CP0-8 Daily Progress Report11-02.2021

The document provides a daily progress report from a fabrication yard and laying site for a water transmission pipeline project. It includes statistics on the cumulative and daily quantities of various pipeline fabrication activities like edge cutting, rolling, fitting, welding, testing, coating, and laying. At the laying site, it lists 4 contractors and their progress in laying pipes between specified chainages, with a total of 127 meters laid on that day.

Uploaded by

Jagadeesan S M
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
41 views1 page

CP0-8 Daily Progress Report11-02.2021

The document provides a daily progress report from a fabrication yard and laying site for a water transmission pipeline project. It includes statistics on the cumulative and daily quantities of various pipeline fabrication activities like edge cutting, rolling, fitting, welding, testing, coating, and laying. At the laying site, it lists 4 contractors and their progress in laying pipes between specified chainages, with a total of 127 meters laid on that day.

Uploaded by

Jagadeesan S M
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 1

Package Name: CP-08, Supplying,fabrication & Laying of clear water transmission main from Harohalli to Vajarahalli.

DAILY PROGRESS REPORT ON FABRICATION YARD DATE :11-02-2021


MS PIPELINE WORKS
Previous Day Present Day Cumulative Quantity
Plate
Sl. No. Description
Thickness Numbers Meters Numbers Meters Numbers Meters

20 1328 3320 24 60.0 1352 3380.0


1 Edge cutting (Nos)
18 290 725 0 0.0 290 725.0
20 1282 3205 12 30.0 1294 3235.0
2 Rolling (Nos)
18 290 725 0 0.0 290 725.0
20 427 3165 2 15.0 429 3180.0
3 Fit up (Meters)
18 96 720 0 0.0 96 720.0

20 420 3150 5 37.5 425 3187.5


4 SAW Welding (Meters)
18 96 720 0 0.0 96 720.0

20 380 2850 5 37.5 385 2887.5


5 Radiography test (Meters)
18 96 720 0 0.0 96 720.0

20 365 2737.5 2 15.0 367 2752.5


6 Hydraulic test (Meters)
18 96 720 0 0.0 96 720.0

20 168 1260 5 37.5 173 1297.5


7 Copper slag Blasting
18 0 0 0 0.0 0 0.0

20 153 1147.5 0 0.0 153 1147.5


8 Epoxy coating (Meters)
18 0 0 0 0.0 0 0.0

20 151 1132.5 0 0.0 151 1132.5


9 Wrapping of welded mesh (Meters)
18 0 0 0 0.0 0 0.0

20 135 1012.5 5 37.5 140 1050.0


10 Guniting
18 0 0 0 0.0 0 0.0

20 121 907.5 6 45.0 127 952.5


11 Laying
18 0 0 0 0.0 0 0.0

DAILY PROGRESS REPORT ON LAYING SITE DATE :11-02-2021


MS PIPELINE LAYING DETAILS
CHAINAGE IN MTRS LAYING DETAILS ( IN NOS)
SL.NO CONTRACTOR NAME TOTAL MTRS AS ON REMARKS
FROM TO TODAY TOTAL
YESTRDAY
1 UBEN PROJECTS 585 952.5 367.5 49 0 49 Work in Progress
2 MAHENDRA REDDY KOKU 1300 1577.5 277.5 35 2 37 Work in Progress
3 BEM ENTERPRISES 4830 4920 90 10 2 12 Work in Progress
4 RGN ENTERPRISES 5800 6017.5 217.5 27 2 29 Work in Progress

TOTAL 952.5 121 6 127