If The Current E-Pay Production Stays and Requires Development To Be On A Different Set of Machines
If The Current E-Pay Production Stays and Requires Development To Be On A Different Set of Machines
If The Current E-Pay Production Stays and Requires Development To Be On A Different Set of Machines
Scenario 1
If the current E-pay production stays and requires development to be
on a different set of machines:
A) Hardware :
a) Items:
S. Item Name/ Product specs Qty Reqd Unit Cost Total Cost
N
1 App Servers(Old DB Server) (HP Proliant 2 0 0
DL385G2) Rack mounted
1 CPU (Quad Core), 4 GB RAM, 2 X 146 Gb 15K
rpm (Network, USB, ILO2 Advance Pack, serial
ports etc same as in production) with RHEL 5.0
Standard installed
2 Web Servers (HP Proliant DL385G2) Rack 2 315000 630000
mounted
1 CPU (Quad Core), 4 GB RAM, 2 X 146 Gb 15K
rpm (Network, USB, ILO2 Advance Pack, serial
ports etc same as in production) with RHEL 5.0
Standard installed
3 DB Serves (Prod warehouse ) 2 0 0
4 Network / LAN Switch 8 port L2 , Unmanaged 2 40000 80000
switch
5 IP Console Adapters (2 Nos for HP Proliant 6 16000 96000
DL585G2 , 2 Nos for HP Proliant DL3852 , 2 Nos
for HP rx6600) with RHEL 4.5 & above installed
6 Foldable Monitor 17 “ TFT with Integrated KBD , 1 260000 260000
Mouse , 16 port IP KVM Switch (Line item 5
included )
7 36 U Rack with grounding / Earthing Kit , 1 70000 70000
Redundant PDU fed by different power sources ,
ballast option kit , Rack light kit, rack coupling
kit etc.
Total 1136000
B) Software :
a) Items
or
Total S/W Cost : 59,27,848 + 20,00,202 = 79,28,050 (if able to split CPU in app
server from 2 to 1)
Total H/W and S/W Cost for New Development Setup : 1,08,91,974 + 11,36,000 =
1,20,27,974
Or
Total H/W and S/W Cost for New Development Setup : 79,28,050 + 11,36,000 =
90,64,050 (if able to split CPU in app server from 2 to 1)
II) For New Development Setup:
Scenario 2
If the current E-pay production stays and require development not to
be on a different set of machines:
A) Hardware :
a) Items:
S. Item Name/ Product specs Qty Reqd Unit Cost Total Cost
N
1 Web Servers(Old DB Server) (HP Proliant 2 0 0
DL385G2) Rack mounted
1 CPU (Quad Core), 4 GB RAM, 2 X 146 Gb 15K
rpm (Network, USB, ILO2 Advance Pack, serial
ports etc same as in production) with RHEL 5.0
Standard installed
2 App Servers ( core FOIS Dev Server) 2 0 0
3 DB Serves (Prod warehouse ) 2 0 0
4 Network / LAN Switch 8 port L2 , Unmanaged 2 40000 80000
switch
5 IP Console Adapters (2 Nos for HP Proliant 2 16000 32000
DL585G2 ) with RHEL 4.5 & above installed
Total 1,12000
B) Software :
a) Items
Total H/W and S/W Cost for New Development Setup : 1,12,000 + 89,24,672 =
90,36,672
II) For New Development Setup:
Scenario 3
If Only Core FOIS Prod and Dev have to stay:
II) For New Development Setup:
Scenario 4
If the current E-pay production stays and development to be
distributed onto existing machines:
A) Hardware :
a) Items:
S. Item Name/ Product specs Qty Reqd Unit Cost Total Cost
N
1 App Servers( Existing Core FOIS App server) 2 0 0
2 Web Servers (Existing Prod web Server) 2 0 0
3 DB Serves (Prod warehouse ) 2 0 0
4 Network / LAN Switch 8 port L2 , Unmanaged 2 40000 80000
switch
5 IP Console Adapters (2 Nos for HP Proliant 2 16000 32000
DL585G2 , 2 Nos for HP Proliant DL3852 , 2 Nos
for HP rx6600) with RHEL 4.5 & above installed
Total 112000
B) Software :
a) Items
Total H/W and S/W Cost for New Development Setup : 1,12,000 + 29,63,924 =
30,75,924
Pros and Cons for Each Scenario
Scenario 1
Extra space needed in server room to install for just two new servers in a rack
No major migration effort needed
If unable to split the CPU from 2 to 1 in App server then new setup cost will
be approx 1.2 Cr
Scenario 2
Virtualization on the core FOIS T&D setup will effect the performance of
training environment and hampering development
No extra space need in the server room
Scenario3
A challenging and new scenario
Rigorous testing has to be done to make the existing application to run on a
new OS.
App server can only be released when the rigorous testing is done on a new
platform i.e HP-UX which can be done in two ways. Firstly, buying new two
servers with HP-UX or testing on existing core FOIS T&D setup.
Scenario 4
No extra space need in the server room
No extra hardware needed
Major cost is involved in buying licenses of Weblogic.
Virtualization on the core FOIS T&D setup will effect the performance of
training environment and hampering development