Unit 10
Unit 10
Unit 10
Contract Practice
Contract Practice 1
Note:
This set of notes is largely based on the information
from the books as listed in the Reference section
herein, and the author hereby acknowledges that
ownership of copyright of these materials, where
referred to or cited therefrom belongs those authors
and they are adopted for educational purpose only.
While every care has been taken in the assembly of
this set of notes, no responsibility for loss occasioned
to any person acting or refraining from action
occasioned by or as a result of any material included
herein can be accepted by the author.
Contract Practice 2
1
7/10/2017
Learning Outcomes
The students should be able to understand:
1. The origin of and usual problems in construction
disputes
2. The contract procedures for settlement of
disputes in SFBC 2005
3. The process of civil litigation
4. The common alternative dispute resolution (ADR)
methods employed in construction industry.
Contract Practice 3
Dispute Resolution
Origins of Construction Disputes
i. Contract Document Errors
ii. Poor Cost Estimation by Contractor
iii. Changed Working Conditions
iv. Consumer Reaction to Defects
v. Communication Problems amongst Project
Team Members
- Hohns H. Murray (1979)
Contract Practice 4
2
7/10/2017
Dispute Resolution
Usual Problems and Consequence
identified by Construction Industry
Council (“CIC”):
i. Interim Payment Disputes
ii. Overdue Final Account and Delayed Release of
Retention
iii. Payment to Suppliers
iv. Challenge to Impartiality of Consultants
v. Abandonment of Works
Contract Practice 5
Dispute Resolution
Important Principles suggested by CIC:
Contract Practice 6
3
7/10/2017
Contract Practice 7
Contract Practice 8
4
7/10/2017
5
7/10/2017
6
7/10/2017
Civil Litigation
Contract Practice 14
7
7/10/2017
Civil Litigation
Court System in Hong Kong
Small Claims Tribunal – Less than HK$50,000
Contract Practice 15
8
7/10/2017
Contract Practice 18
9
7/10/2017
Contract Practice 19
Contract Practice 20
10
7/10/2017
1. What is Mediation?
a consensual process where an
independent third party attempts to assist
the disputing parties in working towards a
negotiated settlement of a dispute.
Contract Practice 21
MEDIATION
Mediation Ordinance Cap 620, section 4 states that:
Mediation is a structured process comprising one or
more sessions in which one or more impartial
individuals, without adjudicating a dispute or any aspect
of it, assist the parties to the dispute to do any or all of
the following: -
(a) identify the issues in dispute;
(b) explore and generate options;
(c) communicate with one another;
(d) reach an agreement regarding the resolution of the
whole, or part, of the dispute.
Contract Practice 22
11
7/10/2017
MEDIATION
2. Features & Characteristics
a. Decision made by the parties not mediator
b. Parties control the mediation process and termination
c. Flexible & Speedy procedure
d. Rules of natural justice do not apply
e. Inexpensive
f. Win – win situation
g. Private process and without prejudice basis
h. Less tension
Contract Practice 23
MEDIATION
3. Role of Mediator
a. does not impose a decision on the parties
b. does not provide legal advice and would not take sides
c. will not determine who is right and who is wrong in the
disputes
d. will help the parties explore the strengths and
weaknesses of their cases
e. identify possible solutions
f. observe confidentiality in respect of all matters
disclosed
Contract Practice 24
12
7/10/2017
MEDIATION
4. Why mediation?
a. On 2 April 2009, the Judiciary implemented the Civil
Justice Reform (“CJR”) with a view to encourage and
facilitate the settlement of disputes by ADR if the Court
considers appropriate.
b. Practice Direction 6.1 (“PD 6.1”) came into effect on 2
April 2009. Parties in construction cases are
encouraged to attempt mediation as a possible cost-
effective means of resolving disputes.
Contract Practice 25
MEDIATION
4. Why mediation?
c. Practice Direction 31 ("PD 31") came into effect on 1
January 2010 (a new PD31 effective from 1 Nov 2014).
It states that the underlying objective of the Rules of the
High Court and the District Court is to facilitate the
settlement of disputes. The Court has a duty to further
that objective by encouraging disputing parties to use
ADR.
d. If a party has not engaged in mediation to the minimum
level of participation, or has no reasonable explanation
for not engaging in mediation, this party may face an
adverse costs order.
26
HKU SPACE: Becoming a Quantity Surveyor
13
7/10/2017
ADJUDICATION
What is Adjudication?
a. A dispute resolution process conducted by a sole
adjudicator in accordance with the adjudication rules
and the terms of the contract and its applicable law.
b. Specific issue to be resolved will be referred to the
decision of a third party neutral known as the
Adjudicator.
c. The adjudicator will produce a decision after the parties
has presented their evidence and submissions in written
or oral form.
Contract Practice 27
ADJUDICATION
What is Adjudication?
Contract Practice 28
14
7/10/2017
ADJUDICATION
Practice in Hong Kong
a. Unlike UK where adjudication was introduced by the
Housing Grants, Construction and Regeneration Act
1996. No statutory framework in Hong Kong yet.
b. Airport Core Programme Adjudication Rules 1992
c. Pilot scheme governed by HKSAR Construction
Adjudication Rules 2004
d. HKIAC Adjudication Rules 2009
e. Security of Payment Legislation (public - all, private –
new building only > HK$5M)
Contract Practice 29
EXPERT DETERMINATION
What is Expert Determination?
15
7/10/2017
EXPERT DETERMINATION
Features of Expert Determination
EXPERT DETERMINATION
Features of Expert Determination
16
7/10/2017
ARBITRATION
What is Arbitration?
Contract Practice 33
ARBITRATION
Features of Arbitration
a. Private and confidential process.
b. Party autonomy – choice of language, arbitrator, venue,
rules of arbitration.
c. Flexible procedures.
d. Exclusionary rules of evidence do not apply.
e. Rules of natural justice shall be observed.
f. Award is final and binding subject to very limited ground
for challenge.
g. Award is enforceable as if it is a court judgment.
Contract Practice 34
17
7/10/2017
ARBITRATION
Practice in Hong Kong
a. Arbitration Ordinance (Cap 609) come into effect on 1
June 2011.
b. Domestic and international regime are now fused, and
largely adopted the UNCITRAL Model Law.
c. Schedule 2 retains some of the provisions under the
old domestic arbitration regime, which parties may opt
in. (section 99 of Cap 609)
Contract Practice 35
ARBTRATION
Contract Practice 36
18
7/10/2017
19
7/10/2017
Contract Practice 39
20
7/10/2017
Contract Practice 41
Contract Practice 42
21
7/10/2017
4.3 Economical
4.4 Flexible
22
7/10/2017
Others:
Med-Arb: a hybrid 2-stage process. (see s.33 of Cap 609
arbitration ordinance allows an arbitrator to act as mediator if all
parties consent in writing.)
DRB: Dispute Review Board is widely used in USA. An
independent board of 3 people established at start of project, that
evaluates disputes as they arise during the project and make non-
binding settlement recommendations to the parties.
DAB: Dispute Adjudication Board is a pre-arbitration step with
bind decisions. First introduced by FIDIC since 1995. Similarly
formed as DRB but member of DAB can only be terminated by
mutual agreement of both parties.
Contract Practice 45
Class Exercise
Contract Practice 46
23
7/10/2017
References
Agreement & Schedule of Conditions of Building Contract for use in
the HKSAR, Private Edition – With Quantities 2005 Edition.
Hohns H. Murray (1979) Preventing and Solving Construction
Contract Disputes, Van Nostrand Reinhold Company
General Conditions of Contract for Civil Engineering Works 1999
Edition. HKSAR.
Guidelines on Dispute Resolution, Version 1, September 2010,
Construction Industry Council, Hong Kong
Reference Materials for Application of Dispute Resolution in
Construction Contracts, Version 1, January 2013, Construction
Industry Council, Hong Kong
Hong Kong Mediation Code, Department of Justice
HKIAC Adjudication Rules 2009
Contract Practice 47
CONTRACT PRACTICE
Lecture 10 – Dispute
Resolution
- The end -
Contract Practice 48
24