0% found this document useful (0 votes)
66 views4 pages

PPM Assignment 2

The document discusses the 7 phases of a construction project: 1) Concept Design - Develop design brief and conceptual designs 2) Preliminary Design - Modify conceptual designs and prepare preliminary drawings and cost estimates 3) Drawings for Approval - Prepare drawings for statutory and client approvals 4) Working Drawings - Prepare working drawings, specifications, and tender documents 5) Appoint Contractors - Invite and evaluate tenders to appoint contractors 6) Construction - Oversee construction through site visits, approvals, and ensuring work follows contracts 7) Completion - Prepare completion reports and assist with obtaining occupancy certificates
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
66 views4 pages

PPM Assignment 2

The document discusses the 7 phases of a construction project: 1) Concept Design - Develop design brief and conceptual designs 2) Preliminary Design - Modify conceptual designs and prepare preliminary drawings and cost estimates 3) Drawings for Approval - Prepare drawings for statutory and client approvals 4) Working Drawings - Prepare working drawings, specifications, and tender documents 5) Appoint Contractors - Invite and evaluate tenders to appoint contractors 6) Construction - Oversee construction through site visits, approvals, and ensuring work follows contracts 7) Completion - Prepare completion reports and assist with obtaining occupancy certificates
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 4

Q1. What is a project? What are diff. phases of project management? Discuss each phase briefly.

A1. A project is a series of related a tasks which when they are carried in the correct order will lead to the completion of the project. Projects are
temporary, generally resulting in the creation of a tangible product or outcome. This is as opposed to a programme, which is a series of
interrelated projects that may be carried out repeatedly or continuously in order to support an ongoing process.

A construction project, sometimes just referred to as a ‘project’, is the organized process of constructing, renovating, refurbishing, etc.
a building, structure or infrastructure. The project process typically starts with an overarching requirement which is developed through the
creation of a brief, feasibility studies, option studies, design, financing and construction.

Construction projects are typically one off's. That is, a project team, brief and financing are put together to produce a unique design that
delivers a single project.

The Architect shall, after taking instructions from the Client, render the following services:

CONCEPT DESIGN [STAGE 1]:

1.01 Ascertain Client's requirements, examine site constraints & potential; and prepare a design brief for Client's approval.
1.02 Prepare report on site evaluation, state of existing buildings, if any; and analysis and impact of existing and/ or proposed
development on its immediate environs.

1.03 Prepare drawings and documents to enable the Client to get done the detailed survey and soil investigation at the site of the project.

1.04 Furnish report on measures required to be taken to mitigate the adverse impact, if any, of the existing and / or proposed
development on its immediate environs.

1.05 Prepare conceptual designs with reference to requirements given and prepare rough estimate of cost on area basis.

PRELIMINARY DESIGN AND DRAWINGS [STAGE 2]:

1.06 Modify the conceptual designs incorporating required changes and prepare the preliminary drawings, sketches, study model, etc.,
for the Client's approval along with preliminary estimate of cost on area basis.

DRAWINGS FOR CLIENT'S/ STATUTORY APPROVALS [STAGE 3]:

1.07 Prepare drawings necessary for Client's/ statutory approvals and ensure compliance with codes, standards and legislation, as
applicable and assist the Client in obtaining the statutory approvals thereof, if required.
WORKING DRAWINGS AND TENDER DOCUMENTS [STAGE 4]:

1.08 Prepare working drawings, specifications and schedule of quantities sufficient to prepare estimate of cost and tender documents
including code of practice covering aspects like mode of measurement, method of payments, quality control procedures on
materials & works and other conditions of contract.

APPOINTMENT OF CONTRACTORS [STAGE 5]:

1.09 Invite, receive and analyze tenders; advise Client on appointment of contractors.

CONSTRUCTION [STAGE 6]:

1.10 Prepare and issue working drawings and details for proper execution of works during construction.

1.11 Approve samples of various elements and components.

1.12 Check and approve shop drawings submitted by the contractor/ vendors.

1.13 Visit the site of work, at intervals mutually agreed upon, to inspect and evaluate the Construction works and where necessary clarify
any decision, offer interpretation of the drawings/specifications, attend conferences and meetings to ensure that the project
proceeds generally in accordance with the conditions of contract and keep the Client informed and render advice on actions, if
required.

1.14 In order to ensure that the work at site proceeds in accordance with the contract documents/drawings and to exercise time and
quality controls, the day-to-day supervision will be carried out by a Construction Manager (Clerk of Works/ Site Supervisor or
Construction Management Agency in case of a large and complex project), who shall work under the guidance and direction of the
Architect and shall be appointed and paid by the Client.

1.15 Issue Certificate of Virtual Completion of works.

COMPLETION [STAGE 7]:

1.16 Prepare and submit completion reports and drawings for the project as required and assist the Client in obtaining "Completion/
Occupancy Certificate" from statutory authorities, wherever required.