Sap PR Thorw MRP
Sap PR Thorw MRP
Contributed By
Yogesh Jagtap
Under the guidance of Prashun
Shetty
1) Number Ranges-
2) Master Data-
3) Planned Order-
4) Planning Run-
MRP Group-
You can define the default MRP group for every material type and plant. Example ZFNS
material type assign MRP group 0010 Make-to-Stock Production to plant SDP1.
MRP Areas-
1) The plant MRP area will have a plant together with all its storage locations and
stock with subcontractors. The plant MRP area is created automatically when you
convert the existing planning file entries to planning file entries for MRP areas.
SPRO Path-
Path-
MRP Type-
If it’s routine for a vendor to deliver material on a particular day of the week, it
makes sense to plan to buy this material on that particular day and adopt this
cycle.
2) ND-No Planning.
Both the reorder level and the safety stock level are define manually in the
appropriate material master.
The integrated forecasting program determine the both the reorder level and
safety stock level. Historical or past consumptions data are used by the system
to predirect future requirement. The forecast value are used by the system to
work out reorder level and safety stock level.
1) Reorder Point Planning-
In Reorder point procedure, procurement trigger when is triggered when the
sum of plants stock and firm receipt falls under reorder point.
When enter MRP type as ‘VB’ Manual Reorder Point Planning then we need to
enter below MRP type Reorder point.
2) MRP Controller-
1) MRP Controller is responsible for material requirement point planning or
Material availability.
2) MRP controller task include executing and monitoring material requirement
planning.
MM-PP Integration By Using MRP Page 9
3) They ensure that material required to manufactured finished product or
superior assemblies are available on time.
2) MRP2 -
1) Procurement –
E-In-house Production
F-External Procurement
X-Both Production
2) Scheduling-
1) In-house production Days-
2) Planned Delivery Time-
No of calendar days required to obtained material.
3) GR Processing Time-
Number of workdays required after receiving the material to quality
inspection and placement into storage location.
Safety Stock- The quantity of stock to satisfy high requirement in the stocking up period.
Path
Path-
Path-
Path-
Path-