This document outlines the tasks, durations, and schedule for constructing a single-story bungalow house in Perak, Malaysia over 165 days. It involves preliminary works like site preparation over 16 days, structural works like foundations and framing over 106 days, architectural works like walls and finishes over 51 days, mechanical and electrical installations over 85 days, external works like landscaping over 12 days, and closing activities like inspections over 28 days. The project is scheduled to be completed by June 18th, 2021.
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0 ratings0% found this document useful (0 votes)
150 views4 pages
Membina Dan Menyiapkan Sebuah Rumah Banglo Setingkat Di SI Perak 2
This document outlines the tasks, durations, and schedule for constructing a single-story bungalow house in Perak, Malaysia over 165 days. It involves preliminary works like site preparation over 16 days, structural works like foundations and framing over 106 days, architectural works like walls and finishes over 51 days, mechanical and electrical installations over 85 days, external works like landscaping over 12 days, and closing activities like inspections over 28 days. The project is scheduled to be completed by June 18th, 2021.
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 4
Task Name Duration
Membina dan menyiapkan sebuah rumah banglo setingkat di SI Perak
2 165 days PRELMINARIES WORKS 16 days Site Posessition 0 days Mobilisation 7 days Site Preparation 3 days Site Hoarding 3 days Setting Out 1 day Earthwork 2 days STRUCTURAL WORKS 106 days Pad Foundation 20 days Setting Out 1 day Exavation Work 2 days Lean Concrete 1 day Formwork 5 days Reinforcement Bar 5 days Anti termite 1 day Concreting Work 5 days Column Stump 11 days Reinforcement Bar 3 days Formwork 3 days Concreting work 5 days Ground Beam 17 days Extcavation Work 1 day Lean Concrete 1 day Formwork 5 days Reinforcement Bar 5 days Concreting 5 days Ground Slab 15 days Site Preparation 2 days Formwork 3 days DPM 2 days BRC (mesh rein) 3 days Concreting Work 5 days Column 15 days Reinforcement Bar 5 days Formwork 5 days Concreting Work 5 days Roof Beam 28 days Formwork 5 days Reinforcement Bar 5 days Concreting Work 5 days Roof Structure 13 days Roof Trusses 5 days Wire mesh 2 days Aluminium sheet 2 days Roof Tile 5 days Fascia board 2 days ARCHITECTUAL WORKS 51 days Brickwall 7 days Door Frame 2 days Door and window Leaf 2 days Plastering 7 days Floor Rendering 3 days Floor and Wall Tile 5 days Ceiling Frame 3 days Ceiling Board 3 days Painting 5 days MECHANICAL AND ELECTRICAL WORKS 85 days Wiring 7 days Electrical Fitting 3 days Connect to TNB 1 day Piping and Plumbing 7 days Sanitary Fitting 3 days Connect to Main Source 1 day Sewerage Pipe 5 days Manhole 3 days Water Tank 1 day Airconditioning 2 days EXTERNAL WORKS 12 days Parimeter Drain 3 days Apron 2 days Fencing 7 days Landscaping 5 days Roadwork 5 days CLOSING WORKS 28 days Inspection 2 days Defect Work 14 days Site Clearance 5 days Testing and Commensioning 7 days Handing Over 0 days MONTHLY COST CUMULATIVE COST PERCENTAGE CUMULSTIVE PERCENTAGE Start Finish Weightage