Method Statement of Construction of Pier and Abutment For Viaduct (Rev.2)
Method Statement of Construction of Pier and Abutment For Viaduct (Rev.2)
Method Statement of Construction of Pier and Abutment For Viaduct (Rev.2)
Contents 目录
1. Introduction 项目概况.......................................................................................3
2. References, Definitions and Abbreviations 参考文件,定义和缩写...............7
2.1 References 参考文件...............................................................................7
2.2 Definitions 定义.......................................................................................7
2.3 Abbreviations 缩写..................................................................................8
3. Permits 许可.......................................................................................................8
4. QA Classification of Materials 材料类别..........................................................8
护....................................................................................................................................9
5.1 Stockyard 砂石料存放场.........................................................................9
5.2 Storage and Management of Rebar 钢筋储存管理.................................9
5.3 Cement 水泥..........................................................................................10
5.4 Admixture 外加剂..................................................................................10
5.5 Construction Water 施工用水................................................................10
5.6 Coupler/Steel sleeve 钢筋连接套筒......................................................11
5.7 Release agent 脱模剂.............................................................................11
6. Plant and Equipment 车辆与机械设备...........................................................11
6.1 Plant 永久设备.......................................................................................11
6.2 Equipment 机械设备.............................................................................11
7. Method of Construction 墩(台)身施工方法..............................................13
7.1 Statement Introduction 方案概述..........................................................13
7.2 Installation of operation platform for pier/abutment construction.........14
墩(台)身施工操作平台安装..................................................................14
7.3 Flow chart of pier construction 墩身施工工艺流程.............................16
7.4 Construction procedures 施工步骤........................................................18
7.5 Construction method remarks 施工方法说明.......................................20
1
墩(台)身施工方案 Method Statement of Construction of Pier and Abutment
理..........................................................................................................................53
9.2 Special Environmental Protection Plan (SEMP) 具体环境保护计划...58
2
墩(台)身施工方案 Method Statement for Construction of Pier and Abutment
1. Introduction 项目概况
The viaducts of Padma Bridge Rail Link Project include:
帕德玛大桥铁路连接线高架桥分为:
3
墩(台)身施工方案 Method Statement for Construction of Pier and Abutment
4
墩(台)身施工方案 Method Statement for Construction of Pier and Abutment
5
墩(台)身施工方案 Method Statement for Construction of Pier and Abutment
6
墩(台)身施工方案 Method Statement for Construction of Pier and Abutment
7
墩(台)身施工方案 Method Statement for Construction of Pier and Abutment
“Temporary access road” means the roads used for construction during the construction
period, and can also be used for inspection and maintenance, and emergency.
临时通道是指施工期间用于工程施工的道路,工程结束后可作为桥梁检修通道和
救援通道。
2.3 Abbreviations 缩写
BR Bangladesh Railway 孟加拉铁路局
BUET Bangladesh University of Engineering and Technology 孟加拉工程技术大学
h Hour 小时
mo. Month 月
No. Number 编号
ER Employer’ s Representative 雇主代表
Qty. Quantity/Quantities 数量
ToC Table of Contents 目录
3. Permits 许可
ITEM Accept Reject
项目 接受 拒绝
Approval of Method Statement
施工方案报批 √
Approval of Drawings
相关图纸报批 √
Approval of Calculation Report(if
any) √
相关计算书报批(如果有)
Approval of Materials
材料报批 √
Checklist of
Equipment/Machinery √
机械设备检查表
Technical Disclosure
技术交底 √
Training on HSE
HSE 培训 √
QAM1 – Material that must be submitted to the Contractor for approval and to the Engineers
Representative for SONO (Statement of No Objection)
QAM1-必须提交雇主或工程师代表批准的主体工程材料
QAM2 – Materials that must be submitted internally for approval.
QAM2-施工分部自检的主体工程材料
行防护,免于机械损伤和暴露退化的风险。
Rebar shall not be mixed with acid, salt or oil. Contaminated rebar are not allowed to be
used.
钢筋不得与酸、盐、油类等杂物混合堆放;严禁使用被污染的钢筋。
5.3 Cement 水泥
The cement is delivered to site by specialized cement truck and stored in the cement tank at
concrete batching plant; for any cement stored over three (3) months, it will be retested
before using such cement.
水泥采用专用水泥运输车运送到现场、存放在混凝土搅拌站的水泥罐中,超过 3
个月的水泥,在使用前需重新检测。
5.4 Admixture 外加剂
The admixture products shall be provided by qualified supplier, and its quality shall meet the
Employer’s requirements. Special-made container shall be adopted for transportation and
storage of admixture. When saved, container shall be stock in the place with wind-proof,
rain-proof and free of sun exposure, and properly covered.
外加剂采用质量符合雇主需求要求的供应商提供的产品,在运输和储存过程中采
用特制容器运输及保存,保存时,容器放在具有防风、防雨、阳光暴晒的场所,并覆
盖。
5.5 Construction Water 施工用水
The water used for mixing and curing must be tested and meet the requirements of technical
specifications; the water used for concrete mixing shall be extracted from groundwater and
stored in the water pond within the batching plant.
用于混合和养护用水必须检测,并符合技术规格书要求;用于混凝土生产的水抽
取地下水并储存在搅拌站内的蓄水池内。
5.6 Coupler/Steel sleeve 钢筋连接套筒
The coupler/steel sleeve products shall be provided by qualified supplier, and its quality shall
meet the Employer’s Requirements or approved by CSC. Steel sleeves shall be properly
packed by wooden box or plastic material during transportation and storage.
The release agent is provided by suppliers who have qualifications; it is transported by tanks
10
墩(台)身施工方案 Method Statement for Construction of Pier and Abutment
or barrels; any lubricants (engine oil) are prohibited to use as release agent.
脱模剂采用合格供货商提供的产品,运输采用罐装或桶装保存,禁止使用润滑油
(机油)作为脱模剂。
Crawler crane
2 75t 2 / / 2018.9
履带吊
Wheel crane
3 60t / 1 1 2019.9
轮胎吊
Rebar
processing
Rebar cage processing
10 machinery / 2 1 1 2019.12
钢筋加工
钢筋加工机
械
Gantry crane Rebar cage processing
11 20t 4 1 1 2019.3
龙门吊机 钢筋加工
Submersible
Curing
20 pump / 30 20 20
2018.11 养护
水泵
12
墩(台)身施工方案 Method Statement for Construction of Pier and Abutment
model and bound into integrity in the mould, transported to the site by flat-bed truck, and
hoisted and positioned by a crane.
高架桥 Type1、Type3、Type4、Type5、Type6 型墩身分段施工,即分次绑扎钢筋、
安装模板与浇筑墩身混凝土,墩身单次施工标准节高度为 6m,墩帽一次性整体浇筑。
墩身主筋标准节段长 6m,在钢筋加工车间内加工成半成品后运至现场绑扎;墩帽变
截面段钢筋在钢筋加工车间下料成型后利用胎架绑扎成整体,用平板车运至现场,用
吊机整体吊装、定位;
Pier body of Type 2 portal frame pier shall be constructed by sections, which means rebar
binding, formwork installation and pier body concreting shall be in batches of operations.
Standard section height of every single construction for pier body shall be 6m. Cross beam
of the piers shall be cast once completely.
Type2 型门式框架墩墩身分段施工,即分次绑扎钢筋、安装模板与浇筑墩身混凝
土,墩身单次施工标准节高度为 6m,墩顶横梁一次性整体浇筑。
Standard section length of the main rebar of the pier body is 6m. Rebar shall be processed
into semi-product in the workshop and bound after being transported to the site. Rebar for
the cross beam of portal frame pier shall be cut into model and bound after being transported
to the site.
墩身主筋标准节段长 6m,在钢筋加工车间内加工成半成品后运至现场绑扎;门
式框架墩横梁的钢筋在钢筋加工车间下料成型后运至现场绑扎。
A triangle support platform shall be set up on the formwork, or a floor-type steel pipe
staging shall be set up around the pier body as an operation platform for on-site pier body
rebar binding and the entire pier cap rebar hoisting.
墩身钢筋现场绑扎、墩帽钢筋整体吊装时在模板上层设置三角支撑平台或在墩身
周围需搭设落地钢管支架作为操作平台。
Rebar binding and concreting for the caps and bodies of Type1, Type2, Type3 abutments
shall be in batches of operations.
Type1、Type2、Type3 桥台的台帽、台身分次绑扎钢筋、分次浇筑混凝土。
Main rebar shall adopt roll-forged straight crew thread sleeve connection, other rebar shall
adopt over-lap connection.
主筋采用滚轧直螺纹套筒连接,其余钢筋连接采用搭接接头。
Formwork for piers shall adopt fixed die steel plate, and which shall be manufactured by
professional factories. Pier formwork shall set 3.0m as the height of standard sub-sections,
13
墩(台)身施工方案 Method Statement for Construction of Pier and Abutment
and assisted with different adjusting sections (eg. 0.5m, 1m and 2m etc.) to meet different
pier heights.
桥墩模板采用定型钢模板,由专业厂家制造。墩身模板按照 3.0m 作为标准分节高
度,再配以不同的调节段(如 0.5m、1m 和 2m 等),满足不同墩高的需要。
Crawler cranes or truck cranes shall be employed to assist installation of formwork and rebar
in construction.
施工时利用履带吊机或汽车吊机配合安装模板、钢筋安装。
Concrete shall be produced at batching plant, transported to construction points by mixer
trucks, pumped into formwork by pump trucks, and placed to casting points via tremie on the
top construction platform.
混凝土由混凝土拌合站生产,搅拌车运输至工点,采用汽车泵入模,并通过顶部
施工平台及串筒将混凝土下落至浇筑点。
7.2 Installation of operation platform for pier/abutment construction
墩(台)身施工操作平台安装
Operation platform for viaduct pier/abutment construction has the following three types:
type 1 is combined platform, means 4 fabrication modules around the pier. The main column
adopts steel pipe and be welded into module with section steel. Height of each module is 6m,
and operation platform shall be set every 2m, walkway and guardrails shall be attached on
the combined module. Drawing of combined platform see attachment 4.
用于高架桥墩(台)身施工的操作平台的种类分为以下三种:第一种为组合式平
台,沿墩身周边分 4 个组拼模块。主立柱采用钢管,并配以型钢焊接成模块,每个模
块高度 6m,每 2m 一层设置操作平台,走道、护栏附着于组合模块上,组合式平台图
纸详见附件 4。
Type 2 is the operation platform set up by floor-type steel pipe staging, drawing of operation
platform see attachment 4.
第二种采用落地钢管支架搭设的操作平台,操作平台图纸详见附件 4。
Type 3 is the integration of formwork and construction platform. Operation platform shall be
set on the top of formwork at every 3.0m standard section. The platform consists of triangle
support, operation platform and guardrails, combines into an integrity with the formwork.
Ladders shall be set next to the pier as an up-down passage for construction personnel, and
shall be heightened as the concreting of the pier. drawing see attachment 4.
第三种为模板、施工平台一体化,每 3.0m 标准节模板顶端的设置操作平台。平
台由支撑三角架、操作平台和护栏组成,与模板组合成整体。墩旁设置人行爬梯,爬
14
墩(台)身施工方案 Method Statement for Construction of Pier and Abutment
梯与随墩身浇注接高,作为施工人员上下通道。图纸详见附件 4。
Setting-out of the axle line and side line of the pier body 墩身中轴线及边线测量定线
Concreting and curing of the bottom section of the pier body 浇筑墩身底节混凝土、养护
Circulation in sequence until completing the construction of the straight section of the pier body 依次循
环,直至完成后续直线段墩身施工
Scabbling treatment to the construction joint 施工缝凿毛处理
Formwork removal 拆模
Fig.7.3.1 Pier body construction flow chart, of which, the pier cap rebar frame adopts
integrated binding and hoisting
图 7.3.1 墩帽钢筋骨架采用整体绑扎和吊装施工的墩身施工工艺流程图
7.3.2 See Fig.7.3.2 for pier body construction flow chart, of which, the pier cap rebar
frame adopts in-situ binding.
墩帽钢筋骨架采用现场绑扎施工的墩身施工 工艺流程详见“图 7.3.2 墩帽钢筋骨
架采用现场绑扎施工的墩身施工工艺流程图”。
Setting-out of the axle line and side line of the pier body 墩身中轴线及边线测量定线
16
墩(台)身施工方案 Method Statement for Construction of Pier and Abutment
Concreting and curing of the bottom section of the pier body 浇筑墩身底节混凝土、养护
Concreting and curing of the 2nd section of the pier body 浇筑墩身第二节混凝土、养护
Circulation in sequence until completing the construction of the straight section of the pier body 依次
循环,直至完成后续直线段墩身施工
Formwork removal 拆模
Construction joint position of the rectangular chamfer pier see the below table 7.4.1
矩形切角墩的施工缝的设置位置见下表 7.4.1。
Table 7.4.1 Construction joint setting table of piers of viaducts
表 7.4.1 高架桥墩施工缝设置表
18
墩(台)身施工方案 Method Statement for Construction of Pier and Abutment
Remarks: except for rectangular chamfer piers, the principle for pier body construction joint
section dividing is: concreting of pier cap and straight section pier body shall be in batches,
single construction height of the straight section shall not exceed 6m, and pier cap shall be
concreted once.
注:对于除矩形切角墩以外的墩身的施工缝分节原则为:墩帽与直线段墩身分次
浇筑,墩身直线段单次施工高度不超过 6m,墩帽为一次浇筑。
19
墩(台)身施工方案 Method Statement for Construction of Pier and Abutment
The subsequent procedure only can be commenced after getting the approval from CSC
engineers.
在得到 CSC 工程师批准后方可进行下道工序施工。
20
墩(台)身施工方案 Method Statement for Construction of Pier and Abutment
embedded parts or formwork tie rod collide with rebar, then the position of rebar can be
adjusted appropriately.
利用履带吊或汽车吊安装底节墩身钢筋、模板、施工平台及通道。为防止模板现
场拼缝漏浆,在面板拼缝处贴双面胶带。预埋件或模板拉杆与钢筋有冲突时,可适当
调整钢筋位置。
②Strictly control the top elevation of the formwork in the construction of bottom
section of the pier body, to eliminate the effect of top elevation deviation after construction
of the pile cap.
墩身底节施工时严格控制模板的顶面标高,消除承台施工后顶标高偏差的影响。
③After completing the installation of the formwork, at the round of the inner side of
the bottom of the pier body, cement mortar with the same grade as the concrete of the pier
body shall be applied to prevent leakage at the formwork bottom during concreting. If the
deviation is wide, level with cement mortar whose grade is the same with or higher than the
concrete of the pier body prior to the installation of formwork.
墩身模板安装好后,应在墩身底口内侧抹一圈与墩身混凝土同标号的水泥砂浆,
以防止浇筑混凝土时模板底口漏浆;若偏差较大,安装模板前底面应先使用与墩身同
标号或更高标号水泥浆找平。
④After completing, inspecting and qualifying every procedure then commence the
concreting of the bottom section. Strictly control the casting speed of the concrete ≤2.0m/h,
to prevent cement mortar rising at the chamfer of the inner side. After completing the
concreting of pier body, level the top surface to ensure that the top surface is on the same
elevation. And conduct curing to the concrete.
各工序施工完成经报验合格后浇筑底节混凝土。严格控制混凝土的浇筑速度
≤2.0m/h,防止内侧倒角处翻浆。墩身混凝土浇筑完毕后,顶面应收浆抹平,保证顶
面在同一水平面内。同时对混凝土进行养护。
7.5.2 Standard section construction of the pier body 墩身标准节段施工
① Scabble the pier top to expose the fresh concrete, and clean the residues caused by
scabbling to make sure the joints are connected well. The outer side of the pier top shall not
be damaged by scabbling, boundary of scabbling shall be 2-3cm to the edge of the pier body.
Maintain the type of line of the pier top parallel and level, and maintain the joints are on the
same line, to avoid affecting the outlook of the concrete joints.
将墩身顶面凿毛至新鲜混凝土为止,并将混凝土表面凿毛的渣子清理干净,确保
接缝连接完好。凿毛时应注意不得损坏混凝土顶口的外侧面,凿毛界线距墩身边缘线
21
墩(台)身施工方案 Method Statement for Construction of Pier and Abutment
2-3cm,保持顶口线型平齐,保证接缝在一条线上,以免影响混凝土接缝处的外观质量。
② For the piers which adopt combined platform and floor-type steel pipe staging
platform, the staging platform shall be lengthened to 6.0m. check and adjust the embedded
main rebar for the 1st section construction, and lengthen the main rebar of the 2nd section, and
bind the horizontal rebar.
对于采用组合式平台和落地钢筋支架脚手平台施工的桥墩,脚手平台接高 6.0m,
检查并调整第一节施工时预埋主筋,接长墩身第二节主筋,并绑扎水平钢筋。
For the piers which adopt the integration construction of formwork and construction
platform, by using the construction platform on the formwork top of the 1 st section of the
pier body, check and adjust the embedded main rebar for the 1st section construction, and
lengthen the main rebar of the 2nd section, and bind the horizontal rebar within 3.0m of the
lower part of the 2nd section of the pier body. Complete the above procedures and report &
inspect for qualification. Set the top formwork of the 1 st section as a support to install the
3.0m formwork of the lower part of the 2nd section, and set the staging on this formwork as
an operation platform to bind the horizontal rebar within 3.0m of the upper part of the 2 nd
section. Complete the binding and report & inspect for qualification, and install the 3.0m
formwork of the upper part of the 2 nd section, set up tie rod and adjust the formwork to meet
the requirements of the Specification. Cast and cure the concrete of 6m pier body of the 2 nd
section. Set up cat ladder next to the pier body and lengthen it as the concreting of the pier
body.
对于采用模板和施工平台一体化施工的桥墩,利用第一节墩身模板的顶端的施工
平台,检查并调整第一节段施工时预埋主筋,接长墩身第二节段主筋,并绑扎第二节
段下半部 3.0m 高范围内水平钢筋,以上完成并报验合格后以墩身第一节顶部模板作
支撑,安装墩身第二节下端 3.0m 模板,并以此模板上的脚手平台作为工作平台绑扎
第二节段上半部 3.0m 高范围内水平钢筋,绑扎完成报验合格后安装墩身第二节上端
3.0m 模板,布设拉杆并调整模板至满足规范要求。浇筑第二节 6m 墩身混凝土,养生。
墩旁设置人行爬梯,爬梯与随墩身浇注接高。
③ After completing the rebar binding of the 3 rd section, formwork of the 3rd section
remain unmoved, remove and polish the formwork of the 1st and 2nd sections in sequence and
fabricate them at the top of the 3rd section to commence the construction of the 3rd section of
the pier body. Circulation as the above to complete the construction of the pier body.
待第三节墩柱钢筋绑扎完毕后第三节模板不动,第一节、第二节模板依次拆除、
打磨、拼装至第三节顶,开始第三节墩身施工。依此循环浇注完成墩身施工。
22
墩(台)身施工方案 Method Statement for Construction of Pier and Abutment
23
墩(台)身施工方案 Method Statement for Construction of Pier and Abutment
concrete. Rebar of bearing cushion or constraint block shall be pr-embedded or rebar binding
of bearing cushion and constraint block shall be completed prior to the concreting
construction. Bearing cushion shall be constructed independently after concreting of pier cap
is completed and certain strength of the concrete is achieved. Bearing cushion shall be cast
once by using steel formwork. Top elevation and four-corner elevation difference of the
bearing cushion shall be strictly controlled within the requirements of the design and the
Specification. Bolts holes for the bearing shall be preserved according to the positions of the
bearing anchor bolts, depth and diameter of the preserved holes shall meet the requirements
on the bearing design drawing. Constraint block at the center of pier top shall be constructed
after the box girders at the both sides of the pier erected and sealing off and anchorage
covering completed.
支座垫石采用 M50 混凝土,墩顶约束块采用 M35 混凝土。墩顶混凝土施工前应
预埋支座垫石、约束块钢筋或完成支座垫石、约束块钢筋的绑扎作业。支座垫石在墩
帽混凝土完成并具有一定的强度后再单独进行施工;支座垫石采用钢模一次浇筑完成,
支座垫石顶面标高及四角高差应严格控制在设计及规范要求内,支座应按支座地脚螺
栓位置预留螺栓孔,要求预留孔的深度和孔径满足支座设计图纸中的要求。墩顶中心
约束块待该墩两侧箱梁全部架设完成,并完成封锚后再进行施工。
Fig.7.5.4.1 Scabbling in the bearing cushion area Fig.7.5.4.2 Concreting of bearing cushion
图 7.5.4.1 墩顶的支座垫石区域凿毛 图 7.5.4.2 支座垫石混凝土浇筑
7.6 Rebar processing and installation of pier body 墩身钢筋加工与安装
7.6.1 General requirements 总体要求
① Rebar cutting shall be strict accordance with the shop drawing, and the rebar
reference numbers and length of the raw material. Make overall arrangements to minimize
the loss of rebar. All kinds of rebar shall be classified and stacked by reference numbers to
24
墩(台)身施工方案 Method Statement for Construction of Pier and Abutment
avoid disorder.
严格遵照施工图放样下料,根据钢筋编号和供料尺寸的长短,统筹安排以减少钢
筋的损耗,各编号钢筋分类码放避免混淆。
② Rebar shall be adjusted by rebar wrench or reinforcing steel pipe, acetylene heating
adjusting is not allowed, and safety shall be secured when applying force in adjusting.
钢筋调整时要用钢筋扳手或加力钢管调整,不得用乙炔火烤热调,调整用力时要
注意安全。
③Reinforcement raw materials and semi-finished products transported to the
construction site must be covered and cushioned to avoid corrosion caused by contact with
water source or ground and exposure to wet air.
钢筋原材及托运至施工现场的半成品必须采取抄垫及覆盖措施,避免钢筋接触水
源或地面以及暴露在潮湿的空气中导致锈蚀。
④ Diameter of the binding wire shall not be less than 1mm for rebar binding, and the
direction of the wire shall be back to the formwork. The bind wire shall not be projected out
of the concrete surface to be an erosion source after concreting. Overlap length of rebar
binding see the below table:
钢筋绑扎时采用直径不小于 1mm 的扎丝扎结,扎丝的朝向应背向模板一侧,防
止浇筑混凝土后扎丝露出混凝土面而成为锈蚀源。钢筋绑扎搭接长度见下表:
Table 7.6.1 Minimum overlap length of rebar binding
表 7.6.1 钢筋最小绑扎搭接长度
Rebar diameter (mm) Overlap length (mm) for M35
25
墩(台)身施工方案 Method Statement for Construction of Pier and Abutment
钢筋直径(mm) concrete
M35 混凝土搭接长度(mm)
12 500
16 700
20 850
25 1050
32 1350
⑤ Ensure that thickness of the net protective layer for rebar shall not be less than the
design requirements (minimum thickness of the out-most protective layer for rebar is
40mm). considering about the in-situ construction deformation and requirement of the
Specification, the self-made M35 concrete cushion block with 40mm thickness shall be
adopted for the rebar protective layer. Surface of the cushion block shall be clean and shall
not contaminated by oil staff, and the colour of the block shall be consistent with the outlook
of structural concrete. Blocks shall be laid in quincunx types, and shall be more than 4 nos in
each square meter, and shall be bound and fixed with the out-most rebar with binding wire.
确保钢筋净保护层厚度不小于设计要求(最外层钢筋最小保护层厚度 40mm)。
考虑到现场施工时钢筋的变形及规范要求,钢筋保护层采用项目部自制 40mm 厚的
M35 混凝土垫块。垫块表面洁净,不能受到油污的污染,垫块颜色与结构混凝土外表
一致。垫块按梅花型布置,每平米不少于 4 个,垫块安放时必须使用扎丝与最外层钢
筋进行绑扎固定。
⑥ The working staff shall be familiar with the binding sequence prior to rebar binding.
钢筋在绑扎前,操作人员需熟悉绑扎顺序。
7.6.2 Rebar cutting and processing 钢筋下料和加工
Rebar of pier body, bearing cushion and constraint block shall be processed in the workshop,
and rebar cutting shall be in accordance with the requirements of design drawings,
construction joints, relevant specifications and rebar connections. Calculation of cutting
length shall be done in advance, recheck to confirm there is no error and then proceed. A
rebar sample shall be made prior to rebar cutting processing, and the sample shall be trial
bent and processed, the bending size shall be carefully checked and verified, mass
production can be proceeded in the condition that the sample is qualified. Vertical main
rebar for pier body which will be connected by adopting roll-forged straight crew thread
sleeve, the connection connects of the vertical main rebar shall be threaded according to the
sleeve size and connection requirements. In order to avoid the exposure of the steel sleeve,
the steel sleeve is installed at the same time. Half-product of the molding rebar shall be
26
墩(台)身施工方案 Method Statement for Construction of Pier and Abutment
stored by classification and hang with signs, and cushioned and covered according to the
requirements. Any other materials shall not be placed on top to avoid deformation due to
over-loading.
墩身钢筋、支座垫石钢筋和限位块钢筋在钢筋加工车间集中加工,钢筋下料根据
设计图纸、施工缝、相关规范和钢筋接头要求,提前对下料长度进行计算,复核无误
后下料制作。在制作加工开始前,必须首先制作出钢筋大样,并进行试弯、加工,仔
细检查、核对弯制尺寸,合格后方可进行批量生产。对于采用剥肋滚轧直螺纹套筒进
行连接的墩身竖向主筋,竖向主筋套筒连接接头处按套筒规格和连接要求进行车丝,
为避免连接套的暴露时间,连接套采用在钢筋安装时同时进行。成型钢筋半成品分类
标识挂牌存放,并按要求进行抄垫、覆盖,顶部不得堆放其它物品,以免堆载过重引
起钢筋变形。
7.6.3 Rebar installation 钢筋安装
For the rebar installation at the straight section of the pier body, the rebar shall be processed
into model in the workshop and transported to the site by flat-bed truck. Crane shall be
employed and assisted with labour to install the pier body rebar and embedded parts (if any)
after the construction operation platform for pier body installed. The installation process
shall be instructed by professionals, to avoid safety accidents. Butt jointing of the main rebar
of the pier body shall be connected by machines, and the rebar connects shall meet the
requirements of the Specification. The stir-up bars shall be installed after the butt jointing of
the main rebar completed, connects of the upper & lower levels of the stir-up bars shall be
misaligned. Wind cables or temporary supports shall be set up if it is necessary after rebar
frame fabrication completed, to avoid rebar frame distortion or deformation. Position of the
rebar must be correct during rebar binding, a plummet shall be used to check the verticality
of the rebar frame at any time, and adjust the position in time. CSC shall be invited to
inspect after the installation.
对于直线段墩身钢筋安装,直线段墩身钢筋在钢筋车间加工制作成型后,使用平
板车托运至现场,在墩身施工操作平台安装完成后,采用吊机加人工配合的方法安装
墩身钢筋和预埋件(如有),安装过程要有专人指挥,防止出现安全事故。墩身主筋
对接采用机械连接,钢筋接头满足相关规范要求;箍筋在主筋对接完成后进行安装,
箍筋上下层接头错开布置,钢筋骨架拼装完成后,必要时拉设缆风或临时支撑,以防
止钢筋骨架扭曲变形。钢筋绑扎时一定要注意钢筋位置正确,应随时用线锤检查钢筋骨
架的垂直度,并及时调整。钢筋安装完成后邀请 CSC 检查。
There are two methods for the pier cap rebar installation:
27
墩(台)身施工方案 Method Statement for Construction of Pier and Abutment
墩帽钢筋安装有两种方法:
Method 1: rebar of pier cap, bearing cushion and pier top constraint block shall be processed
into model in the workshop and transported to the site by flat-bed truck. After completing the
installation of construction operation platform and bottom formwork for pier cap, crane shall
be employed and assisted with labour to install rebar of pier cap, bearing cushion, constraint
block at the center of pier top and embedded parts. CSC shall be invited to inspect after the
above procedures completed.
方法一:墩帽钢筋、支座垫石钢筋和墩顶约束块钢筋在钢筋车间加工制作成型后,
使用平板车托运至现场,在墩帽施工操作平台和底模安装完成后,采用吊机加人工配
合的方法安装墩帽钢筋、支座垫石钢筋、墩顶中心约束块钢筋和预埋件,墩帽钢筋、
支座垫石钢筋、墩顶约束块钢筋和预埋件安装完成后邀请 CSC 检查;
Method 2: rebar of pier cap, bearing cushion and pier top constraint block shall be processed
into model in the workshop, bound into rebar frame with the embedded parts on the mould
bed, and transported to the site by flat-bed truck. Crane shall be employed to lift the pier cap
rebar frame to the design position after the construction operation platform is installed. CSC
shall be invited to inspect after the whole pier cap rebar frame is in position.
方法二:墩帽钢筋、支座垫石钢筋和墩顶约束块钢筋在钢筋车间加工制作成型后,
与预埋件在胎架上整体绑扎成墩帽钢筋骨架,然后用平板车托运至现场,在墩帽施工
操作平台安装完成后,采用吊机整体吊装墩帽钢筋骨架至设计位置,墩帽钢筋骨架整
体吊装到位后邀请 CSC 检查。
Fig.7.6.1 Pier body rebar in-situ binding Fig7.6.2 Pier cap rebar in-situ binding
图 7.6.1 墩身钢筋现场绑扎 图 7.6.2 墩帽钢筋现场绑扎
28
墩(台)身施工方案 Method Statement for Construction of Pier and Abutment
Fig.7.6.3 Whole pier cap rebar frame hoisting after binding fig.7.6.4 Whole pier cap rebar frame installation
29
墩(台)身施工方案 Method Statement for Construction of Pier and Abutment
预埋件包括用于形成支座地脚螺栓安装孔的预埋管、墩身观测标、用于永久标示
千斤顶位置的预埋件等。用于形成支座地脚螺栓安装孔的预埋管采用 PVC 管或其它
材质的管道,预埋管的长度和外径需要满足支座设计图纸中支座地脚螺栓安装孔的要
求,PVC 管内灌沙,两端用胶带封堵;预埋管的设置需放样精确,定位牢固,防止浇
筑混凝土过程中移位;预埋管在垫石混凝土初凝后转动拔出。墩身观测标数量为每墩
2 个,分别位于墩身横桥向两侧,具体埋设位置见图 7.6.5;墩身观测标高出地面(水
面)0.5m~1.0m 左右,当墩身较矮,或梁底距离地面不足 4m 墩身观测标可设置在墩
身标对应位置的顶帽上;墩身观测点采用不锈钢材质,如图 7.6.6。
Jessore direction
Observation mark-2
Observation mark-1
KEEP AWAY
Date:
30
墩(台)身施工方案 Method Statement for Construction of Pier and Abutment
Pier body formwork adopts modeled large size steel formwork, which can guarantee
adequate strength, rigidity and planeness, size of the formwork see the design drawing. Set
3.0m as a standard section height for the formwork of the straight section of the pier body,
and assisted with different adjusting sections, to meet piers with different heights.
墩身模板采用定型大块钢模板,保证有足够的强度、刚度和平整度,模板尺寸见
模板设计图;墩身直线段模板按照 3.0m 作为标准分节高度, 再配以不同的调节段,
满足不同墩高的需要。
Surface of the plates shall be cleaned and release agent shall be applied prior to formwork
installation. The release agent shall be completely and evenly applied on the surface, and
shall not contaminate the cast concrete and rebar etc.
模板安装前,应先清理面板表面,然后涂刷脱模剂,应确保完整地、均匀地涂刷
至表面,脱模剂不得污染已浇筑混凝土和钢筋等。
Formwork surface of the 1st section shall be compact with the concrete surface of the pier
kicker, if compactness can not be achieved, measures shall be taken to fill the seam, to
prevent leakage during concreting. Formwork portions shall be connected and fixed by
screw bolts, and the seams shall be applied with double side adhesive tape to prevent leaking
from the seams. The formwork tie rods shall adopt spiral rebar which shall be custom-made
by the tie rod type, pier body thickness, formwork structure etc., and both ends shall be
threaded and equipped with screw cap and fixed with formwork. Of the tie rods, the diagonal
rods shall wear PVC pipes to protect the concrete and facilitate extracting the rods when
removing formwork. Both the ends of the PVC pipes shall be extended to the outer side of
the formwork.
首节墩身模板面与墩身 kicker 混凝土表面密贴,若无法密贴,则采用措施将缝隙
填塞,以防止混凝土浇筑时漏浆。分块模板间采用螺栓拼接固定,模板拼缝间加双面
胶带,以防止拼缝处漏浆。模板拉杆采用螺纹钢筋,根据拉杆类型、墩身厚度、模板
结构等定尺制作,两端车丝带螺帽与模板固定;其中,贯穿墩身厚度的对拉杆外套
PVC 管,便于拆除模板时抽出对拉杆和保护混凝土,安装时 PVC 管两端延伸至模板
面板外侧。
After completing rebar installation for pier body or pier cap, then formwork can be installed
piece by piece. Installation of formwork shall abide by the principle of “further to closer,
hoisting vision not to be interrupted”, which means according to the position of the cranes,
install the formwork of the further side first, then install the formwork which is closer to the
cranes, and make sure the safety and accuracy of the installation. During the installation,
31
墩(台)身施工方案 Method Statement for Construction of Pier and Abutment
employ total station to verify the plane positions and elevations of the four angle points on
the cross section and the center points of the four sides of the pier body by three-dimensional
system of coordinate. When the lower formwork is accurately in position, lift the upper
formwork above the installation position and place it slowly, and push it in position
manually. When the upper formwork is aligned with the connection seam of the lower
formwork, steady and vertical, then fix them by using positioning bolts (partially connection
bolts), and roughly adjust the formwork, and then install the remaining connection bolts, but
not tighten to precisely adjust the position of the formwork. Install and position the
remaining formwork on the same level with the same method. When the whole level of
formwork is fixed temporarily, survey to check if the elevation of the formwork top and the
plane position can meet the requirements, if the requirements can not be met then adjusting
shall be continued unit the requirements can be met, and finally tighten the connection bolts.
墩身或者墩帽钢筋安装完成后,即可逐块安装模板。模板按照“先远后近、不挡
吊装视线”的原则进行安装,即根据起重设备的位置,先安装较远一侧的模板,后安
装靠近起重设备一侧的模板,确保模板安装的安全和准确。模板安装时,采用全站仪
以三维坐标法校核墩身截面上四个角点和四面分中点的平面位置和高程;下层模板精
确就位后,起吊上层模板在待安装位置上方缓缓下放,人工推模就位,当其与下层模
板拼缝对齐、立稳并扶垂直后,先用定位螺栓(部分拼接螺栓)及时固定,并粗调模
板,位置调整完成后随即安装剩余拼接螺栓,但无需拧紧以便后续精确调整模板位置。
按照同样的方法完成该层其余模板的安装、定位,待一层模板全部临时固定后,测量
检查模板顶口的标高、平面位置是否满足要求,若不能满足要求则进行调整,直至满
足要求后拧紧拼接螺栓。
32
墩(台)身施工方案 Method Statement for Construction of Pier and Abutment
止对混凝土造成震动、干扰和损坏。模板用吊机分块卸下,吊放至平整的场地,清除
粘在模板上的混凝土,涂刷脱模剂备用。
7.8 Concrete construction 混凝土施工
7.8.1 Technical indexes of concrete 混凝土技术指标
① Concrete strength grade of pier body, abutment and constraint block shall be M35, the
slump shall be 180~220mm.
墩身、桥台和约束块混凝土强度等级为 M35,坍落度为 180~220mm。
② Concrete strength grade of bearing cushion shall be M50, the slump shall be 180 ~
220mm.
支座垫石混凝土强度等级为 M50,坍落度为 180~220m。
③ Temperature of concrete in formwork shall not exceed 30℃.
入模温度不超过 30℃。
④ Select OPC52.5 common Portland low alkali cement, and the performance indexes of
the cement shall meet the requirements of the Specification.
选用 OPC52.5 普通硅酸盐低碱水泥,水泥的性能指标应符合规范要求。
⑤ Fine aggregates: choose the natural medium sand which has reasonable grading, even
and strong quality, low water absorption and smaller porosity, the modulus of fineness shall
be 2.0~3.5, soil content shall not be more than 3.0%. coarse aggregates: choose the clean
stones which has reasonable grading, excellent particle size, even and strong quality and low
linear expansivity, the total content of acicular and schistose particles shall not be more than
35%, soil content shall not be more than 1.0%.
细骨料:选用级配合理、质地均匀坚固、吸水率低、孔隙率小的洁净天然中沙,
其细度模数 2.0~3.5,含泥量不大于 3.0%。粗骨料:选用级配合理、粒径良好、质地
均匀坚固、线胀系数小的洁净碎石,针、片状颗粒总含量不大于 35%,含泥量不大于
1.0%。
7.8.2 Concrete production 混凝土生产
Concrete for the foundation and substructure between CH7+171.615 ~CH17+999.27 of V1
shall be supplied by 1# batching plant, and concrete for the foundation and substructure
between CH17+999.27~CH23+953.27 shall be supplied by 2# batching plant. Concrete for
the foundation and substructure between CH41+475.263 ~ CH44+52.391 of V2 shall be
supplied by 3# batching plant. Concrete for the foundation and substructure between
CH50+733.373 ~ CH54+766.448 of V3 shall be supplied by 4# batching plant. Concrete
34
墩(台)身施工方案 Method Statement for Construction of Pier and Abutment
shall be transported to the site by mixer trucks, and during the transporting the concrete shall
be kept mixing to avoid segregation, and the temperature of concrete in formwork shall be
controlled not exceed 30℃.
V1 高架桥 CH7+171.615~CH17+999.27 范围基础及下部结构由 1 号混凝土拌合站
生产供应,CH17+999.27~CH23+953.27 范围基础及下部结构由 2 号混凝土拌合站生
产供应;V2 高架桥 CH41+475.263~CH44+52.391 范围基础及下部结构由 3 号混凝土
拌合站生产供应;V3 高架桥 CH50+733.373~CH54+766.448 范围基础及下部结构由 4
号混凝土拌合站生产供应。混凝土罐车运抵至施工现场,在运输过程中同时对混凝土
进行搅拌,防止离析,混凝土入模温度控制不得高于 30℃。
7.8.3 Concrete casting 混凝土浇筑
Formwork, rebar and embedded parts shall be checked carefully prior to concreting, and
records shall be kept. Concreting can be proceeded in the condition that the requirements of
design and the Specification are met.
混凝土浇筑前,对模板、钢筋、预埋件进行详细的检查,并作好记录,符合设计
及规范要求后方可浇筑混凝土。
Temperature and slump of the concrete transported to site shall be tested, and concrete
blocks shall be made, and work-ability of the concrete shall be inspected. Concrete can be
used only in the conditions that the above indexes are qualified.
对到达现场的混凝土坍落度及温度测试、制作混凝土试块,并观察混凝土的和易
性,符合要求才能使用。
Truck pump, floor-type pump or hopper shall be used for concreting casing.
混凝土采用汽车泵、混凝土地泵或吊斗方式进行浇筑。
Casting of concrete shall adopt the method of horizontal stratification, and the stratification
thickness shall be no more than 45cm. Free falling height of the concrete shall not exceed
2m, tremie shall be used to concrete if the free falling height exceeds 2m.
混凝土采用水平分层法浇筑,分层厚度不大于 45cm,混凝土的自由下落高度不
应超过 2m,如果混凝土的下落高度超过 2m,须采用串筒进行浇筑。
Internal vibrators shall be used for concrete vibration. In concrete vibration, to avoid seams
being formed, the internal vibrator shall be inserted 5cm ~10cm into the lower level when
the upper level is being cast. The vibrator shall be fast insert and slowly withdrawn, and the
movement space shall not be 1.5 times of the effect radius of the vibrator. The insert points
shall be even or into lines or interlocking movement to avoid missing vibration. Each
vibration shall be around 20 ~ 30s, to avoid less-vibration or over-vibration. After
35
墩(台)身施工方案 Method Statement for Construction of Pier and Abutment
completing vibration, withdraw the vibrator slowly with it is still vibrating. The concrete
shall be vibrated compactly, and the positive signs of compactness are: the concrete no
longer sink, no bubbling and the surface start bleeding.
混凝土振捣采用插入振动棒。混凝土振捣时,为避免形成接缝,浇筑上层时插入
式振捣器伸入到下层 5cm~10cm;振动棒要快插慢抽,移动间距不大于振动棒作用半
径的 1.5 倍;振捣时插点均匀、成行或交错式移动,以免漏振;每一次振动时间约 20
~30s,以免欠振或过振,振动完毕后,边振动边徐徐拔出振动棒;混凝土应振捣密
实,混凝土密实的标志:混凝土不再下沉、不再冒气泡、表面开始泛浆为宜。
Distance of 5 ~ 10cm shall be kept between the vibrator and the side form to avoid
deformation of the side form caused by the vibration or colliding with the formwork, rebar,
embedded parts etc.
振捣棒与侧模保持 5~10cm 的距离,防止侧模受振动器影响而发生变成或碰撞模
板、钢筋、预埋件等。
Concreting shall be continuous, if it has to be interrupted by certain causes, the interruption
time shall not exceed the initial setting time. Make sure that the concrete at the lower level is
covered by the concrete at the upper level within the initial setting time, and vibration shall
be intensified to ensure the compactness of the concrete. During the rainy season, to avoid
interruption caused by rain storm, tarpaulin shall be furnished prior to construction and cover
the concrete when it is raining.
混凝土浇筑应连续进行,若因故必须间断时,其间断时间不得超过混凝土的初凝
时间。保证在初凝时间内上层混凝土必须覆盖下层混凝土,并加强混凝土振捣,确保
混凝土密实。雨季施工期间,为防止暴风雨造成混凝土浇筑中断,施工前准备篷布,
遇下雨及时覆盖。
The concrete surface shall be finished and leveled after concreting, two times of finishing
shall be conducted to avoid cracks occur on the surface, the first finishing shall be done close
to the initial setting, the second finishing shall be done close to the final setting.
混凝土浇筑完成后对混凝土表面进行收浆抹平,为避免产生表面裂缝进行两次收
光抹面,第一次在混凝土接近初凝前,第二次在混凝土接近终凝前完成。
36
墩(台)身施工方案 Method Statement for Construction of Pier and Abutment
Curing to the concrete shall be done after the concreting completed. Prior to the removal of
formwork, cover the top with geotextile and water it, to keep the concrete in a wet condition
all the time. If it is the time to remove formwork and the duration has exceeded 14 days after
concreting, the curing time can meet the requirements, then the concrete surface curing is not
necessary to be continued. If it is the time to remove formwork and the duration is less than
14 days after concreting, then the concrete surface (vertical lateral side) shall be wrapped up
by PVC membrane to keep wet prior to the removal of formwork, and the concrete surface
shall be watered to be wet before wrapped up by PVC membrane. As the membrane can
prevent water being evaporated, regular watering is not necessary, and the concrete top
surface shall be covered by geotextile and cured by watering.
混凝土浇注完成后,及时对混凝土进行养护。在模板拆除前,采用顶部覆盖土工
布并洒水养护,保持混凝土始终处于湿润状态。若模板拆除时混凝土浇筑时间超过 14
天,则养护时间满足要求,模板拆除后不需要对混凝土外表面继续养护。如果模板拆
除时混凝土浇注时间少于 14 天,则模板拆除后,混凝土外表面(竖直侧面)养护采
用塑料薄膜包裹保湿养护,仅需在包裹塑料薄膜前洒水使外表面湿润,薄膜可以防止
水分蒸发,无需间隔一定时间洒水,混凝土顶面采取覆盖土工布洒水保湿养护。
混凝土外观修补,严格执行以下原则:
1 The repair can only be carried out with instructions from CSC engineers.
任何修补需得到 CSC 工程师表面检查后才能进行;
② Request for inspection after removal of formwork, and repair shall better be executed in
the early stages to ensure good mating effect between the fresh and old concrete.
在拆除模板后及时报检,尽量在混凝土早期完成修补工作,保证新老混凝土最佳
咬合效果;
③ Use proper repair agent according to the types of defects.
根据不同缺陷的修补要求,选择适当的修补原材料;
④ Curing of the concrete surface after repair shall be well protected to prevent other
construction activities from affecting its strength and mating effect.
对修补后的混凝土表面进行认真养护,防止其他施工活动影响其强度及咬合效果
的实现。
⑤ The repair area shall be limited so as not to induce second-time pollution or damage to the
concrete.
不得人为扩大修补面积,造成对混凝土二次污染和破坏;
⑥ For prefabricated parts to be repaired, experience must be drawn from previous tasks so as
to ensure that the concrete surface after treatment meet specifications.
对于需要修补的预制件,通过不断总结修补经验,保证混凝土表面达到符合规范
要求的外观条件;
⑦Analyze the causes of defects, and execute quality control from the source so as to
minimize the quantity of repair.
分析混凝土缺陷产生的原因,从源头进行质量控制,减少混凝土修补的工程量。
7.9.1 Repair Procedures 修补流程
①Repair procedures for appearance
外观修饰流程
Check of concrete surface→ preparation→ surface finishing→ logging of record→
inspection and acceptance.
混凝土表面检查→准备工作→执行表面修饰→填写修饰记录→修饰验收。
②Repair procedures for concrete
混凝土修补流程图
38
墩(台)身施工方案 Method Statement for Construction of Pier and Abutment
Logging of records
填写修补记录
Curing
养护
修复材料配合比设计
Construction
Numbe Name Material Mix Note
method
r 编号 名称 材料 配合比 备注
施工方法
Anti-corrosion of
M35 Thick Field Test exposed rebar of
Cement + water Brush
1 Cement Slurry Determination embedded rebar
水泥+水 涂刷
M35 水泥稠浆 现场试验确定 预埋钢筋等外露
钢筋防腐
M35 和 M50
Cement + sand + Field Test
Cement mortar Brush/ smear
2 water Determination
M35 和 M50 水泥 涂刷/抹压
水泥+砂+水 现场试验确定
砂浆
For holes and
damaged edges
M35 和 M50 fine and corners with a
Sika Field test
aggregate concrete Pouring size of more than
3 214+aggregate determination
M35 和 M50 细骨 浇筑 10mm
Sika 214+骨料 现场试验确定
料混凝土 超过 100mm 孔
洞、棱角缺损修
补
For voids, holes
and damaged
Surface repair Painting/ edges and corners
Manufacturer
liquid Fosroc Renderoc smearing with a size of less
4 厂家提供
表面修补浆 FC 涂刷/抹压 than 10mm 气
泡和小于 10mm
孔洞、棱角缺损
修补
Crack closed Manufacturers
Radcon Brush/Spray
5 Adhesive to provide
Formula#7 涂刷/喷涂
裂缝封闭胶 厂家提供
For holes and
damaged edges
and corners with a
Repair mortar 修 Pouring/ smear
Fosroc Renderoc Manufacturer size between
6 补砂浆 浇筑/抹压
HSXtra 厂家提供 10mm and 100mm
超过 10mm、小
于 100mm 孔洞、
棱角缺损修补
Manufacturers Painting/
Bonding agent
7 Nitobond EP to provide spraying 涂
粘结剂
厂家提供 刷/喷涂
40
墩(台)身施工方案 Method Statement for Construction of Pier and Abutment
Types of
concrete
S/N Symptoms Repair Measures Causes and Precautions
defects
序号 缺陷表现情况 缺陷修补措施 原因及预防
混凝土缺陷
类型
①If there is slurry leakage around rod holes, the non- Reason:
compacted concrete shall be removed, and with a brush to 原因:
remove the concrete residue. Required by structural design.
如存在拉杆孔周边漏浆情况,将孔洞周围不密实混凝 模板结构设计需要。
Rod Hole 土剔除,用毛刷清除混凝土残渣。 Precaution:
1
拉杆孔 ②Wet rod holes with water, then use cement mortar to fill 预防措施:
the hole, and compact. Optimize design to minimize the use of inserted rods
用水润湿拉杆孔洞,使用水泥砂浆填补孔洞,抹压密 inside concrete.
实。 尽可能优化设计避免在混凝土内部设置拉杆。
Reasons:
原因:
①For small flecks on the concrete surface, repair is not ①Formwork surface is not cleaned up.
required. But if the concrete at the fleck area is loosened, 模板表面未清理干净。
②Release agent is not used properly.
execute repair according to Item 4. 对于混凝
脱模剂使用不当。
土表面存在小面积斑点,不需要进行修复。如果斑点 Precautions:
Chromatic 处混凝土松动,应按照下表第 4 项修复方法进行修
2 aberration 预防措施:
复。 ①Polish the formwork to rid rust. Before the release
色差 ②When there is big chromatic aberration, grind carefully
agent is used, wash the formwork, and keep the
with abrasive paper and then wipe clean with nylon cloth.
formwork clean before concreting. 对
当混凝土表面色差较大时,用砂纸仔细打磨,用尼龙
模板打磨去除锈迹,每次使用脱模剂前都要清洗模
布擦拭干净。
板,混凝土浇筑前应确保模板清洁。
②Use approved release agent in a proper way.
使用经过批准的脱模剂,按正确的方法使用。
41
墩(台)身施工方案 Method Statement for Construction of Pier and Abutment
Types of
concrete
S/N Symptoms Repair Measures Causes and Precautions
defects
序号 缺陷表现情况 缺陷修补措施 原因及预防
混凝土缺陷
类型
Reasons:
原因:
For voids with a dia. More than 10mm, repair is required. ①Workability of concrete is not good.
For voids with a dia. less than 10mm, but close to each 混凝土和易性不好。
other, and surface is not even, dense or smooth, repair is ②Not enough vibrating during concreting.
also required. 浇筑过程中振捣不足。
直 径 大 于 10mm 的 气 泡 需 要 进 行 修 补 , 气 泡 小 于 Precautions:
10mm 但距离较近,表面不够均匀、致密、光滑,也 预防措施:
应进行修复。 ①Control batching of concrete to maintain good
①Use knife to rid of rough edges around the voids. 用 workability.
灰刀将气泡边缘的毛边剔除。 控制好混凝土搅拌,确保良好的和易性。
Bubble ②Spray water to wet the concrete surface and clean up, ②Strength control of vibrating. Vibrating time shall be
3
气泡 then blow dry. long enough but avoid over-vibrating. 加
喷水将混凝土表面湿润并清理干净,吹干表面。 强混凝土振捣控制,确保振捣时间充足但是不过
③Mix mortar according to manufacturer’s instructions, 振。
and use scraper blade to take small amount of cement ③During vibrating, the vibrating needle shall be quickly
based mortar to fill in the voids, then squeeze and inserted but slowly withdrawn to ensure air can be
compact, and scrape away the surplus mortar. discharged from the concrete surface. 振捣
按照生厂商指示配制砂浆, 用小刮刀刮取适量水泥基 过程中振捣棒快插慢拔,确保气泡能够从混凝土表
砂浆填入气孔中,并用刮刀挤压贴实,并刮除结构物 面排出。
表面多余的浆体。
42
墩(台)身施工方案 Method Statement for Construction of Pier and Abutment
Types of
concrete
S/N Symptoms Repair Measures Causes and Precautions
defects
序号 缺陷表现情况 缺陷修补措施 原因及预防
混凝土缺陷
类型
①Mark the actual scope of the area of honeycomb and pitted surface with slate Reasons:
pencil, and mark an area that is 15mm larger than the previously marked area 原因:
as repair area. ①Not enough vibrating.
用石笔在混凝土表面标记出蜂窝麻面的实际范围,然后在距蜂窝麻面外 振捣不足。
围至少 15mm 处标记为修补区域。 ②Big gap between formworks,
②Cut out an incision of 10mm deep according to the mark to isolate the causing mortar overflow.
problematic area, in case the repair material to form a plane of weakness. 模板缝隙大使得混凝土中砂浆
按照标记切割出 10mm 深的切口,隔离出问题区域,防止修复材料形成 流出。
薄弱边。 Precautions:
③Chisel or peel away the un-compacted concrete within the repair area using 预防措施:
small chisel or other tools, then remove the cement mortar on the surface of the ①Strength control of vibrating.
Honeycomb
honeycomb area. Vibrating time shall be long
and pitted
4 用小凿子或其他工具对修补区域内未压实的混凝土进行凿削,直至混凝 enough but avoid over-vibrating
surface
土完好为止,然后去除蜂窝区域表面的水泥浆。 加强混凝土振捣控制,确保振
蜂窝麻面
④Joint inspection with CSC engineers and then carry out repair work. 捣时间充足但是不过振。
与 CSC 进行联合检查,以便进行下一阶段维修工作。 ②The joints between formworks
⑤Use brush to clean up the remaining concrete, and the flush clean with water. shall be sealed firmly to prevent
用刷子清洗剩余的混凝土,用水冲洗干净。 mortar leakage. Bonding agent on
⑥Use mortar to repair according to the manufacturer’s instructions. the concrete surface or rebar shall
根据生厂商指示,使用砂浆进行修复。 be removed permanently. 模板
⑦If the defect is severe, NCR shall be issued. The repair work shall be carried 连接处应密封好,防止砂浆漏
out according to the specified procedures stated in the NCR. 当缺 出。在混凝土表面或者钢筋上
陷比较大时,应该提交不合格报告,提出缺陷问题。后续工作只能按照 的粘合剂将被永久除去。
通过不合格报告程序规定的修复程序进行。
43
墩(台)身施工方案 Method Statement for Construction of Pier and Abutment
Types of
concrete
S/N Symptoms Repair Measures Causes and Precautions
defects
序号 缺陷表现情况 缺陷修补措施 原因及预防
混凝土缺陷
类型
①Use sander to grind the extruded parts without damaging Reason:
the rebar protective layer. 在不影响钢筋 原因:
保护层的情况下,采用打磨机直接对凸出部分进行磨 Deformation of formwork.
Due to 削。 模板变形。
formwork ②Use abrasive paper to grind, clean with water, then use Precaution:
deformation, the nylon cloth to clean up the polished area. 用砂纸 预防措施:
surfaces of 打磨,再用水清洗,然后使用尼龙纸清洁抛光区域。 Weekly check to ensure there is no deformed
几何尺寸不 formwork.
prefabricated ③Replace or repair the formwork that cause dents or
符,混凝土
concrete damages on concrete to keep the surface consistent and 每周检查一遍,确保没有变形的模板。
鼓包
slabsmay have even. 修理或更换造成的混
5 Wrong
bulges. 由于 凝土凹损部位的模板,以确保模板表面一致均匀。
dimensions
and concrete 模板的变形, ④For bulges, repair according to Item 4 and at the same
bulges 预制混凝土板 time rectify deformed formwork.
的混凝土表面 表面压痕隆起造成的鼓泡,使用第 4 项方法,同时纠正
可能出现一些 畸形的模板。
不均匀的鼓包 ⑤If the deformation of formwork is severe, the concrete
现象. protective layer might be weakened. Use detector to
check the thickness of the protective layer.
如果模板严重变形,这可能会削弱混凝土保护层,混
凝土表面保护层检测仪检查混凝土保护层厚度。
44
墩(台)身施工方案 Method Statement for Construction of Pier and Abutment
Types of
concrete
S/N Symptoms Repair Measures Causes and Precautions
defects
序号 缺陷表现情况 缺陷修补措施 原因及预防
混凝土缺陷
类型
For faulting height <10mm, no treatment is required. For Reasons:
faulting height ≥10mm, use portable grinder to level the 原因:
raised part to have a smooth jointing surface. 1. Formwork joint is not smooth.
错台高度<10mm 时可不做处理;当错台高度≥10mm 1.模板接缝不平顺;
时,采用手提式打磨机将错台高出部分磨平,使相接 2. Formwork swelling occurs during pouring
面平滑过渡。 2.浇筑时发生涨模。
Precautionary measures:
预防措施:
Before and during pouring, strictly inspect the fixation
Faulting of of formwork to ensure that the joint is smooth and
6 joints fixation firm.
错台 浇筑前和浇筑过程中严格检查模板固定情况,确保
模板接缝平整,安装稳固。
45
墩(台)身施工方案 Method Statement for Construction of Pier and Abutment
Types of
concrete
S/N Symptoms Repair Measures Causes and Precautions
defects
序号 缺陷表现情况 缺陷修补措施 原因及预防
混凝土缺陷
类型
7.1 For damages or defects more than 100mm deep: 超过 100mm Reasons:
深的损坏或缺陷: 原因:
①Cut an incision of 15mm deep around the defect area to prevent the Deformation of formwork.
formation of plane of weakness. Clean up the concrete around the 模板变形。
incision. For areas with exposed rebar, chisel concrete to 10mm Treatment is not careful.
below the exposed rebar.在缺陷边缘区域切割 15mm 深的切口, 处理不够细致。
防止修复材料形成薄弱边,清除锯口处混凝土。钢筋外露的地 Removal of formwork is not careful.
方,混凝土凿除至外露钢筋以下 10mm。 模板拆除操作不够小心。
②Clean up the chippings at the damage or defect area, wet with water Removal of formwork is too early.
and clean up. Blow dry of the surface then apply binding agent. 过早拆除模板。
清除损坏或缺陷区域的碎屑,喷水润湿并进行清洁。将表面吹
干后用粘合剂涂抹。
Angular ③Set up formwork at the damage or defect area, batch fine aggregate Precautions:
7 defect concrete according to mix design, then cast concrete into the 预防措施:
棱角缺损 formwork and cure. 在损坏或缺陷处竖立模板,按照所需 ①Abide by the time specified in the method
的混合设计配制细骨料混凝土,然后将混凝土浇筑到模板中, statement, and remove carefully of the
做好养生。 formworks to maintain enough strength of
7.2 For damages or defects between 10mm deep and 100mm deep: concrete.
超过 10mm 深和低于 100mm 深的损坏或缺陷: 严格遵守方案规定时间,小心拆除模板,
①Cut an incision of 15mm deep around the defect area to prevent the 确保混凝土具有足够强度。
formation of plane of weakness. Clean up the concrete around the ②During removal of formwork, protect the
incision. For areas with exposed rebar, chisel concrete to 10mm segments carefully.
below the exposed rebar.在缺陷边缘区域切割 15mm 深的切口, 拆模过程仔细保护节段梁。
③Removal of formwork and hoisting of
防止修复材料形成薄弱边,清除锯口处混凝土。钢筋外露的地
segments shall be instructed by site
方,混凝土凿除至外露钢筋以下 10mm。
engineers and foremen.由现场工程师及领
班监督拆除模板、吊装节段梁。
46
墩(台)身施工方案 Method Statement for Construction of Pier and Abutment
Types of
concrete
S/N Symptoms Repair Measures Causes and Precautions
defects
序号 缺陷表现情况 缺陷修补措施 原因及预防
混凝土缺陷
类型
②Clean up the chippings at the damage or defect area, wet with water and clean up, then
blow dry of the surface.
清除损坏或缺陷区域的碎屑,喷水润湿并清洁。然后吹干表面。
③Set up formwork at the damage or defect area, mix mortar, cast into the formwork and
then repair and harden according to manufacturer’s instructions.
在损坏或缺陷处竖立模板,配制砂浆,然后放入模板中,按制造商的说明进行修
整和固化。
7.3 For damages or defects less than 10mm deep
有低于 10mm 深的损坏或缺陷:
①Cut an incision of 15mm deep around the defect area to prevent the formation of plane
of weakness. Clean up the concrete around the incision. For areas with exposed rebar,
chisel concrete to 10mm below the exposed rebar.在缺陷边缘区域切割 15mm 深的切
口,防止修复材料形成薄弱边,清除锯口处混凝土。钢筋外露的地方,混凝土凿
除至外露钢筋以下 10mm。
②Use scraper blade to take small amount of mortar to fill the damage or defect area, and
repair and harden according to manufacturer’s instructions.
使用小刮刀取适量的砂浆,以填补损坏或缺陷,并按照制造商的说明进行修正和
固化工作。
7.4 Damage to concrete end
混凝土端部损坏
①Check the damage together with CSC engineers, and with the consent of CSC
engineers, carry out follow-up actions. If incision is unrequired, cast concrete into the
gap for repair. If not possible, repair according to Item7.1, 7.2 and 7.3.
与监理一同检查损坏情况,经监理同意后开始后续工作。如果可以不锯出口子来
进行修复,在缝隙里现场浇筑混凝土修复损坏部分;如果不行,则需要 按照第
7.1 和第 7.2 和第 7.3 项程序修复损坏。
47
墩(台)身施工方案 Method Statement for Construction of Pier and Abutment
Types of
concrete
S/N Symptoms Repair Measures Causes and Precautions
defects
序号 缺陷表现情况 缺陷修补措施 原因及预防
混凝土缺陷
类型
Reason:
原因:
①Concreting is suspended or stopped for a long time.
混凝土浇筑长时间中断/暂停。
Precautions:
预防措施:
①Concreting shall be continuous and the suspension
time shall be short.
Cold joints Evaluate the casting lines and cold joints according to 连续浇筑混凝土。缩短中断时间。
8 冷缝 their actual conditions. ②Enhance training to shorten concreting time.
浇注线和冷缝应根据具体情况进行评估。 加强工人培训,缩短浇筑时间。
③Due to discontinuous concreting, the concrete is
hardened. Stop concreting and apply retarder or
conduct dabbing, as construction joints, then resume
concreting.
由于不连续浇注而使混凝土硬化,停止混凝土浇
筑,并立即在表面上施加缓凝剂、表面凿毛处理,
作为施工缝,然后继续浇筑混凝土。
9.1 If the crack width is not less than 0.1mm and the Reasons:
混凝土表面 surface is not deep: 如果裂缝宽度 原因:
裂纹 ≥0.1mm,在表面且不深: ①Workability of concrete is not good.
9 Cracks of ①On concrete top/horizontal plane, paint sealant on cracks 混凝土和易性不好。
concrete using 15mm-wide (or other proper size) brush one or two ②Over-vibrating causes excessive fine powder on
surface times till crack is properly sealed. concrete surface.
48
墩(台)身施工方案 Method Statement for Construction of Pier and Abutment
Types of
concrete
S/N Symptoms Repair Measures Causes and Precautions
defects
序号 缺陷表现情况 缺陷修补措施 原因及预防
混凝土缺陷
类型
在混凝土顶部/水平面上,将裂缝封闭胶涂在裂缝上, 过度捣振使得混凝土表面产生过量细粉。
使用 15mm 宽(或其他适当宽度)的刷子,根据需要 ③Curing is not sufficient.
涂刷 1 或 2 次,直至裂缝密封妥当。 养护不足。
②On concrete side/vertical plane, paint sealant on cracks ④The removal of concrete protective layer is too early,
using 15mm-wide (or other proper size) brush one or two and because of the influence of quickened evaporation
times till crack is properly sealed. and heat, crack is more likely to occur.
在混凝土侧立/垂直面上,将裂缝封闭胶涂在裂缝上, 过早取掉混凝土覆盖层,加速蒸发和热效应影响,
使用 15mm 宽(或其他适当宽度)的刷子或者喷涂根 增加开裂的风险。
据需要涂抹 1 或 2 次,直至裂缝密封妥当。 Precautions:
After painting, curing of sealant for cracks according to 预防措施:
manufacturer’s instructions. ①Control well of the mix ratio of concrete to maintain
good workability.
在涂抹后,按照制造商要求,对裂缝封闭胶进行养
小心控制混凝土配比,确保良好的和易性。
护。
②Avoid over-vibrating to prevent excessive fine powder
9.2 If the crack crosses a whole section and is not less
from getting on the surface and increase the risk of
than 0.1mm, re-prefabrication is required. 如果
cracking.
裂缝贯穿整个截面且宽度≥0.1mm,则需要重新匹配
避免过度捣振,将过量的细粉带到表面,增加开裂
预制。 风险。
7 days after concreting, check cracks and identify and log ③Curing immediately after repair to maintain
cracks with a width of more than 0.05mm. After 28 days, continuous curing.
if crack width is less than 0.1mm, no repair is required.
在修整后立即进行养护,确保表面养护连续。
浇筑 7 天后,一同对裂缝进行检查,并识别并记录宽 ④Set up cover during curing to reduce evaporation.
度 大于 0.05mm 的 裂缝 。 28 天后 ,如 果裂 缝宽 度 在养护期间适当覆盖,以减少蒸发。
<0.1mm,则无需维修。
49
墩身施工方案 Method Statement for Pier
① The main construction management personnel should be licensed, site operators must
undergo safety training and pre-job education. Foreign laborers after safety training and education,
for on-the-job operations.
主要施工管理人员应持证上岗,现场作业人员必须经过安全培训和岗前教育。外
来劳务人员在经过安全培训教育后,进行上岗作业。
50
墩身施工方案 Method Statement for Pier
a good condition. And intensify the maintenance during construction to ensure the construction can
be executed smoothly.
所有施工机具设备均要事先进行检修,并保持良好状态。并加强施工期间的维修和
保养,以确保施工正常进行。
⑦ Construction joints shall be roughened, and the concrete laitance and loose layer shall be
chiselled away to expose the coarse aggregates.
施工缝要进行凿毛,要求凿除砼浮皮及松散层直至见到粗集料。
⑧ Quantity of rebar in pier body shall not be less than the design quantity, and the rebar
connects shall not be on the same cross section, shall be staggered. The protective layer shall meet
the design requirements, grade of the protective layer block shall be the same as the concrete of
pier body. Embedded bars position shall meet the construction of pier body.
墩身钢筋根数不得少于设计数量,钢筋接头不得在同一断面上,需错开。钢筋保护
层符合设计要求,保护层混凝土垫块需与墩身混凝土标号一致。钢筋预埋位置、应满足
墩身施工要求。
⑨ Four sides of the formwork shall be smooth, verticality, planeness and cleanness and
position deviation shall meet the requirements of the technical Specification. Release agent shall be
applied prior to concreting, and waster engine oil is restricted.
模板应保证四周平顺,垂直度、平整度、模板光洁度、位置偏差符合技术规格书要
求,浇筑混凝土前模板应涂刷脱模剂,禁止使用废机油。
⑩ Temperature of concrete of pier body shall not exceed 30℃, mixing water shall adopt ice
or cooling water device, aggregates shall be covered from sunshine. Concrete mixer truck shall be
covered with geotextile and watered. Concrete pouring shall be even to avoid segregation.
Vibration shall be even to avoid miss-vibration or less-vibration.
墩身混凝土温度不应超过 30℃,拌合用水应采取加冰或冷水装置,粗细集料应采取
遮阳措施。混凝土运输车罐体可覆盖土工布并晒水。混凝土布料要均匀,避免离析。振
捣要均匀适当,防止漏振或少振。
53
墩身施工方案 Method Statement for Pier
for labor.
制定科学合理的劳动作息制度,合理安排劳动作业强度;
⑭Refer to the HSE management measures of sub-section works for relevant
information.
关于其它相关内容,详见各分项工程安全健康与环境管理措施。
⑮ Refer to HSMP (Health and Safety Management Plan) for relevant measures.
关于其他相关措施,详见安全、健康管理计划。
⑯Risk Assessments & Hazard Identification & Mitigation Measures Of Test Pier
Operation is shown in the table below.
Table 9.1-1:Risk Assessments & Hazard Identification & Mitigation Measures
风险源辨识表
54
墩身施工方案 Method Statement for Pier
55
墩身施工方案 Method Statement for Pier
56
墩身施工方案 Method Statement for Pier
equipment
16 Mechanical failure Lifting damage Equipment protection Low
17 Lifting Operational violation Lifting damage Safe operating procedure In
Personal protective
18 machinery Noise other damage In
equipment
19 Oil Open fire Fire Safe operating procedure Low
57
墩身施工方案 Method Statement for Pier
No Hazards Measures
序号 危害项目 措施
Air quality and Spray water on the construction access roads to reduce dust.
dust Speed limit of car is 20km/h to reduce dust
1
空气质量及灰 对施工便道采取洒水降尘措施;车速限制在 20Km/h,以免
尘 引起过大的灰尘;
Temporary dumboards shall be installed in mosques, schools,
and dense populated areas and other sensitive areas to maintain
noise levels ≤ 60 dB (Bangladesh standard). If it is beyond
Noise pollution normal, the construction time is limited and good soundproofing
2
噪音污染 equipment is required.
在清真寺,学校,人口稠密区域和其他敏感地区安装临时挡
板,保持噪音在≤60 dB(孟加拉国标准)水平。如果超出正
常则限制施工时间,同时要求使用好的隔音设备
58
墩身施工方案 Method Statement for Pier
No Hazards Measures
序号 危害项目 措施
The accommodation area should be kept away from the water
Surface/Ground
source. Take effective measures such as providing septic tanks,
water pollution
3 garbage bags, and other sanitation facilities.
地表水和地下
住宿区应远离水源地。采取有效措施,如提供化粪池,垃
水污染
圾袋,和其他卫生设施。
Provide personal protective equipment (such as protective
clothing, safety shoes, helmets, masks, gloves, goggles, etc.) to
construction workers.
Store containers shall be placed in clearly marked temporary
storage site to prevent vehicles or heavy machinery from
running over. The temporary storage area preferably has a
certain inclination or is equipped with a drainage ditch. If a leak
Fuel and
occurs, the raw material can be discharged into a safe area.
dangerous
4 Take precautions when handling and storing fuels and lubricants
substance
to avoid environmental pollution.
燃料及危险品
向施工人员提供个人防护用品,(如防护服、安全鞋、头
盔、面罩、手套、护目镜等)。
储存用的容器放在清楚标示的临时存放位置,以免车辆或
重型机械碾过。临时储存区最好有一定的倾斜度,或配有
排水沟,如果发生泄漏,原料可排入安全区域。
在处理和储存燃料和润滑油时,采取预防措施,避免环境
污染。
Cement shall be kept in cement tank and filters need to be
installation to avoid leakage. Storage, mixing and loading area
Construction
must be large enough to avoid dust spread.
5 activities
水泥储存于水泥罐中,安装过滤器,避免外漏。
施工因素
储存,混合及装载区域应足够大,以防止在操作过程中粉
尘扩散
59