Subcontracting Process
Subcontracting Process
Version: 3.0
Last Updated: 06/11/2019
Table of Contents
1 Scope & Purpose...............................................................................................................................1
3 Inputs.................................................................................................................................................1
4 Outputs..............................................................................................................................................1
5 Entrance Criteria................................................................................................................................2
6 Exit Criteria.......................................................................................................................................2
7 Process Flow......................................................................................................................................2
8 Procedure...........................................................................................................................................3
8.1 Subcontractor Designation................................................................................................................................3
9 Risk Considerations...........................................................................................................................4
10 Reference Documents........................................................................................................................4
APPENDICES.............................................................................................................................................5
Appendix A: Acronyms....................................................................................................................................................5
Appendix B: Documents and Records..............................................................................................................................6
Appendix C: Reporting Thresholds..................................................................................................................................8
List of Tables
Table 1: Roles and Responsibilities.................................................................................................................................................................1
Table 2: Acronyms.......................................................................................................................................................................................... 5
Table 3: Records.............................................................................................................................................................................................. 6
Table 4: Reporting Thresholds......................................................................................................................................................................... 8
List of Figures
Figure 1: Process Flow Diagram...................................................................................................................................................................... 3
Revision History
Rev. # Release Date Author Reviewer(s) Approver Description of Change
3.0 06/14/19 M. Parimi CRB M. Couto Updated to reflect the VMD Corp Branding
2.0 04/07/17 S. Ovalle CRB S. Ovalle Updated to reflect new standard template and
include inputs, outputs, entrance criteria, exit
criteria, risk considerations
1.0 03/07/17 S. Ovalle CRB S. Ovalle Baseline version of document
This document formalizes an association with another organization to perform a part of the work based upon an award is a
“Subcontract”. The party performing the effort under a subcontract agreement is the “Subcontractor”.
Role Responsibility
Contracts Administrator Prepares subcontract agreement, negotiates terms, executes and manages changes to
agreement, close out subcontract
Sponsor/Program Director Submits request for subcontractor, reviews invoices, verifies subcontractor’s work,
include subcontractor status in customer status report
Subcontractor Reviews subcontract, executes agreement, submits invoices, submit final documents as
required
Customer Awards work to Prime
3 Inputs
Inputs are the policies, processes, documents, records, environmental or organizational factors, or any other factors that exist prior
to entering the process and influence process performance. The process relies on the following inputs:
Contract
Statement of Work (SOW) or Performance Work Statement (PWS)
Non-disclosure Agreement (NDA)
Federal Acquisition Regulations (FAR)
4 Outputs
Outputs are the processes, documents, records, or other factor that the process produces or changes. The process generates the
following outputs:
5 Entrance Criteria
Entrance criteria describe the conditions that should exist prior to a process being initiated. The entrance criteria for the process
include:
6 Exit Criteria
Exit criteria describe the conditions that should exist prior to concluding the process. The exit criteria for the process include:
7 Process Flow
The figure below provides a visual representation of the process. Further explanation of the process activities follows.
8 Procedure
8.1 Subcontractor Designation
If the subcontractor is designated in the proposal and a subsequent award is issued to the contractor, it is not essential to
comply with the procurement prerequisites for competitive bidding or sole source justification since the Sponsor already
endorsed the selection.
There are two methods of selecting a subcontractor: competitive bidding or sole source procurement. Competitive
bidding is a common method of subcontractor selection. This method requires solicitation of proposals from an
individual or a number of companies and a final selection of a subcontractor is made from those responding. The
company is selected based on technical merit and cost objectives. When the procurement requires performance from a
sole entity because services or expertise are not available from other sources, the Contractor will identify the need for the
services and why the selected subcontractor is the sole source available for the required services.
The subcontractor shall submit invoices for payment as outlined in the terms and conditions of the subcontract
agreement. The invoice should be reviewed to ascertain that the program number is referenced and correct, costs are
properly allocated and the amount invoiced is within the cost of the subcontract and charges were incurred within the
period of performance of the prime contract. Invoices are to be submitted to the Accounts Payable Department for
payment.
o Final invoice
o Final fiscal report
o Final technical report
9 Risk Considerations
None
10 Reference Documents
The following documents relate to this process:
ISO 9001:2015 International Standard; Clause 8.4 – Control of externally provided processes, products and services
Quality Management System Manual
Control of Documented Information Process
Corrective Action Process
Internal Audit Process
Risk Management Process
Operations Process
HR/Recruiting Process
Business Development/Proposal Management Process
Subcontracting Process
Supplier Evaluation Process
APPENDICES
Appendix A: Acronyms
The following table presents the definitions for acronyms used in this document.
Table 2: Acronyms
Acronym Definition
NDA Non-disclosure Agreement
PWS Performance Work Statement
SOW Statement of Work
TA Teaming Agreement
Table 3: Records