by
4. Additional ROE should be allowed for hydro projects taking into consideration
5. ROE during construction period should be allowed. Matter was earlier taken up with
CERC while furnishing our replies to draft CERC Regulations but the same did not
find favour. Considering the effective impact on ROE, NHPC may take up the matter
with Ministry of Power and CEA for taking suitable policy decision.
6. Provision regarding additional 1% for local area Development under Rehabilitation &
Resettlement as per amended tariff policy applicable for private developers should
96 | P a g e
Part B: - New Issues
1. Differential rates of tariff for peak and off peak hours should be allowed for getting
higher returns.
2. The Corporation should tie-up long term loan not less than 17 years to
a) Derive maximum benefit under tariff i.e. match the cash out flow towards
b) Govt. of India may be approached for issuing necessary guidelines to banks and
financial institutions directing them to extend long term loan, separate exposure
limit for hydro sector and restoration of section 10(23)(G) of Income Tax Act,
3. 15% of the generation capacity of new projects be sold outside long-term PPA, to
Electricity Policy, 2005 (Clause No.5.7.1). The matter is to be further pursued with
MOP .
97 | P a g e
1. The power stations should incur add Cap expenditure as per the Norms allowed in
CERC Notification.
giving detailed justifications, cost benefit analysis, estimated life extension, financial
3. We should invest more and more in new project, in order to improve profitability.
4. Efforts should be made to achieve higher NAPAF over and above normative value.
Best maintenance practices are to be adopted for further improving the operating
performance of the power stations. Performance of all the power stations needs to be
during the years 2007-08 & 2008-09 was about Rs.122 Crores & Rs.191 Crores
6. A number of R&D initiatives including various coatings have already been taken up
in our power stations as preventive measures to reduce damage caused by silt. The
result/feedback of such steps needs to be compiled and further pursued for finding
98 | P a g e
7. Utilization of accommodation available at various power stations needs to be
Construction of quarters for the new projects needs to be seen in this reference and
present.
and Teesta-V Power Stations are yet to be received. Timeline should be specified for
with operation & maintenance, tariff petitions, matter relating to Appellate Tribunal
CONCLUSION
99 | P a g e
process since it is a public limited company . All the working of company is
process and critical analysis of CERC norm, I can give some suggestions to
the increase in Interest rates in the market and escalation factor also needs to
be realistic.
Although the new tariff structure, shows a much more realistic and factual
and making it easily available for the generators, there is still a scope of
further improvement in the tariff structure from the point of view of both –
I hope that my recommendations will be useful for the company and the
100 | P a g e
BIBLIOGRAPHY
SOURCES OF INFORMATION
101 | P a g e
2. Interaction with the various employees.
LIST OF BOOKS
4. POWERLINE Magazine,.
Websites
1. www.nhpcindia.com
2. www.nsdl.co.in
3. www.cerc.com
4. www.google.com
5. www.powermin.nic.in
6. www.cercind.gov.in
102 | P a g e
GLOSSARY
103 | P a g e
3. AFC Annual Fixed charge
104 | P a g e
19. PFP Plant free power
105 | P a g e
106 | P a g e
107 | P a g e