Nse Technical Report and Post Graduate Experience Format - 2
Nse Technical Report and Post Graduate Experience Format - 2
AND
PRESENTED TO
BY
September 9, 2020
“TECHNICAL REPORT”
BY
September 9, 2020
CERTIFICATE OF SUBMISSION
…………………………………………………
………. …………………………………………………
…………………..
Signature of candidate and date Signature of Senior Engineer and date
………………………………………………… …………………………………………………
………… ……………………
Name of Candidate Name of Senior Engineer
TABLE OF CONTENTS
CHAPTER ONE: DESIGN AND CONSTRUCTION OF (FIRST BEST OF
10)
ST
1.0 DESIGN AND CONSTRUCTION OF (YOUR 1 PROJECT TITLE)
1.1 PRELIMINARY STUDIES/INVESTIGATIONS
1.2 DESIGN CONSIDERATIONS/CRITERIA
1.3 METHODOLOGY AND DESIGN CALCULATIONS
1.4 STANDARDS AND SPECIFICATIONS
1.5 INSTALLATION/ANALYSIS/TEST & CALCULATIONS (BEME)
1.6 ANALYSIS OF TEST RESULTS AND COMMISSIONING
CHAPTER THREE
3.0 RELEVANCE OF PROJECTS
3.1 RELEVANCE OF PROJECT 1
3.1.1 RELEVANCE OF PROJECT 1 EXAMPLE: (UNIVERSITY OF IBADAN,
MULTI-PURPOSE 150 ROOM ACCOMODATION/RESEARCH PROJECT) TO
THE SOCIETY AT LARGE
TRANSPORTATION (WHERE
APPLICABLE) RECREATION (WHERE
APPLICABLE)
WATER SUPPLY (WHERE
APPLICABLE) EMPLOYMENT
(WHERE APPLICABLE)
IMPROVEMENT OF QUALITY AND STANDARD
OF LIVING E.t.c
3.1.2 RELEVANCE OF PROJECT 1 EXAMPLE (UNIVERSITY OF IBADAN, MULTI-
PURPOSE 150 ROOM ACCOMODATION/RESEARCH PROJECT) TO THE
ENGINEERING PROFESSION
ENCHANCEMENT OF RESEARCH (DATA COLLECTION ,
RESEARCH FINDINGS, INNOVATIONS e.t.c)
DEVELOPMENT/TECHNOLOGICAL BREAKTHROUGH
DELIVERY OF PECULIAR, FUNCTIONAL AND SAFE DESIGNS
CONSTRUCTION ACUMEN AND INDIGENOUS
TECHNOLOGICAL GROWTH DEVELOPMENT OF
ENGINEERING MANPOWER
DEVELOPMENT OF PROJECTS AND
MANAGEMENT SKILLS DELIVERY OF PROJECT
3.2 RELEVANCE OF PROJECT 2
3.2.1 RELEVANCE OF PROJECT 2 TO THE SOCIETY
3.2.2 RELEVANCE OF PROJECT 2 TO THE ENGINEERING PROFESSION
RECOMMENDATION
Building re-design resolves client requirements into a set of instructions for the construction of a
building. Below I provide a summary of a process that, while it varies from project to project
nonetheless tends to follow a series of well-established stages e.g.
Feasibility Study
structural surveys of existing buildings (if they are expected to be retained and used)
site topography
Looking for evidence of underground chambers, voids, tunnels, pipes, watercourses, etc.
checking with statutory utilities whether any of their infrastructures pass under or over
the site
checking with statutory utilities about the capacity of the services supplying the site
aground investigations report looking at the ground's
o bearing capacity,
o mineral composition
o chemical composition
o presence of flora & fauna (esp. protected species / invasive species)
a review of planning policy requirements and their potential impact on-site capacity
a review of the surrounding neighborhood (the site context)
Detailed design
Detailed design (sometimes referred to as design development or detailed design and technical
design) takes on and develops the approved concept design. By the end of this stage, the design
should describe all the main components of the building and how they fit together,
Overall layout. Road layouts and landscape. Operational flows. Horizontal and vertical
circulation routes. Schedules for accommodation. Identification of standard and non-standard
room layouts. If appropriate, room datasheets. Building dimensions and gridlines. Architectural
plans sections and elevations of buildings, parts of buildings and components. Outline
specification including schedules of components, defining the performance and/or material
standards required (including colors). Elements of design that require specialist input or early
choice of manufacturer. Requirements for mock-ups, testing, samples or models necessary to
satisfy performance or public relations requirements (including computer-generated images).
Key assemblies, component drawings, and schedules. Initial schedules of finishes, doors, and
ironmongery, sanitary fittings, room numbers, and signage. Structural plan sections, elevations,
and specifications. Building services plans, sections, and elevations. Definition of phases if the
project is to be phased. Safety strategy.
Changes tend to cost more and cause more disruption as the design progresses, and there is a
tendency for budgets and designs to diverge unless strong management is in place.
CALCULATION SHEET
Design Calculation Sheet
Date: SEPTEMBER 2017
Basic Design Information
Imposed Load : 2.5 kN/m²
Finishes : 1.2 kN/m²
Partition Allowance : 1 kN/m²
Soil Bearing Pressure : 180KN/m²
Slab Design, fcu : 25 N/mm²
Slab Design, fy : 410 N/mm²
Beam Design, fcu : 25 N/mm²
Beam Design, fy : 410 N/mm²
Column Design, fcu : 25 N/mm²
Column Design, fy : 410 N/mm²
Foundation Design, fcu : 25 N/mm²
Foundation Design, fy : 410 N/mm²
Density Of Concrete : 24 kN/m³
Subject:
BM 1 - (450 x 230)
Made By:
Checked By:
Sheet No:
8
Design Code:
BEME
COST INDEXING FOR DIFFERENT MATERIAL
CONCERETE
A. Grade 20 (1:2:4)mix
(i) Cement = 7bags @ 2550 = 17850
(ii) Freight = for 7 bags @ N30 = 210
(iii) Chipping = 1.37 tons @ N65000/Trip =686
(iv) River sand = 0.686 ton @ N10,000/Trip = 686
(v) Water assume w/c = 0.67 = 5.16 gallon = 25
(vi) Labour = 7 bags @ N600 = N4200
(vii) Mason (daily rate) @ N3000 = N3000
Total N34876
(viii) Add overhead 10% of 34876 = N3487.6
(ix) Add profile 20% of 34876 = N6975.2
3
Net cost index for placing Im of 1:2:4 con N45337.8
B. Grade 15 (1:3:6) mix
i. Cement = 5 bags @ N2550= N12,750
ii. Freight = for 5 bags @ N30 = N150
iii. Chipping = 1.44 tons @ N65000/trip = N9,360
iv. River sand = 0.72 ton @ N10,000/Trip N720
v. Water = 4.4 gallon = N18.03
vi. Labour = 5 bags = N3000
vii. Mason (Daily rate) @ N3000= N3000
viii. Total N28998.03
ix. Add overhead 10% of 20, 982 N2899.803
COST OF BLOCK:
The cost of block (6” x 6” 18”) (150mm thick), mortar (1:6) and labourrequired =
N100
Cost of laying the block (rib floor) = N50
2 2
1m = 10blocks. /m
Cost index for constructing 1m2 of block wall = 150 x 10 = N1500per m2
i. Overhead 10% of N 1,500 = 1650
ii. Add profit 20% of N 1,500 1800
N1, 800
3. FORM WORK
The cost index shall be determined base on 3. 6 x 3. 6 sq. meters of planks
surface area = 3. 6 x 3. 6 = 12.96m2
The 12.96m2 contains
i. Cost of 12 plank (1 x 12 x 12) @N1,050 = N12,600
ii. “ “ 6 purlin (2 x 2 x 12) @N300 = N1,800
= N4422
Total = N 28,743
Cost for provision and fixing in place 12 plank with a surface area of 12.96m3 = N28,
743
= Cost for 1m2 = 1 x 28743 = 2,217.8 say 2,220
12.961
4. STEEL REINFORCEMENT
A. REINFORCEMENT (Y12)
Purchase cost of 1 length (11m) =2050
Freight = 400
Labour for cutting bending and fixing =2480
C. REINFORCEMENT (Y10)
vi. Purchase cost of 1 length (11m) = N1, 020
vii. Freight =N 30
viii. Labour for cutting bending and fixing = N 600
= N 1,650
ix. Add overhead 10% of = N1650
x. Add profit 20% of = N330
= N 2145 say N2150
Since 11m = N2150
1m =2150 = N 195 per m;
11
Y10/m = 0.616kg = N 195; 1kg = 195/0.616 = N316/kg
=N316000/ten
5. EXCAVATION WORK
i. Consider excavation cost of N2000 per partition (12F)
ii. Width of trench = 0.675m
iii. Depth = 1.2m
iv. partition = 3.6m
v. Total Vol. = 0.675 x 1.2 x 3.6 = 2.92m3
vi. Total Cost = N2000
Additional cost due to collapse of trench say 5% of 2000 = N100
3 3
Cost/m = 2100 = 719 Say N720/m
2.92
6. HARDCORE FILLING
i. 1 trip (i.e. 454m3) of hardcore cost = N 25,000
Earthworks
General Excavation. Top soil for
E421 disposal. Depth 663.81 20.00 13,276.2
not exceeding 150mm
Excavation of foundations. Material
E333 for re-use other 152.172 850.00 129,346.2
than topsoil, rock or artificial hard
matetrial. Depth
not exceeding 0.5 - 1m
Filling and compaction to structures in
E615 150mm layers. 152.172 75.00 11,412.9
imported natural material other than
topsoil, rock or artificial hard material.
Filling ancillaries, preparation of
E721 surface with natural 99.50 180.00 17,910
rock material. Max. size: 150mm
Layers
In Situ Concrete
Provision of concrete for ordinary
structural use.
Cement to BS 12.2omm Max. size
aggregate.
Grade C15 (1: 3: 6)
Grade C20 (1: 2: 4)
Placing of concrete
Mass, Blinding, thickness not 28,260.
F611 exceeding 50mm 2.00 00 56,520.00
Mass Footings. Thickness not 101.330 28,260. 1,175,050.8
F622 exceeding 225mm 8 00 0
Reinforced mass concrete suspended
F631 slab 150mm 17.855
Reinforced, Bases and starters. 33,280.
F722 Thickness: 225-00mm 5.22 00 173,721.60
N2,503,296.
B2/1 To collection 9
Concrete Ancillaries
Formwork fair finish. For concrete
components of constant cross- 322.120
G282 section, Columns m 1 50.00 16106.005
Reinforced, high yield steel bars to BS
4449
G524 12mm Diameter ton 0.15 338,000 50700
G525 16mm Diameter ton 0.50 219,000 109500
G522 8mm Diameter ton 0.80 225,000 180,000
Blockwork
Lighweight blockwork, one block 2,777.0
U411 construction, 3.00 0 8,331.00
vertical wall
N357,137.0
B2/2 To Collection 05
Concrete Ancillaries
Formwork fair finish. For concrete
components of constant 0.00
cross-section
G282 Columns m 155.00 50.00 7,750.00
G281 Beams m 16.00 50.00 800.00
Formwork fair finish. Plane Horizontal.
G213 Width: not exceeding
2,220.0
0.2-0.4 m2 96.00 0 213,120.00
Formwork fair finish. Plane sloping. 2,220.0
G223 Width: not exceeding m2 6.00 0 13,320.00
0.2-0.4
Deformed high yield steel bars to BS 370,000
G522 4449 8mm Diameter ton 0.70 .00 257,150.00
235,000
G524 12mm Diameter ton 1.80 .00 423,000.00
215,000
G525 16mm Diameter ton 2.50 .00 537,500.00
3,387,872.0
B3/1 To Collection 0
QUANTI
ITEM DESCRIPTION UNIT TY RATE AMOUNT
(=N=) (=N=)
Collection
2,503,296.
B2/1 9
357,137.00
B2/1 5
Bill No. 2 Carried to GRAND 2,860,433.
SUMMARY 905
GRAND SUMMARY
2,550,000.0
BILL NO. 1 - GENERAL ITEMS 0
2,870,432.6
BILL NO. 2 - SUB STRUCTURE 0
4,722,422.0
BILL NO 3- SUPER STRUCTURE 0
10,142,854.
SUB TOTAL 60
Add 10% Contingencies 1,014,285.46
N11,157,14
GRAND TOTAL 0.06
CHAPTER 2 :
FULL TITLE OF PROJECT: Design and construction of cover slab and drain
for the school entrance drainage.
BRIEF INTRODUCTION: In October of 2009 I was enlisted into the national
youth service corps (NYSC) program and was posted to serve in kebbi state. My
place of primary assignment was kebbi state ministry of works. The entrance into
the school next to my house had a drainage running by it and it was badly
dilapidated and has made it impossible for a heavy car e.g. truck or water tankers
to enter the building without the risk of the fabricated metal cover which was
already bent, from collapsing and causing damage to the car or individuals, so
there was a need to make a permanent amendment which will be durable and cost-
effective. So I designed and helped constructed a cover slab that ticks the above
boxes and gives a guarantee of lasting really long.
YEAR OF PROJECT: 2009
Loads considered:
1. Dead load (for slab)
2. HA + KEL (40kN/m)
3. HB loading (45 units - 112.5kn)
DESIGN INFORMATION
DESIGN CODE - 1. BS 8110: PART 1 (1997) AND PART 2 (1985) - STRUCTURAL USE OF CONCRETE
(CODE OF PRACTICE FOR DESIGN AND CONSTRUCTION)
2. BS 153, PART 3A (ROAD AND BRIDGE STANDARD LOADING).
MATERIAL DATA
N/mm
Characteristic strength of Concrete fcu = 25 ²
N/mm
Charateristic strength of reinforcement fy = 410 ²
Mass density of reinforced concrete, γ = 24 kN/m³
Loads considered
1 dead load (for slab)
HA + KEL (40kN/m) (Imposed
2 Load)
3 HB loading (45 units) (Imposed Load)
450 450
150
1000
150
25mm
A A
450m
400mm m
0.025
25
1300
PLAN OF COVER SLAB
1300
SECTION A - A
1300
LOADIN
G
(+)
UDL w
= 78.36 kN/m2
1.15
1.15
a= 375 mm
b= 75
375
d d d d d
d d d d
B=
(A) b+2d
A = a + 2d (B)
a= 375 mm
B
A
A = a + 2d = 0.713 a b d A B
B = b + 2d = 0.413 (m) (m) (m) (m) (m)
0.375 0.075 0.169 0.713 0.413
(Ref. Reynolds Reinforced concrete Designer's Handbook Table (11))
HB LOAD, W = 112.5 kN
MOMENTS
1. DEAD LOAD, DL
n= 11.024 kN/m²
L= 1.15 m
3. FROM HB LOADING
477.554
w= 5 kN/m²
L= 1.15 m
MIL(HB
MIL(HB) = wL²/8 = 78.94573 kN-m w L )
(kN/m²) (m) (kNm)
477.554 78.945
5 1.15 73
SUMMARY OF MOMENTS
1. MDL + MIL(HA + KEL)
MDL = 1.82240 kNm
5
MIL(HA + KEL)= 24.45389 kNm
26.276
MDL + MIL(HA + KEL) = 29 kN/m MDL MIL MTOTAL
(kNm) (kNm) (kNm)
1.82240 24.4538 26.276
5 9 29
2.MDL + MIL(HB)
1.82240
MDL = 5 kNm
MIL(HB) 78.9457
= 3 kNm MDL MIL(HB) MTOTAL
MDL + MIL(HB) = 80.76814 kNm (kNm) (kNm) (kNm)
1.8224 78.9457 80.7681
05 3 4
SECTION ANALYSIS/DESIGN
Use Maximum moment
80.7681
Mmax = 4 kNm
b= 450 mm
d= 169 mm
fcu = 25 N/mm²
K = M/(bd2fcu)< 0.156 Mmax b d fcu K
(N/mm
K = M/(bd2fcu) = 0.25137 (kNm) (mm) (mm) ²)
80.768 0.2513
14 450 169 25 7
RECOMMENDATION
1. Routine cleaning and maintenance of drains should be carried out ones a
month and 4 times during the rainy season
2. Carry out reconnaissance surveys and studies of the site before the design of
any structure.
3. Knowledge of the steps involved in the preparation of the bill of
engineering measurement and evaluation (BEME) and cost estimate for any
project is of utmost importance for an engineer
Conclusion
My experience on the FREMA Secondary School, cover slab and drain design
and construction initiated my first foray into full structural design and project
management which I was involved in from site reconnaissance to BEME
preparation and project planning and execution. In the course of this project, I
participated both managerially and technically. I was actively involved in the
analysis of survey data, production of design, preparation of BEME, cash flow
analysis, supervision/overseeing of engineering construction work, management
of meeting with the client.
To be frank these responsibilities were initially tasking on me since as a young
engineer I was suddenly ushered into the engineering field but I was able to rise
to the occasion and I have immensely benefited from the experience I garnered
from the exposure at such an early stage of my career.
CHAPTER 3
2. Carry out reconnaissance surveys and studies of the site before the design of
any structure.
3. Knowledge of the steps involved in the preparation of the bill of
engineering measurement and evaluation (BEME) and cost estimate for any
project is of utmost importance for an engineer
4. Building re-design resolves client requirements into a set of instructions for
the construction of a building. Below I provide a summary of a process that,
while it varies from project to project nonetheless tends to follow a series of
well-established stages e.g.
1. consideration
HB loading requirements derive from the nature of exceptional industrial
loads (e.g. electrical transformers, generators, pressure vessels, machine
presses, etc.) likely to use the column slab in the area.
The vehicle load is represented by a four axled vehicle with four wheels
equally spaced on each axle. The load on each axle is defined by a number
of units which is dependent on the class of road and is specified in BD 37/01
Chapter 4 as follows:
Motorways and trunk roads require 45 units, Principal roads require 37.5
units and other public roads require 30 units. One unit of HB is equal to
10kN per axle. There are five HB vehicles to check although most vehicles
can be discounted by inspection. The spacing between the inner two axles of
the vehicle has five different values which produce the range of HB vehicle
to consider.
1 unit of HB loading.
Only one HB vehicle is considered to load anyone superstructure. The
vehicle is positioned within one notional lane or straddles two notional lanes
in order to obtain the worst effect on the member. HA loading is placed in
any remaining lane not occupied by the HB vehicle. Also, if the deck is long
enough, the HA UDL only is placed in the lane occupied by the HB vehicle
but is omitted from the length of lane within 25m from the front and back of
the HB vehicle.
5.
Conclusion
My experience on the FREMA Secondary School, cover slab and drain design
and construction initiated my first foray into full structural design and project
management which I was involved in from site reconnaissance to BEME
preparation and project planning and execution. In the course of this project, I
participated both managerially and technically. I was actively involved in the
analysis of survey data, production of design, preparation of BEME, cash flow
analysis, supervision/overseeing of engineering construction work, management
of meeting with the client.
To be frank these responsibilities were initially tasking on me since as a young
engineer I was suddenly ushered into the engineering field but I was able to rise
to the occasion and I have immensely benefited from the experience I garnered
from the exposure at such an early stage of my career.
Changes tend to cost more and cause more disruption as the design progresses, and
there is a tendency for budgets and designs to diverge unless strong management is
in place.
“MY POST-GRADUATE EXPERIENCE”
BY
BY
APRIL, 2014
CERTIFICATE OF SUBMISSION
………………………………………………… …………………………………………………
………. …………………..
Signature of candidate and date Signature of Senior Engineer and date
………………………………………………… …………………………………………………
………… ……………………
Name of Candidate Name of Senior Engineer
CHAPTER ONE
1.0 SECONDARY EDUCATION (SCHOOLS ATTENDED WITH DATE)
1.1 HIGHER EDUCATION (SCHOOLS ATTENDANCE WITH DATE)
1.2 NYSC (PLACE OF PRIMARY ASSIGNMENT WITH DATE)
1.3 IN-SERVICE TRAINING : POSTGRADUATE (COURSE AND INSTITUTE WITH
DATES)
1.3.1 COURSE 1 (TITLE)
INSTITU
TE DATE
1.3.2 COURSE 2 (TITLE)
INSTIT
UE
DATE
1.3.3 COURSE 3 (TITLE)
INSTITU
TE DATE
1.3.4 COURSE 4 (TITLE)
INSTITU
TE DATE
QUALIFICATION:
First School Leaving Certificate (FSLC) 1995
Senior School Certificate Examination (SSCE) 2001
Bachelor Engineering (Civil) 2007
CHAPTER TWO
SUMMARY OF QUALIFICATIONS
I am a Civil Engineer with more than 5 years of experience in structural design, geotechnical
engineering, construction management, health and safety, research and development, leadership
and mentoring, as well as problem-solving, stable, thoughtful, technical, responsible, good
communication skill, intransigent in HSE with a clear potential to learn.
Key skills include:
Vast understanding of Civil and Geo-Technical Engineering concepts
Proficient in Microsoft Word, Microsoft Excel, Microsoft PowerPoint
Strong familiarity with design software like Civil-Soft, ORION, AutoCAD CIVIL3D,
AutoCAD and MatLab
Ability to work well with team members to ensure efficient operations
Excellent time management and organizational abilities
Outstanding internal and external communications skills
Extensive background in risk assessment and investigation
Fluent in English (written and oral communication skills)
Organizational and strategic planning
Multitasking
WORK EXPERIENCE: