A1. A project is a series of related a tasks which when they are carried in the correct order will lead to the completion of the project. Projects are
temporary, generally resulting in the creation of a tangible product or outcome. This is as opposed to a programme, which is a series of
interrelated projects that may be carried out repeatedly or continuously in order to support an ongoing process.
A construction project, sometimes just referred to as a ‘project’, is the organized process of constructing, renovating, refurbishing, etc.
a building, structure or infrastructure. The project process typically starts with an overarching requirement which is developed through the
creation of a brief, feasibility studies, option studies, design, financing and construction.
Construction projects are typically one off's. That is, a project team, brief and financing are put together to produce a unique design that
delivers a single project.
The Architect shall, after taking instructions from the Client, render the following services:
1.01 Ascertain Client's requirements, examine site constraints & potential; and prepare a design brief for Client's approval.
1.02 Prepare report on site evaluation, state of existing buildings, if any; and analysis and impact of existing and/ or proposed
development on its immediate environs.
1.03 Prepare drawings and documents to enable the Client to get done the detailed survey and soil investigation at the site of the project.
1.04 Furnish report on measures required to be taken to mitigate the adverse impact, if any, of the existing and / or proposed
development on its immediate environs.
1.05 Prepare conceptual designs with reference to requirements given and prepare rough estimate of cost on area basis.
1.06 Modify the conceptual designs incorporating required changes and prepare the preliminary drawings, sketches, study model, etc.,
for the Client's approval along with preliminary estimate of cost on area basis.
1.07 Prepare drawings necessary for Client's/ statutory approvals and ensure compliance with codes, standards and legislation, as
applicable and assist the Client in obtaining the statutory approvals thereof, if required.
WORKING DRAWINGS AND TENDER DOCUMENTS [STAGE 4]:
1.08 Prepare working drawings, specifications and schedule of quantities sufficient to prepare estimate of cost and tender documents
including code of practice covering aspects like mode of measurement, method of payments, quality control procedures on
materials & works and other conditions of contract.
1.09 Invite, receive and analyze tenders; advise Client on appointment of contractors.
1.10 Prepare and issue working drawings and details for proper execution of works during construction.
1.12 Check and approve shop drawings submitted by the contractor/ vendors.
1.13 Visit the site of work, at intervals mutually agreed upon, to inspect and evaluate the Construction works and where necessary clarify
any decision, offer interpretation of the drawings/specifications, attend conferences and meetings to ensure that the project
proceeds generally in accordance with the conditions of contract and keep the Client informed and render advice on actions, if
required.
1.14 In order to ensure that the work at site proceeds in accordance with the contract documents/drawings and to exercise time and
quality controls, the day-to-day supervision will be carried out by a Construction Manager (Clerk of Works/ Site Supervisor or
Construction Management Agency in case of a large and complex project), who shall work under the guidance and direction of the
Architect and shall be appointed and paid by the Client.
1.16 Prepare and submit completion reports and drawings for the project as required and assist the Client in obtaining "Completion/
Occupancy Certificate" from statutory authorities, wherever required.