Conduct Loop Test
Conduct Loop Test
The Loop checking is defined as pre-Commissioning activity which is initiated after installation of
instruments in the field and carry out the instrument loop checks between installed field instrument and
respective control system i.e. PLC or DCS.
checking is the final process before the commissioning of the processing system. Loop checking is the
process that confirms the components wired correctly and also helps to ensure that the system is
functioning as designed.The loop checking checks the connection between each component in the control
loop. A control loop consists of transmitter/sensor, process controller, final control element.Before start,
the loop check include, first list the number of loops, test actions, the procedure for documenting the
check and plan should specify the type and characterization of signal. For example, differential flow
meter generates a signal that has a square root relationship between flow rate and differential pressure.
The resistance from any point of the electric installation should be earthed. The resistance from the
earthing electrode to the point where the main earthing conductor is connected to the neutral conductor of
the supply system shall not exceed 5 ohms.
Connect the short lead to the earth electrode and measure the earth resistance of the main earthing
conductor
The resistance shall not exceed 5 ohms for the main earthing conductor
Earth continuity test:
Using the long lead and zeroed meter, measure for each circuit, the earth conductor resistance from the
circuit extremity to the switchboard.
To confirm the measured values are less than those values as provided by table
This test is applicable to all circuits, including socket outlets circuit, lighting circuits and fixed equipment
circuits.
Insulation resistance test:
The insulation resistance tests to ensure there is no current flow between conductor and ground or
insulation surface. If there is no current flow the wire could prevent electric shock hazards, fire hazards
and equipment damage.
Test procedure:
Ensure all protective device in the circuit is switched ON.
Set the insulation tester to megaohms
Connect an insulation tester cable to the main earth bar and the other cable to the active and neutral
connected together. Do not perform tests between assets and neutrals.
Measure the insulation resistance of the total installation, if the resistance is greater than 1 megaohm then
the normal to work.
If resistance is less than 1 megaohm disconnect the appliances. Then test the circuit separately to ensure
that the insulation resistance of both the circuit and the appliances complies with the following
Not containing a heating element- is not less than1 mega ohm or
Containing a heating element-is not less than 0.01 mega ohm
Polarity test:
Polarity tests are carried out to ensure that the correct connection of the active, neutral and ground
conductors to the electrical equipment ensures that the switches are not installed in neutral conductors.
Test procedure:
Isolate the active conductors by turning the main switch OFF and tagging
Confirm the consumer and sub main cables by simply testing from the point of distribution board to the
main switch board using an ohm meter and long test loads. Test result= 0 ohms
Confirm the switching of the active conductors using an ohm meter with the long cable connected to the
active conductor on the board and the short wire connected to the terminals of the switch as follows
Switch ON = 0Ώ for both terminals, Switch OFF = 0Ώ for one terminal and infinite for the other terminal.
With the MEN link in place, confirm the polarity of the sockets using a 10Ώ resistor and an ohm meter.
Connect the 10Ώ resistor between the active circuit conductor and the neutral bus, then connect the
multimeter cable to the ground terminal and the second cable to the active terminal. Test the resistance
value for.
Fault loop impedance test:
This test is performed to confirm that the impedance value of the fault loop of each circuit will be low
enough to guarantee the operation of the protection device during a fault.
Test procedure
Loop Check :
An operational check of the field, controller and HMI elements of a control loop. A Loop Check is
intended to ensure the integrity of the following.
The field sensing device is properly installed in accordance with engineering specifications.
The field sensing device is properly connected to it’s communication path to the Distributive Control
System Controller. (e.g. Current Loop, Multiple device Bus Communication Protocol, etc.)
The field sensing device develops and transmits a proper analogous signal in response to a variable
impressed upon it or a simulation command issued to it.
The corresponding logic in the DCS Controller is ranged accordingly for the field sensing device analog
and engineering units.
The HMI of the DCS Controller accurately displays the engineering unit response to the signal of the field
sensing device.
Alarm points are properly entered into the logic of the DCS Controller and the HMI displays and logs
these appropriately as they are reached.
Where control functionality is required, that the signal from the field sensing device is received by the
control algorithm and generates the appropriate corrective output signal.
If present, the field control device, (e.g. Control Valve, Variable Speed Control etc.), is properly installed
in accordance with engineering specifications.
The field sensing device is properly connected to it’s communication path to the Distributive Control
System Controller. (e.g. Current Loop, Multiple device Bus Communication Protocol, etc.
The Field control device responds appropriately to the corrective signal received from the DCS Controller
and that this action is appropriate to the desire process variable.
Where specified, the response action of the valve is correctly transmitted to the DCS Controller and
displayed on the HMI.
SUMMARY
The Loop Check is intended to locate and identify deficiencies in the Field/Controller/HMI interface. This
includes, but is not limited to, wiring and cabling issues, engineering issues and mechanical installation
issues.
It is not the focus of the Loop Check to correct any deficiencies found. Full information concerning the
deficiency is captured and passed on to the appropriate parties for correction. Minor corrections can be
accepted, but this should be limited in scope.
Procedure:
A list of Loops is collected and identified by Tag Number.
Loops are grouped by Location, Availability, System, Equipment or other criteria. (Note: Locational
Grouping of Loops results in the most efficient execution of Loop Check.
The field team can be routed in a logical geographical progression of one device to another adjacent
device without time loss for accessing different floors, buildings, plant sections etc.
Loop availability can prevent this. If at all possible, Loop availability should be planned to accommodate
Locational Grouping)
Each Loop Folder is populated with either a comprehensive Loop Sheet, and/or individual elements,
consisting of the following
Action
Field Device Accessory List (e.g. Transmitter 3 Valve manifold, Valve Pneumatic Latch etc.)
DCS Parameters
Ranges
Alarm points
DCS HMI Graphics assignments
From the Pending Loops file, the Console Engineer and the Field Technician draw the Loop Folders to be
checked in that time period.
The Console Engineer (or Operator) and the Field Technician review the contents of each Loop Folder in
the group to be checked, comparing parameters for parity and completeness of data.
The Console Engineer prepares his record keeping tool, tracker, for the loops to be checked in the agreed
upon sequence.
The Field Technician evaluates the test equipment to be used, collects same and proceeds to the first
device to be checked.
The Field Technician communicates to the Console Engineer the Tag of the device he is at
The Console Engineer calls up the appropriate I/O channel
Transmitters
The Field Technician reviews the installation and process connections to ensure they are in accordance
with the specification details and good installation practice.
Either by impressed signal, (“Pump Up”) or Communicator command, the Field Technician drives the
transmitter output signal through it’s range. Slowing at Alarm Points so the Console Engineer can
confirm alarm action.
(NOTE: Common is a 0% 25% 50% 75% 100% Check. This was originally necessary to confirm the
linearity of earlier Pneumatic and ElectroMechanical devices, it no longer is as critical and becomes a
matter of agreed upon preference.)
The Field Technician confirms the process connection line up is as desired. (e.g. For a Differential Flow
Transmitter to be placed in service after check out, the three valve manifold would have the balance
closed and the process ports open)
Control Loops
While the transmitter signal impression is occurring, the Console Engineer will call up the Control
Algorithm faceplate and by placing the control mode (PID Controller) to Auto, determine that the output
action is appropriate.
Control Valves
The Field Technician reviews the installation to ensure it is in accordance with the specification details
and good installation practice.
If pneumatic, the Field Technician opens the air source checking for proper pressure adjustment and air
quality.
The Console Engineer adjusts the output signal to the valve while the Field Technician observes the
action of the valve.
Jointly, the Field Technician and the Console Engineer determine if the resultant action is appropriate for
the control signal sent and the previously determined action of the control algorithm.
Where present, the Console Engineer observes any feedback from the valve to be in agreement with the
reported position of the valve action by the Field Technician.
Either by Signal Impression, manual toggling, or conductor manipulation, the Field Technician causes a
change in state of the field device signal.a
The Console Engineer observes the indication of the signal to be in agreement with the physical state as
impressed on the device by the Field Technician.
The Console Engineer records the results of the results of the signal impression, alarm points, ranges,
valve actions, etc.
If no deficiencies were noted during the Loop Check, the Loop Folder is placed in the Completed Loops
File. At this point, the client signs for the Loop as being complete.?ll
The resolution team draws Kick Back forms from the Active Kick Back file.
Each time the deficiency is addressed, the Kick Back form is submitted to the Console Engineer.
Date
Resolving Party
Thorough description of the corrective actions taken
Recommendations for further actions
Responsible party assigned to further actions
When the deficiency is corrected, the Kick Back form is submitted to the Console Engineer.
Date
Loop checking procedure of Instruments
This article is about the loop checking procedure of all instruments like flow transmitter, valves,
vibration, DCS loop, switchgear loop and ramaining pressure and level types instruments.
HART Communicator
Dead Weight Tester
Air Compressor
MC5 FF Multifunction Calibratorll
Test Gauges with Ranges per Specification
Absolute Pressure Gauge
Portable 120Vac, 60Hz Gasoline Powered Generator
Pulse/Frequency Generator
DC Power Supply Regulated 24Vdc Variable
Nitrogen Tank w/ High Pressure Regulator
Thermo Bath
Hydrostatic Test Pump
Set of Precision Weights
Digital Thermometer
Glass Thermometer
Potentiometer
Portable Pressure Calibrator (DRUCK)
Process Calibrator
Advanced Temperature Calibrator
RTD Conversion Chart
Circuit Tester
Decade Resistance Box
Digital Manometer (Mercury or Water Manometer)
Mercury and Water Manometer
Hand Pump
Hygrometer (Humidity Tester)
Air Regulator
Pneumatic Comparator
Vacuum Pump
Oscilloscope
Radio Communication Equipment (intrinsically safe as per approved)
Multi meter
Test Bench with clean, dry and oil free instrument air
Set of Tools, Hose & Fittings
Stop Watch
Millivolt/Temperature conversion chart
TK-3 (for checking of vibration element)
Spirit Level
BEAMEX MC5 Calibrator
Others,if any
All tools utilized in a classified area should be intrinsically safe and suitable for hazardous
areas.Resolving Party
Thorough description of the corrective actions taken
iii. If any ESD logic / interlocking are involved in applicable loop, then first normal condition should be
prepared by forcing the applicable ESD points on ladder on logic and same procedure to be carried
out for DCS logic.
Share this:
Share
Like this:
Tags:Instrumentation Calibration
Reference
Introduction to instrument third edition
The purpose of this document is to assure that all the control loops installed by the contractors are
operational and within applicable standards and manufacturer’s tolerances and that systems are installed
in accordance with design specifications.
With this method cost and time will be minimized and safety integrity will be maintained.
This technical report is an informative document providing guidance on performing testing of control
loops.
It covers the functionality test of digital and analog instruments and controllers used in all areas of the
plant.
Inspection of all parameters and instrument response based on the checklist will depend on the
approved Inspection & Test Plan (ITP) of the construction.
Loop – is defined as a combination of one or more instruments arranged to measure and / or control a
process variable i.e. form the measuring device, including all components in between
(electrical/pneumatic).
Loop Checking – is defined as the checking for correct operation of all instrument systems and loops and
the preparation of all instrumentation for commissioning. This includes the operation of equipment by
means of the plant wide Distributed Control System (DCS), ESD, FGS and correct operation of the
associated graphics on the Man Machine Interface (MMI).
Loop/Function test is divided by a two-group operation. One group to be in the field (Field Technician)
and the other group to be positioned in the control room or front of local panel (Operator Station
Technician).
Loop check also includes
– Wiring integrity check in field and at control system
– HOOK-UP verification vs installation of Instrument
– Perform analog inputs 3-point check, 0%, 50%, 100%; or more if needed
– Perform analog output 4-point check, 0%, 25%, 75%, 100%
– Perform switch contact check
After finishing loop/function test, the field instruments shall be restored immediately, especially notes:
– Connector tightly as original
– If open air supply valve during loop/function test, close it when finished
– For D/P pressure type, 3 valve manifold closed
– Lead pipe valve restored
TYPES OF LOOPS
There are two types of loops are in the field of instrumentation.
1.Open loop: It has no feed back.
2.Close loop :It has feed back.
In instrumentation a Close loop is consist of 3 basic Parts.
1.Input device (pressure ,level ,flow ,temperature transmitters)
2.Output device (Control valve)
3.Controller (DCS, PLC , etc.)
To minimize overlaps and duplicate efforts, it is very important that the loop check team be prepared and
are aware of their responsibilities
GENERAL REQUIREMENTS
Loop shall be termed ready for testing when all the construction punch list items have been
satisfactory closed out.
Factory Acceptance Test (FAT) of DCS, ESD, FGS Systems and all other control panels associated
with mechanical and other packages have been successfully concluded.
The appropriate pre-installation instrument calibration/testing has been completed, recorded on the
Instrument Calibration Record and witnessed/accepted by Owner Representative.
All punch items are completed. All required documentation drawings are assembled within each
package.
Loop checking shall be witnessed by QC Group in accordance with approved ITP.
The components within the loop have been installed in accordance with process piping, instrument air
piping, mounting details and Instrument drawings. All cabling and wiring has been installed, tested and
labeled, recorded on the Cable Test Report and witnessed/accepted by Owner Representative.
Digital Multimeter
Current / Voltage Standard Source Instruments
Decade Resistor Box/Millivolt Generator
HART Communicator
Screw driver sets
Allen wrench set
Portable Pressure Calibrator
Hand Pump
Temperature Calibrator
Other Relevant Tools
Test equipments must be calibrated and performing in rated accuracy.
All parties involved in this activity must be familiar with applicable safety practice.
Wearing appropriate PPE’s and use of proper tools in opening the instrument terminals boxes must be
maintained.
Safety belts will be required in some other areas where the instruments are mounted on high
elevations.
Observed proper polarity connections for electronic instruments and any other instruments requiring
separate supply.
COMMUNICATION REQUIREMENTS
During early commissioning or pre commissioning activities like flushing and blowing it must be ensured
that the (operational) commissioning crew is fully equipped with means of communication.
PROCEDURE
Verify the feruling (tag) of the wiring on field device, Field junction box, Marshalling panel/rack and
DCS cabinet.
Verify the Tag of Instrument on Operator Console.
Verify the Power requirement of the instrument are correctly configured for the device under test.
Verify correct cable termination at both DCS termination points and Device under test.
Verify that HOOK-UP installation has been correct.
Test the wiring termination by doing cold wire test or continuity test end to end from Field device until
Marshalling Panel.
Apply Input Signal through Hand Pump to High Side of Transmitter with 0%,50% and 100% for
Raising or Falling and observe reading on DCS Console.
OR
Simulate the instrument by HART to increase or decrease the simulating to 0,50,100 % of the instrument
range and check on DCS console.
Verify the ferruling (tag) of the wiring on field device, Field junction box, Marshalling panel/rack and
DCS cabinet.
Verify the Tag of Instrument on Operator Console.
Verify the Power requirement of the instrument are correctly configured for the device under test.
Verify correct cable termination at both DCS termination points and Device under test.
Verify that HOOK-UP installation has been correct.
Test the wiring termination by doing cold wire test or continuity test end to end from Field device until
Marshalling Panel.
Check Switch by simulating the signal by actuating the Switch “ON” and “OFF” by hand or put
jumper at switch terminal head.
Check DCS alarms etc. Actuate the switching action and check all the related system such as
alarms,trip signal, indicating lamp etc.
SIMPLE LOOP
loop test
loop checking
FLOW LOOP
FLOW LOOP
Verify the ferruling (tag) of the wiring on field device, Field junction box, Marshalling panel/rack and
DCS cabinet.
Verify the Tag of Instrument on Operator Console.
Verify the Power requirement of the instrument are correctly configured for the device under test.
Verify correct cable termination at both DCS termination points and Device under test.
Verify that HOOK-UP installation has been correct.
Test the wiring termination by doing cold wire test or continuity test end to end from Field device until
Marshalling Panel.
Apply Input Signal through Hand Pump to High Side of Transmitter with 0%,50% and 100% for
Raising or Falling and observe reading on DCS Console.
Perform simulation using 0%,50%,and 100% of full scale and verify the indication on the DCS
Console and local indicator if provided.
In case of flow loop is having control output element, manually set the output to 0%, 25%,75% and
100% of the operating signal in the HMI. Check for the valve stroke and tight closing of control valve.
Check the fail-safe position of the valve after completing the test by removing the air supply to the valve.
PRESSURE LOOP
PRESSURE LOOP
Verify the ferruling (tag) of the wiring on field device, Field junction box, Marshalling panel/rack and
DCS cabinet.
Verify the Tag of Instrument on Operator Console.
Verify the Power requirement of the instrument are correctly configured for the device under test.
Verify correct cable termination at both DCS termination points and Device under test.
Verify that HOOK-UP installation has been correct.
Test the wiring termination by doing cold wire test or continuity test end to end from Field device until
Marshalling Panel.
Apply Input Signal through Hand Pump to High Side of Transmitter with 0%,50% and 100% for
Raising or Falling and observe reading on DCS Console.
Perform simulation using 0%, 50%, and 100% of full scale and verify the indication on the DCS
Console and local indicator if provided.
In case of flow loop is having control output element, manually set the output to 0%, 25%, 75% and
100% of the operating signal in the HMI. Check for the valve stroke and tight closing of control valve.
Check the fail-safe position of the valve after completing the test by removing the air supply to the valve.
LEVEL LOOP
LEVEL LOOP
Verify the ferruling (tag) of the wiring on field device, Field junction box, Marshalling panel/rack and
DCS cabinet.
Verify the Tag of Instrument on Operator Console.
Verify the Power requirement of the instrument are correctly configured for the device under test.
Verify correct cable termination at both DCS termination points and Device under test.
Verify that HOOK-UP installation has been correct.
Test the wiring termination by doing cold wire test or continuity test end to end from Field device until
Marshalling Panel.
Apply Input Signal through Hand Pump to High Side of Transmitter with 0%,50% and 100% for
Raising or Falling and observe reading on DCS Console.
Perform simulation using 0%, 50%, and 100% of full scale and verify the indication on the DCS
Console and local indicator if provided.
In case of flow loop is having control output element, manually set the output to 0%, 25%, 75% and
100% of the operating signal in the HMI. Check for the valve stroke and tight closing of control valve.
Check the fail-safe position of the valve after completing the test by removing the air supply to the valve.
TEMPERATURE LOOP
TEMPERATURE LOOP
Verify the ferruling (tag) of the wiring on field device, Field junction box, Marshalling panel/rack and
DCS cabinet.
Verify the Tag of Instrument on Operator Console.
Verify the Power requirement of the instrument are correctly configured for the device under test.
Verify correct cable termination at both DCS termination points and Device under test.
Verify that HOOK-UP installation has been correct.
Test the wiring termination by doing cold wire test or continuity test end to end from Field device until
Marshalling Panel.
For thermocouple input, use a voltage source and deliver input signals corresponding to 0%, 50%, and
100% of the input span of temperature transmitter according to the standard table. While in RTD input,
connect the decade resistor box in place of RTD and obtain the resistance values corresponding to 0%,
25%, 50%, 75% and 100% of the span and use the obtained resistance as the input value.
Verify the indication in the DCS indicator and local indicator if provided.
In case of temperature loop is having control output element, manually set the output to 0%, 25%, 75%
and 100% of the operating signal in the HMI. Check for the valve stroke and tight closing of control
valve. Check the fail-safe position of the valve after completing the test by removing the air supply to the
valve.
Reassemble the temperature element to the original position
Share this:
Share
Like this:
Visual and Technical Checking of Instrumentation and Control System
This article defines the minimum requirements for initial inspection, loop check, and commissioning of
control systems during new plant construction, as well as those inspections, loop checks, and
commissioning that might be necessary following major revisions/modifications or repair. This document
outlines specific steps that need to be taken in the…
Tags:Instrumentation Articles
SHOW COMMENTS
Subscribe Youtube Channel
paktechpoint subscribe
Parts 2
Say true if the statement is correct false if the statement is incorrect(10 marks)
1,checking is the final process before the commissioning of the processing system.
2,Do not perform tests between assets and neutrals.
3,The loop checking checks the connection between each component in the control loop.
4,if resistance is than, mega-ohm- disconnect the appliances.
5,The fielding sensing device is properly installed in accordance with engineering specification.