This document provides a risk classification assessment for new products and production processes. It outlines 4 criteria to evaluate: 1) product-related factors, 2) production process factors, 3) time-related factors, and 4) supplier-related factors. Each criterion contains sub-factors that are scored from 0 to 2, with the total score used to recommend an overall risk classification of A, B, or C, with A being the highest risk. The document advises that the automatic point assessment should only be a suggestion, and a supervisor may also consider objective priorities in determining the overall risk classification.

Uploaded by

cinconcon
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLS, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
132 views1 page

ABC Risk Classification

This document provides a risk classification assessment for new products and production processes. It outlines 4 criteria to evaluate: 1) product-related factors, 2) production process factors, 3) time-related factors, and 4) supplier-related factors. Each criterion contains sub-factors that are scored from 0 to 2, with the total score used to recommend an overall risk classification of A, B, or C, with A being the highest risk. The document advises that the automatic point assessment should only be a suggestion, and a supervisor may also consider objective priorities in determining the overall risk classification.

Uploaded by

cinconcon
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLS, PDF, TXT or read online on Scribd
You are on page 1/ 1

Risk classification : A, B or C Assessment

1. Product- 1.1 Complexity (type and number of functions, level of system integration, number of variants, number of departments involved)
related high = 2, average = 1, low = 0
criteria 1.2 Product innovation (concept; design; material; function; appearance; feel)
(Product) Basically new = 2, part-criteria new = 1, known = 0
1.3 Critical problems in the past (field rejects; in-house problems)
No. of incidents : very frequent = 2, frequent = 1, low = 0
1.4 Launch problems in the past
high = 2, average = 1, low = 0
1.5 Development effort (expertise; different development areas involved)
critical = 2, fairly critical = 1, not critical = 0
2. Production 2.1 Process innovation
process- New technology for the supplier = 2, for the location = 1, none = 0
related 2.2 Predicted process stability (level of automation; manual production; production system; scrap levels)
criteria critical = 2, fairly critical = 1, not critical = 0
(Process) 2.3 Production facility / machinery technology
New technology for the supplier = 2, for the location = 1, none = 0
2.4 Infrastructure (re number and complexity of sub-suppliers, location, logistics)
critical = 2, fairly critical = 1, not critical = 0
2.5 Delivery / call-off times (combination of long transport distances, range of variants, JIT- / JIS deliveries, several delivery locations)
critical = 2, fairly critical = 1, not critical = 0
3. Time-related 3.1 Procurement times for production facility and machines, if appropiate, related to the date for placing the order
criteria critical = 2, fairly critical = 1, not critical = 0
3.2 Procurement times for tools, if appropiate, related to the date for placing the order
critical = 2, fairly critical = 1, not critical = 0
3.3 Procurement times for parts and basic materials
critical = 2, fairly critical = 1, not critical = 0
3.4 Critical timing issues in the past
critical = 2, fairly critical = 1, not critical = 0
3.5 Frequency of changes (effects on / by other delivered products / dependency on design and system)
high = 2, average = 1, low = 0
4. Supplier- 4.1 Supplier assessment (new supplier, reliability of deliveries, overall reliability, sub-supplier management)
related critical = 2, fairly critical = 1, not critical = 0
criteria 4.2 New product for the supplier
new = 2, new for the location = 1, known to the supplier = 0
4.3 New supplier production location
new, no experience = 2, new, with experience = 1, a previous or known location = 0
4.4 Supplier project management (complexity of the supply chain, contact personnel, availability, general readiness, capacity, structure)
critical = 2, fairly critical = 1, not critical = 0
4.5 Problems with earlier (other) deliveries (launch; field and in-house problems)
very frequent = 2, frequent = 1, low = 0

Risk classification A: 40 -18 points (suggestion)


Risk classification B: 17 - 8 points (suggestion)
Risk classification C: 7 - 0 points (suggestion)

The automatic assessment by points should be regarded as a proposal. A superordinated / object-related classification of
priorities is recommendable as well!